Volume of planned

No. Bridge Position Operation


works total
1 M1 BRIDGE km 45+208 Finishing works 4
2 M3 BRIDGE km 48+951 Bearing beams 4
3 M3 BRIDGE km 48+951 Abutments 4
4 M3 BRIDGE km 48+951 Precast girders 60
5 M3 BRIDGE km 48+951 Montage of girders 60
6 M3 BRIDGE km 48+951 Deck slab 2
5 M4 BRIDGE km 50+816 Abutment piers 4
6 M4 BRIDGE km 50+816 Deck slab 2
7 M5 OVERPASS km 51+438 Bearing beams 4
8 M5 OVERPASS km 51+438 Precast girders 21
9 M6 OVERPASS km 54+014 Piles 14
10 M7 OVERPASS km 56+354 Bearing beams 4
11 M7 OVERPASS km 56+354 Precast girders 18
12 M8 BRIDGE km 56+773 Abutment piers 4
13 M8 BRIDGE km 56+773 Deck slab 2
14 M9 OVERPASS km 58+170 Deck slab 1
15 M11 OVERPASS km 59+967 Deck slab 1
15 M14 OVERPASS km 62+938 Deck slab 1
Volume of planned works in Volume of executed production up to
December 30th of December
1 1
4 4
2 2
9 9
60 20
1 0
2 2
1 1
2 2
7 0
0 5
4 0
18 10
2 2
1 1
0.5 0
1 0.5
0.5 0
Volume of executed production from 26th of Description of executed production from 26th of
December to 30th of December December to 30th of December
0
0
1 concreted 1 abutment
0
20
0
1 concreted 1 abutment
1 concreted 1 deck slab
1 concreted 1 bearing beam
0
5 concreted 5 piles
0
3 concreted 3 precast girders
0
1 concreted 1 deck slab
0
0
0