Professional Documents
Culture Documents
TJGP WTIP MR RFQ E004 Rev
TJGP WTIP MR RFQ E004 Rev
CHECK APPR
REV DATE PREP BY DESCRIPTION
CONTRACTOR
TOTAL OR PARTIAL REPRODUCTION AND/OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN WITHOUT PRIOR WRITTEN
AUTHORIZATION OF THE OWNER
THE APPROVAL THIS DOCUMENT/DRAWING DOES NOT RELIEVE THE CONTRACTOR OF THE RESPONSIBILITY TO MEET ALL
REQUIREMENT ON THE CONTRACTOR
TABLE OF CONTENT
1. INTRODUCTION ..................................................................................................................................5
2. DEFINITIONS........................................................................................................................................5
3. SCOPE OF VENDOR SUPPLY ...........................................................................................................6
3.1 Equipment / Materials ....................................................................................................................6
3.2 Special Tools ..................................................................................................................................6
3.3 Spare Parts.....................................................................................................................................7
3.3.1 Commissioning and Start up Spare Parts ..........................................................................7
3.3.2 One (1) Years Operation Spare Parts ................................................................................7
3.3.3 Two (2) Years Operation Spare Parts ................................................................................8
3.4 Operational Consumables .............................................................................................................8
3.5 Anchor Bolts / Setting Bolts / Nuts ................................................................................................8
3.6 Surface Painting and Rust Prevention / Preservation ..................................................................9
3.6.1 Surface Painting ..................................................................................................................9
3.6.2 Rust Prevention / Preservation ...........................................................................................9
4. SCOPE OF VENDOR SERVICES ..................................................................................................... 10
4.1 Vendor’s Drawings, Document and Data Requirements .......................................................... 10
4.1.1 Document Submission ..................................................................................................... 10
4.1.2 Company’s and Purchaser’s Comments on Vendor Document..................................... 10
4.1.3 Manufacturing Schedules ................................................................................................ 11
4.1.4 Vendor Weekly and Monthly Reports .............................................................................. 11
4.1.5 Units of Measurement ...................................................................................................... 11
4.1.6 Language .......................................................................................................................... 11
4.1.7 Certificate of Origin........................................................................................................... 11
4.1.8 Packing List (Shipping Document) .................................................................................. 11
4.1.9 Installation/Operation/Maintenance Manual.................................................................... 11
4.1.10 3D Model........................................................................................................................... 12
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
1. INTRODUCTION
This requisition covers the specific purchase conditions relating to “Request for Quotation” for
Equipment / Materials to be used for Pembangunan Fasilitas Water Treatment Injection Plant
Lapangan Tanjung, Tabalong, South Kalimantan, Indonesia.
The following documents attached hereto shall constitute an integral part of this requisition:
Note: Unless otherwise specified, the latest issue of all documents shall be applied.
2. DEFINITIONS
The following definitions are applicable in this document.
(1) Bidder shall comply with the following requirements for special tools and devices.
A) Special tools and devices necessary for the lifting, erection, assembly, testing and
maintenance of the equipment and accessories shall be provided.
B) They shall be easily identified and small tools shall be packed in lockable steel boxes,
although exceptions may be made for particularly large tools.
C) Bidder shall also provide a list, description, drawings and documentation of such special
tools and devices.
D) The prices for each tool and device shall be indicated separately and included in the total
lump sum price.
E) Lifting certificate (inspected by 3rd party) for all the lifting tools must be provided.
(2) Vendor shall supply one (1) complete set of special tools and devices stated above.
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
(3) Vendor shall advise any optional provisions available for the loan or rental of expensive
specialized tools or appliances when required.
(4) Special Tools List shall be filled-in on BOM List.
[ ] Not Required.
[X] Required as the Lump Sum. See below.
(1) Bidder shall recommend the spare parts required for commissioning and start-up of the
equipment. The list of spare parts, description, price breakdown and delivery times shall be
separately provided in his proposal.
(2) Commissioning and Start up Spare Parts shall be purchased with the main Equipment /
Materials after final selection by Purchaser. Vendor shall deliver them together with the main
Equipment / Materials.
[ ] Not Required
[X] Required as the Lump Sum. See below.
(1) Bidder shall recommend the spare parts for one year operation of the Equipment / Materials,
and submit a list of spare parts, description, price, delivery period, information and any other
information for evaluation in his proposal.
(2) These spare parts will be purchased with Equipment / Materials by Purchaser in accordance
with Company’s instruction. Vendor shall deliver them together with the main Equipment /
Materials.
(3) Recommend Quantity of Two (2) Years Operation Spare Parts shall be filled-in on BOM List.
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
[ ] Not Required
[X] Required include Quotation. See below.
(1) Bidder shall recommend the spare parts for two year's maintenance of the Equipment /
Materials, and submit a list of spare parts, description, price, delivery period, information and
any other information for evaluation in his proposal.
(2) These spare parts will be purchased with Equipment / Materials by Purchaser in accordance
with Company’s instruction. Vendor shall deliver them together with the main Equipment /
Materials.
(3) Recommend Quantity of Two (2) Years Operation Spare Parts shall be filled-in on BOM List.
[ ] Not Required
[X] Required as the Separated Quotation. See below.
(1) Bidder shall provide Purchaser a list of the specifications and quantities of operational
consumables with price information, such as lubricants, grease, dessicant etc. if any, for
initial charge and one year normal operation. The list of them shall be separately provided
for initial charge and for one year normal operation.
(2) Vendor shall submit a table showing the operational consumables schedule in the format
provided by Purchaser. If the consumables are Bidder’s exclusive products, Bidder shall
provide their price list.
(3) Operational Consumables may be purchased with Equipment / Materials after the
Purchaser’s review. Vendor shall deliver them together with the main Equipment / Materials.
[ ] Not required
[X] Provided Anchor Bolts and Nuts by Purchaser
[ ] Provided by Vendor as the Lump Sum
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
[ ] Not required
[X] All surface preparation and painting up to the finish coat
[X] As instructed in TJGP-WTIP-QA-PRC-E006 “SURFACE PREPARATION AND
PAINTING PROCEDURE”.
[X] Finish color in accordance with TJGP-WTIP-PL-SPE-E003 “SPECIFICATION OF
PAINTING AND COATING”.
[ ] Per Vendor’s standard approved by Purchaser
[ ] Grease, plastic or other suitable substances which Vendor recommends, and approved
by Purchaser
[X] As instructed in TJGP-WTIP-QA-PRC-E005 “HANDLING, SHIPPING & STORAGE
CONTROL PROCEDURE”.
(1) All the important parts (such as machined surfaces, internal surface and etc.) of Equipment
/ Materials shall be rust-proofed adequately for ocean freight and storage at site.
(2) All flange openings for Purchaser’s tie-in shall be closed with metal blind flange and gasket.
Before shipping, Equipment / Materials shall be witnessed by Purchaser’s inspector to
ensure proper preservation has been applied per project requirements.
(3) Vendor shall submit a preservation procedure for Purchaser’s review that meets the
requirements in the reference specifications. Vendor shall provide adequate rust prevention
suitable for transportation to construction site and storage at construction site to ensure that
the Equipment / Materials shall ultimately satisfy his guarantee. Equipment and Materials
shall endure at least two months of sea lift and twelve (12) months of outdoor storage at site.
(4) If Vendor has any specific instruction on the site storage for required period, Vendor shall
issue the instruction as one of the Vendor documents. Each Vendor’s recommendations for
preserving its particular piece of material must be reviewed and implemented. Whenever the
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
A) Items fabricated from textiles, plastics, mica, rubber, cork, paper, leather and leather
products
B) Electrical and electronic parts and equipment such as condensers, electrical connectors,
distributor rotors, circuit breakers, fuses, switches, resistors and rectifiers
C) Items that would suffer damage to mechanism or structure or where malfunction or
unsafe operational conditions would result due to application or removal of the
preservative compound
4.1.6 Language
All Vendor documents and drawings, except equipment specification and the instruction manual
for the operator, shall be in the English language.
The Installation/Operation/Maintenance Manuals for the operator shall be the dual language in
Bahasa Indonesia and English.
[ ] Not required
[X] Required as the Lump Sum. See below.
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
4.1.10 3D Model
Vendor shall submit electronic data of 3D Models of the packaged equipment with all the
information related to them, to Purchaser for PDMS format or equal.
(1) Vendor shall conduct tests and/or inspections and provide all the related documentation in
accordance with the requirements specified in the "Scope of Inspection" (Attachment-5) and
Specifications / Codes listed for in the “Applicable Document List” (Attachment-3).
(2) The Vendor’s manufacturing procedures, including WPS/PQR with weld map, non-
destructive examination (RT, UT, MT and PT), PWHT procedure, PMI procedure and major
repair procedures, shall be reviewed and approved by Purchaser prior to the
commencement of manufacturing.
(3) Inspection and test plan (ITP)
Vendor shall prepare an ITP for Purchaser’s approval in accordance with the “Applicable
Document List” (Attachment-3) and the “Scope of Inspection” (Attachment-5).
(4) Pre-inspection meeting (PIM)
[X] PIM shall be held at the Vendor’s shop or sub-vendor’s shop prior to the
commencement of fabrication
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
The Vendor shall arrange PIM for main / critical parts at sub vendor’s shop. PIM shall be
arranged by the vendor and Notification shall be issued to Purchaser. The necessity of PIM
for sub vendor shall be discussed and fixed at KOM.
Vendor is advised that failure to provide such notice shall result in inspection being delayed.
If a witness inspection is cancelled due to the vendor’s reason, the cost of the inspection for
Company and Purchase occurred shall be borne by the vendor.
4.3 Meeting
[X] Technical Meeting ([X] once or [ ] twice, (one week for one time))
at Contractor’s designated office in (Jakarta, Indonesia)
[X] Hazard and Oparability (HAZOP) and Hazard Identification (HAZID) Study
Meeting at Contractor’s designated office in (Jakarta, Indonesia)
All the costs for attendance at the above meetings shall be borne by Vendor and be included as
the Lump sum.
[ ] Not required
[X] Required as the Separated Quotation. See below.
(1) If Vendor’s field work or services are mandatory to guarantee the quality and performance
of the equipment, Bidder shall quote the price of such necessary field work or services with
details, specifying the number and qualifications of the required personnel with rates for
each qualification level, the scope of work and supply as well as the work description. Such
field work or services shall cover the necessary work, such as supervision for installation
and commissioning, instruction, calibration, inspection and witness.
The details shall be divided into three phases of field activity. (i.e., installation, assembly,
adjustment, alignment and performance testing.)
(2) Personnel to be dispatched must be able to speak the English language sufficiently to
perform their duties.
(3) Breakdown of all expenses and fees related to the field services, including, but not limited
to, super visors, equipment and tools, aids and personal protection equipment used for field
service, travel and accommodation, shall be included in the proposal.
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
(4) Bidder shall provide the information of country of dispatch for personnel for field service. If
Bidder has both resources for personnel from overseas and within Indonesia for field
service, it shall provide the both cases quotation separately.
[ ] Not required
[X] Required as the Separated Quotation. See below.
Vendor shall provide all training materials, facilities, professionals, and specialists required to
train Company's operations and maintenance personnel to a level where they can handle the
equipment supplied. Bidder shall separately submit a proposal for a training program, duration,
number of trainers and training cost (per diem rate and other conditions) for the training
requirements stated below.
(1) Training shall be performed at Jakarta, Banjarmasin, Tabalong, or within Project Site
(Classroom and On Job Training at Site).
(2) Company assumes the number of trainees shall be approximately 25 persons per class,
and the degree and amount of training required shall vary with individual positions and
responsibilities.
(3) Indonesian or English language shall be used for all lectures in the course.
(4) Personnel to be dispatched as trainer must be able to speak the English language.
(5) Breakdown of all expenses and fees related to the training services, including, but not limited
to, trainers, arrangement of facilities, tools, aids and personal protection equipment used for
training, travel and accommodation, shall be indicated in the proposal.
(6) Vendor shall develop and submit the detailed training program 6 months in advance of the
training.
(7) Vendor shall provide and/or arrange all training facilities and materials to be used by trainers
and trainees.
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
(8) Bidder shall provide the information of country of dispatch for personnel for training service.
If Bidder has both resources for personnel from overseas and within Indonesia for training
service, it shall provide the both cases quotation separately.
Vendor shall submit the list of all Sub-vendors including following data.
A) China
B) India
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
(1) Preliminary Packing List is submitted 1 month after Purchase Order issue date
Transportation Shipping Drawings is submitted 3 months prior to the contractual delivery
date
(2) Revised Preliminary Packing List is submitted 2 months prior to the contractual delivery date
(3) Revised Preliminary Packing List is submitted 1 months prior to the contractual delivery date
(4) Final Packing List is submitted 1 week prior to the contractual delivery date
Length : 11.0 m
Width: 2.0 m
Height: 2.0 m
Gross weight: 20.0 Metric tons
If the packaged general containers size exceeds general container size, the maximum weight
and measurement of a cargo shall be as follows:
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
Maximum Dimension
Length: 30.0 m
Width: 4.5 m
Height: 4.1 m
Gross weight: 110.0 Metric tons
7. PRECEDENCE OF DOCUMENTS
In the event of conflict between any of the requirements of the applicable documents, including
the documents, specifications, and standards referenced herein, for the purpose of determining
the requirements of the applicable documents, the order of precedence of the documents shall
be as follows:
Purchaser has no responsibility to discover any deviations or alternatives entered in any parts of
the Bidder's proposal other than the said deviation list. If Vendor is awarded the order, Vendor
must comply with the applicable documents as revised only to reflect the deviations and
alternatives listed and accepted by Purchaser.
An alternative proposal shall be evaluated only if the base proposal is duly submitted.
Company and Purchaser do not accept any deviations raised after placing order.
9.1 General
Vendor shall implement the project by the established and documented Project Quality
Management System in compliance with ISO 9001: 2015 Edition that have been certified and
registered by the international independent certification body.
Implementation of the Quality Management System shall be in accordance with the Vendor’s
Quality Manual, Project specific Quality Plan, and Quality Control Plan.
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
In case that Vendor applies other quality management system equivalent to ISO 9001-2015,
Vendor shall submit the all of documents related to Quality Management System including the
latest internal or third party audit reports for the Purchaser’s assessment and approval.
9.3 Evidence of Third Party Audit Report Subject to ISO 9001: 2015
Vendor shall submit a copy of the latest third party audit reports, such as the latest initial audit,
surveillance audits or recertification audit report (translated, where necessary, into English)
undertaken by a recognized international independent certification body to demonstrate that
Quality Management System is compliant with ISO 9001: 2015 Edition. And any actions by
Vendor to correct any audit findings recorded in the report shall be described by Vendor.
Latest Management Review Report including Internal Audit Report, depending on the
requirements described in the paragraph 9.3 Management Review and 9.2 Internal Audit in ISO
9001-2015.
Vendor shall submit the Project Quality Plan to Purchaser for review within one (1) month after
the placement of Purchase Order.
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
The Project Quality Plan shall contain all Project specific procedures, including Purchaser’s, to
be applied to all of the required activities.
The Project Quality Plan shall be developed in accordance with ISO 10005: 2005 Edition “Quality
Management Systems – Guidelines for Quality Plans”.
[X] MIGAS
[ ] DEPNAKER
[ ] DIMET
[ ] BATAN
Note.
Vendor shall be familiar with applicable government regulations and requirements and shall
responsible to implement the government requirement including inspection and testing and
compiling all the inspection / test reports.
(1) Company is responsible to obtain MIGAS Certification. Purchaser and Vendor shall be
responsible to support Company in obtaining the Government certificates.
11.5 Instrumentation
a) Instrumentation Standardization
VENDOR shall select their instrument from instrument Vendor as registered in APDN, AML
SKK Migas and PML Pertamina EP.
11.6 Piping
a) Non-standard size
Non-standard pipe sizes (such as 1-1/4” NPS, 2-1/2”NPS, 22” and 5”NPS) shall not be used.
12.8.1.2 The following information shall be indicated for each material, as a minimum requirement;
a. Vendor drawing (or document) number - per Contractor’s numbering method specified.
- It is acceptable to indicate vendor’s document number together with Contractor number,
if necessary.
Part identification number (tag number) of the material shown in the above (a) document.
b. Part description (material name).
c. Unit of quantity indication.
d. Delivered quantity in a cargo.
12.8.1.4 Photographs
Vendor shall take digital photos of the materials contained in each cargo before packing.
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
The photos are used as record of quantity and material conditions. When “after delivery
claims,” such as material shortage or damage, happen, those photos will be reviewed to
confirm whether the condition claimed for happened before shipment or during shipment.
Notes:
1. Vendor’s for scope of supply is shown by mark “X” in column of inclusion or exclusion
2. Special Tools: See Section. 2.3 of this requisition
3. Spare Parts: See Section. 2.4 of this requisition
4. Anchor Bolt & Nuts See Section 3.5 of this requisition
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
GENERAL
Unpriced PO - - 1P 1N+1P +
2X
Operating and Maintenance Manual (Bilingual – Bahasa and English) - - 1P+3X 1N+1P +
3X
Basic Design
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
P&ID - - 1P 1N+1P +
2X
MSDS - - 1P 1N+1P +
2X
Piping
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
Instrument
Instrument List (with loose supply items information) - - 1P 1N+1P +
2X
Loop Drawing - - 1P 1N+1P +
2X
Electrical
Others
Painting Specification - - 1P 1N+1P +
2X
DOCUMENTS
Deviation/Alternative and Exception List 1E - - -
1P 1N+1P +
Copy of Unpriced P.O - -
2X
QMS Document
QC Document
NDE/PMI Procedure - 3M 1P -
NDE/PMI Personnel List - 3M 1P -
PWHT Procedure, if any - 3M 1P -
Note: W=Week, M=Month, X=Xerox copy, N=Electronic file (Native), P=Searchable File such as PDF
(1) To be submitted by using Purchaser’s Monthly Progress Report Form through FAX or E-mail.
(2) Including Field Test, if any
(3) MRB shall be reviewed and endorsed by Purchaser’s inspector and submitted to Purchaser
within 2 weeks after shipment.
(4) Vendor is requested to issue on the date specified in section 5.3 above.
(5) Vendor is requested to issue 3 months prior to contractual delivery date.
(6) Vendor is requested to issue 10 days prior to contractual delivery date.
(7) Vendor is requested to issue 4 months prior to contractual delivery date
(8) MIGAS MDR shall be submitted separately as per specification apart from Original MRB
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
When inspection or tests witnessed by Purchaser, Company are required, Vendor shall note the following:
(1) Vendor shall provide all test equipment and facilities required for the witnessed inspection and/or test at his cost if
requested by Inspector.
(2) Vendor shall furnish sufficient personnel to execute the inspection and/or test at his cost.
(3) Inspections and examinations required by applicable codes, laws, or emirate regulations shall be made by Vendor’s
inspectors and other personnel who are officially qualified in accordance with those applicable codes, laws, or emirate
regulations.
(4) If any defect is found during a witness at random, the witness percentage shall be increased. In the event of discovery
of further defects, witnessed inspections and/or tests are to be carried out on the entire defective lot.
(5) For all inspections and tests, Vendor shall make available to Inspector complete inspection and test records and
certificates, whether witnessed or non-witnesses.
(6) Purchaser and Company reserve the right to witness and/or audit the Vendor's quality control at the Vendor's facilities
when and to the extent deemed necessary by Purchaser or Company.
(7) The witnessed inspections and the document review by Purchaser do not relieve Vendor of his responsibilities or
obligations.
(8) The Scope of Inspection attached in this Requisition summarizes the planned inspection and test items to be conducted
by Purchaser and Company. It also shows the necessary records and certificates, which shall be prepared by Vendor.
(9) Purchaser inspection level may be increased or decreased based on the Vendor's performance and shall be finalized at
the pre-inspection meeting.
(10) Inspection procedures including Inspection and Test Plan (ITP) shall be submitted for Purchaser’s approval prior to pre-
inspection meeting.
(11) Purchaser and Company reserve the right to observe any test or inspection during fabrication.
(12) In order to perform the inspection work smoothly and accelerate the MRB submission. The vendor should get
Contractor's approval (without comment) prior to the final inspection for Vendor document mentioned in Attachment-3.
Before Manufacturing
1 Mill Certificates V R R OR
4 During Manufacturing
1 Fabrication of Vessel
INSPECTED BY
No. TEST AND INSPECTION RECORD REMARKS
VENDOR PURCHASER Company
Material, Fit
1.5 Parts for Lifting V H R OR
up, VT, NDE
4 Pressure Test
2 Hydrostatic Test V W R OR
6 Painting Inspection V S R OR
INSPECTED BY
No. TEST AND INSPECTION RECORD REMARKS
VENDOR PURCHASER Company
C Compressor
Run test :
1. Mechanical running test
2 2. Vibration measurement V W W OR
3. Sound level measurement
3 Dimensional Check V W W OR
D Electric Motor
Run Test
1. Mechanical Run Test
2. Vibration measurement’
4 V W W OR
3. Sound Level Measurement
E Instrumentation / Valves
INSPECTED BY
No. TEST AND INSPECTION RECORD REMARKS
VENDOR PURCHASER Company
F Steel Structure
G Painting (General)
1 Surface Preparation V S R OR
2 Measurement of DFT V W R OR
3 Visual Inspection V S R OR
3 Functional Test V W W OR
INSPECTED BY
No. TEST AND INSPECTION RECORD REMARKS
VENDOR PURCHASER Company
- Bundle location
6 V W R OR
- N2 purging/ VCI
- Rust prevention
- Etc
Packing Inspection V W R OR
K Documents
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA
INSPECTED BY
No. TEST AND INSPECTION RECORD REMARKS
VENDOR PURCHASER Company
Note:
All Witness (W) and Hold Point (H) inspection and test items shall be done at VENDOR’s facilty in
Indonesia, otherwise it will subject to CONTRACTOR’s approval.
PT PERTAMINA EP
PEMBANGUNAN FASILITAS WATER
TREATMENT INJECTION PLANT
LAPANGAN TANJUNG KSO NINDYA -ARTHA