Professional Documents
Culture Documents
1 s2.0 S1875510014002054 Main
1 s2.0 S1875510014002054 Main
a r t i c l e i n f o a b s t r a c t
Article history: Pipeline networks transmit gas between the source of natural gas and customers. The high cost of
Received 26 May 2014 transportation is a challenge that must be addressed to decrease costs. Optimizing transmission oper-
Received in revised form ations can decrease energy consumption in compressor stations of the network. Considering significant
13 July 2014
fuel consumption in network, the present study examined common methods of optimizing fuel
Accepted 14 July 2014
Available online 3 August 2014
consumption in gas transmission networks and then simulated a simple network model using Simone
simulation software. The theoretical effects of the methods were then applied to the National Iranian Gas
Network, which currently transfers gas using 65 compressor stations and 33,000 km of high pressure
Keywords:
Gas pipeline
pipeline. The methods studied were: use of maximum and balanced capacity of pipelines; adjusting the
Optimization optimum inlet pressure at city inlets, industries and power plants; use of appropriate connections to
Network operation assist gas transportation flow and decrease compressor load; and selecting appropriate numbers of
Simulation in-service compressors to handle the volume of gas transferred. Results indicate that substantial cost
Fuel consumption savings can be realized from the decrease in gas consumption of turbo-compressors that will also
postpone overhaul time by decreasing the hours of operation.
© 2014 Elsevier B.V. All rights reserved.
1. Introduction Most gas reserves are located in the southern portions of Iran,
with the exception of Khangiran field in northeastern Iran and
Natural gas is becoming one of the most widely used sources of several small fields in central and western Iran. The National Ira-
energy in the world due to it's low price and environmental friendly nian Gas Company yearly transmits 170 billion m3 of natural gas
characteristics. from gas plants in southern Iran to consumers across the country
Based on latest BP review, Iran, Russia and Qatar hold around using 33,000 km of pipeline and 65 gas stations housing 233 turbo-
half of the worlds proved gas reservoirs (British Petroleum, 2014). compressor units. The main sources of consumption are:
Estimations indicate that Iran owns 16.8% of global gas reservoirs
which is the largest one. Residences, retail businesses, and small industry
Usually the location of natural gas resources and the place Power plants
where the gas needed for various applications are far apart. In order Large industry
to overcome the problem of long distance two common ways are Injection into oil reservoirs or gas storage
widely suggested: The application of pipeline networks and Liq- Export.
uefied Natural Gas (LNG). As reported in Ibrahim et al. (2000), short
distances gas transportation by pipelines is more economical than Fig. 1 shows that most gas is used in residences, retail busi-
LNG transportation. In this work pipeline networks are chosen. nesses, and small industry (>50%). Large industry and power plants
are the next largest users.
Residences, retail businesses, and small industry show different
* Corresponding author. Department of Chemical Engineering, Faculty of Tech- patterns of usage than the other consumers. For example, con-
nology and Engineering, Tarbiat Modares University, Tehran, Iran. Fax: þ98 21 sumption increases from 110 MMSCMD in summer to
82883314.
450 MMSCMD in winter in response to the need for heating. By
E-mail addresses: m.fasihizadeh@modares.ac.ir, maryam_fasihizadeh@yahoo.
com (M. Fasihizadeh), vafaiesm@modares.ac.ir (M.V. Sefti), torbati@nigc.ir contrast, peak consumption for power plants is in summer, when
(H.M. Torbati). power is needed for cooling systems; consumption by power plants
http://dx.doi.org/10.1016/j.jngse.2014.07.018
1875-5100/© 2014 Elsevier B.V. All rights reserved.
320 M. Fasihizadeh et al. / Journal of Natural Gas Science and Engineering 20 (2014) 319e327
The software solution was investigated in the present study editing environment. Scenarios are then defined for each condition
because it does not require installation of additional equipment. using the modeling assumptions.
The optimization of pipeline network has been interesting for It is necessary to mention that simulation has been done to
many researchers using numerical and analytical calculations present effects of arrangement changes on fuel and power con-
based on the type of problem. These studies differ in decision sumption of turbo compressors and also correctness of recom-
setting and physical models. Optimization of gas pipeline can be mended methods performance.
done statically or dynamically. Optimization models for mid-term In the present study, objective function includes fuel and power
planning and contracting purpose do not require dynamics infor- consumption of turbo compressors and line pack fluctuations have
mation so steady state model are appropriate. For real time oper- not been considered due to following reasons:
ations, system dynamics must be captured in order to ensure
feasible and implementable policies (Zavala, 2014). Tabkhi classi- Line pack volume is related to fuel gas consumption.
fied several types of pipeline network optimization methods Line pack volume of Iran network has no considerable fluctua-
(Tabkhi, 2007). tion in warm and mild seasons, consumption in residence and
The proposed plans are defined as steady state model and retail business is nearly constant, and other sections such as
classified by the operational constraints listed above. Simulations power plants and large industries don't face with unpredictable
are then carried out to test the feasibility of implementation. changes.
Practical examples were tested using Simone pipeline simulation As network and line pack volume are very large, small changes
software to evaluate the impact of methods on the network. in gas consumption managed by pack line volume.
Simulation has contributed significant achievements in Scenario 1: All compressors on both pipelines are operating and
analyzing the pipeline network problems (Hoeven, 2003). Pipeline all interconnections are closed (Fig. 3).
simulation is used to determine the design and operating variables
of the pipeline network for various configuration (Woldeyohannes 3.3. Optimizing fuel consumption
and Abd Majid, 2011).
Using the simulation software, the simple network is mapped in The methods proposed to optimize fuel consumption in the gas
the edit section and different scenarios are defined in the run transmission network are:
environment. The program is executed bearing in mind the
following modeling assumptions for the gas transmission network: Use the potential and maximum capacity of the pipelines
Adjust the optimum inlet pressure at the city inlets and for in-
Compressors are located at 140 km intervals dustry and power plants
Network inlet gas pressure (from source) is 1050 psia Use the appropriate interconnections to assist gas flow and
Minimum suction pressure is 700 psia decrease compressor loads
Maximum discharge pressure is 1050 psia Select the appropriate number of in-service compressors
Pipeline roughness is 0.0007 inch (to calculate pressure)
Gas velocity in the pipeline is <13 m/s
Minimum suction pressure of gas compressors and maximum
3.3.1. Maximum and balanced capacity of pipelines
gas velocity in the pipeline reflect actual conditions
Optimal use of potential pipeline capacity for gas transmission
An average efficiency has been used for simulating turbo
increases the useful lifetime of equipment by decreasing the load
compressors
and the in-service time, which decreases fuel and power con-
sumption at the gas compressor stations. The effect of symmetric
After running the program, modeling results are examined as
distribution of compressors on network performance is checked for
tables and graphs. The most important results are values for vol-
3 scenarios:
ume of gas transferred, pressure at the end of the pipeline,
compressor power and fuel consumption, compressor suction
Scenario 1: All compressors on one pipeline work and those on
pressure and gas velocity.
the other pipeline are bypassed. Power consumption is
184.1 MW and fuel consumption is 1.55 MMSCMD to transfer
3.1. Simulation stages 127 MMSCMD of natural gas (Fig. 4).
Scenario 2: Assume a symmetric arrangement for both pipelines
3.1.1. Using Simone simulation software for simulation using 4 compressors. Power consumption is 111 MW, fuel con-
Case study simulations: Two 700 km parallel connected pipelines sumption is 0.94 MMSCMD, and pressure at the end of the
with compressors installed at 140 km intervals are mapped in the network is 700 psia (Fig. 5).
Scenario 3: Assume a symmetric arrangement for the two pressure must decrease at the city gate stations. It is clear that large
pipelines. Power consumption is 96 MW, fuel consumption is differential pressure between the pipeline and the desirable user
0.81 MMSCMD, and pressure at the end of the network is pressure is a source of energy loss. At some stations, energy loss can
700 psia (Fig. 6). be decreased using throttling valves instead of expansion turbines;
this is not discussed here because such a project required instal-
The results of these evaluations indicate that a considerable lation of additional equipment.
decrease in fuel and power consumption occurs when the com- Fixed positions are assumed for all consumers and gas stations,
pressors are symmetrically distributed between the two pipelines so that network energy consumption can be optimized by changing
(scenarios 2 and 3) over the conditions in scenario 1. It is also clear the arrangement of the compressors so that pressure decreases
that different options may exist to arrange the symmetry. Scenario before it reaches the delivery point. To test this assumption, two
3 was found to consume the least fuel and power of the three hypothetical consumers are added to the network and two sce-
choices. narios using the same number of compressors with different con-
figurations were tested. To achieve comparable results, symmetry
3.3.2. Providing and adjusting optimum inlet pressure for cities, was assumed and the pressure remained unchanged at the end of
industry and power plants the network at 700 psia.
The main goal in such a complicated network is to be able to
transfer gas under adequate pressure to the end of the network. Scenario 1: Higher pressure (917 psia) is maintained at the
Consumers along the line (cities, major industry and power plants) branch delivery points placed beyond the in-service compres-
require a number of branches from the high pressure pipelines. sors. To transfer 140 MMSCMD of gas to the end of the network
When entering the distribution system from the pipeline, gas requires 124 MW of power and 1.05 MMSCMD of fuel (Fig. 7).
Scenario 2: Lower pressure is achieved at one branch by Three scenarios are designed to test the effects of in-
changing the arrangement of the compressors at delivery points terconnections on the network for two consumers.
located beyond the by-passed compressors. To transfer
140 MMSCMD of gas to end of the network, 122 MW of power Scenario 1: All interconnections are closed and the gas flows in
and 1.03 MMSCMD of fuel is needed (Fig. 8). two independent parallel pipelines. Study of possible
compressor arrangements requiring minimum power indicates
The results showed that a proper compressor arrangement that 3 compressors should be by-passed (nos. 3, 4, 8). Using
produces lower pressure at the branches and decreases pressure 113 MW of power and 0.95 MMSCMD of fuel, 150 MMSCMD of
loss. Although, power and fuel consumption decrease slightly, the gas can be transmitted to the network end point (Fig. 9).
overall effect is considerable for an extended network with many Scenario 2: Open two interconnections between the inlets of
consumers, such as the Iranian Gas Trunk. compressors 3 and 7 (valve no. 5), which decreases power
consumption about 2 MW. Fuel consumption is 0.93 MMSCMD.
Scenario 3: The interconnections between inlets of compressors
2 and 6 (valve no. 3) and 3 and 7 (valve no. 5) are opened. Power
3.3.3. Use of appropriate interconnections to decrease compressors consumption decreases about 10 MWe101 MW. Fuel con-
load sumption decreases to 0.85 MMSCMD and pressure at the
Many interconnections exist along the pipelines as branching to network end point remains unchanged (Table 1).
users occurs. Effective use of the interconnections can improve
network efficiency. Improper use of interconnections can decrease Evaluation of results indicates that scenario 3 has a positive
efficiency and increase energy loss; thus, selecting appropriate ar- effect on decreasing energy consumption (power and fuel). Open-
rangements for interconnections (closing and opening) under ing some interconnections, such as the ones between inlets of
different operational conditions, especially for sudden changes in compressors 1 and 5, has no effect on the network. Appropriate
pressure, is a major function of network optimization management. opening of interconnections can decrease power and fuel con-
The following are assumed: sumption, but improper openings can increase power consumption
and cause flow to recycle back into the pipeline. For example, when
Network inlet flow is 150 MMSCMD parallel compressors exist and one is open while the other is by-
The size of deliveries is 23 and 25 MMSCMD passed, the discharge interconnection should not be opened
Network outlet flow is 101 MMSCMD because recycling will occur.
Table 1
Different scenario for using of appropriate interconnections.
Scenario no. 1-3 Closed Closed Closed Closed Closed Closed 900 885 113 0.95
Scenario no. 2-3 Closed Closed Closed Closed Open Closed 832 871 111 0.93
Scenario no. 3-3 Closed Closed Open Closed Open Closed 880 870 101 0.85
3.3.4. Selecting proper number of compressors for network reducing the number of compressors in service did not produce
All compressors should be in service to maintain the network in optimal conditions. Scenario 2 was defined as a means of com-
operational condition and maintain flow. In the simulated network, parison. A comparison of the two scenarios shows that using fewer
the maximum allowable flow is 179 MMSCMD, fuel consumption is compressors and maintaining desirable pressure at the end of
3.3 MMSCMD, and power consumption is 388.1 MW. network in scenario 2 increased the load on the other in-service
It is not necessary for all compressors to operate continually compressors and increased the total power consumed, which are
when the transfer flow is low. Deciding which compressors should not optimal conditions. This suggests that choosing the appropriate
be operational depends on the amount that power and fuel con- number of in-service compressors should consider all operational
sumption can be decreased while respecting network constraints. To aspects.
test this hypothesis in the simulated network, inlet gas was
decreased from its maximum flow of 179 MMSCMDe150 MMSCMD. 4. Optimizing Iranian gas transmission network
At this rate, it is not necessary for all compressors to be in service; by
keeping operational conditions constant, new scenarios can be After evaluating simulation outputs and verifying accuracy of
defined. these methods using simulation algorithms, different methods
applied for Iranian gas transmission network for two years, sepa-
Scenario 1: 7 compressors remain in service to transfer gas using rately and in combination.
188 MW of power and 1.6 MMSCMD of fuel to obtain 700 psia of Before applying each one of recommended methods, facing any
pressure at the end of the network (Fig. 10). problem originated from network managing decisions prevented
Scenario 2: 6 compressors remain in service using 214 MW of by getting exact information about production and consumption
power and 1.8 MMSCMD of fuel with the pressure remaining plans in the near future. Then appropriate arrangement selected
unchanged at the end of the network (Fig. 11). using mentioned rules. After that Simone software utilized for
evaluating it and at last, recommendations implied in network by
The results indicate that decreasing the transfer flow in Scenario dispatching control center after informing different network
1 eliminates the need for all compressors to be in service; however, disciplines.
It is necessary to mention that according to last published sta- The average amount of gas transmitted (ðQ Þnetwork ) is multiplied
tistics, Iran Network transferred about 600 MMSCMD in 2013 from by the average length of the network (ðLÞnetwork ) and
gas plants to different consumers, while line pack been about ðQ Þnetwork ðLÞnetwork is compared for different months. This was
1,000,000,000 MMSCMD, so instantaneous fluctuations in pro- carried out for three years (2009 through 2011) (Fig. 12).
duction or consumption neutralized and do not have considerable Fig. 12 shows that the amount of gas transmitted over 1000 km
effect on the number of gas compressor stations and network of pipeline increased and that network capacity in 2011 was greater
arrangement. than for 2009.
In addition, as arrangement changes are done consciously Fig. 13 shows that, despite the 8.4% increase in network trans-
and considering overhaul plans and last for two or three weeks, mission potential in 2010 over 2009, fuel consumption per
there is no need to shut down and start up compressors 1 MMSCMD of transferred gas and the hours of operation
continuously and consequently, no more cost should be paid by decreased. It is clear that the recommended guidelines were useful
network. and that results further improved in 2011. The amount of gas
Results compared for fuel consumption and average amount of transmitted in 2011 increased by about 12.4% although the fuel
gas transmitted. Real data used for regional gas transmission. It is consumption per 1 MMSCMD of gas transferred and hours of
daily mean value for different months from 2009 to 2011 were: operation decreased (Table 2).
Observed differences in results can be interpreted as following:
Power consumption and operational hours for turbo compres- Iranian gas network changed from production and consumption
sors at gas stations point of view in 2011 in comparison with 2010 as some new turbo
Fuel consumption at stations compressors and pipelines added to network, however, new facil-
Volume of gas transmitted and consumed and the balance of ities are negligible when compared to whole network.
production versus consumption for each region In addition, generally, number and duration of overhauls for
Length of the trunk line pipelines and gas compressor stations are different in various years.
Fig. 13. Amount of gas transmitted, fuel consumed, and hours of operation of compressors in 2009e2011.
Fuel gas consumption in compressor station Ibrahim, H., Bin Yaman, A.S., Thanh Lien, T., Budi Santoso, I., Laothumthut, P., 2000.
Natural Gas Pipeline Development in South East Asia. Asia Pacific Energy
m/s meter per second (velocity unit)
Research Center, Tokyo.
MW mega watt (power unit) Rios-Mercado, R.Z., Kim, S., Boyd, E.A., 2006. Efficient operation of natural gas
transmission systems: a network based heuristic for cyclic structures. Comput.
Operat. Res. 33, 2323e2351.
References Tabkhi, F., 2007. Optimization of Gas Transmission Networks (Ph.D. thesis). INPT.
Woldeyohannes, A.D., Abd Majid, M.A., 2011. Simulation model for natural gas
transmission pipeline network system. Simul. Model. Pract. Theory 19,
Borraz-Sa nchez, C., Rios-Mercado, R.Z., 2005. A hybrid metha-heuristic approach for
196e212.
natural gas pipeline network optimization. In: Hybrid Metha Heuristics. Wu, S., Rios-Mercado, R.Z., Boyd, E.A., Scott, L.R., 2000. Model relaxations for the
Springer, pp. 54e65. fuel cost minimization of steady-state gas pipeline networks. Math. Comput.
British Petroleum (BP), June 2014. Statistical Review of World Energy. David Wood Model. 31, 197e220.
& Associates. http://www.bp.com/statisticalreview. Zavala, V.M., 2014. Stochastic optimal control model for natural gas networks.
Hoeven, T.V.D., 2003. Constrained network simulation. In: The 35th Annual Meeting Comput. Chem. Eng. 64, 103e113.
of Pipeline Simulation Interest Group (PSIG). Bern, Switzerland.