IR-01 Dt. 25-11-2022
IR-01 Dt. 25-11-2022
www.astrongroup.com
Client: Nesma & Partners Contracting So. Ltd Report No: IR-01
Vendor: GLOBAL SCALES & SYSTEMS CO. LTD. Visit Date: 25th Nov. 2022
Sub-Vendor: METTLER TOLEDO Next Visit: N/A
No. 111 Taihu West Road, Xinbei District,
Location: PO No: 120-00288
Changzhou City, Jiangsu Province, China
Project: MARJAN INCREMENT PROGRAM IL No: N/A
SA Dummy Po: N/A Client Ref: N/A
EC Job No: ASA-803 IC Job No: N/A
Summary of Items Inspected (Refer Page 2 for Details)
PO Item No Description Quantity
1 10-01044 1 lot
BRIDGE SCALE, WEIGHBRIDGE: ZONE #1
PLATFORM DIMENSIONS: 18 X 3.4 METER
FOUNDATION: PITLESS C/W POWERCELL
PDX LOADCELL, C6 GRADE, RECEIVERS
CABLES: CELL TO CELL CABLE
TERMINAL: IND780 PDX
BUMPERS AND ANCHOR BOLTS
FOR PROPANE AREA
Size60 TON
Mfr. : METTLER TOLEDO
Model: VTC 205
2 10-01045HOMERUN CABLE FOR BRIDGE SCALEPOWERCELL PDX 120m
HOMERUN CABLESUITABLE FOR BRIDGE SCALE MODELVTC
205.ZONE 1
FOR PROPANE AREA
3 10-01046BRIDGE SCALE SIDE RAILS2 SIDES FOR EACH BRIDGE SCALE 2no
FOR PROPANE AREA
4 10-01047SIGNAL LIGHT FOR BRIDGE SCALERED I GREEN 1no
FOR PROPANE AREA
5 10-01048PAINTING FOR BRIDGE SCALEMODEL VTC 205 AS PER 1lot
ARAMCOSTANDARD
FOR PROPANE AREA
6 01-03733SOFTWARE 1no
DATABRIDGETM SS SCALE HOUSE SOFTWAREFOR PROPANE BRIDGE
SCALE
7 009158 1lot
24 10-01046 12no
BRIDGE SCALE SIDE RAILS2 SIDES FOR EACH BRIDGE SCALE
FOR SULFUR AREA
25 605953 1lot
FREIGHT CHARGE
SEA FREIGHT CHARGEEROM CHANGZHOU CHINATO DAMMAM- KSA
SEA PORT
26 408320TRANSPORTATION CHARGESTRANSPORTATION FROM SEA 1lot
PORT TO JJOB SITE
27 416312 1lot
CUSTOM DUTY
INCLUDING CUSTOM DUTY, CLEARANCE AND SABR FEES
Results of Inspection Order status
Inspection Summary:
1, Check the item against the approved general arrangement drawing;
2, Visual inspection;
3, Material certificates to be verified;
4, Nameplate data to be verified against NMR 602 requirement and data sheets.
5, Manufacture packing.
Attachments NCR ☐ Punch List ☐ Release Note ☐ Certificate
RECORD OF HOURS
Inspection / Report Hrs.: 01 Day Travelling Hrs.: - Distance Travelled: -
Inspection Engineer Inspection Coordinator
1. Personnel Met
S. No Name Designation Company
1 Howard Yin Engineer METTLER TOLEDO
2 Liner Inspection ASTRON
1 Check the item against the approved general arrangement drawing; Acceptable
Acceptance with
4 Nameplate data to verified against NMR 6-2 requirement and data sheets
comments
9. Attachments
1) Attachment 1-Calibration certificate
2) Attachment 2-MT report
3) Attachment 3-Packing list
4) Attachment 4-Procedure document
5) Attachment 5-Factory test Digital Indicating scale inspection report
6) Attachment 6-Painting inspection report
10. Photographs
(Insert as per Sec 4.0 including values of measurements taken)
Pic 1. Modules for all 7 sets truck scales Pic 2. Modules for all 7 sets truck scales
Pic 3. Modules for all 7 sets truck scales Pic 4. Modules for all 7 sets truck scales
Pic 5. Modules for all 7 sets truck scales Pic 6. Modules for all 7 sets truck scales
Pic 13. Checked the end plates Pic 14. Checked the end plates
Pic 15. Checked the end plates Pic 16. Checked the end plates
Pic 17. Checked the end plates Pic 18. Checked the end plates
Pic 19. Checked the Hardware box Pic 20. Checked the Hardware box
Pic 21. Checked the Hardware box Pic 22. Checked the Hardware box
Pic 23. Checked the Hardware box Pic 24. Checked the Hardware box
Pic 25. Checked the Hardware box Pic 26. Checked the Hardware box
Pic 27. Checked the Hardware box Pic 28. Checked the Hardware box
Pic 29. Checked the Hardware box Pic 30. Checked the Hardware box
Pic 31. Checked the Hardware box Pic 32. Checked the Hardware box
Pic 33. Checked the Hardware box Pic 34. Checked the Hardware box
Pic 35. Checked the Hardware box Pic 36. Checked the Hardware box
Pic 37. Checked the Hardware box Pic 38. Checked the Hardware box
Pic 39. Checked the Hardware box Pic 40. Checked the Hardware box
Pic 41. Checked the Hardware box Pic 42. Checked the Hardware box
Pic 43. Checked the Hardware box Pic 44. Checked the Hardware box
Pic 45. Checked the Guardrail Pic 46. Checked Home Run Cable
Pic 47. Checked the Guardrail Pic 48. Checked Home Run Cable
Pic 49. Checked the Accessory box Pic 50. Checked the Accessory box
Pic 51. Checked the CANBUS Pic 52. Checked the CANBUS
Pic 53. Checked the CANBUS Pic 54. Checked the CANBUS
Pic 55. Checked the Cabinet box Pic 56. Checked the Cabinet box
Pic 57. Checked the Cabinet box Pic 58. Checked the Cabinet box
Pic 59. Checked the Cabinet box Pic 60. Checked the Cabinet box
Pic 61. Checked the Cabinet box Pic 62. Checked the Cabinet box
Pic 63. Checked the Cabinet box Pic 64. Checked the Cabinet box
Pic 65. Checked the Cabinet box Pic 66. Checked the Cabinet box
- End of Report -