Professional Documents
Culture Documents
Risk - ICE
Risk - ICE
infrastructure projects
Dr Chris Bridges CEng FICE
(chris.bridges@smec.com)
19 November 2020
1
• https://australiangeomechanics.org/chapter/queensland/
2
Contents
• Introduction
• Understanding
• Impacts
• Recommendations
3
Introduction
4
Geotechnical engineering
Introduction
5
Geotechnical engineering
Introduction
6
What is risk?
“Risk is like love: we all know what it is, but we don’t know how to define it”
(Joseph Stiglitz quoted in (Nguyen, 2007))
RISK = LIKELIHOOD x CONSEQUENCE
“……the fear of an evil ought to be proportionate, not only to its magnitude,
but also to its probability…”.
(from 1662 by Arnaud (Arnaud, 1850))
Introduction
7
Higher Risk
Introduction
8
Understanding
9
Civil engineers do not understand
geotechnical engineering
“The major part of the college training of civil engineers consists in the
absorption of the laws and rules which apply to relatively simple and
well-defined materials, such as steel or concrete. This type of education
breeds the illusion that everything connected with engineering should
and can be computed on the basis of a priori assumptions.
Unfortunately, soils are made by nature and not by man, and the
products of nature are always complex.”
(Terzaghi, 1936)
Understanding
10
This lack of understanding continues today
(Kajastie, 2020)
Understanding
11
A lack of appreciation of geotechnical risks
Project Management High level risks –
(General Geotechnical Risks) General lack of
appreciation of
geotechnical risks – i.e
Line Management of Different Project Risks
restrict geotechnical
budget
Specific Geotechnical Risks
Specific risks
Team
Contractural Technical Leadership and
Experience
Material
Geological Engineering
Properties
(Baynes, 2010)
Understanding
12
Poor investment in investigation can have
impacts 180
160
As-built construction cost as % of engineers
140
120
100
80
60
40
20
0
0 2 4 6 8 10 12
Investigation cost as % of construction cost (excludes variations)
Material
Geological Engineering
Properties
(Baynes, 2010)
Understanding
14
Contractual risks are the foundations
for poor project performance
Contractual
Man
Sup
• Risk transfer SC
• GBR - Crossrail
Organization
PC
Cons
0 10 20 30 40 50 60 70 80 90 100
Percentage Risk Allocation
Cl = client; PM = project manager; Cons = consultants; PC = primary contractor; (Loosemore & McCarthy, 2008)
SC = subcontractor; Sup = supplier; and Man = manufacturer
Understanding
15
Different parties to a contract view risks
differently
(Lo, Fung, & Tung, 2006 - Construction Delays in Hong Kong Civil Engineering Projects)
Understanding
18
Team risks are often forgotten Hydraulics/
Hydrology -
parameters for
scour
assessment,
climate change, Environmental -
Site
flooding acid sulfate soils,
Investigation
Team
contaminated
Contractor -
land, cultural
ground
heritage,
investigation
sensitive areas,
data
sustainability
• Leadership
• Availability Alignment -
Shallow in cuts
to avoid blasting, Contractor -
low constructability,
cut/fill balance
Manager
Independent
Structures -
Verifier /
earth pressures /
Independent
foundation
Checking
parameters,
Engineer -
retaining wall
design
and foundation
verification &
design
compliance
Client - design
life,
Pavement -
maintenance,
subgrade
compliance,
properties,
whole-of-life
expansive soils
cost,
stakeholders 19
Geological risks are often considered as
the main geotechnical risks
• groundwater • strength and stiffness
• geological features • anthropogenic materials
• compressible soils • geomorphology and landform
• unstable slopes • problem soils
Understanding
20
Material properties are critical to design
Undrained shear strength (kPa)
0 20 40 60 80
0
-5
-10
-20
-25
-30
-35
-40
Range of interpretations
-5
-10
-20
-25
-30
-35
-40
Understanding
23
Can we be sure of the data we receive
Understanding
25
Understand its reliability
“Every experienced contractor knows that ground investigations can
only be 100% accurate in the precise locations in which they are carried
out. It is for an experienced contractor to fill in the gaps and take an
informed decision as to what the likely conditions would be overall”.
(Mr Justice Coulson (Van Oord UK Ltd & Anor v Allseas UK Ltd, 2015))
Understanding
26
Don’t believe all you see
Understanding
27
28
Understand the scale of your
information
Understanding
29
Understand the scale of your
information
30
Understand the limits of your analysis
1297kN
734kN
Sieffert & Bay-Gress (2000) Comparison of European bearing capacity calculation methods for shallow
foundations Proc. Instn Civ. Engrs Geotech. Engng, 143, 65-74 Understanding
31
Understand the limits of your analysis
Bad (>150)
Good (105-115)
Bearing - 66% Poor / Bad
Within 25% Settlement - 90% Poor / Bad
Excellent (95-105) of the answer
Good (85-95)
Fair (75-85)
Poor (50-75)
Under-estimate
Bad (<50)
0 2 4 6 8 10 12 14
(Morgenstern, 2000)
Understanding
32
DESIGN ELEMENT UNDER DESIGN OVER DESIGN ACCEPTABLE REFERENCE
SETTLEMENT AT FAILURE
4/8 43 / 86 3/6
SHALLOW FOUNDATION ON SAND: (Morgenstern,
BEARING CAPACITY 10 / 34 9 / 31 10 / 34 2000)
SETTLEMENT
18 / 58 10 / 32.3 3 / 9.7
EMBANKMENT COLLAPSE HEIGHT 21 / 48.8 4 / 9.3 18 / 41.9 (Morgenstern,
2000)
EMBANKMENT ON SOFT GROUND, (Kelly et al., 2018)
SETTLEMENT WITH TIME: 106 DAYS 15 / 44 4 / 12 15 / 44
1095 DAYS
17 / 55 1/3 13 / 42 33
Impacts
34
Geotechnical risks cause project impacts
GEOTECHNICAL CAUSE RANK RANK
1.2
(COST IMPACTS) (DELAY IMPACTS)
Lack of sufficient boring locations 1 1
38.3
Misclassified / mischaracterized 2 2
60.5
soils
Cost overrun (%) Higher groundwater table than 3 3
expected
Negative No impact Positive Dewatering due to seepage 4 3
Design changes to 4 2
2.5
superstructure
Prescribed soil treatment not 5 4
36.7 suitable
Variation of piling quantities due 5 3
60.8
to wrong pile type
Schedule overrun (%)
Mismatch in pile quantities 6 5
Negative No impact Positive Erosion and sediment control 7 6
(Marr, 2019)
Impacts
36
Case study literature
Impacts
37
Mistakes can be expensive
Impacts
39
Settlement at Camborne House
exceeded predicted settlement
(9mm) after only concourse
tunnel completed by about
20mm.
40
41
42
The findings
• lack of on-site NATM authority at Heathrow
• lack of experience among the field engineers, the tunnelling foremen
and the crews – design did not take this into account – poor
workmanship an issue
• lack of full-time geologists within an NATM supervision team
• Contractors geotechnical sub-contractor not kept in the loop
• Instrumentation - limited data available, poor quality, serious
omissions, "inadequate" computer software
• there was still enough data available to see what was happening
Impacts
43
Mistakes can be expensive
• Contractor fined £1.2M + £100k costs (contract value £60M)
• Recovery took nearly two years and cost around £150M - nearly
three times the cost of the original contract
Impacts
44
……and embarrassing
(Anon, 2020)
Impacts
45
Recommendations
46
• Project details - scope, alignment etc
• Desk study, historical records etc.
Establishing
the Context • Site investigation data
47
In developing solutions and presenting
these to our clients we must be aware of
the limitations
• Investigations sample a very small amount of the site
• Engineers can derive a range of interpretations for a single set of test data
• Software outputs are only as good as the information we put in and need to be checked against what
we consider to be reasonable
• Team leadership and inexperience can seriously affect project outcomes and magnify the likely risks
Recommendations
48
Geotechnical engineers should be
• Engaging senior professionals early as possible in the project
• Using independent reviewers or verifiers
• Communicating and building relationships with the various parties and stakeholders (establishing
trust) as early as possible
• Adopting procedures based on precedence so that methods of analysis etc. are the same for each
project i.e. Department of Transport and Main Roads (2015) and United States Army Corps of
Engineers (2003)
• Explaining the design and design intent to the relevant site engineers prior to construction,
including likely risks and uncertainty
chris.bridges@smec.com
Bridges, C.A. (2019) Geotechnical risk: it’s not only the ground. Australian Geomechanics Recommendations
54(1) 27-38 50
References
• Anon. (2020). Piling design error leads to Sheffield building demolition. Ground Engineering(October), 6.
• Arnaud, A. (1850). Logic, or the Art of Thinking being the Port-Royal Logic (Translated from the French by Baynes) (T. S. Baynes, Trans.).
Edinburgh, UK: Sutherland and Knox.
• Baynes, F. J. (2010). Sources of geotechnical risk. Quarterly Journal of Engineering Geology and Hydrogeology, 43, 321-331.
• Bond, A., & Harris, A. (2008). Decoding Eurocode 7. Abingdon, UK: Taylor & Francis.
• Bridges, C. (2019). Geotechnical risk: it's not only the ground. Australian Geomechanics, 54(1), 27-38.
• Buxton, J. A., Henry, B., Crabtree, A., Waheed, A., & Coulthart, M. (2011). Using qualitative methods to investigate risk perception of
Canadian medical laboratory workers in relation to current prion disease infection control policies. Journal of Toxicology and Environmental
Health, Part A, 74, 241-247.
• Castro-Nova, I., Gad, G. M., Touran, A., Cetin, B., & Gransberg, D. D. (2018). Evaluating the Influence of Differing Geotechnical Risk
Perceptions on Design-Build Highway Projects. ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering,
4(4). doi:10.1061/AJRUA6.0000993
• Committee of Inquiry. (2005). Report of the Committee of Inquiry into the Incident at the MRT Circle Line workste that led to the collapse of
the Nicoll Highway on 20 April 2004 (Volume 1 (Part I)).
• Douglas, M. (1970). Natural symbols: explorations in cosmology. London, UK: Barrie & Rockliff.
51
References
• Kahan, D. M., Braman, D., Slovic, P., Gastil, J., & Cohen, G. (2007). The Second National Risk and Culture Study: Making Sense of - and
Making Progress In - the American Culture War of Fact. Retrieved from New Haven, Connecticut, USA:
• Kajastie, N. (2020). Covid issues mask other concerns. Ground Engineering(October ), 3.
• Kasperson, R. E. (2012). A Perspective on the Social Amplification of Risk. The Bridge, 42(3), 23-27.
• Lo, D. O. K., & Cheung, W. M. (2005). Assessment of landslide risk of man-made slopes in Hong Kong (GEO Report No. 177). Retrieved from
Hong Kong Special Administrative Region, PRC:
• Lo, T. Y., Fung, I. W. H., & Tung, K. C. F. (2006). Construction Delays in Hong Kong Civil Engineering Projects. Journal of Construction
Engineering and Management, 132(6), 636-649. doi:10.1061/ASCE0733-93642006132:6636
• Loosemore, M., & McCarthy, C. S. (2008). Perceptions of Contractual Risk Allocation in Construction Supply Chains. Journal of Professional
Issues in Engineering Education and Practice, 134(1), 95-105.
• Marsden, E. (2017, 31 July 2017). Risk perception. Retrieved from https://risk-engineering.org/static/PDF/slides-risk-perception.pdf
• Morgenstern, N. R. (2000). Performance in Geotechnical Practice. Paper presented at the The Inaugural Lumb Lecture, Hong Kong.
• National Research Council. (1984). Geotechnical Site Investigations for Underground Projects: Volume 1: Overview of Practice and Legal
Issues, Evaluation of Cases, Conclusions and Recommendations. Retrieved from Washington, DC, USA:
• Nguyen, N. C. (2007). Risk management strategies and decision support tools for dry land farmers in southwest Queensland. Australia.
(PhD), University of Queensland, Gatton. Queensland. Australia.
52
References
• Peracha, Q., & Pengelly, E. (2020, 27 Jan 2020). The day tunnels below Heathrow collapsed and created giant crater between runways.
Retrieved from https://www.getsurrey.co.uk/news/surrey-news/day-tunnels-below-heathrow-collapsed-17601515
• Sbaraini, A., Carter, S. M., Evans, R. W., & Blinkhorn, A. (2011). How to do a grounded theory study: a worked example of a study of dental
practices. BMC Medical Research Methodology, 11(128). doi:https://doi.org/10.1186/1471-2288-11-128
• Slovic, P., Fischhoff, B., & Lichtenstein, S. (1979). Rating the Risks. Environment, 21(3), 14-39.
• Smith, C. (2018, 13 June 2018). HS2 £1bn over target costs following geotechnical risk warning. Retrieved from
https://www.geplus.co.uk/news/hs2-1bn-over-target-costs-following-geotechnical-risk-warning-13-06-2018/
• Smith, C. (2019). HS2 plans to reduce ground risk cost described as “carnage”. Retrieved from https://www.geplus.co.uk/news/hs2-plans-to-
reduce-ground-risk-cost-described-as-carnage-28-01-2019
• Willingham, R. (2019, 9 December 2019). Melbourne Metro Tunnel project grinds to a halt amid dispute over deadlines and costs. Retrieved
from https://www.abc.net.au/news/2019-12-09/melbourne-metro-tunnel-project-grinds-to-halt-amid-dispute/11779986
53
Appendices
54
Driven Steel Pile
Total Capacity (kN)
Bad (>150)
Base Capacity (kN)
Fair (115-125)
Accuracy of Prediction (%)
Poor (50-75)
Under estimate
Bad (<50)
0 2 4 6 8 10 12
Number of Predictions
55
Jet Grouted Pile
Bad (>150)
0 1 2 3 4 5 6 7 8 9 10
Number of Predictions
56
Embankment Collapse Height
Bad (>150)
Poor (125-150)
Non-conservative
Fair (115-125)
Accuracy of Prediction (%)
Muar Embankment
Good (105-115) Prediction Competition
60% Poor / Bad – majority
on the conservative side of
Excellent (95-105) MIT Embankment prediction
Prediction Competition
Good (85-95)
Fair (75-85)
Poor (50-75)
Bad (<50)
Conservative
0 2 4 6 8 10 12 14 16
Number of Predictions
57