Professional Documents
Culture Documents
Tripartite Progress Meeting Responses From MSR-Oct 20, 2023
Tripartite Progress Meeting Responses From MSR-Oct 20, 2023
Tripartite Progress Meeting Responses From MSR-Oct 20, 2023
1. INTRODUCTION
i. Contract Data
Contract Name: Construction Works of Soddo Junction (Dimtu) - Bilate Military Training Center
Road Project
Funding: The Government of the Federal Democratic Republic of Ethiopia
Project Location: SNNPRS, Wolayita Zone
Project Length: 70 Km (25km Main Road, 23 km Compound Road, Airfield 3.12 km Runway +
0.45 km Taxiway/est. 22 km)
Project Start & End Points: Dimtu Town (330 Km from Addis Ababa) and Bilate Military Training
Center
Design Standard: Upgrading to DC-5 AC Paved Road Functional Classification
Employer: Ethiopian Roads Administration
Engineer: Gondwana Engineering PLC in sub-consultancy with YLS Engineering PLC
Contractor: Powercon PLC
Resident Engineer – Tamrat Abera (FT) Structural Inspector – Yared Messele (FT)
D. Resident Engineer – Ashebir Tajebe (FT) Drafts Person – Eliyas Botola (FT)
P/Material Engineer – Bereket Yohannes (FT) Work Inspector (2) – Dejene Gizaw & Efrem Hailu
S. Quantity Surveyor – Recently Resigned (FT) (FT)
Senior Surveyor – Jibril Hussen (FT) Secretary – Lemlem Fisseha (FT)
RoW Mag. Specialist – Achenef Mariye (FT) Lab. Assistant (2) – Baye Tilahun & Musse
Gender Specialist - Yonas Besha (FT) K/Mandersso (FT)
Interm. P/ME – Dagmawi Yohannes (FT) Surveyor Ass. (4) – Nahom Million, Matiwos
Interm. Str. Eng. – Kirubel Temesgen (FT) Masre, Abayneh Milkessa & Melat Birhanu (FT)
Interm. H.Way Eng. Muluken Yirba – (FT) S. Highway Engineer – Daniel Legesse (Int)
Interm. Claim Exp. – Selamawit Amanuel (FT) S. Structural Engineer – Tezera Fikru (Int)
Interm. Environmentalist – Asasahegn Girma (FT) S. Geotechnical Engineer – To be Named (Int)
Interm. Quantity Sur. – Melaku Minda (FT) S. Claim Expert – Shawel Adal (Int)
Sur. (2)–Wondwossen Gobezie & Habtamu S. Environmentalist – Solomon T/Yohannes (Int)
Getie (FT) S. Hydrologist – Abiyu Darmulo (Int)
Lab.Tech. (2)– Eliyas Kedir & Olana Hailu (FT) S. Road Safety Specialist – To be Named (Int)
Material Inspector – Nebiyat Kedir (FT)
Page 1 of 13
b) Contractor’s Key Personnel Mobilization
Page 2 of 13
Reporting Month: October 2023
Equipment Description
Unit Planed Mobilized Active Shortage
Engineer’s Car No 9 9 9 -
Page 4 of 13
FINANCIAL ACCOMPLISHMENT
To date
Previous Month Previous Quarter
st
(Apr 14, 2022 to Oct
Description (Sept 2023) (1 Quarter of 2016 EFY)
20, 2023)
% ETB % Km % ETB
Plan (Master) 3.70% 69.38 9.01% 168.85 43.72% 819.59
Actual 1.06% 18.08 3.43% 58.50 19.83% 338.25
Actual/Plan (Master) (%) 28.65% 38.08% 45.36%
Airfield - Earthworks
Station
S. No. Work Description Side Remark
From To
3 Excavation Works
0+000 0+680 FW Completed
3.1 Removal of unsuitable material
1+740 2+000 FW Completed
0+680 1+400 FW Completed
3.2 Common Excavation
1+740 2+000 FW Completed
0+680 1+400 FW On progress
3.3 Hard Rock/Boulder Excavation
1+740 2+000 FW On progress
4 Final Subgrade
4.1 Subgrade Final Preparation 0+000 0+680 FW Not Completed
1+400 1+740 (-30,30)
FW Completed
2+000 2+080 LHS Completed
2+000 2+080 RHS Completed
2+080 2+200 LHS Completed
2+080 2+200 RHS Completed
Page 7 of 13
Airfield - Earthworks
2+200 2+300 FW Completed
2+300 2+600 LHS Completed
2+300 2+800 RHS Completed
2+600 2+800 LHS Completed
2+600 2+800 LHS Completed
5 Capping Layer
1+600 1+720 FW Completed
b) Pavement
Airfield - Pavement
Sub base layer placing Pilot stretch from Km 1+600 – 1+720 (-7.5, CL, 7.5)
Not Started yet.
Base Course Base course material has been produced about 8,450 m3 to
date.
Asphalt related works of any are not started yet.
Asphalt plant is not mobilized and commissioned yet.
Bituminous Surfacing
Bitumen is not procured.
Crushing of Asphalt aggregate is not started yet.
c) Drainage Structures
Page 8 of 13
Activity Station
Current Status Remarks
From To
- A total of 63 Minor Structures (MAR)
0+000 18+000 Not Yet Started
- A total of 53 PC, 10 SC/ BC
- 5 RCP locations are completed
18+000 22+500 On Progress - 48 RCP are not yet started.
Minor Drainage
- 12 SC/BC are not yet started.
(RCP, SC/BC)
- A total of 10 Minor Structures (8 RCP
and 2 SC/BC)
22+500 25+297 On progress
- 4 RCP locations completed
- 2 SC/BC locations not started yet
Secondary
Grouted Stone
0+000 3+300 Not Yet Started LHS
Pitched drain
(Runway)
Masonry Ditch
0+000 1+300 Not Yet Started RHS & LHS
(Runway)
Masonry Ditch
0+000 0+465 Not Yet Started RHS, LHS & Rear
(Apron)
Town Section
0+000 2+400 Not Yet Started Dimtu Town Section
U-Ditch
Village Section 8+300 10+300 Bilate Eta Village Section
U-Ditch Not Yet Started
14+000 14+900 Monopole Village Section
Military
Compound Road
U-Ditch 22+500 25+297 Not Yet Started RHS & LHS
(Extension of
MAR)
U-Ditch for
All Compound
Military Not Yet Started RHS & LHS
Roads
Compound Road
km 8+020-8+260 LHS, km 8+360-9+820
Secondary Main Access LHS, km 10+300-11+060 RHS, km 11+080-
Not Yet Started
Irrigation Canal Road 11+280 BHS, km 11+500-12+060 BHS, and
km 12+080-13+720 LHS
d) RoW Monitoring
Station Current Status Remarks
Page 9 of 13
From To
Public Utilities and Houses (Dimtu
0+007 0+640 Finalized
Town Section)
E-Pole at Monopol (14+000 to
0+640 25+297 Finalized
14+7000 Village not yet removed
E-Pole (0+000 to 0+500 not yet
Runway Finalized
removed)
E-Pole, Water Supply lines and
Compound Road Finalized
optic fibers along few segments
Page 10 of 13
f) Employment Opportunities:
Soddo Skilled 10 62 72 1 7 8 9 28 37 1 41 42
Junction
(Dimtu) - Semi-Skilled 42 105 147 0 0 0 41 50 91 1 55 56
1
Blate Military Unskilled 0 154 154 0 74 74 0 120 120 0 108 108
Training
Center Total 52 321 373 1 81 82 50 198 248 2 204 206
Page 11 of 13
7. OUTSTANDING ISSUES
i) Potential Delays, Early Warnings, Causes and Mitigation Measures
Shortage of resources (Earthmoving Machineries, Concrete Mixers, Cement, Fuel etc.)
To resume and improve daily production rate for the precast productions (RC Pipe, RC U-
Drain, Edge Cub Stone etc.)
Poor and unsustainable performance of the crusher plant and inadequate quarry
development.
Failure to start preparatory works for Asphalt Surfacing works (Bitumen supply, Asphalt
Plant Installation & Commissioning etc.)
Limitations in the provision of Laboratory Equipments and Engineer’s Facilities (Office &
Housing Furniture, Tools, Lab Equipments, Potable Water etc.)
Non-compliance on dust control and management of crusher site and access roads.
ii) Potential Variation or Claims Increase in Quantities, Early Warnings, Causes and
Mitigation Measures
Even though it will be identified after the consent from the Employer on the final
design review, the underlisted items could be the causes of cost variation or claims:
8. INFORMATION REQUIRED
Final design review has already submitted.
The Employer’s consent on the new MTC masterplan remains unclear.
Page 12 of 13
11. ENVIRONMENTAL & SOCIAL MANAGEMENT
Environmental and Social Management Plan, Preparation, management inspection
and audits.
Life training skills, HIV/STD awareness campaign and testing.
Page 13 of 13