ACTIVITY CHECKLISTS

Date :
Checklist for Wet Cladding Granite Work
WIR No. :

Project : Dwg Name :


Zone/Stretch Location : Dwg No. & Revision :
Status (Tick mark on applicable
cell)
SL. No. Checking Points Comments
Yes No NA

General items checklist Where applicable to this section.

1 Approved Shop drawing available


2 Method Statement available
3 MAR/MIR available
Before Granite Work

Is the granite laying pattern and material approved from the


1
client /Architect by witnessing the MOCKUP

Are the preceding activities like fixing of light points, plumbing


2
sleeves or required provisions are made as per the drawing

3 Are the defective tiles removed before work is started?


4 Granite pieces are liad on sand bed to check for colour variation.
5 is the thickness of granite is as per the specification
During Granite Works
6 Is the surface over which the granite is being laid clean and even?
7 Did Numbering given before starting claidding Work ?
8 Do granite patten match with each other ?
Are there provisions provided for service conduits, junction boxes,
9
etc.?
Post Granite Works
10 Is the pattern of laying granite as per the drawing and specification?
11 Is the thickness of joints between slabs accurate?
12 Is the true level of the surface and plumb OK?
13 Is the slope to the granite given accurately?
14 Is the dead mortars and debris removed?
15 Are the granite joints matching?
16 Is the finishing of edges for cut granites acceptable?
17 Are the grooves provided properly?
18 Is the finishes of granite work done accurately?
19 Is the granite grinding and polishing acceptable?
Is the cladding around electrical, sanitary fittings, doors and
20
windows done properly?
21 Are the right angles acceptable?
Project-Specific Items:

Comments:

Vendor Name:
Date:
Vendor RepOK
Inspected. Signature :
to proceed.
Date:
SYN Rep: