Kontrolli juhend // Inspection Procedure: Materjal // Material: Materjali paksus // Material thickness:
Purustamata visuaalne kontroll// None Distructional Visual Control S235 inside tank 6mm // 4mm outside tank
Keevituse protsess // Welding proces Liite tüüp // Joint type Pinna sisukord // Surface condition: Kontrolli eesmärk // Inspection goal:
Spray can nr. Penetrante Red Spray can nr serial nr. A03114
Spray can nr. Developer White Spray can nr serial nr. B2114 N.4
Diisel test// Dieselt fuel Test Pump Pump nr. 00075-00.00S . Diisli kütte/ Diesel fuel 1000 L
300 Liiteviga kokkusulamatus// Join complete meltingness Pole lubatud// Not allowed
400 Läbikeevitamatus// Weldththrough spots Pole lubatud// Not allowed
500 Penetranti kontroll// Leak test usind Penetrant test Pole lubatud// Not allowed
600 Diisel kütte kontroll // Leak test usinf Diesel fuel Pole lubatud// Not allowed
21.09.2023
Date __________________
Customer
Conteinertech AS
Project
DT 31A 9130-7
Protective paint system PUR 120/1
Paint work contractor SHROMA OÜ
Part/assembly name
Diesel tank Drawing number DT31-000-00A
Surface preparation ISO 8501-1, ISO 8501-3
Blast cleaned with blast material grid WGH 050
Surface preparation grade
Sa2 Sa2 ½ Sa3 St2 St3
Date
19.09.2023 20.09.2023
Ambient temperature
°С
19 19
Relative humidity
%
65 65
Object temperature
°С 17 17
Dew point
°С
12,27 12,27
Desingnation of paint and type Normadur 65 HS
NDFT
µm
120
DFT min 139
µm
DFT mean 186
µm
DFT max
µm
240
Number of checks 30
Remarks
Inspection result