Professional Documents
Culture Documents
Sabhw
Sabhw
RUKUM
JAN, 2021
PVT. LTD.
PVT LTD
KUPANDOLE, LALITPUR
KATHMANDU, NEPAL
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
EXECUTIVE SUMMARY
OF
SANI BHERI 3 HYDROELECTRIC PROJECT
Sani Bheri 3 Hydroelectric Project is situated in Eastern and Western Rukum District,
Province no 5 and 6. Project area lies between 28°37’15’ N to 28°40’15” N latitude and
82°30’50” E to 82°36’56” E longitudes. It is located about 570km (road distance) towards
North-West of Kathmandu and from Kathmandu to Solabang is about 550km which is all
season black topped road and further about 25km from Solabang to near Headworks is
fair weathered earthen road which is the main access road from Kathmandu to project
site. Further, around 2km access road is to be constructed to make accessible to
powerhouse adit, surge shaft and intake site.
Project lies in the left bank of the Sani Bheri River. Headworks site is located near the
suspension bridge near Sisneri village. Powerhouse is located near Bhal Khola. Sani
Bheri River is a snow-fed river originating from the high mountains.
The proposed intake of Sani Bheri 3 Hydropower Project lies at Latitude 28° 38' 27" N and
Longitude 82° 33' 30" E, at about Elevation 1055 amsl. It is just downstream of the
confluence of Sani Bheri River and small tributaries. The drainage area at the proposed
weir site is about 2216 km2.The proposed powerhouse site of Sani Bheri 3 Hydropower
Project lies at Latitude 28° 40' 03" N and Longitude 82° 29' 48" E, at about Elevation 950
amsl and located at about 6.5 km downstream of the proposed intake. The total
catchment area at proposed powerhouse site is 2316 km2
Design discharge of the project is 51.00 m3/s. Design of the headworks has been carried
out considering the 100 years return period flood discharge of 1100 m3/s.
Installed capacity of the Sani Bheri 3 Hydroelectric Project is 46.30MW. This scheme
comprises of 38m long barrage with crest elevation at EL.1056.50m will divert the design
flow discharge to the intake at left bank of the River. An undersluice of width 2.00 meters
has been provided before the intake. The intake 4.0m width & 4.0m high will be provided.
Settling basin of the plant is located about at the distance of 300m from the intake. It is
Surface type. It has three basins with length 85 meters, width 11.0 m and 8.30 m height.
Total length of headrace tunnel of 5 m is 6430m. A surge shaft with finished diameter of
12m and height of 47m is proposed at the end of headrace tunnel. Powerhouse is
connected by a 180m long penstock having 4.10m diameter. Three Francis turbines of
15.60MW capacities each will be installed in a surface powerhouse. 230 m tailrace
discharges water back to the Sani Bheri River.
About 4 km long single circuit 132kV Transmission line is required to evacuate power from
project’s powerhouse up to proposed Baphikot Substation.
Total annual energy generation from the plant is 255.92GWh. Out of which 177.07GWh is
the wet energy and 78.82 GWh is the dry energy.
Cost estimate of Sani Bheri 3 Hydroelectric Project has been carried out based on 2020
price level. Major cost components are divided into Land and support, Pre-operating
expenses, infra-structure works, main civil works, hydro-mechanical works and
electromechanical works & transmission line works. Cost of value added tax and
contingencies have also been considered in the cost estimate. Total construction cost of
i
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Financial cost of the project includes taxes, duties, contingency and interest during
construction. Based on the assumed disbursement of the cash flow, the total cost of the
project is estimated NRs. 9250.59 million.
Financial analysis of the project is carried out to assess the financial viability of the
project. PPA is expected to follow the prevailing practice in Nepal i.e. NRs. 8.40/kWh in
the off peak dry season, NRs 10.55/kWh for peak hour dry energy and NRs. 4.80/kWh in
wet season with annual escalation of 3% for eight times from the commercial operation
date.
Internal rate of return of the project is 14.09%. Likewise, benefit cost ratio is 1.41 and NPV
is NRs. 2964 million. The financial parameter indicates the financial viability of the project.
ii
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
General
Project Name Sani Bheri 3 Hydroelectric Project
Name of River Sani Bheri
Nearest Town Musikot Bazaar
Gross Head 110.83 m
Location
District / Province no: Rukum / Province 5 and 6
Type of power plant: Peaking -Run-of-River
Project Co-ordinate
Easting 82°30’50” E to 82°36’56” E
Northing 28°37’15’ N to 28°40’15” N
Hydrology
Catchment area at intake site 2216 km2
Long term annual average flow 66.52m3/s
Design Discharge (Q40) 51.0 m3/s
Design flood at intake (1 in 100): 1085 m3/s
Diversion weir
Type Barrage
Crest level 1056.5m
Length 38 m
Height 18 m from the Bed level
Sluice
Width 2.00 m
Height 0.75 m
Intake
Type Side Intake with 4 no of orifices
Size opening 4.00 m*4.00 m clear opening
Approach Culvert
Length 263.0 m
Width 5.20 m
Height 5.20 m
Settling basin
No of bays 3.00 nos.
Nominal size of trapped particle 0.20 mm, 90.00% trap efficiency
Uniform Length 85.00 m
Width 11.0m
Depth 8.30m
iii
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Waterways
Headrace Tunnel
Type Horse Shoe
Length 6430 m
Diameter 5m
Surge Shaft
Height 47 m
Diameter 12 m
Penstock
Length 180 m
Diameter 4.10 m
Maximum shell thickness 16.00 mm to 28.00 mm
Powerhouse
Length and width 48.00m x 16.00 m
Tailwater Level 944.00 masl
Tailrace
Length of Tailrace canal 230.00 m
Turbine
Type Francis (Vertical Axis)
No of units 3
Rated output 16305 kW
Rated Speed 300 rpm
Rated Efficiency 92%
Generator
No of Units 3
Type Cylindrical Pole, synchronous
Rated Capacity 18510 KVA
Rated Efficiency 96.5%
Power factor 0.85
Speed 300 rpm
Frequency 50HZ
Generation voltage 11 kV
Power Transformer
No of Units 2
Type Three phase, oil immersed
Rated Capacity 30MVA
Transmission Line
Voltage Level 132 KV single circuit line
Length Approximate 4 Km
From Power house
To Baphikot Sub-station
iv
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Environmental Study
Downstream release 1.28 m3/s
Construction Period 4 Years
Project evaluation
Project cost without IDC NRs. 8,250,127,277.77
Project cost with IDC NRs. 9,210,591,876.42
Internal rate of return (IRR) 14.09 %
BC ratio 1.41
Return on Equity 20.12 %
Net Present Value NRs. 2964.65 (million)
v
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
TABLE OF CONTENTS
1 INTRODUCTION ...................................................................... 1-1
1.1 BACKGROUND .............................................................................................. 1-1
1.2 OBJECTIVE AND SCOPE OF W ORK .................................................................. 1-1
1.3 ORGANIZATION OF REPORT ........................................................................... 1-2
2 DESCRIPTION OF PROJECT AREA ...................................... 2-1
2.1 LOCATION .................................................................................................... 2-1
2.2 PHYSICAL FEATURES .................................................................................... 2-1
2.2.1 Topography..............................................................................................2-1
2.2.2 Climate ....................................................................................................2-1
2.2.3 Geology ...................................................................................................2-2
2.3 ACCESSIBILITY ............................................................................................. 2-2
3 FIELD INVESTIGATION AND DATA COLLECTION ............... 3-1
3.1 TOPOGRAPHICAL SURVEY AND MAPPING ........................................................ 3-1
3.1.1 Available Maps ........................................................................................3-1
3.1.2 Surveying .................................................................................................3-1
3.1.3 Horizontal and Vertical Control.................................................................3-3
3.1.4 Accuracy ..................................................................................................3-4
3.1.5 Data Processing ......................................................................................3-4
3.1.6 Detail Topographical Survey ....................................................................3-4
3.1.7 Mapping ...................................................................................................3-4
3.1.8 River Cross Section and Profile ...............................................................3-4
3.2 HYDROLOGICAL INVESTIGATIONS ................................................................... 3-4
3.2.1 Collection of Available Meteorological and Hydrological Data ..................3-4
3.2.2 Establishment of Gauging Station ............................................................3-6
3.2.3 Water Level Recording and Flow Measurement .......................................3-6
3.3 GEOLOGICAL AND GEOTECHNICAL INVESTIGATIONS ......................................... 3-6
3.3.1 Collection of Available Data and Maps .....................................................3-6
3.3.2 Surface Geological Mapping ....................................................................3-7
3.4 CONSTRUCTION MATERIAL SURVEY ............................................................... 3-7
4 HYDROLOGY AND SEDIMENT STUDY.................................. 4-1
4.1 CATCHMENT CHARACTERISTICS ..................................................................... 4-1
4.1.1 Basin Physiography .................................................................................4-1
4.2 REFERENCE HYDROLOGY AND STREAM FLOW DATA........................................ 4-5
4.2.1 Reference Hydrology ...............................................................................4-5
4.2.2 Discharge Measurements ........................................................................4-5
4.3 MEAN MONTHLY FLOW ................................................................................... 4-6
4.3.1 Mean monthly flow by catchment correlation method ...............................4-6
4.3.1 Mean monthly flow by MIP method ..........................................................4-6
4.3.2 Regional Hydrological Method .................................................................4-7
4.3.3 Mean Monthly Flow by WECS/DHM Method ............................................4-7
4.4 ADOPTED MONTHLY FLOW ............................................................................. 4-8
4.5 FLOW DURATION CURVE ............................................................................... 4-8
4.6 LOW FLOW ANALYSIS .................................................................................. 4-11
vi
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
vii
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
viii
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
ix
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
List of Tables
x
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
xi
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
List of Figures
Figure 2-1: Physiography of the Nepal Himalaya (after Dahal and Hasegawa, 2008) and
location of the SB3HP site .................................................................................................. 2-1
Figure 2-2: Climatological Map of Nepal and location of Project area ................................. 2-2
Figure 3-1: Gauge installation by Hydrology team .............................................................. 3-6
Figure 4-1: Catchment area of Sani Bheri River at headworks .......................................... 4-2
Figure 4-2: Catchment area of Sani Bheri River at Powerhouse ......................................... 4-2
Figure 4-3: Thiessen polygon map for Sani Bheri Catchment at Intake Site ....................... 4-4
Figure 4-4: Adopted Mean Monthly Flow at intake site ....................................................... 4-8
Figure 4-5: Hydrograph Computed from different methods ................................................. 4-9
Figure 4-6: Flow Duration Curve at Intake of Sani Bheri 3-Hydropower Project ................ 4-10
Figure 5-1: Geological map of the Nepal Himalaya (DMG) ................................................. 5-3
Figure 5-2: Regional Geological Map of the Project area. (Department of Mines & Geology)
........................................................................................................................................... 5-5
Figure 5-3: Stereographic Projection of joint sets and hill slope in headworks site left bank 5-
8
Figure 5-4: Stereographic Projection of main joint at inlet Portal area................................. 5-9
Figure 5-5: Contour density diagram (Headrace Tunnel). ................................................. 5-11
Figure 5-6: Stereographic Projection of discontinuities (Headrace Tunnel) ....................... 5-12
Figure 5-7: Joint rosette of major joint sets along the tunnel alignment............................. 5-12
Figure 5-8: NGI Q-System from Barton and Grimstad 1993 ............................................. 5-17
Figure 5-9: Earthquake epicentre map of Nepal (DMG, 2006) .......................................... 5-21
Figure 5-10: Active faults of Nepal Himalayas (Adopted after Upreti 2009)....................... 5-22
Figure 5-11: Seismic Hazard Map of Nepal ...................................................................... 5-25
Figure 5-12: Seismic Risk Map of Nepal ........................................................................... 5-25
xii
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
xiii
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Abbreviations
% Percentage
amsl Above mean Sea Level
Km Kilometre
KN Kilo Newton
kV Kilovolt
kW Kilowatt
kWh Kilowatt hour
M Metre
masl Meter above sea level
m2 Square metre
m3/s Cubic metre per second
MIP Medium Irrigation Project
mm2 Square millimeter
MW Megawatt
N Newton
NEA Nepal Electricity Authority
º Degree
xiv
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
1 INTRODUCTION
1.1 Background
Nepal is in a phase of sustainable economic development characterized by harnessing its
maximum hydroelectric potential. According to the annual report (2020) of Nepal Electricity
Authority (NEA), NEA is supplying 3021 GWh, IPP is 2991 GWh. At present, nearly 1729
GWh is imported. The Peak demand is 1408 MW. Power demand is gradually increasing at
the rate of approximately 80 MW per year but production growth is only 60 MW. In order to
meet the increasing power demand in an efficient manner, there is an urgent need to identify
and promote small to medium sized hydroelectric projects which can be implemented at the
earliest. Thus, NEA and Department of Electricity Development (DoED) are encouraging to
develop such project from private sectors for harnessing the water resources potential in a
sustainable manner.
Realizing the fact that, efforts from the Government of Nepal only, will not be sufficient an
open and free policy has been adopted for expediting hydroelectric development with private
sector investment. Necessary laws and regulations including the Hydroelectric Development
policy (2001) has been proclaimed to encourage the Independent Power Producers (IPPs) to
build, own, operate and transfer Hydroelectric project. In this context, Sani Bheri 3
Hydroelectric Project (SB3HP) was identified in Rukum District of Nepal and now it is in
development phase.
Sani Bheri 3 Hydroelectric Project (SB3HP) located on the right bank of Sani Bheri River is a
Peaking-Run-of-River type project. It is located in Rukum District of Mid-Western
Development Region of Nepal. The entire project area (i.e. intake to powerhouse and
tailrace) is located in Pipal, Pokhara, Sobha, Syalapakha Village Development Committee
(Now Sisne Rural Municipality and Musikot Municipality) in Rukum District.
Topographic mapping
Geological mapping
• Geo-technical investigations
1-1
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Chapter 1 Introduction
1-2
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
2.1 Location
Sani Bheri 3 Hydroelectric Project is situated in eastern and western Rukum District, Mid
Western Development Region. Rukumkot and Musikot are the headquarters of Eastern and
Western Rukum. The project is located at an aerial distance of 65km from Tulsipur, Dang in
the north. Similarly, the project location is approximately 115km west of Baglung.
Geographically the area lies between latitude 28°37’15’ N to 28°40’15” N and longitudes
82°30’50” E to 82°36’56” E.
2.2.1 Topography
Project area lies in the Lesser Himalayan region (Figure 2-1) and the catchment area of
project is 2216 sq km. Sani Bheri River is one of the tributaries of Thulo Bheri River which
which is a major tributary of the Bheri River Basin. Sani Bheri River originates from Sisne
Himal at an elevation of approx 5000 masl and flows towards south west.
Figure 2-1: Physiography of the Nepal Himalaya (after Dahal and Hasegawa, 2008) and
location of the SB3HP site
2.2.2 Climate
Nepal experiences an exceptional climate variation owing to its steep gradient from high
Himalayas in north to plains in south. Five different climatic zones i.e. tropical, sub-tropical,
temperate, alpine and tundra (Figure 2-2) have been classified from low land in south to
snow peaked Himalayas in north. The country as a whole receives most of rainfall due to
south-west monsoon, which arises from the Arabian Sea and passes through India before
entering Nepal from eastern part during June-July. Difference between the warm humid
summer and the cold dry winter becomes more marked with the change in the altitude. As
the project area lies in the moderate altitude, the catchment area experiences warm
2-1
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
temperate to sub-tropical atmosphere. Like other parts of Nepal, this region is also influenced
by the monsoon climate. Relative humidity may be as high as 90% during the wet season
and as low as 40% during dry season.
2.2.3 Geology
Area lies in the Lesser Himalaya of Central Nepal, consisting of shale, slate, and phyllite and
quartzite. Structurally, Main Central Thrust (MCT) is located towards North of the project
area. Rocks in this area are some deformed due to presence of thrusts and folds.
2.3 Accessibility
The project site is easily accessible by road from the East-West highway. The highway from
Kathmandu till Solabang (Rukum) is black topped all weather road. From Solabang to the
project site, the road is a gravel road which is accessible only in dry season. The distance of
along the road from Kathmandu is as below:
It is a day’s travel to reach Tulsipur by taking vehicle. From Tulsipur, it will almost take 8
hours to reach the headworks site of the project. Solabang is a bazaar on the highway to
Musikot or Rukumkot.
An alternative to reach the project site could be taking a flight from Kathmandu to Nepalgunj
which is about 45 minutes. From Nepalgunj, one can reach Tulsipur via Kohalpur and
Ameliya in the East-West highway. The distance from Nepalgunj to Tulsipur is about 120
2-2
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Kms. Nepalgunj is close to Rupediya of India and has a customs facility for transport of
material and equipment from India and third countries.
2-3
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
• Detailed topographical survey was executed covering the area from Headwork to
tailrace by depicting all the physical and manmade features as existing at the site.
Unique features which might be useful for references later are depicted.
• All the survey works were under taken using UTM grid co-ordinates and elevations
• All the permanent control points are made significant with concrete pillars or on the
stable boulders by marking with enamel paint
• Closed traverse survey was carried out from the proposed sites covering headworks,
waterway and proposed powerhouse site.
• All the permanent ground control stations were marked on permanent boulders and
with cement concrete.
• River cross-sections at proposed headworks, powerhouse and tailrace sites are taken
and profiles plotted
3.1.2 Surveying
A senior surveyor and his group carried out the detailed topographical survey of the project
area. All the data necessary to determine the locations, coordinates and levels were obtained
by direct measurement in the field. To achieve the required accuracy and standard, Total
Stations with least count of 1” was used. Stepwise methodologies used to conduct survey
work are as follows.
• Desk Study
Prior to the field survey, desk study was carried out by using topographical maps (Scale
1:25,000) published by Government of Nepal, Survey Department. Detailed information
about the project area for the survey was noted. Finally all the available plans, profiles and
location maps prepared during the identification of study were collected.
• Reconnaissance survey
3-1
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
After finalizing the desk study, a team of multi-disciplinary experts were mobilized for field
verification. First step of survey was to reconnaissance the ground control stations and detail
topographical mapping around the project area.
The data and information on the National Geodetic Network present in the vicinity of the
project area have been obtained from the PESCE Consult Pvt. Ltd. Lalitpur. The points have
been established by the DGPS (PENTAX).
The Co-ordinates and their elevations are tabulated below in Table 3-1
The survey teams established sufficient survey stations in and around the project
components. Major control points were made of concrete with the nail in centre. Some of the
major control points were marked either by iron pin in the rock or fixed by cross marks
chiselled on the boulders. Chiselled marks were made conspicuous by enamel paint.
• Control Traversing
Basic ground control survey was carried out from the points established .A closed traverse
was carried out from the headwork’s site to powerhouse sites. Several other required ground
control stations were established by conventional traverse survey covering the entire area to
be mapped from the headwork’s site to powerhouse site. Altogether seven control points and
benchmarks were established between headworks and powerhouse area of the project. The
control points were established in between the power house and headwork of the project
.The coordinates and the elevations of the established ground control stations are given in
Table 3-2.
3-2
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
BRIDGE
6 IBM-1 651736.866 3170073.434 1068.664 BOULDER
7 IBM-2 651687.155 3170147.074 1061.602 BOULDER
CONCRETE Slab OF
8 BM-4 646721.314 3172335.413 994.897 BRIDGE
9 BM-5 646736.555 3172398.693 983.842 BOULDER
Horizontal Control
The traverse surveys for horizontal control have been performed by establishing a framework
of survey lines, connecting a series of traverse stations in the headworks area and
measuring the lengths and directions of these lines. Based on these measurements, the
relative horizontal positions of the traverse stations have been computed.
Horizontal controls have been established through closed traverse originating and
terminating at control stations of higher order than the order of the survey being performed.
Depending on the position of control stations, loop traverse originating and terminating at the
same control stations or connecting traverse beginning at one and ending at another control
station have been adopted.
In order to ascertain the co-ordinates of survey stations required for mapping, the traverse
loops have been formed on the ground. The Horizontal/Zenithal angles and the horizontal
distances have been recorded in the Total Stations. The recorded data have been
downloaded and processed in the computer and the correct co-ordinates and elevations
have been found after the proper adjustment of tolerable errors in traversing.
Vertical Control
Vertical control survey establishes the elevations of control stations and benchmarks in the
project area. These stations or benchmarks do serve as points of departure and closure for
leveling operations and as a reference framework for determining elevation difference in the
project area.
The terrain is very steep and undulating so that the trigonometric approach of control has
been introduced. Therefore, a well-known Trigonometrical Leveling Method has been
introduced for having the elevations of control points. Trigonometric Leveling has been
performed to determine the difference in elevations between stations by observing the
zenithal angles and the horizontal distances between them and applying the fundamentals of
trigonometry. The leveling has been originated from and tied into existing control, and the
elevation of any station on the level line or circuit has been fixed by algebraically summing its
elevation difference from the existing control with the elevation of that control.
3-3
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Angular measurements for horizontal survey have been performed with a repeating Total
Stations with a minimum least count resolution of 1" (second). For distance measurements,
an Electro-magnetic Distance Measuring (EDM) device has been used. Here, in this project,
a TOPCON Total Stations with the least count 1" (second) has been used.
3.1.4 Accuracy
The traversing work has been carried out by using the precise Topcon Total Stations with the
least count 1" (second). The closing errors are in permissible limits and distributed according
to common survey standards.
The terrain features were surveyed by means of spot surveying. Spot positions were taken
by tacheometric method from different traverse points. Inaccessible points like rock faces,
top of cliff, landslide edge etc. were sighted from at least two known points reading both the
horizontal and vertical angles. Features such as riverbanks, high flood level, landslides, cliff,
house, cultivated lands, roads etc were recorded.
3.1.7 Mapping
Detailed topographical mapping of headworks site, audit tunnel, surge shaft, powerhouse
and tailrace area were carried out in required scale. Plans, section and maps were prepared
in digital environment by exploiting the AutoCAD, Land Development software compatible to
AutoCAD 2010.
3-4
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
There are some meteorological stations established by the DHM in and around the Bheri
basin. Meteorological stations near to the project site area are given in Table 3-3.
Climatological Records
Nearest meteorological station for the temperature is located at Gurjakhani (index no. 616),
and Dunai (index no 312). As per the climatological record, annual maximum temperature in
the project area generally occurs in June which ranges from 10.20 to 28.00C. Similarly,
minimum temperature generally occurs in January which ranges from -0.7 to 110C. Detailed
records of temperature data of station at GurjaKhani and Dunai are listed in Table 3-4.
3-5
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
3-6
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Selection of the layout of the project components such as diversion weir, settling basin,
tunnel inlet portal, tunnel alignment, surge shaft, penstock alignment and powerhouse
location was done on the basis of geological and topographical condition of the area.
Slope stability analysis of different structure area of the project was carried out on the basis
of aerial photo interpretation, geological observation and geological data analysis. An
analysis of the foliation plane to determine the stability of the rock mass at different structure
area of the project was done by using Lower Hemisphere Projection of the foliation plane in
Schmidt’s equal area net. The wedge formed by the planes was analyzed with respect to the
hill slope surface and tunnel alignment.
3-7
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The proposed intake of Sani Bheri 3 Hydropower Project lies at Latitude 28° 38' 27" N and
Longitude 82° 33' 30" E, at about Elevation 1055 amsl. It is just downstream of the
confluence of Sani Bheri River and small tributaries. The drainage area at the proposed weir
site is about 2216 km2.
The proposed powerhouse site of Sani Bheri 3 Hydropower Project lies at Latitude 28° 40'
03" N and Longitude 82° 29' 48" E, at about Elevation 950 amsl and located at about 6.5 km
downstream of the proposed intake. The total catchment area at proposed powerhouse site
is 2316 km2.The catchment area at head works and powerhouses are presented in Figure 3-
1 and Figure 3- 2 below respectively.
Based on the topographical maps, there are no lakes within the Sani Bheri River basin. All of
the above-mentioned drainage areas have been estimated based on the latest topographical
maps compiled from 1:25,000 scale aerial photography of 1996 by the Survey Dept. and also
with GIS application. The 30 m by 30 m resolution Digital Elevation Model has been used in
Arc-GIS application to delineate catchment area at different reaches. Further geoprocessing
tools have been used to reclassify the catchment areas into different elevation bands.
Different ranges of area with their calculated value for headworks and powerhouse are
presented in Table 4-1 below.
Table 4-1: Reclassified catchment area for Headworks and Powerhouse (Km2)
Area
Area Area
Area Below 2000m Area 4000m Total
Location 3000m to above
2000m to to 5000m Area
4000m 5000m
3000m
Headworks 175 663 815 443 120 2216
Powerhouse 214 712 827 443 120 2316
4-1
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
4-2
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The estimated mean annual basin precipitation for the Sani Bheri-3 Hydropower Project
catchment is about 1722mm. The monsoon rains contribute about 80% of the total annual
precipitation. The onset of monsoon starts from June to September. The nearby precipitation
stations with thiessen boundary area and average of all are given in Table 4-3 below.
The estimated mean annual basin precipitation for the Sani Bheri-3 Hydropower Project
catchment is about 1722mm.The thiessen Polygon for the catchment area with respect to
DHM stations is presented in Figure 4-3.
4-3
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Figure 4-3: Thiessen polygon map for Sani Bheri Catchment at Intake Site
The monthly temperature from the nearby stations of the catchment of Sani Bheri-3 HEP is
presented in Table 4-4.
The basin experiences cold during the month June to October and most dry and very cold
occur during the month December to February. Since the Index No. 616 and 312 are nearby
4-4
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
the Sani Bheri River basin, this can be used as the representative climatological station. The
maximum extreme temperature of the project site goes up to 29.4°C and that of minimum
extreme temperature goes down to -0.2°C.
Reference hydrology for the project has been analyzed from catchment area correlation
method.
Long term mean monthly flow in the river has been estimated by transposing available
discharge data from Thulo Bheri River. The discharge data from Thulo Bheri River at Rimna
(St 265) has been used to co-relate flows at Intake site. The transposing ratio is 0.32 for
catchment area and 1.10 for precipitation.
4-5
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Jan Feb March April may June July Aug Sep Oct Nov Dec Average
33.42 25.06 18.10 13.92 36.20 83.55 201.91 348.12 229.7 111.40 57.09 43.17 100.14
4-6
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The regression for long term average monthly flows showed that total drainage area “A” and
the monsoon wetness index “MWI” produced the statistically most significant regression
coefficients. The list below gives the formulae to be applied to ungauged basins for the
estimation of the long-term average monthly flows.
From the average monthly flows obtained by regression, the average annual flow was
developed for each of the ungauged sites. The monthly flow data from above equations are
shown in Table 4-9. The long-term average flow at the intake site has been estimated as
109.48m3/s.
Jan Feb March April may June July Aug Sep Oct Nov Dec Average
24.3 20.5 28.1 32.8 103. 291. 112. 54.6 36.0 109.48
0 0 19.53 1 4 47 72 336.22 253.62 75 7 3
4-7
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The results of this study are used as an alternate approach for estimation of mean monthly
discharges at the Intake site. The Table 4-10 shows the results from WECS/DHM method.
The long-term average flow at the intake site has been estimated as 116.59m3/s.
Jan Feb March April may June July Aug Sep Oct Nov Dec Average
25.1 21.3 20.13 23.3 35.1 105. 314. 367.44 278.14 121. 53.3 34.0 116.59
6 7 2 5 40 53 04 3 3
Jan Feb March April may June July Aug Sep Oct Nov Dec Average
14.92 12.81 13.61 21.68 44.72 77.15 168.38 201.84 131.60 60.82 30.83 19.87 66.52
180
160
140
120
100
80
60
40
20
-
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
Figure 4-4: Adopted Mean Monthly Flow at intake site
4-8
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
River at Rimna station (St no 265). The flow duration curve has been derived based on the
monthly average discharge generated using catchment area ratio method and application of
precipitation ratio. For the purpose of comparative study, flow duration curve was also
estimated by empirical methods; HYDEST, MHSP and MIP. The hydrograph from all the
methods used in study has been presented in Figure 4-5 below.
400
MHSP
350
300
250 Hydest
200
150
100
50
From the above hydrograph it is clear that all other methods then CAR with Thulo Bheri
overestimate the flow of Sani Bheri at Intake site.
The percentage exceedance flow value from catchment correlation with Thulo Bheri River at
Rimna gauging station has been adopted for further analysis. The adopted values
corresponding to percentile and no of days are presented in Table 4-12 and the flow duration
curve is presented in Figure 4-6 below.
4-9
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Flow Duration Curve at Intake of Sani Bheri-3 HEP FDC By CAR Method
220
200
180
Discharge(m3/sec)
160
140
120
100
80
60
40
20
0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
% of Exceedence
Figure 4-6: Flow Duration Curve at Intake of Sani Bheri 3-Hydropower Project
Based on the flow duration curve, discharge corresponding to 40 percentile time is taken as
design discharge at intake for hydropower generation.
4-10
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
For such type of ungauged rivers, HYDEST 2004 DHM method was used for low flow
computation. For the purpose, different durations viz: 1-day, 7-day, 30 days and monthly
were adopted to compute the low flow for different return periods. The low flow estimation
equation is as follows and corresponding factors and constants are presented below in Table
4-13.
𝑄 = �𝐶𝑑, 𝑇 + 𝐹𝑑, 𝑇 × √𝐴 ≤ 5𝑘 �^2; Where A<5k =Basin area below 5000 amsl
Here, from the analysis 20-year 1-day low flow is 10.81m3/sec. But from CAR method
adopted in calculation of long term monthly flow from the discharge data available at Rimna
Gauging station of Thulo Bheri the lowest flow is 9.35 m3/sec on the march month of
1985.This flow is the lowest flow derived between 1977 to 2006 i.e. from 29 years data.
4-11
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
4.8.1 General
Design flood assessment involves the computation of a set of values of various return
periods of say 10, 20, 50 and 100 years, through frequency analysis of flood series or
through hydro-meteorological approach with the help of inputs of rainfall storm parameters
provided by the Meteorologist and flood data provided by the river gauging units. These peak
flood values are required to design headworks and powerhouse complex.
The flood estimation at the intake and powerhouse site was estimated based on the historical
flood records observed at Thulo Bheri River at Rimna (station no 256) considering the
homogeneity of this catchment to Sani Bheri River Catchment. The precipitation ratio of Sani
Bheri catchment to that of Thulo Bheri catchment is greater then 1 in all months. Since flood
is frequent in monsoon period we have taken precipitation factor of 2 to derive the
instantaneous flood discharge at Sani Bheri HEP intake site and Powerhouse site from the
instantaneous flood discharge available at Rimna station of Thulo Bheri.
The availability of limited discharge measurement data, daily water gauge readings and the
uncertainties involved in the raw and historic-reconstituted data series necessitated the
application of flood frequency analysis. Different methods of flood frequency analysis and the
resultant value is discussed below.
Flood frequency analysis was performed using a customized Excel spreadsheet. Following
types of frequency distribution functions were used in the flood frequency analysis from the
generated annual maximum flood series data between 1977 and 2006. Analyses were done
separately for Intake and powerhouse site.
Analyses of the generated instantaneous data were done using different methods given
below.
4-12
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
ratio for intake and powerhouse to transfer instantaneous discharge from Rimna gauging
station are 0.32 and 0.33 respectively. The instantaneous discharge data used for flood
frequency analysis from DHM and correlated at headworks and powerhouse site is
presented in Table 4-14 below.
Table 4-14: Instantaneous Flood Discharge at Different Locations Used for Analysis
4-13
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Table 4-15: Summary of flood (m3/s) analysis by different methods for Intake
Return Flood frequency methods
Period Gumbel's Gumbel's Log- Log-normal
(yrs) Analitical Graphical Pearson Distribution
Type III
Distribution
Table 4-16: Summary of flood (m3/s) analysis by different methods for Powerhouse
Return Flood Frequency Methods
Period Gumbel's Gumbel's Log- Log-Normal
(yrs) Analitical Graphical Pearson Distribution
Type III
distribution
Or
b) 20 years return period flow, calculated on the basis of non-monsoon yearly peaks.
The floods of various return periods are estimated on the basis of analysis of the
transposed non-monsoon flood peaks at Sani Bheri River Diversion site, assuming that
June to October is affected by monsoon. Non–monsoon flood peaks (November to May
4-14
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
peak values) were used to estimate the 20-year return period diversion flood using
Gumbel's Analytical method, Gumbel’s graphical, Log-Pearson Type III and Log Lognormal
distribution.
The non-monsoon flood peaks corresponding to different return period are calculated as
given in Table 4-17 below.
From the above table, the maximum 20-year return period flood from different methods is
73.94m3/s. The maximum non-monsoon flood observed at intake site is 73.49m3/sec. Here
both values used in selection criteria seems to be same. Therefore, for present study the
diversion flood has been adopted as 74m3/s.
The yield from High Himalaya above Elevation 5000m, high mountain between Elevation
3000m to 5000m, and middle mountain below elevation 3000m is considered as 500ton/km2,
2500ton/km2 and 5000ton/km2 respectively.
The catchment area of Sani Bheri basin at the proposed intake site is 120km2 in high
Himalaya, 1258km2 in high mountains and 838km2 in Middle Mountain. The sediment yield
from this method is 7.40 Million tonnes/annum which is equivalent to a mean concentration of
4905 parts per million by weight (ppm) at the intake site using the mean monsoon discharge
of 116.32m3/s.
4-15
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Hence, from the above equation, the total annual suspended sediment yield is about 3.27
million tons which is equivalent to a mean concentration of about 2165 parts per million by
weight (ppm) at the intake site using the mean monsoon discharge of 116.32m3/s.
4-16
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
5.1 Introduction
This report summarizes a brief description of regional geology, a detailed geological,
engineering geological study in the project area and provides an assessment of the stability
conditions of head works, tunnel alignment and powerhouse structures as well as foundation
conditions of important hydro-technical structures.
5.2 Objectives
The main objectives of the present geological study are as follows:
• To obtain information on regional geology of the project area and site specific surface
geological condition in order to assess the suitability and stability of particular
structures
• To collect and analyze general and detail geology and geomorphology of the project
area and particular site
• To carry out detail geological maps, geological cross sections and profiles of major
project structures like head works, surge shaft, penstock alignment, power house and
tailrace area
• To determine and classify the physical properties of rock to design various hydraulic
structures
• Conduct field survey to collect and verify geological information prior to general and
detail geological mapping of project components and particular structures
• Identify geological and seismic hazards such as faults, thrusts and landslides etc.
5.4 Methodology
To accomplish the objectives and scope of work, desk study, field visit, and field data
analysis were carried out. During the desk study, available geological information and
geological maps of the Central and Western Nepal relevant to the project area was
5-1
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
thoroughly studied. After the desk study, the field visit to the project was conducted. During
the field visit, discontinuity survey and geological mapping of the project area including
headworks, tunnel alignment, adits, surge shaft, penstock alignment and power house area
was done. The instability and mass wasting studies and necessary geological data were also
collected. After field observation, the detail analysis of geological data was carried out which
includes graphical analysis, slope stability analysis and rock mass classification.
All these zones are extending from east to west and run almost parallel to each other. But
they differ in lithology, structure, tectonics, and geological history. There are several active
faults along which large landslides often occur.
5-2
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Project
Area
5-3
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The dip directions of rocks ranges from 200° to 250° (south to south west) with dip amount
ranging from 40° to 60°
5-4
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Figure 5-2: Regional Geological Map of the Project area. (Department of Mines &
Geology)
With respect to jointing, foliation joint is the dominated joint system in the rock mass. The
foliation joints have strike 070 to 250 degrees and dip ranging from 10 to 30 degrees towards
South west. In addition, one set of almost vertical prominent cross joint and random joints
can be seen along the rock exposure of tunnel alignment. The Vertical joints have strike 325
to 355degree with steep dip angle of more than 60 degrees towards North West is seems
critical. The foliation joints are relatively sheared and folded and are smooth undulating in
character. However, the cross joints are more rough and open in character.
5-5
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Quaternary Deposits
Alluvium
The Sani Bheri River is carrying a significant amount of sediments and gravel. The project
site is at the upper reaches of Sani Bheri River therefore the area is enriched with coarse
alluvium materials. Alluvium deposits are found along the left and right bank of the Sani
Bheri River and formed flat river terraces. It comprises mainly rounded to sub-rounded
boulder, pebble cobble, coarse gravel and sand of light grey coloured. Diversion weir, side
intake, gravel trap, approach canal and settling basin etc. lie on alluvium deposit. This is also
a potential source of construction materials for the project.
Colluvium
Colluvium deposit is heterogeneous soil covering the bed rock all around the mountain slope
by slope debris flow, landslide and slope accumulation by land dynamics. Colluvium
deposits are found at most part of the project area. It comprises of angular big boulder,
gravel and sandy silty clay matrix. Colluvium is light reddish brown, grey-to grey green colour
and contains about 40 percentage coarse materials and 60 percentage fine materials. Shape
of the materials is angular to sub-angular. A fine material contains sandy silty clay and it is
considered as heterogeneous soil. The most of the bed rock along the tunnel alignment is
covered by colluvium deposit.
Diversion Weir
The headworks site is selected considering the favorable location available in the area from
various aspects like foundation across the weir axis, stability of both side hill slope and
sediment deposit pattern. The proposed weir location is at an elevation of about 1050m and
the river is about 70m wide .The exposed rock (see plate 4-1) type at the both bank of
headwork’s site is predominantly metasandstone with thin layer of shale and slate. The rock
at the left bank is moderately weathered, thin to medium foliated with medium to high
persistancy having three sets of planner to undulating joints (including foliation plane) filled
with silt. The RMR and Q value of the exposed rock is about 40 to 45 and 0.4 to 1
respectively which is defined as poor rock. No slope instability problem is anticipated. Right
bank of weir consists of both bed rock and alluvium deposit.
5-6
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Plate 5.1: Location of diversion weir with exposed rock in both bank
Slope stability analysis of hill slope of weir axis area was carried out on the basis of aerial
photo interpretation, geological observation and geological data analysis. An analysis of the
foliation plane to determine the stability conditions of the rock mass at the intake and weir
area was done by using Lower Hemisphere Projection of the foliation plane and
discontinuities in Schmidt’s equal area net. The wedges formed by the planes were analysed
with respect to the hill slope surface. In Figure 5-3, foliation plane is opposite direction to hill
slope and similarly there is no significant wedge is formed. Hence, over all stability condition
at this area seems to be more or less stable.
5-7
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
N
Symbol Feature
Pole Vectors
J1
W E
J2
1:FP
Figure 5-3: Stereographic Projection of joint sets and hill slope in headworks site left
bank
Intake, gravel trap and Approach canal
The side intake and gravel trap lie in the bed rock as mention above. Approach canal lies on
the alluvial deposit. The alluvial deposit consists of rounded to subrounded boulder, cobble
and pebble of quartzite, limestone, gneiss and Phyllite. Estimated thickness of this deposit is
about >5m.
Settling Basin
Surface settling basin lies on the alluvial terrace deposit on left bank. The alluvial sediment is
light-grey to brown, medium dense, silty gravel. The settling basin area is primarily cultivated
land on flat area consisting gravel bearing pebbly and sandy soil with some boulders of
gneiss, schist and quartzite. The thickness of this deposit is more than 20m. The material
consists of sub-angular to well-rounded pebbles, cobbles.
5-8
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
2. 60/350 J1 (Joint)
3. 70/060 J2(Joint)
Rock Mass Classification using CSIR classification has been carried out in the vicinity of this
area which gave the RMR values in the range of 30-45. Thus, the rock can be classified as
poor. Rock quality is estimated and presented in Table 5.1.
N
Symbol Feature
Pole Vectors
J1
J2
W E
J3
1:FP
5-9
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
In general, the rock along the tunnel is considered to be very weak to medium strong in
strength. The rock is hard with expected to be intact compressive strength in the range of 2-
30MPa. The rock is highly to moderately weathered. The rock is exposed mainly in the small
streams and at higher elevation in the form of steep cliff and road cutting along the tunnel
route. Bedrock is mostly covered by very thin to thick veneer of colluvial deposit along the
tunnel alignment. No major faults and thrusts crossing the tunnel are noticed during the
present mapping however several thin bands of shear zones and local faults are noticed in
the tunnel route mainly along the tributaries. This zone is categorized as very poor to
extremely poor rock. The mapping in the river sections and hill slopes were projected to the
5-10
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
tunnel horizon in order to produce the required geological information along the tunnel route.
The geological condition along the tunnel alignment is mainly based on surface mapping.
The contour density diagram and stereographic projection of main joints for the headrace
tunnel are shown in Figure 5.5 & Figure 5.6.
N
Color Density Concentrations
0.00 - 1.50
1.50 - 3.00
3.00 - 4.50
4.50 - 6.00
6.00 - 7.50
7.50 - 9.00
9.00 - 10.50
10.50 - 12.00
12.00 - 13.50
13.50 - 15.00
Maximum Density 14.85%
Contour Data Pole Vectors
Contour Distribution Fisher
Counting Circle Size 1.0%
5-11
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
W 4 3 2 1 1 2 3 4 E
1 Tunnel
Figure 5-7: Joint rosette of major joint sets along the tunnel alignment
Properties of discontinuities measured at the outcrops along the surface of tunnel alignment
are tabulated below (Table 5.2, Table 5.3 & Table 5.4). Presently the characteristics of the
discontinuities at the HRT are inferred on the basis of the observed discontinuities on the
outcrops which might also be differing in actual underground situation.
5-12
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
5-13
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The tunnel covers about 14% poor rock mass, 33% of poor to very poor rock, 31 % poor rock
mass. The rest 22% is expected to cover by extremely poor rock mass. The rock
classification is based on surface geological mapping along the tunnel route and more
detailed geological condition will be achieved only after the excavation of the tunnel section.
The penstock alignment passes through slightly steep topography at the beginning,
moderate topography at the middle part and gentle topography at the end or just above the
powerhouse site. The geological condition of the penstock alignment is slightly poor, passes
through colluvium deposit. There is not any exposure of the bed rock along the alignment
however there is a possibility of bed rock at shallower depth.
5-14
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The tailrace will be a reinforced concrete box culvert aligned towards further downstream
from the powerhouse along the toe of the left hill slope to maintain the level from turbine axis
to the outlet at Bheri River. The tailrace alignment will passes through the alluvium river
terrace deposit. The alluvial deposit of this area consists of rounded to subrounded boulder,
cobble and pebble of banded gneiss, limestone, quartzite and phyllite. This is a light and
simple structure therefore there will not be any geotechnical problem for the foundation.
Power House
5-15
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Q= RQD/Jn* Jr/Ja*Jw/SRF,
Where,
The Barton’s rock support chart also incorporates equivalent excavation dimension, which is
the ratio between the span or height of an underground opening and an excavation support
ratio (ESR). The ESR mainly reflects degree of safety and support demand by an
underground opening.
Barton et.al (1980) provides additional information on rock bolt length. The length L of
rockbolts can be estimated from the excavation width B and the Excavation Support Ratio
(ESR):
L = 2+ 0.15B
ESR
Therefore by the above equation length of rock bolt for headrace tunnel in Sani Bheri 3 HEP
comes about 2.5m; however 3m is adopted for safety.
5-16
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Table 5-7: Predicted rock mass quality and support design for Headrace Tunnel
Rock mass Rock Assigned tunnel rock support
quality support
description (RS)
class
5-17
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Q=0.1 -0.5 RS V Wall and Crown: 25mmmm diameter 3 meters long systematic
grouted rock bolts at a spacing of 1.2m c/c and 12.5cm thick
steel fiber shotcrete.
The headrace tunnel will be in hydrostatic condition during its operation. Since the designed
rock support in the table is not water tight, the concept of pre-injection grouting should be
applied at the required length of headrace tunnel to control possible water leakage during
operation.
The tentative volume could be exploited from the mentioned deposit are tabulated in the
table below (Table 5.8).Most of the deposits consist of about 50- 60% coarse aggregate
(gravels to boulders) and about 30 - 40% fines (silt to sand).Coarse aggregate mainly
consists of lime stone (30%) gneiss (30%) , quartzite (25%) and phyllite schist (15 %).
5-18
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Plate 5-6: Potential site for construction material in river deposit at downstream of
headworks area
5-19
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Plate 5-7: Potential site for construction material in recent river deposit around
Powerhouse area
5.13 Seismicity
5.13.1 General
Evolution of the Great Himalayan Arc is the result of collision between the Indian and
Eurasian Tectonic Plates over a distance of 2400km from Pakistan in the west and Burma in
the east. The Himalayas are located near plate boundary. Therefore, Himalayan region is
considered to be seismically active zone. Seismic activity in the Himalayas results from the
strike slipping of the Indian basement along a sub-horizontal decollement interface, which is
known as Main Himalayan Thrust (MHT). It coincides with MFT in south and roots along MCT
is beneath the High Himalaya and southern Tibet. Magnitude and recurrence of Himalayan
earthquake depend upon the geometry and plate velocity of Indian plate with respect to
Tibetan plate. Convergence rate of Indian Plate in the Himalayan region is estimated to be
about 20 mm/year.
Thus, being a part of Himalayas, Nepal Himalaya is considered to be active seismic zone.
However, the existence of tectonic features such as Main Central Thrust (MCT), Main
Boundary Thrust (MBT) and Himalayan Frontal Fault (HFF) further accelerates the rate of
seismic risk. Therefore, proximity to such structural features is important while assessing the
seismicity of the Hydroelectric project.
Recent seismicity condition and historical records indicate that the Himalaya has
experienced recurrence of great earthquakes. National Seismological Centre (Department of
5-20
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Mines and Geology, 2006) has been recording small to medium sized earthquakes that
frequently occurring in the territory of Nepal. Earthquakes Epicenter Map of Nepal shows that
medium sized earthquakes (6 to 7 magnitude) are mostly confined to the MHT between the
foot hills and the Higher Himalaya, Figure 5.9. The data of the recorded earthquake indicates
that the recurrence of earthquake 6<M<7 in western Nepal is one time in six years, Table
5.6. However, uncertainty of the strong ground tremor is very high since the active fault
systems in the vicinity of the project area are not reported.
5-21
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Table 5-9: Recurrence of earthquake in Nepal between the period 1994 and 2000 (after
DMG, 2006).
Paleoseismology deals with the history of earthquakes: their location, magnitude and
frequency of occurrence. Thus, by study of the past occurrences of large earthquakes, it is
possible to forecast the likelihood of future earthquakes in terms of location, magnitude and
probable timing. It identifies and studies the source of earthquakes (active faults), their
potential to produce future large earthquakes from their past records, and to try to forecast
and provide information on future earthquake activity, usually using some probabilistic
approach. Paleoseismological activities in the Nepal Himalaya have been evidenced from the
sediments of Kathmandu valley and Terai plain (Gajurel et al., 1998; Nakata et al., 1998;
Lavé et al, 2005; Yule et al., 2006). A detailed active fault map prepared in the Nepalese
Himalaya indicates that source of earthquake i.e. active faults are situated very far from the
Figure 5-10: Active faults of Nepal Himalayas (Adopted after Upreti 2009)
project site (Upreti, 2009, Figure 5-10). Seismic hazard map prepared by Department of
Mines and Geology (2002) using a peak horizontal acceleration at bedrock has a 10%
probability of being exceeded over 50 years.
5-22
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Records of seismic activities are limited in the Nepal Himalayas and hence correlation of
seismic events with the adjacent Himalayan Region would be a useful source of information
for designing the hydraulic structures. Several Seismicity studies have been carried out for
various projects in the country during the study and engineering design phases and seismic
design coefficient are derived for those projects. Theoretically, Nepalese standard and Indian
Standard are two basic criteria to derive the design coefficient for the design of hydraulic
structures in the absence of detailed seismicity study of the projects. Therefore, based on
seismicity study carried out for other projects and theoretical methods, the basic design
coefficient for Sani Bheri 3 Hydroelectric Project can be derived based on Nepalese standard
and Indian Standard.
5-23
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
For the maximum acceleration of 200 gal according to Seismic Hazard Map of Nepal, Figure
5-11, (Published by DMG, National seismological Center - September 2002) and reduction
factor of 0.6 the calculated effective design seismic coefficient for the Project is
approximately 0.12 according to Nepalese Standard.
αc = α0 x β x I
Therefore, the design horizontal seismic coefficient for the weir at Project is 0.16 according to
Indian Standard.
5-24
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
5-25
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Head works constitute a diversion weir, intake and approach canal and settling basin. The
diversion weir will be founded on alluvial deposit. Similarly left abutment of weir, intake
founded on bed rock. Other structures will be founded on alluvial terrace deposit.
5-26
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The scattered boulders along the banks of the rivers can be crushed and used for coarse
aggregate. Deposits for fine aggregate are also adequate in the project area.
The following investigations are strictly recommended for the detail design of the project.
• Construction material survey and lab testing shall be carried out for the suitability of
coarse and fine aggregate.
5-27
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
For this study, all the measurements of length and elevations were taken using Google Earth
images which may vary from the actual values at site.
Maximum head can be achieved when the dam is located at the upper license boundary and
the powerhouse is located at the lower license boundary. In the case of Sani Bheri 3 HPP,
same principle is used for the initial location of the project components.
With the dam located at the upstream location of the project boundary, there will be no
reservoir for the peaking storage. The river is very wide at most of the half reach of the
project boundary. Hence the dam location is selected at the location where the river narrows
down to a gorge of about 50m. At this location, the dam width will be less and the wide valley
upstream provides for the storage required for the peaking.
Alternative A1: The dam located at the upstream most location of the project boundary
The project will be a simple Run-of-River (ROR) project with a free flow overflow weir. The
waterways are proposed to be a combination of headrace pipe and tunnel.
The total length of the waterways is about 11.8 km with a gross head of 165m.
The project will be Peaking Run-of-River (PROR) project with the peaking capacity of six
hours. The dam will consist of gated barrage and earthen dam. The waterways is proposed
to be completely tunnel.
The total waterway length is about 5.5 km with a gross head of 98m.
6-1
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
In this study, two alternatives are studied. The first alternative L1 is with the waterway on the
left bank of the river and the other alternative L2 with the waterway on the right bank of the
river. The descriptions of both the alternatives are described below.
6.2.1 Alternative L1
In this alternative, the project components are proposed to be located on the left bank of the
river.The dam is proposed u/s of the suspended bridge at Sisneri with a side intake on the
left bank. Settling basin is proposed about 320m d/s of the intake. The waterways consist of
pressurized concrete culvert, headrace tunnel and penstock pipe. The powerhouse is
proposed on the banks at Bhal Khola village. A tailrace of about 300m is proposed after the
powerhouse. The total waterway length is about 7.3 kms.
The elevation difference between the river water elevation at headworks and tailrace is 98m.
6.2.2 Alternative L2
In this alternative, the project components are proposed to be on the right bank of the river.
The dam location is same as in Alternative L1. The side intake is proposed on the right bank
with settling basin at about 230m d/s of the intake. The waterways consist of headrace pipe,
6-2
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
tunnel and penstock pipe. The powerhouse is proposed on the right bank of Sani Bheir River
at Bhal Khola village. The total length of the waterways is 6.45 kms.
The elevation difference between the river water elevation at headworks and tailrace is 95m.
6-3
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Comparing the length of the waterways, both the alternatives have almost equal waterway
length. Even if L2 has half of the waterways as headrace pipe, the cost for transportation and
installation of 5.8m diameter pipe will almost be similar to the cost of tunnel with increased
maintenance cost during the operation period.
6-4
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
After the study of all these issues, alternative L1 is chosen as the final layout for Sani Bheri 3
HPP considering the head, social issues and geology of the area.
6-5
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
A 38m long gated barrage and 35m long earthen dam shall divert the design flow. A side
intake having four orifices 4.0m x 4.0m is proposed. A low pressurized approach culvert of
length 316m delivers water to the settling basin. Three bay settling basin is proposed with
85m length, 11m width and 7m depth on the left bank of the river.
A low pressurized concrete headrace culvert of length 495m will convey water from settling
basin to the headrace tunnel. The tunnel is horse shoe shaped and is 6345m long. A orifice
type surge shaft is proposed at the end of the tunnel with an internal diameter of 16m.
A 4.1m diameter steel penstock of 195m length will deliver discharge to the 3 units of turbine
in producing the power.
The powerhouse and the tailrace structures are placed on the left bank of the Sani Bheri
River. A powerhouse of 48m x 16m size will be constructed in the plain area at an elevation
of 950 masl. Three units of vertical axis Francis Turbine are proposed in the powerhouse.
The tailrace water level after turbine is fixed at 944 masl.
7.3.2 Headworks
Headworks consist of peaking reservoir, barrage, earthen dam, intake, undersluice,
approach culvert, and settling basin. The components are described below.
7-1
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The reservoir shall be operated from FSL to MDL during the dry season only when the
sediment in the river is less and energy is required during the peak hours. The dry season is
considered for the months of December till May.
During the monsoon season (i.e. June till mid-October), the reservoir will be operated at the
MDL of 1050 masl also referred here as Monsoon Operation Level (MOL). In this season,
because of high rainfall and river discharge, sediment in the river is high. Hence, by
operating at the lower level, risk of live storage depletion is minimized.
7.3.4 Barrage
The barrage and earthen dam is located about 120 m u/s of the suspended bridge nearby
Sisneri. A gated concrete gravity barrage is proposed as the suitable diversion structure for
this purpose.
7-2
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The length of the barrage is 38m in length and the operating deck is 18.5m above the river
bed level. The operating deck is proposed at 1058.5 masl that is 2m above the FSL. The
barrage is proposed with three gates to pass the flood and flushing the sediment deposited in
the reservoir. The size of the openings is proposed to be 8m width and 9m high. The
openings are sized to pass the 100 year return period flood of 1100 m3/s as a free flow. The
openings are to be controlled by the provision of radial gates.
A stilling basin is proposed d/s of the barrage gates to dissipate the energy before releasing
the water into the river d/s stream. The length and depth of the stilling basin provided are
50m and 3m respectively from the river bed.
The stability of the barrage has been checked with the water elevation of the design flood.
The barrage shall be constructed completely with concrete. Similarly, the d/s slope of the
weir is proposed to have high strength concrete of at least C50 with steel fibres to protect
from scour.
The seepage protection beneath the barrage is proposed to be controlled by grouting works.
At present a preliminary estimate has been made, however, drilling and permeability test in
the barrage foundations are necessary to finalize the grouting possibility, type and depth.
The earthen dam is chosen as the earth material for the dam is easily available at the site.
The dam will have the base length of 81m and the width of 17.6m at the foundation to 35m at
the top. The top of the dam will have an elevation of 1058.5 masl.
The core of the dam will be constructed of impervious clay core and to prevent the surface
wearing, a layer of rock riprap is proposed.
The cost of the dam was estimated based on the volumes of concrete, reinforcement and
formworks. Similarly, the incremental revenue is based on the energy increased for every 1m
increment in the gross head of the project.
7-3
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
7.3.7 Intake
Side intake with four orifices is proposed. The dimensions of the orifice are 4.0m length and
4.0m height. The orifices are designed to have flow velocity of 1m/s at the design flow.
Coarse trash rack is proposed in front of the intake orifices to avoid trashes during the high
flows.
Four vertical sliding gates are proposed for the flow control. The operation platform is
proposed at 1058.5 masl above the designed flood elevation.
Intake gate will be closed and plant operation is stopped if the flood at river exceeds 1 in 5
years return period operation flood.
A trash passage channel is proposed above the intake to divert the floating trash d/s of the
barrage.
7-4
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Three basins are provided so that the power plant can be operated partially during the
flushing of one basin.
The total length of the settling zone is 85m with width of each basin as 11m. The average
flow velocity is designed to be below 0.2m/s for the design discharge. The inlet transition is
designed to have an inlet angle of 12°. The length of the inlet transition zone is 36m.
The flushing of the basin is proposed as conventional gravity flushing and intermittent. At the
end of the settling basin 2.0m diameter pipes are provisioned to flush the deposited
sediments back to the Sani Bheri River.
The settling basin is proposed to be covered. Since the project is a PROR, the water
elevation varies from 1056.5 masl to 1050.0masl. During the lean season, the sediment in
the river is minimum and the settling basin will be pressurized but during the monsoon the
settling basin will be a free flow basin. Hence, the floor of the basin is proposed at
1051.0masl.
Foundation preparation of the settling basin is the critical element. The basin will be founded
on a farm land and hence good compaction with the selected material is required for the
foundation. The compaction shall be done in layers of 15cm with selected cohesion less
materials. An in-situ density tests shall be carried out to have the bearing capacity of at least
200kn/m2.
Headrace culvert
A pressurized approach culvert is proposed convey discharge from settling basin to the
headrace tunnel. The culverts are proposed with the size 5.2m x 5.2m and the longitudinal
slope is 1 in 600.
Headrace tunnel
Headrace tunnel on the left bank hill is proposed as a main waterways system for Sani Bheri
3 HPP.
7-5
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
A horshoe shaped tunnel is proposed for the project as the rock in the project area is not of
very good quality (details in the Geology report). The tunnel is proposed to be completely
concrete lined because of the weak rock.
An optimization study on the tunnel size resulted in the finished diameter of 5.1m. However,
a tunnel of size with internal diameter 5.0m is proposed for the project. The c/s area of the
tunnel is 21.57 m2 and the length of the tunnel is 6430m from the inlet portal to the surge
shaft.
The optimization study of the penstock diameter considered the following input parameters:
7-6
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Even though the optimum pipe diameter is 4.2m, a diameter of 4.1m is proposed which will
increase the flow velocity to 4.01 m/s and is very much under the limit. This will have cost
saving in quantity of steel and transportation of the pipe. The thickness varies from 16mm to
28mm.
The shape of the blocks has been governed by the topography and the bend angle. All the
blocks will be constructed of plum concrete with C20 grade. Anchorage bars will be provided
around the bend and temperature and shrinkage bars will be provided on the surface of the
blocks.
All the blocks will be stable regarding sliding, overturning and bearing of the foundation.
The powerhouse consists of a reinforced cement concrete (RCC) structure that houses the
machine floor, control section and all the mechanical and electrical equipment. The size of
7-7
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
the powerhouse is 48.0 m x 16.0 m x 35.0 m. Three generating units of 15600 kW installed
capacity each will be accommodated in the powerhouse. There will be provision for the
auxiliary plants and service area. A concrete raft foundation is provided for the machine
foundation in the powerhouse.
A rectangular concrete conduit of 5.2 m x 5.2 m has been proposed to convey water from
powerhouse to Sani Bheir River. The length of this tailrace conduit is 230 m.
7-8
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The selection of unit capacity is based on the assumption that minimum number of units
could be installed for the more economic development of the project, reliability of generation,
and minimum loss of power during maintenance and operational efficiency at different stage
of time. Unit capacity is generally determined by considering the available discharge
throughout the seasons, load demand, type of operations, efficiency of the machine, etc.
Single unit is not preferred due to the fact that total generation loss will occur in the time of
the unit breakdown and hence three units will be suitable for the Project, considering the
minimum discharge which is 65.25 % of the Rated Design Discharge for each turbine that is
11.53 m3/sec. of Feburary. Considering the above factors, three (3) units’ arrangement is the
best option for the Project. Therefore, the study of Sani Bheri 3 Hydropower Project reveals
that the installation of three (3) generating units will be more economical and reliable for the
following reasons:
• With three (3) turbines, the peak power is the same as with four turbines and partial load
efficiency will also maintain the required standard and be fine.
• In dry season, one unit shall run at nearly 2/3 of full load and hence the turbine
performance and efficiency will be high for selection of three turbine as it relates to
higher efficiency (i.e Efficiency Greater than 88 %) of the generating units.
• The required repair and maintenance works of the power units (which are in idle
condition) can be performed in the yearly dry season in such a way that with the
exception of a temporary reduction of the plant power, no energy loss will occur.
7-9
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The Shaft Power Output of each Turbine is calculated by the following relation:
Where,
ηt = turbine efficiency = 92 %
Therefore,
= 16,304.96 kW
Similarly, the Plant Installed capacity is determined by multiplying the Turbine output by
generator efficiency (0.97).
= 16,305x 0.97 kW
= 15,734.325 kW ~ 15,734 kW
Therefore, the Installed capacity of the plant is 3 x 18,510 x 0.99 x 0.85 KW = 46,728.495
kW. Thus, the adopted capacity of plant is 46.7 MW.
Runner
The runner will be of the reaction type. The turbine runner shall be of integrally casted disc
type having stainless steel quality with 13-4 Cr-Ni material. The blades are manually ground
to the hydraulic shape. The runner will be designed to withstand the loads imposed by any
7-10
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
combination of fully open wicket gate operation at any speed including maximum runaway
speed and maximum head without exceeding the stress limits.
Runner shall be coupled with shaft through shear pin & central bolt. The runner and shaft
coupling are realized by several pins that transmit the torque. This design with central bolt
and shear pins consists of a central bolt from draft tube side to fix the runner to the shaft. The
torque transmission to the shaft shall be done via shear pins. The Francis runner is shown
below.
Spiral Casing
The spiral case is a welded structure which is semi embedded vertically. Major components
of the spiral case are its segments, stay rings and stay vanes. Stay ring is a welded steel
plate designed to direct water from spiral casing to the wicket gate. The stay ring is provided
with adequate number of fixed stay vanes. The spiral case also consists of an inlet flange for
connection to the main inlet valve. It incorporates foundation feet and anchor bolts for
levelling the foundation feet. A hand hole for inspection purpose is included. In addition, a
drainage pipe connection at the lowest point of spiral case as well as a by-pass connection is
provided.
Connection tabs for instrumentation and air relief valve at the top most point of the spiral
case are provided.
Spiral case and stay rings are designed to withstand maximum transient pressures under the
worst condition of head and load with adequate safety margin. Hence, the spiral case will be
pressure tested in workshop at 1.5 times of the design pressure.
Head Cover
The function of head cover is to seal the turbine room from water leakages and take the axial
load acting on the runner crown side chamber. In addition, it contains the wicket gate
bearings and gives support to the shaft seal housing. It also contains the runner seal wearing
rings. The contact surface at the wicket gate blade position is corrosion protected by facing
plates. The wearing ring provides a seal between the runner and the stationary part of the
turbine and is bolted to the head cover assembly. Inspection holes are provided to check the
seal gaps.
7-11
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The head cover consists of head cover, facing plates, coupling connection with stay ring,
hole for wicket gate stem bearing, coupling provision for runner crown seal wear ring, holes
for relief pipes, connection for clearance check at crown seal position and coupling provision
for shaft seal.
The head cover is a single plate design made of Structural Carbon Steel plates according to
IS 2062.
Bottom Ring
Bottom ring contains the wicket gate lower stem bearings. Welded discharge ring assembly
consists of the bottom ring and discharge ring welded together. The wearing ring shall be
bolted with the discharge ring from the draft tube side.
Bottom ring and discharge rings are made of Structural Carbon Steel plates according to IS
2062.
Wicket Gates
The wicket gates are machined according to hydraulic shape and are mounted between the
Head Cover & Bottom Ring. To allow for smooth movement of the Wicket Gates, self-
lubricating bearings are used. The self-lubricated bearings are mounted in the bearing
housing. A thrust ring is provided at the upper stem. The wicket gates are casted from ASTM
A 743 Grade CA-6 NM.
Draft Tube
The draft tube shape is hydraulically optimized and is of circular shape design. As an
embedded part, the draft tube is normally assembled at site depending upon its size. The
draft tube cone is of welded steel plates and have machined flanged for bolting with turbine
discharge ring. The draft tube is reinforced sufficiently on the outside by means of suitable
ribs.
All parts of draft tube are made of Carbon Steel Plates according to IS 2062.
The turbine runner will be directly mounted on the extended shaft of the generator. For
smaller sized machine, this type of arrangement is usually adopted and has benefits like
easy installation, lesser space for turbine-generator and is economical.
7-12
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
4 Rated efficiency 92 %
7.6.1 General
The purpose of the study pertaining to electrical equipment is to identify and dimension the
principal components of the powerhouse electrical equipment for safe and economic plant
operation of Sani Bheri 3 Hydroelectric Project. The powerhouse electrical equipment of the
project includes generators, transformers, switchgears, protection schemes, control systems,
earthing systems, lighting systems, communication systems, etc. The ratings of the
equipment are designed safely to cope with all normal and fault conditions, avoiding any
overstressing of material and equipment. Also, equipment will be of standard design
(IEC/IEEE/IS/BS whichever is applicable), providing highest degree of safety, reliability,
availability and ease in operation.
7-13
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
7.6.2 Generator
Self-excited, self-regulated, vertical axis, three phase, cylindrical pole synchronous
generators built in accordance with IEC standard are proposed to be used. The generators
will have capacity to incorporate sufficient flywheel inertia to achieve stable frequency control
when running in isolated mode. The generator shall have anti-friction / sleeve bearing.
The stator core of the generator will be constituted of stacking of laminations made of silicon
alloy steel sheets. In the axial direction the stator core is subdivided into a number of partial
stacks separated by spacers. These spacers form radial cooling ducts allowing the cooling
air to pass. Stator winding of the generator is a double layer, multi-turn lap type coil winding.
The stator winding is short pitched to suppress harmonics and to obtain nearly sine wave
curve. It will be made of individually insulated stranded copper conductors, stacked and form-
pressed to constitute coils or half coils with the design cross section. Each coil will be
insulated for the full generator voltage.
The rotor will be of the cylindrical pole type and built in accordance with the best practice and
designed to withstand safely all overloads and other stresses encountered during abnormal
operating or runaway speed conditions. The poles will be built of thin steel laminations,
bolted under high pressure and furnished with dovetails for fastening to the rotor rim. Rotor
will be designed so as to allow dismantling of the poles without excessive disassembly of the
stator or rotor.
The damper winding will be installed on pole faces with interconnecting type windings in
order to maintain the stable operation of the generator. The generator will be capable of
withstanding, without damage, a 30-second, 3-phase short circuit at its terminal when
operating at rated MVA, at rated power factor and at 10% over voltage with fixed excitation.
The generator shaft will adopt single shaft structure. It will have maximum rigidity and
strength so as to guarantee no abnormal deformation and vibration at various speeds (inclu-
ding maximum runaway speed) when run together with the turbine. The generator shaft shall
be made of a high-quality medium carbon steel, properly heat treated and accurately
machined all over and polished at the bearing surfaces and at all accessible points for
alignment checks. A complete set of test reports covering metallurgical strength & ultrasonic
tests performed on each shaft shall be furnished.
The generators will have enough electric heaters and de-humidifiers and arranged in fan
shield of generator to protect them from moisture during shut down and to enable a start up
at any time without drying procedure. Insulation and other parts of the generators will not be
damaged when electric heater runs.
Resistance type temperature detectors of PT-100 simplex / duplex type shall be installed
between the upper and the lower layer of the same phase and are symmetrically distributed
in the stator winding over all three phases to indicate the temperature obtained during
operation. An auxiliary terminal box having suitable terminal blocks shall be mounted on the
generator frame to terminate the resistor element connections. The temperature detector
leads shall be kept flexible to facilitate disconnecting them without breakage.
7-14
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
3 Number 3
5 Generator Voltage 11 kV
6 Frequency 50 Hz
7 Class of Insulation F
8 Protection IP54
10 Efficiency 96.5 %
11 Heating class B
12 Number of Poles 20
Generator fire protection will be provided by CO2. The activation of the CO2 fire protection
system will be conditional to the operation of the flame or smoke detectors in the generator
hall combined with the operation of the generator differential protection or a manual push
button instruction. Upon receipt of a signal from the fire detectors and of the generator
differential relays, an alarm will be initiated. The CO2 release will only be initiated after a
preset time delay in order to allow evacuation of the personnel in the hall at that moment
unless the operation is aborted by manual interruption instruction.
The generator shall have following major protection systems:
a) Reverse power relay,
b) Loss of field relay,
c) High speed trip relay,
d) Generator differential protection relay,
e) Under and over frequency relays,
f) Loss of synchronization relay,
g) Field ground detect relay,
7-15
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The switchgears will be provided with housing to install the required set of current
transformers and potential transformers for metering and protection.
Each generator will be synchronized on 11 kV vacuum circuit breaker. All the generator
circuit breakers and fuse switches will be arranged in one continuous row accessible from
the front side with sufficient space on both side of the switchgear assembly for safe
operations. Individual switchgear panels for each generator incomer and outgoing feeder will
be provided to complete the generation level switchgear system.
This switchgear system will work in co-ordination with the control panels accommodated in
the control room.
7-16
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The protection against voltage spikes shall be provided. The AVR shall have fast response
and anti-hunting features. The AVR shall be provided with cross compensating devices for
parallel operation of generators.
The excitation transformer of sufficient size, with 11 kV on primary side shall be used. The
Transformer shall be of dry type.
The excitation shall be suitable for maintaining the voltage for a grid voltage variation of ±
10% & for a frequency variation of ± 5%. The AVR shall be sensitive enough to track and
respond the changes up to +/- 0.5% of normal voltage (average of 3 phases) of the
Generator when operating under steady load conditions (for any load) or excitation within
operating range and shall initiate corrective action without hunting. The response time of
excitation system shall be less than 20 ms.
After the initial maximum voltage following any load rejection up to 100% of rated load, the
AVR shall restore the terminal voltage to a value not more than 5% above or below the
voltage being held before load rejection and shall maintain the voltage within these limits
throughout the period of generator over speed.
a. Two auto channels with one manual mode for voltage control
b. Voltage / frequency during accelerating and decelerating of machine
c. Power factor / KVAR control mode
d. Reactive power shedding
e. KVAR limit
f. Short circuit limit
g. Diode failure indication
Besides these, equipment for limiting and regulating (both automatic/manual mode) on
generator rotor current shall be included. Voltage setting devices and necessary control
switches shall be included. This equipment shall be of a tropical design and shall work
satisfactorily at a temperature of maximum 40°C.
7-17
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
1 Number of Transformers 2
3 Cooling ONAN
4 Rating 30 MVA
7-18
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
11 Efficiency ≥ 99 %
The transformer will be installed outdoor. The transformer will be oil immersed and designed
for the cooling system as specified. The transformer will be capable of operating continuously
at its rated output at all tap positions without exceeding the temperature rise limits.
The incoming side (low voltage side) will be suitable for terminating appropriate sized XLPE
cables inside the cable terminating chamber. The termination arrangement will include cable
terminations for delta connection of the transformer windings besides the phase cable
termination. The outgoing side high voltage terminals will be brought out through high voltage
bushing for connecting to other high voltage apparatus of the switchyard. The neutral points
will be brought out on suitable bushings installed and will be solidly grounded via appropriate
conductors. Following Protections are implemented in Power Transformers at Sani Bheri 3
Hydroelectric Project.
7-19
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
7.6.9 Switchgears
Sani Bheri 3 Hydroelectric Project consists of two (2) numbers of AC generators each rated
11 kV, 50 Hz, 13,330 kVA, 0.85 power factor (lag) and connected to 132 kV system outdoor
switchyard through two (2) numbers of 3-phase power transformers each rated at 14.50
MVA. Each generator output is connected to the 11 kV busbar through a 11 kV switchgear
consisting of vacuum circuit breaker (VCB).
Each generator shall be synchronized with 11 kV Vacuum Circuit Breaker (VCB). All the
generator circuit breakers and fuse switches will be arranged in one row accessible from the
front side with sufficient space on both sides of the switchgear assembly for safe operations.
There will be following number of switchgears in PH.
Table 7-5: Data for Generator and Transformer Incomer Circuit Breaker
7-20
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The indoor current transformers will be designed to carry continuously a current of 120% of
the rated current. The rated current of the secondary windings will be 1 A.
4 Insulation Level:
The burdens of all windings will not be less than 125% of the overall computed (design)
burden of the connected apparatus including cables.
7-21
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The outdoor lightning arresters will be mounted on steel structures and will be fitted with a
pressure relief device. Surge counters shall be supplied. The earth conductor from the
arrester to the counter, as well as the terminal of the counter, will be suitably insulated or
screen protected against accidental touching.
The Lightning Arrestors for the protection of generator will be of rated arrestor voltage of 10
kV.
7.6.13 Governor
Each turbine is controlled by a microprocessor controlled proportional integral derivative
(PID) governor in combination with the oil pressure unit to operate the turbine guide vanes
for regulation of the unit. The main features of the governor include:
7-22
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
For maintaining oil pressure in the system, a jockey pump is supplied. Essential controls and
piping connections to the governor relay valve and servomotors of the turbine guide vane is
also provided. The capacity of governor pumps and servomotors for wicket gate and inlet
valve shall be suitably selected. Further discussions on oil pressure unit are provided on
succeeding sections.
The governor panel and oil pressure unit will be located on the turbine floor near to the
turbine.
The crane will be complete with drives for cross travel, long travel and lifting motion, runaway
rails of adequate size, end carriages & gantry rail. All motions operated from a pendant,
operated by an operator on the machine hall floor.
The gears will be helical type and all bearing and other wearing surface will be splash oil
lubricated. The DC Electromagnetic shoe with EHT braking system will be provided.
7-23
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
One no. of float and float cum boost charger (SCR controlled) operating on 3-phase, 415 V,
50 Hz, AC supply of solid-state design to charge the battery shall be used. The operation of
the charger shall be automatic. Normally, float charger will be feeding the load and charging
battery. In case battery requires boost charging the same shall be done automatically.
The low grounding resistance will be achieved by increasing the grounding area i.e.,
interconnecting the powerhouse ground system with the tailrace pond and other areas (as
7-24
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
satellite area). The ground resistivity measurements will be required which will be performed
during the detail design of the grounding grid.
Power House roof shall be provided with lightning spikes properly connected to ground mat.
In the control room one or more telephone services will also be installed for trunk dialing
communications with the LDC and other substations.
An automatic PABX telephone system is envisaged for the communication between different
sections of powerhouse, offices, the residence of operational staffs, guard house and head
work area.
7.6.20 Illumination
400V/230V, 50 Hz, 4-wire star connections supply will provide single phase supply for the
illumination circuits for normal lighting. The normal lighting in the rooms of the power house
through corresponding Distribution Boards (DBs) will be by energy efficient LED fixtures.
Apart from this arrangement, emergency DC supply circuits and fixtures will provide
illuminations, in critical areas when supply from Station auxiliary transformer fails. In the
entrance incandescent lamp lighting fixtures will be installed. The lighting level / illuminations
designed are presented below:
• 450 lux – for the Control room, Office room, Electrical workshop, Mechanical workshop,
service bay in the Alternator/Generator floor.
• 300 lux – for the LV-switchgear room, MV- switchgear room, Battery room and other
facilities.
• 200 lux – for the pump pits and surge shaft area.
• 150 lux – for the stair cases.
Socket outlets will be provided in the office room; control room; battery room and service
bay, alternator and turbine floor.
7-25
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
The computer supervisory and control system shall have station control level and local
control unit level.The station control level, real time supervisor and control center of the plant
shall be responsible for automatic functions of the whole plant (AGC, AVC, generating
optimization control etc.), historical data process (various operation tables, operation
archives of important equipment and various operating parameters etc.) and man machine
dialogue of whole plant (operation monitor of plant equipment, accident and failure alarm,
manual intervention of operating equipment, modifying and setting of various parameters for
the Computer Supervisory and Control System). Station control level shall be made up of the
relevant equipment located at computer room and central control room. The computer will
adopt dual computers for redundancy and hot standby. At normal condition a computer
works and the other is backing-up. When master computer receives failure, the computer is
changed-over by back-up.
The local Control unit (LCU) shall have turbine-generator local control unit. Each LCU shall
manipulate production procedures and accomplish the supervision and control functions
under controlling. LCUs will be connected with the production procedures by means of input
and output interface, with the network by communication interface and exchanging
information with control level through network. The information shall be exchanged among
LCUs. LCUs may be independent from control level relatively. They shall directly finish real
time data acquisition and pre-processing, supervision, adjustment and control etc. of unit
equipment conditions with station control level divorced.
The operator’s console in the central control room shall be equipped with CRT display that
displays operation conditions of the power station. When the power station is under normal
operation, the operator can monitor the conditions of each equipment in the power station.
The major monitoring items shall be as follow:Operating conditions and output of generating
units
When the system receives any fault or the equipment has abnormality during operation, the
supervisory control system shall automatically give alarm in both sound and picture striking
to the eye to indicate nature, location, time and abnormal parameter values of the event.
7-26
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
moderately polluted environment. The switchgear system for this switchyard shall be
equipped with circuit breakers, current transformers, potential transformers, disconnecting
switches with/without earthing and lightning arrestors and synchronous check relay, etc. for
132 kV incoming and outgoing circuits. The switchgear system here will work in coordination
with the associated control panels accommodated in the control room and shall ensure the
overall protection of the switchyard.
Table 7-10: Data for 132 kV Bus Bar Outgoing/Incomer Circuit Breaker
4 Frequency 50 Hz
7-27
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
7-28
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
4 Insulation Level:
7-29
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
for hot, humid and moderately polluted environment. The switchgear system for this
switchyard shall be equipped with circuit breakers, current transformers, potential
transformers, disconnecting switches with/without earthing and lightning arrestors, metering
units, etc. for 132 kV outgoing circuits as per the arrangement and standard of the already
installed electrical equipment over there; complete connection scheme shall be finalized
during the connection agreement. A single line diagram for the standard Interconnection
arrangement is provided in the List of Electrical Drawings. The switchgear system here will
work in coordination with the associated control panels accommodated in the control room
and shall ensure the overall protection of the switchyard.
In addition, KW meter, KVAr meter, PF meter, Ammeter and Voltmeter shall be installed at
control panel inside control building of substation for 132 kV system to measure respective
quantities.
7.10.1 General
The purpose of the study pertaining to hydraulic steel structures is to identify and dimension
the principal components of the hydraulic steel structures for safe and economic plant
operation of Sani Bheri 3 Hydroelectric Project.
Hydromechanical works to be done at Head Works, Settling basin, Tunnel Inlet, and Tailrace
of sani Bheri 3 Hydroelectric Project mainly consist of the following:
Head Works
• Barrage
7-30
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
• Undersluice gates
• Stoplogs
• Intake gates
• Trashracks
• Stoplogs
Tailrace
Width 8.00 m
Height 9.00 m
Quantity 3 Sets
7-31
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Width 8.00 m
Height 9.00 m
Quantity 3 Sets
Clear width : 4m
Height : 5.20m
Four sets of trashrack will be provided at the Intake for the purpose of preventing injurious
matter and floating matter going to the water turbines and other equipment. Clear opening
(width between bars) of the rack bars will be smaller than the smallest opening between the
runner blades. Trash rack will be designed to withstand the impact forces, static loads and
vibration phenomena which are likely to occur due to the flow of water through rack bars.
Suitable trash cleaning equipment will be provided at coarse and fine trashracks.
Each trash rack will be made of structural steel plates spaced parallel to each other by
spacers. It will be supported by horizontal beam, built up type construction and fixed by the
steel bolts, nuts and washer. Rack bar spacing will be of suitable size.
It will consist of the bar elements, supporting beams and all other necessary components.
The trashrack panels will be fixed on the supporting beams using corrosion-resisting bolts,
nuts and washers. The bars elements of the trash rack will be of rectangular section bars.
Suitable thickness of the bars shall be used. All bar elements shall be rigidly fixed on the
supporting beams to prevent vibration.
Supporting beams will be of I-beam, H-beam, built-up and/or angle type steel construction
and all or both ends of the beams shall be embedded in the concrete structure. The
7-32
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
maximum deflection of the supporting beams shall be less than 1/500 of the clear span at the
center under full load.
Height : 5.20m
7-33
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Density of the steel is 7850 kg/m3. Penstock will be designed to take of internal and external
pressure by shell itself. Total length of penstock pipe is 180m and the internal diameter of the
pipe is 4100mm. Thickness of the steel penstock pipe will vary from 16mm to 28mm.
7-34
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
8.1 General
This chapter deals with the power generation from the project. The energy from the plant is
computed based on the available hydrological data, gross head available and head loss in
different forms (entrance loss, friction loss, transition loss, bend loss and exit loss). The prime
factor in generation of electricity is the discharge which in fact varies daily and seasonally.
Moreover, the efficiency of the turbine and hydraulic loss of head also vary with variation of
discharge. The generation of monthly energy considering the above factors has been
discussed in this chapter.
8.2 Methodology
Energy generation varies according to the available discharge in the river. There will be daily
and seasonal variation in the flow and hence will be the production of energy. The water
surface elevation (FSL and MDL) will also be different according to the season which is
considered in the estimation of energy.
The plant capacity of this project at 40% exceedance flow is 46.30MW and the
corresponding design discharge is 51 m3/s. The generated energy will be sold to Nepal
Electricity Authority (NEA).
8-1
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Minor losses occurs when water passes through structures like trash racks, bends, bell
mouths, etc. which directly obstructs the flow of water. All the minor losses are the function of
V2/(2g),
Where,
V= velocity of flow
For trash racks it depends upon the angle and spacings of bars.
For inlet and outlet transitions, Ko depends upon ratio of inlet and outlet diameters.
For horizontal and vertical bends, it depends upon angle of bend and the ratio of radius of
bend to the diameter of pipe.
The headlosses for different discharge estimated in Sani Bheri 3 HPP is presented in
8.4 Outage
The outage of Sani Bheri 3 HPP is considered as 2 % which is a usual practice by NEA.
8-2
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
8-3
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
9.1 General
Feasibility study shows that the project is technically and financially viable and worth for
implementation. Financial analysis has been carried out to check the feasibility of this project.
Accordingly the implementation schedule of Project has been prepared for the construction
of the project.
Critical sequences of major project activities following the take-over of the project
implementation are as follows:
• Commissioning
Project construction schedule and cost estimate of the project are prepared on the basis of
the present study. It will be refined during the detailed engineering of the project.
9-1
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Construction power required will be approximately 1.5 MW at peak load. The number and
capacity of transformer are estimated, as mentioned in the Table below.
Once river diversion work is complete the construction work will commence from the
excavation at the left bank at the intake, flood guide wall areas. After the excavation the
foundation work for upstream flood guide wall, undersluice, right part of diversion weir and
intake will commence. The part of construction of all these structures will be completed within
a single first dry season so that monsoon flow will not affect the construction at the upper
parts of undersluice, intake, etc. Remaining other structures will be started after the monsoon
is over.
9-2
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
will be started from the parallel sections. It will be divided into panels having expansion joints.
The transition section and the gate structures will be completed at the later stage of the
works. The bottom portion of flushing conduit works will be completed before
commencement of works of head pond. The head pond and spillway works will be completed
in parallel.
Horse shoe shaped tunnel will be fully concrete lined and the finished size will be 5.2 m
diameter section. Shotcrete lining will be carried out simultaneously with the tunnel
excavation as a primary support. In shear zone or fault zones, steel rib support will be
provided immediately after full face drill and blast or heading and benching. Total
construction time for the completion of headrace tunnel has been estimated as 42 months.
Total time required for the excavation of surge shaft including excavation, rock bolting and
shotcrete lining is estimated about 10 months. Concrete lining will be executed after
completion of excavation works.
9-3
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Powerhouse works will commence with protection works at the upstream end that will ensure
safety from river flood and seepage to the powerhouse area. Excavation work will be
followed by foundation concrete, installation of sump pits and other hydro-mechanical items,
superstructures, installation of electro-mechanical item and final finish work. In parallel the
work at tailrace canal and switch yard will be carried out.
• Cement
• Coarse aggregates
• Fine aggregates
• Reinforcement bars
• Explosives
• Diesel
9.4.2.2 Gravel
Required quantity of aggregate available from the potential borrow areas within 5 km range
from the construction site is sufficient for this project. Other borrow areas along the Sani
Bheri River in the downstream are the potential sources of aggregates from where deficit
9-4
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
quantity can be fulfilled. Rest of aggregates required shall be obtained from the quarry site
and by processing of the excavated materials.
9.4.3.3 Explosives
For the underground excavation work, emulsion type explosives should be used for the
better performance. Such explosives will be managed from the Nepal Army and alternatively
imported from Indian market. To achieve better result of tunneling works the explosives play
vital role. For the surface excavation in rock and boulder blasting, explosive products of
Nepal Army will be utilized. All types of detonators need to be imported from Indian market.
Package 2.1: Surface works: Headworks structures, settling basin, Anchor block,
Powerhouse, tailrace etc
Package 2.2: Underground works: Headrace tunnel, surge shaft, construction adits, penstock
tunnel etc.
Package 3.1: Design, manufacture, supply and installation of gates, trash racks, stoplogs,
valves, hoists and cranes.
9-5
Sani Bheri 3 Hydroelectric Project Feasibility Study
Main Report
Design, manufacture, supply and installation of electrical and mechanical equipment (turbine,
generators with accessories, transformers and electrical auxiliaries)
Design, supply and installation of transmission towers and stringing as well as construction of
sub-station facilities.
9-6
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
9-7
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
9-8
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
10 COST ESTIMATES
10.1 Introduction
This section of the report describes the methodology used for derivation of the project cost
and the estimated costs. This final estimate is based on the detailed layout and study of the
optimum project configuration selected from the optimization studies. The rates are based on
different projects in Nepal, Planned or under construction in the past five years. The rates are
based on 2020 price level.
Quantity take offs were carried out on the final drawing with plan metering, as required. The
estimate process was carried out in parallel with Construction Planning presented in chapter
9 as these activities are complementary to each other.
• The cost estimate and financial analysis has been based on the NPR.
• All costs has been first estimated on a per unit basis for each of the components and
then added to obtain the entire project cost.
• Material costs reflect real costs incurred at other projects of similar size or having
similar scope of works.
• Construction material obtainable from the local market whereas some of the steel
items and all of the electromechanical equipment need to be imported.
• Some skilled and all of the semi-skilled and unskilled manpower can be obtained
locally.
• The unit costs include profit, and overhead, which the contractor would charge.
It is expected that an open competitive bidding supposed to be for awarding the contracts
and the project will not be forced to use higher rates for any reason.
10-1
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
• Tunnel
• Surge Shaft
• Penstock Pipe
• Turbine
• Generator
• Transformer
• Auxiliary equipment
• Construction Camp
• Physical Contingencies
• Division of the project into a number of distinct structures like head works, settling
basin, headrace tunnel, surge shaft, penstock pipe, powerhouse, switchyard and
tailrace etc.
• Calculation of the appropriate quantity of each item from map and drawings
• Calculation of cost for each structure by summing up costs estimated for different
component.
10-2
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
• Interpretation of budget prices supplied by potential suppliers, mainly for the large
and more expensive equipment such as turbines, generators, power transformers,
and main inlet valves.
• Percentage of lump sum provisions on a ratio basis based on experience, for lesser
miscellaneous items.
• The cost of the transmission lines were based the current costs incurred in
transmission line construction by NEA.
10-3
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
• A provision has been made for the health and security item covering the costs of
overalls, construction boots, helmets and gloves as well as consumables at the first
aid centers supplied by contractors and owner.
10.5.7 Contingencies
The estimated costs include contingencies which allow for unforeseen cost increases that
may become necessary as more information is obtained and evaluated. In view of the extent
of investigations carried out to date, the present stage of preliminary designs and cost
analysis performed, the following contingencies have been allowed:
• Hydro-mechanical 5%
• Prequalification of tenders
• Evaluation of tenders
• Management of procurement
10-4
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
10-5
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
10-6
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
11 PROJECT EVALUATION
The ultimate aim of a power project is to produce power and energy at financially viable cost.
Financial analysis takes the view of the individual project participants. The financial costs
associated with project are based on normal accounting conventions. Thus, assets are
valued in terms of their engineering costs and are depreciated over their normal lives which
may be determined by law rather than technical or financial criteria.
Financial analysis is connected with the estimation of the financial implications of a proposed
development. It is based on the use of market prices and therefore includes any taxes or
royalties which will be levied on the factors of production and any subsidies, capital or
operating, which may be received as part of development. All costs are charged and all
revenues credited to the analysis in the actual amounts expended or received at the time of
expenditure. For this analysis the financial rate of return and cash flow is assessed from the
perspective of a utility owner/operator.
Financial analysis is done for the leased period, which is 30 years. Base year for the cost
and benefit is taken as 2020.
11-1
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
• Taxable amount is equal to gross revenue less O&M cost, royalty, interest on loan
and depreciation value.
• Debt cover ratio is equal to gross revenue less tax, royalty, O&M cost and EM
replacement cost over interest on loan and loan repayment.
• Royalty applicable for small Hydroelectric project (>10 MW) is NRs 150/kW plus
1.85% of gross revenue for the first 15 years of operation and NRs 1200/kW plus
10% of gross revenue after 15 years according to policy of GoN.
11-2
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
BC ratio 1.41
11-3
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
Table 11-2 presents the financial indicators computed for the project. Minimal criteria of
financial feasibility are net present value (NPV) must be positive, benefit cost ratio (BC ratio)
must be greater or equal to one and financial internal rate of return (FIRR) must be greater or
equal to opportunity cost of capital. In this case opportunity cost of capital could be
considered as prevailing interest rate of bank. From the above criteria this project is
financially feasible. Utility or operator may want to know the rate of return on his investment
after bank financing. Hence return on equity (RoE) also presented in this financial analysis so
that operator can have idea about how much return he will get on his investment.
11.8.4 Results
The result of sensitivity analysis for the selected is presented in Table 11-3. The base case
has been highlighted.
11-4
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
From the financial analyses of project; financially the project looks viable as the NPV is
positive. The benefit cost ration (BCR) is more than 1.0 thus on the safer side. The sensitivity
analysis reveals that the project is still feasible even with 10% increase in estimated cost and
10% decrease in estimated dry energy.
11-5
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
About 3km long access road needs to be built to make access to the project area.
About 4 km long single circuit 132kV Transmission line is required to evacuate power from
this project’s powerhouse up to proposed Baphikot Substation of Rukum District.
Financial analysis is carried out with the assumption that the developer will invest it in local
currency. Developer Company will arrange the required finance through commercial banks
and equity. The project will be developed according to the prevailing Hydroelectric policy.
The entire energy will be sold to Nepal Electricity Authority through a mutually agreed power
purchase agreement.
Total annual energy generation after 2% outages comes out to be 255.90 GWh. Out of which
177.07 GWh is the wet energy and 78.82 GWh is the dry energy.
Cost estimate of Sani Bheri 3 Hydroelectric Project has been carried out based on 2020 price
level. Major cost components are divided into Land and support, Pre-operating expenses,
infra-structure works, main civil works, hydro-mechanical works and electromechanical works
& transmission line works. Cost of value added tax and contingencies have also been
considered in the cost estimate. Total construction cost of the project without interest during
construction as of 2020 is estimated at NRs. 8250.12 Million.
Financial analysis of the project is carried out to assess the financial viability of the project.
PPA is expected to follow the prevailing practice in Nepal. i.e. NRs. 8.40/kWh in the dry
season (off peak), NRs 10.55/kWh for dry season peak and NRs. 4.80/kWh in wet season
with annual escalation of 3% for eight times from the commercial operation date.
12-1
Sani Bheri 3 Hydroelectric Project Updated Feasibility Study
Main Report
Internal rate of return of the project works out to be 14.09%. Likewise, benefit cost ratio is
1.41 and NPV is NRs. 2964 million.
12.3 Conclusions
Proposed run-of-river project of 46.72MW on the Sani Bheri River, located on Rukum District,
is not only technically feasible but also financially attractive. Based on the feasibility study,
this project is recommended for implementation at the earliest.
12.4 Recommendations
Following are the recommendations made during this stage of the study:
• Hydrological review is necessary to confirm the design discharge and low flows. With
the measurement started by fixing gauge station some year back, data measurement
shall be continued and re-analysis is necessary based on recent measured data.
• Efficiency of the hydraulic structures largely depends on the quantity of sediment flow
in the river. The effective way of estimation of the sediment is the measurement
during the monsoon periods. It is recommended for the daily sediment measurements
during next monsoon.
• Geotechnical Investigations like geophysical survey and core drilling are also highly
recommended.
12-2