Time Schedule of Pipeline Construction

ID Text11 Task Name Duration M-1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31
1 0
Overall Time Required 900 days
2 1
Preparation of Bid Documents 20 days
3 2
Invitations of bids, evaluation, approval 30 days
4 3
Issuance of NoA, PG Submission, PG Verification & 28 days
Signing of Contract
5 4
Land Acquisition & Requisition 410 days
6 5
Procurement of Goods for Pipeline Transportation 180 days
System (Line pipe, Induction bends, Valves, Pig traps
& miscellaneous fittings, CP materials, Coating &
wrapping materials

7 6
Pipeline Construction (16'' OD x 6.9 km) 600 days
8 6.1
Mobilization 28 days
9 6.2
Preparation of Site Facilities 60 days
10 6.3
Mobilization of Const. Equipment 40 days
11 6.4
Material take Over 30 days
12 6.5
RoW Grading 180 days
13 6.6
Welder Qualification 15 days
14 6.7
Stringing of Pipes 60 days
15 6.8
Welding of Linepipes 310 days
16 6.9
NDT & Radiography of Welds 310 days
17 6.10
Joint Coating 310 days
18 6.11
Placing of SOW 210 days
19 6.12
Trenching & Lowering 210 days
20 6.13
Back-filling 210 days
21 6.15
Cased Road Crossing 60 days
22 6.14
Tie-ins 55 days
23 6.15
Demobilization 28 days
24 6.16
Site Cleaning 10 days
25 6.17
Pipe Cleaning & Testing 45 days
26 6.18
Dewatering & Drying 30 days
27 6.19
Commissioning 5 days
28 6.20
Handing Over 0 days 3/23