Professional Documents
Culture Documents
Method Statement For Construction Block Paving
Method Statement For Construction Block Paving
Method Statement For Construction Block Paving
METHOD STATEMENT
Method Statement for Construction Block Paving
Department: Date: Document Ref.: Revision:
Civil 7/08/2023 9 02
Project/Contract:
Principal Contractor: Hydrojet Facilities and management
Site Address:
Project Start Date:
Expected Duration:
Completion Date:
Table of Contents
Scope:............................................................................................................................................................ 4
Objectives ..................................................................................................................................................... 4
Personal, Tools, Plants and Equipment......................................................................................................... 4
References Tools, Plants, Equipment and Machinery .............................................................................. 4
References/Supporting Documents.............................................................................................................. 5
Details of Health & Safety Arrangements Include: ....................................................................................... 5
Scope and Procedures................................................................................................................................... 5
Scope of Works and Pre-Activities ............................................................................................................ 5
Methodology/Procedures ............................................................................................................................. 6
Laying of Kerbs ...................................................................................................................................... 6
Placing of Fill/Sub-Base Material .......................................................................................................... 6
Laying of Interlock Paviors/Stones (60 mm & 80 mm Thick) ................................................................ 6
Key Materials Required ................................................................................................................................. 7
List of Key Materials Required .................................................................................................................. 7
Residual Hazards and Safety Requirement ................................................................................................... 7
Specific Identified Residual Hazards ..................................................................................................... 7
List of Safety Requirements .................................................................................................................. 7
Risk Management for Work: ......................................................................................................................... 7
Summary of Activities with Potential Hazards and Risks: ............................................................................. 7
Controls Initiatives: ................................................................................................................................... 8
Communication and Training of Health and Safety: ................................................................................. 8
Checks and Inspections: ............................................................................................................................ 8
Induction and Permits to Work:............................................................................................................ 8
Method Statement details .................................................................................................................... 8
Security: ................................................................................................................................................ 8
Rules: ..................................................................................................................................................... 8
Smoking:................................................................................................................................................ 9
Page 3 of 11
METHOD STATEMENT
Method Statement for Construction Block Paving
Department: Date: Document Ref.: Revision:
Civil 7/08/2023 9 02
Services: ................................................................................................................................................ 9
Unloading Details: ................................................................................................................................. 9
Access:................................................................................................................................................... 9
Tools: ..................................................................................................................................................... 9
Welfare facilities: .......................................................................................................................................... 9
Emergency Arrangements: ........................................................................................................................... 9
Housekeeping: ............................................................................................................................................ 10
Job Safety Analysis (JSA): ............................................................................................................................ 10
The Sequence of Work: ............................................................................................................................... 10
Dependent on the Work: ............................................................................................................................ 10
On Completion of Work: ......................................................................................................................... 10
Use of Equipment: .................................................................................................................................. 10
When working at Height (General): ........................................................................................................ 11
When Working Alone: ................................................................................................................................. 11
Accidents, Incidents and Near Misses: ....................................................................................................... 11
Page 4 of 11
METHOD STATEMENT
Method Statement for Construction Block Paving
Department: Date: Document Ref.: Revision:
Civil 7/08/2023 9 02
Scope:
Block Paving Method Statement Objectives
Objectives
Per Block Paving Method Statement Objectives
This Method Statement describes the Methodology and procedures for Block Paving Works.
This Method Statement (MS) is however to be read, apply and compliance in association with
the attached
Job Safety Analysis.
The Project Health and Safety Plan (Approved HSE Plan).
References/Supporting Documents
List of References/Supporting Documents:
Project Approved for Construction Drawing
Approved Site Survey Plan & Survey Report
Approved Project HSE Plan
Attached Job Safety Analysis
[State/Country] Construction Standard
Activities and Tasks Described in this Method Statement Include the Following:
Laying of Kerbs.
Placing of Fill/Sub-base Material.
Laying of Interlock Paviors/Stones.
Pre-Activities
Ensure approval and release of Work Area and Temporary Land Lease Area by [Client/Facility]
and or other relevant departments before the commencement of work on-site as required.
Before the commencement of work contained herein, [ Organization/ Company] shall obtain
the relevant work permits from [Client/Main Contractor].
Toolbox shall be conducted by the Supervisor.
The use of mandatory PPE (Safety Glass, Safety Shoe, Helmet, Coverall, etc.). Shall be inspected
and implemented by the safety engineer.
Page 6 of 11
METHOD STATEMENT
Method Statement for Construction Block Paving
Department: Date: Document Ref.: Revision:
Civil 7/08/2023 9 02
Methodology/Procedures
Laying of Kerbs
Upon reaching the Site Sub-grade formation level, the Surveyor shall set out the proposed
Kerbs Line according to the approved drawings.
Wooden/metal forms for the Kerbs concrete base construction shall be installed and securely
and tightly braced to limit any deflection during the concrete placement.
Concrete of specified grade and the mix would be placed in erected formwork after wetting to
aid bonding.
Steel Dowel Bars (SBD) shall be installed in the concrete base slab if needed as per approved
drawings
Kerbs shall be placed on Cement Mortar (1:4) bedding, not more than 25 millimetres thickness
on the concrete base to adjust the levels of the Kerbs with a maximum tolerance of 3
millimetres.
In arching/curving locations and corners, Kerbs shall be tailor cut as per the shape and
dimensions.
As soon as Kerbs have been laid, bordering Concrete backing of pre-determined and specified
grade shall be poured behind laid Kerbs for hardness.
Joints between the Kerbs (Not more than 4 millimetres) shall be filled with fluid cement mortar
at the ratio of (1:4).
At every 10 to 20 meters intervals, a moment joint of 20 millimetres thick shall be formed
through the concrete bed and backing as well as the Kerbs. Impregnated fiberboard shall be
used to fill the movement joints.
Curing shall be done for the entirely Kerbs, base and backing for seven days.
Placing of Fill/Sub-Base Material
The area is to be levelled, watered and compacted by the means of a roller or plate compactor
in small areas where a big roller cannot reach.
The level of the formation is to be closely observed, verified, inspected and approved properly.
Approved Sub-base material shall be collected from the stockpile and placed in a maximum of
200 mm compacted layers as applicable.
The material is to be properly mixed and oversize or lump materials shall be removed by
labours.
Laying of Interlock Paviors/Stones (60 mm & 80 mm Thick)
Sand material bedding of approved quality shall be placed in a 50 millimetres layer, levelled
and watered.
Interlock paviors (100 x 200 x 60 millimetres or 100 x 200 x 80 millimetres) shall be collected
from an approved source and laid in an approved pattern as per approved construction
drawings.
Interlock paviors shall be neatly trimmed/cut to fit perfectly into Kerb's edges as applicable.
Fine/dune sand material shall be placed on top of laid Interlock paviors to fill in the joints.
The laid Interlock pavior is then compacted utilizing a Plate compactor.
Page 7 of 11
METHOD STATEMENT
Method Statement for Construction Block Paving
Department: Date: Document Ref.: Revision:
Civil 7/08/2023 9 02
The dune sand shall be hand brushed and removed after the compaction works are completed
to the satisfaction of the Site engineer.
Controls Initiatives:
Appropriate Controls measures have been identified from the risk assessments and are highlighted in
Method Statement and Risk Assessment MSRA include the following key points:
• Proper Health and Safety Communication and Training
• HSE Inspections
• HSE Observations
• Method of working
Communication and Training of Health and Safety:
• All risk assessments, method statement and Safe Systems of Work (SSOW) will be communicated
to the [Organization/Company] team/ operative before work initiate.
• A copy of this documented procedure and other recommended and suggested and applicable
safety arrangements will be communicated and passed onto the client/ sub-contractors or other
stakeholders before work started.
• All relevant toolbox talks will be communicated to the team/ operative before work commencing
ensuring that the team/ operative have had instruction and awareness information provided.
• Further information on the communication and training of Health and Safety can be found in the
Health and Safety Arrangements.
Checks and Inspections:
• All work equipment, devices or machinery will be checked before use for safe operation and to
ensure that it is “fit for purpose” and proper required third-party certification has been done.
• Risk Assessments (RA) and Safe Systems of Work (SSOW) will be checked before work started.
Induction and Permits to Work:
Method Statement details
• Contact with the Client’s site project manager/engineer for any worksite induction or Permits to
Work (PTW) requirements before proceeding with any work on site.
• Contact with the site project manager/engineer that asbestos is not present at the work area.
Asbestos-containing materials (ACM’s) are not to be disturbed by [Organization/Company] This
work required to be conducted by a specialist contractor or Government entities.
Security:
• Before commencing to the site, make sure that the Client’s site project manager/engineer has
authorised access to the workplace and the work area.
Rules:
• The organization’s Contractor, team or operative will carry out their work within the Client’s
Health and Safety rules and arrangements.
• Before commencing work these Health and Safety rules will be communicated to the team/
operative.
Page 9 of 11
METHOD STATEMENT
Method Statement for Construction Block Paving
Department: Date: Document Ref.: Revision:
Civil 7/08/2023 9 02
Smoking:
• [Organization/Company] will strictly comply with a no smoking policy on any Client’s
premises/workplace.
Services:
• All Gutter cleaning Services will not be interrupted due to work conducted by
[Organization/Company]
Unloading Details:
• Delivery to the site to be arranged with Client’s to ensure minimal disruption.
• Ensure adequate access and the best route to the workplace.
• Unload the vehicle of equipment by hand if no mechanical aids are available.
• Manual handling could be done by teamwork.
• Avoid a route that may bring you into contact with the Client’s staff or customers if possible,
ensure that gangways are clear, before bringing materials through, to the work area.
Access:
• All designated gangways and passageways should be free from obstructions.
• Ensure all waste from gutters is collected and disposed of from the work area.
• Ensure all fire exits and firefighting equipment clear of any obstructions.
Tools:
• All sort of Ladders to be used will be inspected before going to the workplace/site.
• All tools and equipment are to be inspected before use.
• All other tools and equipment will be hired by our preferred hire company.
• All tools and equipment hired from the “outsource suppliers” will be inspected properly on
delivery to make sure they are fit for purpose and have had the essential safety inspections/
checks.
Welfare facilities:
• Before work commencing [Organization/Company] will liaise with Client’s local management for
use of toilets and wash facilities.
• Eatables/meals will be provided by the team/ operatives themselves.
Emergency Arrangements:
• The exact location of First Aid (FA) arrangements will be required to be provided by the Client
before work started.
• Fire arrangements will need to be provided by Clients before work commencing including the
location of assembly points, location of fire exits and fire equipment; procedures to follow.
• More details on [Organization/Company] Emergency Arrangements can be provided in the
attached risk assessments and safety arrangements.
Page 10 of 11
METHOD STATEMENT
Method Statement for Construction Block Paving
Department: Date: Document Ref.: Revision:
Civil 7/08/2023 9 02
Housekeeping:
• All work areas will be kept clean and tidy where possible; [Organization/Company] operate a
“clean as you go policy”.
• All tools, equipment and waste will be removed from the site after the job has been completed.
• Any (non-hazardous) waste will be disposed of using the Client’s facilities or where necessary by
the team/operative.
• While handling tools to and from the vehicle use correct lifting techniques to avoid ergonomically
health risks.
• Make sure to keep fingers and or hands away from mechanical hazards and fatal physical injuries.
• To minimize the exposure to vibration, take frequent breaks, use gloves (HAVS).
• Use of hearing protection to minimize noise exposure.
• The use of ladders/ step will be done following the work at height risk assessment; ladders
located/ positioned correctly; individuals working from them for short periods.
When working at Height (General):
• Onsite risk assessment to be conducted appropriately.
• Construct a safe working area.
• Check steps/ ladders before use.
• Use equipment correctly, no overreaching, no standing on the top rung, no sideways force.
• Use of crawling boards on the facility’s building roof to get access to the higher-level guttering on
the main buildings.