ID Task Name Duration Start Finish Jul '23 Predecessors Aug '23 Sep '23 Oct '23 Nov

Jul '23 Predecessors Aug '23 Sep '23 Oct '23 Nov '23 Dec '23
30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24
1 PROJECT TIMELINE 118.94 days
Tue 15-08-23 Sat 30-12-23
2 Project Kick Off, Site Visits, Meetings for finalizing 0.94 days Thu 07-09-23 Thu 07-09-23
3 Locations of Sensors,
Imported Material Panels,(Partial
Delivery Work Deliveries
Process, etc.
will be 6 days Tue 10-10-23 Sun 15-10-23
4 maintained.
Local Timeline
Material dependant
Delivery on SBP Approvals)
(Partial Deliveries will be 5.94 days Mon 07-08-23 Sat 12-08-23
5 maintained)
Cable Conduiting (Client Scope) 36 days Mon 02-10-23 Sat 11-11-23
6 TEAM MOBILIZATION (3 Team per 3 Person) 2.94 days Tue 10-10-23 Thu 12-10-23
7 Installation of Control DB & Instruments with Termination 25 days Fri 13-10-23 Fri 10-11-23 8,9,10,11,12,13,14,15
8 5th Floor 11.94 daysFri 13-10-23 Thu 26-10-23
9 4th Floor 12 days Fri 13-10-23 Thu 26-10-23
10 3rd Floor 12 days Fri 13-10-23 Thu 26-10-23
11 2nd Floor 13 days Fri 27-10-23 Fri 10-11-23
12 1st Floor 13 days Fri 27-10-23 Fri 10-11-23
13 Ground 13 days Fri 27-10-23 Fri 10-11-23
14 Basement 01 12.94 daysSat 11-11-23 Sat 25-11-23
15 Basement 02 12.94 daysSat 11-11-23 Sat 25-11-23
16 Programming, Acquisition of Data, Linking and Binding37.94 daysFri 13-10-23 Sat 25-11-23
17 Commissioning 22.94 daysSat 25-11-23 Thu 21-12-23
18 Handing Over 34.94 daysTue 21-11-23 Sat 30-12-23