Professional Documents
Culture Documents
Palanguia Pow
Palanguia Pow
Date: 1-Mar-19
Name of Project: CONCRETING OF BARANGAY ROAD
Scheme of Work: Project Billboard/Signboard,
Location of Project: Brgy. Palanguia, Pototan, Iloilo Mobilization/Demobilization, Subgrade Preparation
Appropriation : P 3,970,000.00 Aggregate SubBase Course, Portland Cement Concrete
Appropriation Act: For Funding Pavement (Unreinforced);0.20m thk.
Station Limits: 0+000.00 - 0+286.00
0+000.00 - 0+165.00
Length = 451.00 l.m.
Project No.:
Desirable Starting Date:
Type of Work to be Constructed % OF TOTAL
No. of Working Days to Complete:
I Project Billboard / Signboard P 14,489.00 0.47% Manpower/Equipment Requirements
II Mobilization/Demobilization P 30,366.52 0.99% 1 Project Engr
III Subgrade Preparation P 67,076.00 2.18% 2 Foreman
IV Aggregate SubBase Course P 794,658.00 25.79% 3 Masons
V Portland Cement Concrete Pavement (Unreinforced); 0.20m thk. P 2,174,917.70 70.58% 4 Laborer
5 Carpenter
6 Heavy Equipment Prime Mover
7 Dump Truck
8 Motorized Road Grader
9 Vibratory Roller
10 Water Truck
11 Concrete Vibrator
12 Concrete Screeder
13 Concrete Saw
TOTAL P 3,081,507.22 100.00%
DETAILED ESTIMATE OF PROPOSED WORK
SPEC'S. ITEM NO. DESCRIPTION Unit Qty. Unit Cost Total Cost
1 B.5 Project Billboard / Signboard each 2.00 7,244.50 14,489.00
2 B.9 Mobilization/Demobilization l.s. 1.00 30,366.52 30,366.52
3 105(1) Subgrade Preparation sq.m. 2,902.00 23.11 67,076.00
4 200(1) Aggregate SubBase Course cu.m 688.64 1,153.95 794,658.00
5 311(1)b1 Portland Cement Concrete Pavement (Unreinforced); 0.20m thk. sq.m. 2,000.00 1,087.46 2,174,917.70
BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL Sub TOTAL 3,081,507.22
1. Labor (______) Man-Days 64,324.00 1.62%
Total Direct Cost 3,081,507.22
2. Materials 2,654,243.00 66.86%
3. Rentals of Equipment 362,940.22 9.14% OCM 394,331.09
4. Fuels,Oils, and Spare Parts
5. Mob. & Demob. Cont. Profit 305,114.07
6. Admin Cost Cont. Tax 189,047.62
7. OCM 394,331.09 9.93% Engineering
8. Cont. Profit 305,114.07 7.69% Admin Cost
9. Cont. Tax 189,047.62 4.76%
Total Estimated Cost
10. Engineering 3,970,000.00
TOTAL 3,970,000.00 100.00%
POW Page 1 of 44
JEB A. ESCARILLA, MPA ATTY. DENNIS T. VENTILACION
Title: Engineer IV Acting Provincial Administrator
POW Page 2 of 44
APPROVED BUDGET FOR THE CONTRACT
CONCRETING OF BARANGAY ROAD
Brgy. Palanguia, Pototan, Iloilo
B.5 Project Billboard / Signboard 2.00 each 14,489.00 1,872.57 1,448.90 22.92%
200(1) Aggregate SubBase Course 688.64 cu.m 794,658.00 102,702.03 79,465.80 22.92%
ABC Page 3 of 44
D BUDGET FOR THE CONTRACT
CRETING OF BARANGAY ROAD
rgy. Palanguia, Pototan, Iloilo
ABC Page 4 of 44
Province of Iloilo
DETAILED UNIT PRICE ANALYSIS (DUPA)
No.of No. of
Designation Daily Rate Amount
Person Days
1. Labor
Sub-Total for 2
Item B.5 5 of 44
Province of Iloilo
DETAILED UNIT PRICE ANALYSIS (DUPA)
No.of No. of
Designation Daily Rate Amount
Person Days
1. Labor
Total Man-days
Sub-Total for 1 ₱ -
No.of No. of
Name and Capacity Daily Rate Amount
Units Days
2. Equipment
3. Materials
Sub-Total for 3 ₱ -
Total Direct Cost ₱ 102,720.00
OCM 12.92%
Contractor's Profit 10.00%
VAT 5.00% ₱ 1,518.33
1% of CIVIL WORKS EDC ₱ 30,366.52
Total Cost DC>1% Civil Works EDC, USE 1% of Civil Works EDC ₱ 31,884.84
Total Unit Cost ₱ 31,884.84
Item B.9 6 of 44
Province of Iloilo
DETAILED UNIT PRICE ANALYSIS (DUPA)
No.of No. of
Designation Daily Rate Amount
Person Days
1. Labor
3. Materials
No.of No. of
Designation Daily Rate Amount
Person Days
1. Labor
3. Materials
Sub-Total for 3 ₱ -
Total Direct Cost ₱ 67,076.00
OCM 12.92% ₱ 8,668.94
Contractor's Profit 10.00% ₱ 6,707.60
VAT 5.00% ₱ 4,122.63
Total Cost ₱ 86,575.17
Total Unit Cost ₱ 29.83
Item 105(1) 9 of 44
Province of Iloilo
DETAILED UNIT PRICE ANALYSIS (DUPA)
No.of No. of
Designation Daily Rate Amount
Person Days
1. Labor
3. Materials
Item 200(1) 10 of 44
Province of Iloilo
DETAILED UNIT PRICE ANALYSIS (DUPA)
No.of No. of
Designation Daily Rate Amount
Person Days
1. Labor
3. Materials
Item 311(1)b1 11 of 44
Province of Iloilo
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item 311(1)b1 12 of 44
Equipment Capabilty
Output
Item Description Equipment Unit
Min. Max
100 Clearing and Grubbing Bulldozer 3200 4000 sq.m./day
Excavation Bulldozer 200 cu.m./day
102
Compaction Road Roller 240 320 cu.m./day
Embankment Payloader 240 320 cu.m./day
104 Compaction Road Roller 240 320 cu.m./day
Quarrying Bulldozer 400 cu.m./day
Sub-grade Preparation Grader 2400 sq.m./day
105 Road Roller 1600 sq.m./day
Compaction Road Roller 240 320 cu.m./day
Agg. Sub-Base Course Grader 2400 sq.m./day
200/201 Road Roller 240 320 cu.m./day
Water Truck 8000 sq.m./day
EO Page 13 of 44
Rock Crusher Crushing mixed sand and gravel 30 cu.m./hr 240 cu.m./day
Conc. Vibrator Vibrating concrete mix 40 cu.m./hr 320 cu.m./day
Percussion Drilling hard rock 0.75 f/hr
Drilling loose rock 1 f/hr
Drilling lime stone 1.25 f/hr
Drilling sticky clay 1.6 f/hr
Drilling loose clay 2.5 f/hr
Bar Cutter 100 kg./day
EO Page 14 of 44
Summary of Labor Rates
No. Designation Hourly Rate Daily Rate
1 Foreman 82.50 660.00
2 Highly Skilled Laborer 45.63 365.00
Backhoe Operator 45.63 365.00
Backhoe Operator 45.63 365.00
Bulldozer Operator 45.63 365.00
Crawler Crane Operator 45.63 365.00
Diesel Hammer Operator 45.63 365.00
Payloader Operator 45.63 365.00
Road Grader Operator 45.63 365.00
Road Roller Operator 45.63 365.00
Service Truck/Stake Truck Operator 45.63 365.00
Water Truck Operator 45.63 365.00
3 Skilled Laborer 58.38 467.00
Batching Plant Operator 58.38 467.00
Carpenter 58.38 467.00
Mason 58.38 467.00
Skilled Laborer (Concreting) 58.38 467.00
Skilled Laborer (Forms) 58.38 467.00
Skilled Laborer (Reinforcing Steel) 58.38 467.00
Transit MixerOperator 58.38 467.00
4 Semi-Skilled Laborer 45.63 365.00
1Bagger MixerOperator 45.63 365.00
Concrete Saw Operator 45.63 365.00
Concrete Screeder Operator 45.63 365.00
Concrete Vibrator Operator 45.63 365.00
Crane Helper 45.63 365.00
Dump Truck Driver 45.63 365.00
Rebar Bender Operator 45.63 365.00
Rebar Cutter Operator 45.63 365.00
Service Truck / Stake Truck Driver 45.63 365.00
5 Part-time Safety Practitioner 75.00 600.00
6 First Aider 55.00 440.00
7 Unskilled Laborer 45.13 361.00
Backhoe Helper 45.13 361.00
Batching Plant Helper 45.13 361.00
Bulldozer Helper 45.13 361.00
Crane Crawler Crane 36-40T Helper 45.13 361.00
Crawler Crane 46-50T Helper 45.13 361.00
Diesel Hammer Helper 45.13 361.00
Dump Truck Helper 45.13 361.00
Dump Truck Helper 45.13 361.00
Payloader Helper 45.13 361.00
Road Grader Helper 45.13 361.00
Road Roller Helper 45.13 361.00
Service Truck/Stake Truck Helper 45.13 361.00
Survey Aide 45.13 361.00
Traffic Aide 45.13 361.00
Transit MixerHelper 45.13 361.00
Unskilled Laborer (Concreting) 45.13 361.00
Unskilled Laborer (Forms) 45.13 361.00
Unskilled Laborer(Reinforcing Steel) 45.13 361.00
Water Truck Helper 45.13 361.00
Labor Page 15 of 44
2014 ACEL RATES
(Minimum Operation = 8 hrs. per day, Rates including Operators and Helpers)
Flywheel
No. Description Model Capacity Unit Rental Rate per Day
Horsepower
1 Earthmoving Equipment
Bulldozer D6H SERIES II PSDS/DD 165 PHP 27,032.00
Bulldozer w/ Ripper D6H SERIES II PSDS/DD 165 PHP 31,086.80
Payloader LX80-2C 1.50 / 1.95 cu.m. / yd³ 110 PHP 13,864.00
Motorized Road Grader G710A 140 PHP 17,384.00
Road Grader w/ Scarifier G710A 140 PHP 22,599.20
PHP -
2 Compaction Equipment PHP -
Pneumatic Tire Roller 9-WHL, 9.00X20, 4PR 10.00 mt 107 PHP 4,488.00
Vibratory Roller SD100DC 10.00 mt 125 PHP 14,768.00
Tandem Steel Roller CC421 10.10 mt 123 PHP 13,216.00
Plate Compactor 400 - 500 GASOLINE ENGINE 5 PHP 984.00
PHP -
3 Lifting Equipment PHP -
Service Crane w/ Crawler Crane ALL MODELS 21 - 25 mt 145 PHP 12,176.00
Crawler Crane w/ Bucket ALL MODELS 36 - 40 mt 190 PHP 18,259.20
Crawler Crane ALL MODELS 36 - 40 mt 190 PHP 15,216.00
Crawler Crane ALL MODELS 41 - 45 mt 190 PHP 17,208.00
Crawler Crane ALL MODELS 51 - 60 mt 275 PHP 22,224.00
Crawler Crane ALL MODELS 61 - 70 mt 275 PHP 28,576.00
Crawler Crane ALL MODELS 71 - 80 mt 285 PHP 28,760.00
Truck Mounted Crane ALL MODELS 31 - 35 mt 238 PHP 14,888.00
Truck Mounted Crane ALL MODELS 41 - 45 mt 246 PHP 20,848.00
Truck Mounted Crane w/ Bucket ALL MODELS 41 - 45 mt 246 PHP 25,016.00
Truck Mounted Crane ALL MODELS 51 - 60 mt 280 PHP 25,896.00
PHP -
4 Excavating Equipment PHP -
Backhoe SE 130 LC-2 0.80 / 1.04 cu.m. / yd³ 99 PHP 12,296.00
Backhoe w/ Breaker SE 130 LC-2 0.80 / 1.04 cu.m. / yd³ 99 PHP 15,984.80
Backhoe, Wheel Mounted PW60N-1 0.28 / 0.37 cu.m. / yd³ 50 PHP 7,376.00
PHP -
5 Foundation Equipment PHP -
Diesel Hammer K25 - DSL 7,500.00 kg-m PHP 10,288.00
Vibro Hammer DPD600T HYDRAULIC PILE DRIVER 60.00 ton 201 PHP 16,984.00
Vibro Hammer VIBRO FONCEUR, PTC25H1A 4,500.00 kg-m 272 PHP 24,552.00
Vibro Hammer MHF12 w/ Hyd. Power Pack 120.00 kg-m 300 PHP 32,944.00
C.M.V. TH18/65, 2000mmØ 65m Depth &
Drilling Rig 18000 kg-m Drill Torque
300 PHP 101,096.00
PHP -
6 Asphalting Equipment PHP -
Asphalt Distributor ROSCO/5 TON 3,000.00 USG 100 PHP 7,488.00
Asphalt Paver NF220BIIVDM 80 PHP 14,664.00
PHP -
7 Concreting Equipment PHP -
Concrete Screeder WACKER TRUSS SCREED 5.50 PHP 4,360.00
Concrete Paver COMMANDER III, FOUR-TRACK PHP 54,120.00
One Bagger Mixer 4-6 ft³/min PHP 1,376.00
Transit Mixer ALL MODELS 5-6 yd³ PHP 10,544.00
Grouting Machine GARNER DENVER 6x3x6, AIR DRIVEN 300 PHP 6,930.00
PHP -
Flywheel
No. Description Model Capacity Unit Rental Rate per Day
Horsepower
12 Shop Equipment
Welding Machine () ELECTRIC DRIVEN / DC OUTPUT 500.00 AMP PHP 3,128.00
Welding Machine GAS / DIESEL DRIVER 300.00 AMP 48 PHP 2,968.00
14 Miscellaneous Equipment
Concrete Vibrator FLEXIBLE SHAFT TYPE 2" HEAD Ø w/ 5 AMPERE GASOLINE DRIVE UNIT PHP 730.00
Concrete Saw 14" BLADE Ø w/ 4 3/4" CUTTING DEPTH 7.50 PHP 261.04
Bar Cutter 25 mm MAXIMUM REBAR Ø (GRADE 40), SINGLE PHASE PHP 1,758.00
Bar Bender 25 mm MAXIMUM REBAR Ø (GRADE 40), THREE PHASE PHP 2,812.00
Tower Lights Tower Height= 28ft., No. of Lights = 4 x 1000 watts, HP = 10.50, PHP 4,348.00
Generator = 5 kW
15 Plants
Flywheel
No. Description Model Capacity Unit Rental Rate per Day
Horsepower
COMPLETE w/: CEMEN SILO AND SCREW CONVEYOR SYSTEM. WATER AND
SUPPLY SYSTEM. AGGREGATE STORAGE BINS w/ VIBRATORS AND
CONVEYORS SYSTEM. WEIGH HOPPER WITH ELECTRONIC LOADCELL FOR
Concrete Batching Plant PHP 14,076.00
AGGREGATES, CEMENT, WATER AND ADMIXTURE. CENTRAL TWINSHAFT
MIXER. HYDRAULIC SYSTEM AND COMPUTERIZED PLANT CONTROL
SYSTEM
18 Others
SPT & Desanding Machine PHP 4,472.00
Power Broom, Towed Type WITH ENGINE 2 m WIDE 6 - 30 km/h SWEEPING CAPACITY PHP 1,044.32
Hyrdoseeding Machine PHP 7,616.00
Applicator Machine PHP 750.00
Kneading Machine PHP 1,500.00
Drop Hammer PHP 1,600.00
Drop Hammer w/ Accessories PHP 40,000.00
Cutting Outfit PHP 363.60
Bentonite Bin PHP 2,240.00
Bentonite Mixer PHP 1,384.00
Tremie Pipe Set PHP 2,560.00
Steel Wheel w/ Nylon Rope PHP 2,400.00
Pile Integrity Testing (Sonic) & Accessories (includes professional fee of Structural Engr.) PHP 520,000.00
Dynamic Pile Testing (includes professional fee of Structural Engr.) PHP 824,000.00
Pile Integrity Testing (Sonic) & Accessories (includes professional fee of Structural Engr.) PHP 296,000.00
Grinding Machine and Accessories PHP 603.04
Stressing (Jack) Machine PHP 20,000.00
Dolly PHP 9,992.00
Wood / Steel Ladder PHP 800.00
Improvised Bamboo w/ Bucket PHP 1,600.00
Asphalt Kettle/ Drum PHP 80.00
Earthworks Page 19 of 44
NAME OF PROJECT: CONCRETING OF BARANGAY ROAD
LOCATION: Brgy. Palanguia, Pototan, Iloilo
Earthworks Page 20 of 44
QUANTITY TAKE-OFF
Width 5.0M
Length = 196.00
Area of Whole Section Area of Item 311
L1 = 6.20 m Width = 5.00 m
L2 = 7.00 m Thk = 0.20 m
T1 = 0.20 m Area = 1.00 sq.m.
T2 = 0.20 m
Area = 2.64 sqm.
Width 4.0M
Length = 255.00
Area of Whole Section Area of Item 311
L1 = 5.20 m Width = 4.00 m
L2 = 6.00 m Thk = 0.20 m
T1 = 0.20 m Area = 0.80 sq.m.
T2 = 0.20 m
Area = 2.24 sqm.
PROPOSED PCCP
Road Width 5.0M
Length = 196.00 m.
Width = 5.00 m.
Thickness = 0.20 m.
Area = 980.00 sq.m.
Volume = 196.00 cu.m.
DOWEL BARS
TIE WIRE
On Tie Bar
No. of bars = 753.00 pcs.
Length of Wire = 0.50 m.
Total Length = 376.50 m.
No. of kg = 7.10 kgs.
On Dowel Bar
No. of bars = 32.00 pcs.
Length of Wire = 0.50 m.
Total Length = 16.00 m.
No. of kg = 0.30 kgs.
FORM WORKS
Length = 196.00 m.
Width = 5.00 m.
Thickness = 0.20 m.
Volume = 196.00 cu.m.
Total Volume = 196.00 cu.m.
by Transit Mixer
Mixing Concrete: 460.00 sqm./day
Length = 255.00 m.
Width = 4.00 m.
Thickness = 0.20 m.
Volume = 204.00 cu.m.
Total Volume = 204.00 cu.m.
by Transit Mixer
Mixing Concrete: 460.00 sqm./day
length per span = 4.50 m
Length of Span per Day = 230.00
say = 180.00 m.
Total No. of Span = 113.33
Total No. of Span = 114.00 spans
CURING COMPOUND
Length = 196.00 m.
Width = 5.00 m.
Length = 255.00 m.
Width = 4.00 m.
Area = 1,020.00 sq.m.
SEALING JOINT
Length = 196.00 m.
Width = 5.00 m.
Area = 980.00 sq.m.
Length = 255.00 m.
Width = 4.00 m.
Area = 1,020.00 sq.m.
SUMMARY:
95.00 pcs. 16mmØ x 6m RSB (deformed)
8.00 pcs. 16mmØ x 6m RSB (Plain)
738.00 m. Steel forms (Rental)
8.00 kgs. No. 16 Tie Wire
106.00 gals. Curing Compound
240.00 lit. Sealing Joint
Vertical (2"x4")
L= 10.00 m.
Bracing (2"x4")
L= 11.44 m.
Total Length = 21.44 m.
CW Nails
4" = 32.00
No. of kg. = 0.55
No. of kg. = 1.00
2" = 68.00
No. of kg. = 0.18
No. of kg. = 0.50
Pedestal
N= 4
Length = 0.20 m.
Width = 0.20 m.
Height = 1.20 m.
Total Volume = 0.192 cu.m.
Lateral Ties
No. of Pedestal = 4
No. of Ties = 9
Length = 1.00 m.
Total Length = 36.00 m.
P= 0.16 m.
A= 0.77
No. of Plywood = 0.27 pcs.
No. of Plywood = 1.00 pcs.
Wood Frame
Using 2" x 2" x 10' Coco Lumber
N= 1.00 posts
2" x 2" Wod Frame: 29.67
29.67 bd.ft.
No. of pcs. = 9.00 pcs.
CW Nails
4" = 16.00
No. of kg. = 0.28
No. of kg. = 0.50
2" = 34.00
No. of kg. = 0.09
No. of kg. = 0.50
Footing
N= 2.00
Length = 0.30 m.
Width = 0.30 m.
Height = 0.35 m.
Total Volume = 0.06 cu.m.
A - Frame
Vertical (2"x4")
L= 16.64 m.
Bracing (2"x4")
L= m.
Total Length = 16.64 m.
Movable Posts
Output of 1 - Bagger Mixer: 12 cu.m./day
Form Works:
Plywood
N= 10.00 posts
a= 0.25 m.
b= 0.25 m.
t= 0.20 m.
P= 1.20 m.
A= 0.24 sq.m.
Total A = 2.40 sq.m.
Wood Frame
Using 2" x 2" x 10' Coco Lumber
Factor: 29.67
Bd. Ft. = 29.67
No. of pcs. = 8.90 pcs.
Total No. of pcs. = 9.00 pcs.
CW Nails
2" = 320.00 joints
No. of kg. = 0.84 kgs.
No. of kg. = 1.00 kgs.
ITEM 311 Portland Cement Concrete Pavement End Area = 1.00 sq.m.
Thickness = 0.20 m.
ITEM 200 Aggregate Sub - Base Course End Area = 1.32 sq.m.
Thickness = 0.20 m.
Shoulder at Both Sides End Area = 0.32 sq.m.
Total End Area = 1.64 sq.m.
BACK - UP COMPUTATION
END AREA:
TYPICAL ROAD SECTION
Whole Area:
L(1) = 6.20 m.
0.60 2.50 2.50 0.60 L(2) = 7.00 m.
T(1) = 0.20 m.
T(2) = 0.20 m.
1.5% SLOPE 1.5% SLOPE A= 2.64 sq.m.
ITEM 311:
W= 5.00 m.
T= 0.20 m.
PCCP (ITEM 311) A= 1.00 sq.m.
Width = 5.00 m.
Thickness = 0.20 m.
ITEM 200(w/ shoulder):
Aggregate Sub - Base Course (ITEM 200)
Width (L1)= 6.20m. Area Whole = 2.64 sq.m.
Width (L2)= 7.00 m. Area of PCCP = 1.00 sq.m.
Thickness = 0.20 m. Net Area = 1.64 sq.m.
PCCP: x = 0.400
W= 5.00 m.
T 1= 0.20 m.
Shoulder:
W(1) = 0.60 m.
W(2) = 0.60 m.
ITEM 311 Portland Cement Concrete Pavement End Area = 0.80 sq.m.
Thickness = 0.20 m.
ITEM 200 Aggregate Sub - Base Course End Area = 1.12 sq.m.
Thickness = 0.20 m.
Shoulder at Both Sides End Area = 0.32 sq.m.
Total End Area = 1.44 sq.m.
BACK - UP COMPUTATION
END AREA:
TYPICAL ROAD SECTION
Whole Area:
L(1) = 5.20 m.
0.60 2.00 2.00 0.60 L(2) = 6.00 m.
T(1) = 0.20 m.
T(2) = 0.20 m.
1.5% SLOPE 1.5% SLOPE A= 2.24 sq.m.
ITEM 311:
W= 4.00 m.
T= 0.20 m.
PCCP (ITEM 311) A= 0.80 sq.m.
Width = 4.00 m.
Thickness = 0.20 m.
ITEM 200(w/ shoulder):
Aggregate Sub - Base Course (ITEM 200)
Width (L1)= 5.20m. Area Whole = 2.24 sq.m.
Width (L2)= 6.00 m. Area of PCCP = 0.80 sq.m.
Thickness = 0.20 m. Net Area = 1.44 sq.m.
PCCP: x = 0.400
W= 4.00 m.
T 1= 0.20 m.
Shoulder:
W(1) = 0.60 m.
W(2) = 0.60 m.
BACK - UP COMPUTATION
NAME OF
CONCRETING OF BARANGAY ROAD
PROJECT:
LOCATION: Brgy. Palanguia, Pototan, Iloilo
ITEM NO.: B.5
ITEM OF WORK: Project Billboard / Signboard
QUANTITY: 2.00
UNIT: Each
1/4"x4'x8' Marine
1.00 2.40 1.20 2.88
Plywood
No. of
Mark Length Width Height Volume
Units
SUMMARY OF MATERIALS
A. PEO PROJECT SIGN BOARD
4' x 8' Tarpaulin
= 1.00 pc.
(Printed)
1/4"x4'x8' Marine
= 1.00 sheet
Plywood
2" x 2" x 10' Coco
= 4.00 pcs.
Lumber
2" x 4" x 12' Coco
= 4.00 pcs.
Lumber
Assorted Nails = 1.00 kg
Portland Cement = 0.57 bag
Mixed Gravel = 0.06 m³
Marine Plywood:
No. of Set = 1.00 set
Length = 2.40 m.
Width = 1.20 m.
Area = 2.88 m²
Use : 1.00 sheet
Post
2" x 4" x 10' Coco Lumber
No. of Units = 2
Length = 2.95 m.
Total Length = 5.90 m.
No. of Pcs. = 1.97 pcs.
No. of Pcs. = 2.00 pcs.
Bracing
2" x 4" x 10' Coco Lumber
No. of Units = 2
Length = 2.86 m.
Length = 5.72 m.
2" x 4" x 10' Coco Lumber
No. of Units = 2
Length = 0.60 m.
Length = 1.20 m.
Framing
2" x 2" x 10' Coco Lumber
No. of Units = 6
Length = 1.20 m.
Total Length = 7.20 m.
No. of Pcs. = 2.40 pcs.
No. of Pcs. = 3.00 pcs.
Height = 0.35 m.
Volume = 0.063 m.
Marine Plywood:
No. of Set = 1.00 set
Length = 2.40 m.
Width = 2.40 m.
Area = 5.76 m²
Use : 2.00 sheets
Concrete Footing
Footing : 2.00 sets
Length = 0.30 m.
Width = 0.30 m.
Height = 0.35 m.
Volume = 0.063 m.
Post
2" x 4" x 10' Coco Lumber
No. of Units = 2
Length = 4.15 m.
Total Length = 8.30 m.
No. of Pcs. = 2.77 pcs.
No. of Pcs. = 3.00 pcs.
Bracing
2" x 4" x 10' Coco Lumber
No. of Units = 1.00
Length = 6.48 m.
Total Length = 6.48 m.
Framing
2" x 2" x 10' Coco Lumber
No. of Units = 1.00
Length = 14.40 m.
Total Length = 14.40 m.
No. of Pcs. = 4.80 pcs.
No. of Pcs. = 5.00 pcs.
Summary:
Project Sign Board
4' x 8' Tarpaulin (with Format) 1.00 pc.
1/4" Thk. Marine Plywood 1.00 sheet
2" x 4" x 10' Coco Lumber 5.00 pcs.
2" x 2" x 10' Coco Lumber 3.00 pcs.
Assorted CWN 1.00 kg.
Portland Cement 1.00 bag
Washed Sand 0.10 m³
Mixed Gravel 0.10 m³