JV CGCOC GROUP CO.

LTD AND YUEYANG CONSTRUCTION ENGINEERING GROUP CO, LTD


CONSTRUCTION OF KITIME SUB-CATCHMENT PRIMARY, SECONDARY AND TERTIARY SEWER NETWORK CONSTRUCTION-LOT I
Master Work Program
Analysis of Available Working Days of Project Calander

Commencement Date 2-Sep-23


Time for Completion 1-Sep-25

Descriptions
No. Time /Period in Months
Available Holidays during Available Sundays during Estimated Rainy Available Working Available Working
Available Calendar Days
the working period the working period Days Days Hours
1 September-23 28.00 3.00 4.00 9.00 12.00 96.00
2 October-23 31.00 - 5.00 - 26.00 208.00
3 November-23 30.00 - 4.00 - 26.00 208.00
4 December-23 31.00 - 5.00 - 26.00 208.00
5 January-24 31.00 2.00 4.00 - 25.00 200.00
6 February-24 29.00 - 4.00 - 25.00 200.00
7 March-24 31.00 1.00 5.00 - 25.00 200.00
8 April-24 30.00 1.00 4.00 6.00 19.00 152.00
9 May-24 31.00 4.00 4.00 10.00 13.00 104.00
10 June-24 30.00 1.00 5.00 9.00 15.00 120.00
11 July-24 31.00 - 4.00 14.00 13.00 104.00
12 August-24 31.00 3.00 4.00 19.00 5.00 40.00
13 September-24 30.00 3.00 5.00 9.00 13.00 104.00
14 October-24 31.00 - 4.00 - 27.00 216.00
15 November-24 30.00 - 4.00 - 26.00 208.00
16 December-24 31.00 - 5.00 - 26.00 208.00
17 January-25 31.00 2.00 4.00 - 25.00 200.00
18 February-25 28.00 - 4.00 - 24.00 192.00
19 March-25 31.00 2.00 5.00 - 24.00 192.00
20 April-25 30.00 2.00 4.00 6.00 18.00 144.00
21 May-25 31.00 3.00 4.00 10.00 14.00 112.00
22 June-25 30.00 1.00 5.00 9.00 15.00 120.00
23 July-25 31.00 - 4.00 14.00 13.00 104.00
24 August-25 31.00 - 5.00 19.00 7.00 56.00
25 September-25 1.00 - - 1.00 - -
Total 730.00 28.00 105.00 135.00 462.00 3,696.00