Professional Documents
Culture Documents
GRP Pipes Method Statement
GRP Pipes Method Statement
GRP Pipes Method Statement
1.0 General
This method statement is developed as a step by step sequential guideline for the
work to be carried out for the FRP/GRP works. All work activities shall adhere to SAS
/ Acciona and SWCC Safety rules and work permits will be observed.
The instructions cover pipe installation, butt & wrap jointing system of pipe
and backfilling. This procedure required to do lamination by skilled labour.
3.1 Manpower
3.1.1 Safety Supervisor
3.1.2 Civil Supervisor
3.1.3 QA / QC Engineer
3.1.4 Surveyor
3.1.5 Surveyor’s Helper
3.1.6 Foreman
3.1.7 Rigger, Crane Operator
3.1.8 Applicator
3.1.9 Skilled Laborer , Scaffolder
Listed are the typical methods to be done during the installation of all elements.
Following is the outline of methods which will be discussed item by item.
has been found to be an effective way of site storing the pipe. All pipes should be chocked to
prevent rolling in high winds.
The native material must adequately confine the pipe zone backfill to achieve proper pipe
support.
The bedding should be placed over a firm, stable trench bottom so as to provide proper
support. The finished bed must provide a firm, stable and uniform support for the pipe barrel
and any protruding feature of its joint. Provide 100 - 150 mm of bedding.
Rigging plan shall be approved by client and Sufficient scaffolding support shall be
provided , safety measure shall be taken to work inside pipe for wrapping.
The pipe ends to be joined shall fit with as little gap as possible. The gap shall
under no circumstances exceed 13 mm. Gaps in excess of 3mm shall be filled
with a high adhesion filler.
The pipe ends shall be joined without misalignment. If adjusting the alignment
cannot eliminate an offset, step by step, then it should be equalized around the
circumference of the pipe. Any steps between the ends to be overwrapped that
exceed the larger of 1.00 mm or 1.0 % of the nominal diameter to the maximum
of 3.00mm, shall be filled with chop strand mat laminate wetted with the resin. The
SWRO AL-KHOBAR Plant
Resin preparation is an important part of the hand lay-up process. The amount of
catalyst has major impact on the laminate end properties. Use special catalyst for
hand lay-up.
The normal catalyst amount for hand lay-up resin is 1-3% when producing very
thin laminates 1-2.5% is an appropriate range.
The catalyst level should always be in the 1-3% range. Remember that the gel
time of the resin changes with catalyst levels. The ambient temperature will also
influence the gel time – higher temperatures give shorter gel times. Typical gel
time range 15-25 minutes at 25 degree Celsius.
The resin should be stirred for 1 minute before use to have good mixing before
laminate layup. Resin used for hand lay-ups can normally be delivered pre-
accelerated and if non–accelerated resin is used the recommended action is to
add 1% of a 1% cobalt solution to the mixture.
When laminating it is of utmost importance that all tools are clean and without
pollution. There should be no cured resin on the roller surfaces. This will reduce
the effects of the tool and may also fail into laminate resulting in reduced strength
and possible air entraptions.
The pipe ends to be joined shall fit with as little as gap as possible. The gap shall
under no circumstances exceed 13mm. Gaps in excess of 3mm shall be filled with
a high adhesion filler and if offset at ends it should be minimized and prepare joint
ends as mentioned in section 4.
Thoroughly clean the pipe ends that are to be jointed.
SWRO AL-KHOBAR Plant
Check the plies width to be applied on the pipe joint. Extend 50mm extra at each
end to cover the roll out expansion margin during lamination.
Mark on each pipe end a distance ½ the total lay-up width. This marked at each
end to cover the roll out expansion margin during lamination.
For internal lamination, ensure that the safe access is available to work from
inside.
The same procedure and same number of pies shall be applied from inside as for
outside.
An internal lamination shall include groove at the lamination ends. This grooving
shall absorb the laminated plies edges into it. These grooves facilitate the product
flow without reducing the flow momentum.
The grinding procedure shall be repeated if the prepared surface is contaminated
prior to start the lamination work or it is more than 8 hours of grinding.
Wipe the ground areas with clean dry cloth to remove the collected dust and any
surface moisture.
Before applying the first layer of mat, the surface is wet out with resin to improve
the adhesion between the original laminate and the first lay-up layer. The resin will
also blind any particles or minor dusts that are left on the ground surface.(see
attachment for ND 1900 Dia pipe )
4.2.3 Lay-up
Lay-up materials can either be placed directly on the surface before resin
application or wet out on a separate table prior to lay-up. The off line pre-wetting
of the mats can reduce the risk of air entraptions in the laminate and simplify the
lay-up and roll out process.
Apply the layers in the sequence as supplied in the packet of each kit.
Particular care should be taken with first applied layer. Use sufficient resin and
perform a through wet-out to insure good adhesion between the first applied ply
and the grinded pipe surface. Proper wet-out will also assure that the mat drapes
after the surface. After the first layer is thoroughly rolled out, usually two and two
mats can be applied before rollout.
When removing out air the recommended practice is to start from the centre of the
lay-ups and roll towards the edges. The applied pressure has to be controlled to
avoid mat movement and to ensure uniform glass content throughout the laminate.
SWRO AL-KHOBAR Plant
The final chop strand mat ply will though have to be wider than the underlying plies
in order to totally seal the wrap.
The number of lay-ups that can be applied before the laminate has to cure will
vary with surface characteristics.
On large plain areas, up to 10 layers can be applied before curing. Too many
layers will not allow proper heat dissipation when the resin is under curing process
and could cause blistering.
Apply the new lay-up ply, when the first layer is not sticky. Usually it is not
necessary to grind cured surfaces before continuing the lamination unless the
laminate is more than 24 hours old or has glossy surface. Always remove dust
and restart lamination on clean surface.
The final mat glass ply should be rolled separately. The excess resin in the
laminate is usually enough to wet-out this mat.
When the desired thickness of the laminate is reached, it is recommended to wait
a while (15-20 minutes). This gives the laminate time to settle and be fully
impregnated of resin before performing the last operation.
After the last rollout the laminate is finished with mat layer. The mat should cover
the entire laminated area but not exceed the ground surface of the original
material.
The mat should be wet-out properly to ensure a smooth surface after the
exothermic reaction is complete, when the laminate is not sticky to touch a layer
of resin shall be applied.
installation requires the 300 mm over the pipe cover to be compacted. Trench
backfill under areas subjected to traffic load is often compacted to minimize road
surface settlement. Layer by layer compaction for 95% of modified proctor shall
be achieved with plate compactor or vibratory roller.
During execution of works, SAS shall assign quality control engineers that will
Monitor every step of the work to make sure that requirements of the Project are
followed.
o Safety of Crew – Toolbox meeting shall be done every start of work for all
areas to identify the hazards and how to prevent them. All personnel shall
have complete safety protective gears. .
o Equipment operators should be certified.
7.0 Attachment
7.1 HSE Risk Assessment
FIELD JOINT LAMINATION
(Process Sheet - Balance Lay-up)
For ND1900-PN10-SN5000