Professional Documents
Culture Documents
Chapter One
Chapter One
Chapter One
By
Abera Alemayehu
Advisor
Dr. DD
Thesis Submitted to the School of Research and Graduate Studies of Bahir Dar Institute of
Technology, Bahir Dar University in Partial Fulfillment of the Requirement for the Degree
of Master of Science in Power System Engineering in the School of Electrical and Computer
Engineering
[1]
DECLARATION
I, undersigned, declare that this thesis is my own original work, has not
been presented for a degree in this or any other university and all sources of material used for the
thesis have been fully acknowledged.
Abera Alemayehu ______________________
Student Signature
Place Bahirdar
Date of submission____/_____/_____
This thesis has been submitted for examination with my approval as a University advisor.
Dr. DD ____________________
Advisor Signature
[I]
Abstract
[II]
ACKNOWLEDGEMENTS
Firstly, and most importantly I would like to thank the almighty God, who gave me time, health
and wisdom. Without the help of him nothing is done. I would like to express my sincere gratitude
to my supervisor, Dr. Yoseph Mekonnen for giving me great inspiration, ideas, comments and
continuous support throughout the process of thesis Completion. My special thanks also go to
Tefera Terefe for providing his valuable comments and suggestions have greatly helped me to
improve my writing. Last but not least, I am also very much grateful to my wife AA for my sources
of inspiration and strength, who has dedicated her years supporting my study that make me feel
loved, proud and fortunate.
Finally, I want to thank my best friends and colleagues who helped me in numerous ways to make
this thesis successful.
[III]
Table of Contents
DECLARATION.......................................................................................................................................... I
Abstract........................................................................................................................................................ II
ACKNOWLEDGEMENTS ...................................................................................................................... III
CHAPTER ONE .......................................................................................... Error! Bookmark not defined.
1. INTRODUCTION............................................................................................................................... 1
1.1. Background ................................................................................................................................. 1
1.2. Statement of the Problem ....................................................................................................... 2
1.3. Overview of the Study Area ........................................................................................................... 2
1.4. Objectives of the Thesis .................................................................................................................. 4
1.5. Methodology .................................................................................................................................... 5
1.6. Significance of the Thesis ........................................................................................................... 5
1.7. Scope this Thesis Work................................................................................................................... 6
1.8. Scope of the Thesis .......................................................................................................................... 6
1.9. Thesis Organizations ...................................................................................................................... 6
CHAPTER TWO ........................................................................................................................................ 7
2. LITRURE REVIEW AND THEORICAL BACKGROUND ......................................................... 7
2.1. Distribution System Reliability .................................................................................................. 7
2.2. Power System Reliability and Related Concepts...................................................................... 8
CHAPTER THREE .................................................................................................................................. 20
DISTRIBUTION SYSTEM ASSESSMENT AND MODELING ......................................................... 20
3.4.1. Cause of Outages/Interruptions ........................................................................................ 20
3.5. Causes of Electric Power Interruption.................................................................................... 21
3.5.1. Equipment Failures........................................................................................................... 21
3.5.2. Human Factors/Errors ..................................................................................................... 22
3.5.3. GG ...................................................................................................................................... 22
3.6. Load Point Indices .................................................................................................................... 22
3.7. System Reliability Indices ........................................................................................................ 22
3.8. Harmonics.................................................................................................................................. 25
3.10. Reliability and Hazard functions ......................................................................................... 27
3.11. System Modeling ................................................................................................................... 28
[IV]
3.11.1. Radial System Structure of the Feeders .......................................................................... 28
3.12. Capacitor Switching.............................................................................................................. 30
4.3. Optimaziaon Result of the System .................................................................................................. 32
References ................................................................................................................................................... 48
[V]
CHAPTER ONE
INTRODUCTION
1.1. Background
The basic function of an electric power system is to supply customers with electricity. Modern
society demands that electrical energy should be as economical as possible with a reasonable
degree of continuity and quality. The continuity of energy supply can be increased by improved
system structure, increased investment during the planning phase, operating phase or both. Over-
investment can lead to excessive operating costs, which must be reflected in the tariff structure. A
Power system has a number of generating stations of different types interconnected by a system of
transmission lines, sub transmission lines and distribution networks to supply different types of
loads to various consumers. The substation is an important part that provides the final links
between the utility and the customers [1, 2].Substations are fenced yards with switches,
transformers and other electrical equipments. Once the voltage has been stepped down at the
distribution substation, the electricity flows to industrial, commercial, and residential centers
through the distribution system. Conductors called feeders reach out from the distribution
substation to carry electricity to customers. At key locations along the distribution system, voltage
is stepped down by distribution transformers to the voltage needed by customers or end-users.
Electric distribution system power quality is a growing concern. Customers require higher quality
service due to more sensitive electrical and electronic equipments. The effectiveness of a power in
distribution system is measured in terms of efficiency, service continuity or reliability, service
quality in terms of voltage profile and stability and power distribution system performance. In the
context of Ethiopia, electric power interruption is becoming a day to day phenomenon. Even there
are times that electric power interruption occurs several times a day, not only at the low voltage
but also at the medium voltage distribution systems. The drop of the voltage, especially at the
residential loads, is causing early failure of equipments, blackening of light bulbs, and decreased
efficiency and performance of high-power appliances. Damage of electronic devices and burning
of light bulbs have also occurred due to over voltages [3].
It is very important to assess and evaluate the reliability of power system networks in order to
obtain the most accurate and effective way in decision making especially in planning, operation
and maintainace. Historical assessment and predictive reliability methods are normally used to
[1]
evaluate the reliability of distribution system. Predictive methods are categorized in to analytical
and simulation methods.
[2]
Sebeta city distribution substation has 13 radially configured feeders are to engaged to distribute
primary voltage level distribution transformers and industrial loads.
[3]
Fig. single line diagram of sebeta distribution Substation-I
The main objective of this thesis is to analysis and evaluate the of reliability of distribution
networks for sebeta distribution system to improve system reliability by making the optimal
configuration of the existing distribution system network.
[4]
1.5. Methodology
In order to achieve the objective of this thesis there are various procedural task should be carried
out. The first method that should be followed is reviewing different literatures related with power
system reliability assessment, method of improving of reliability and quality of power system.
General methodology for this thesis work are as follows:
Reviewing different related works for this thesis
Gathering data from EEU (sebeta distribution system district) especially interruption data
Modeling of distribution system with ETAP software
Applying optimization technique for obtaining the optimal placement of switches
Simulating the existing and optimal configuration of the given distribution substation and
comparing the result to show the effectiveness of the optimization technique
To assess average duration and frequency of power interruption per year in the system.
To apply fuzzy logic optimization systems for improvement of system reliability and power
quality.
[5]
To show the feasibility of this distribution feeder network reconfiguration i.e. optimal
placement of switches on system reliability and power quality improvement.
Thus the main aim of this study is to present a methodology for network reconfiguration with the
objective of finding, in normal operating conditions, the optimal configuration for the distribution
system that minimizes interruption costs and simultaneously improves reliability.
[6]
Chapter3 deals about Data analysis, application of network reconfiguration. The collected data
analysis and the reliability indices of the study area are provided.
CHAPTER TWO
Power quality and reliability are the two most important terms in power system and they are inter
related to each other in many ways. Reliability is primary concerned with customer interruptions
and it is therefore the concern of power quality. Reliability may be defined in many ways in power
system, this include the continuity of services, meeting customer demand and the vulnerability of
power system.
Reliability can be classified into two components: security and adequacy. Adequacy is the static
evaluation of a systems ability to supply the load [4, 5]. Thus, adequacy majorly deals with static
conditions and not the dynamic and transients of power system. Security is associated with system
dynamics and disturbances in the system. Security is therefore related to the response of the system
to perturbations it is subjected to. The concept of power-reliability is extremely broad and covers
[7]
all aspects of the ability of the system to satisfy the customer requirements. There is a reasonable
subdivision of the concern designated as system reliability which is shown in Figure2.1.
Electrical distribution system is usually radial so exposed to the rates of interruption because of
system component of transformers, breakers and switching devices the growing demand for the
customers to provide high quality services make great requirements for improvements in electrical
distribution system.
[8]
Hierarchical level 1, HLI
Generation facilities
.
Transmission facilities Hierarchical level II, HLII
Distribution facilities
Hierarchical level III, HLIII
[9]
Figure 1.2 Costs according to reliability of the system
As shown in Figure 1.2, the utility cost, i.e. investment cost, maintenance cost and operating cost,
increases while the socio-economic customer interruption cost decreases with increase in the level
of service reliability. The total cost is the sum of the two curves. The optimum level of reliability
occurs at the point of lowest total cost. In a reliability cost/worth analysis, the annual expected
customer interruption costs are added to the predicted annual capital and operating costs to obtain
a total cost evaluation. Possible alternative configurations are examined to minimize the total cost
and to identify the most appropriate configuration.
Power system protection is the back bone and effective way to improve reliability of distribution
system. This section provides various protection devices used for radial configuration of
distribution substation. Proper coordination among protection devices must be considered in order
to reduce the number of interrupted customers during the fault and hence improve the distribution
system reliability.
[10]
To reduce the duration of outages or disruptions
Reduce the actual problem of the system so that the damage is minimal
Deliver the supply in alternative paths for unfaulty section of the system
There are different types of protective devices such as reclosers, circuit breakers, relays, switch
gears and automatic sectionalizer are used to protect the overhead line in distribution system.
2.4.1.1. Reclosers
Reclosers are the protective device which has the capability to sense and interrupt fault currents as
well because it recloses automatically. reclosers are used at the following points in the distribution
network.
Protective relays generally receive information from devices like from current transformers and
potential transformers and send signal to circuit breaker to open when the fault happens. It is
capable of detecting changes in the receiving signal and if the magnitude of the received signal is
outside the present range it operates to initiate an appropriate control action so as to protect the
power system.
High voltage circuit breaker interrupt high fault currents, the insulation medium usually used for
circuit is SF6 (sulfur hexafluoride)
Automatic sectionalizer are automatically de –energized the faulted section so that to separate un
faulted section to be operated safely.
2.4.1.5. Fuses
[11]
A fuse an over current protective devices used in electrical distribution system. Under normal
operating conditions the heat buildup in fuse elements are dissipated in surrounding air and
therefore the fuse remain at the temperature below its melting points. During fault conditions such
as short circuit, the heat becomes very great cannot bed dissipated too enough. This causes the fuse
element to heat up and becomes belting and thus breaking the circuit.
Power quality mainly deals with the interaction among the customers and the utility or it can be
also said that it provides an interaction between the power system and the respective load. Power
quality is the provision of voltage and system design so the user of electric power can utilize
electric energy from the distribution system succefully without interference or interruption. The
broad definition of power quality borders on the system reliability dielectric selection on the
equipment and conductors, long term outage, voltage unbalance in three phase system.
To obtain near perfect power quality the utility could spent vast amount of money and
accommodate equipments with higher power quality needs. Power quality concerns are becoming
more frequent with the proliferation of sensitive electronic equipment and automated process.
Power quality problems are divided into many categories such as interruptions, sags, swells,
transients, noise, flicker, harmonic distortion and frequency variations.
[12]
Reliability is primarily concerned with customer interruptions and is therefore, a subset of power
quality. Though there is general agreement that power quality includes reliability, the boundary
that separates the two is not well defined.
Sustained interruptions (more than a 5 minutes) have always been categorized as a reliability issue,
but many utilities have classified momentary interruptions (less than a 5 minutes) as a power
quality issue.
Short duration voltage variation is very less which means less than 1min. the main
the main reason for this variation are large load energization, fault conditions and
short duration voltage variation include voltage sag, voltage swell and interruption
etc.
[13]
2.4. Electric Power Distribution Network Configuration
Distribution system is portion of an electric system that delivers electric energy from
transformation points on the transmission system to the customer. It generally considered being
anything from the distribution substation fence to the customer meter and often the initial
overcurrent protection and voltage regulators are within the substation fence and are considered
part of the distribution system. The distribution network typical located at every nook and corner
to provide the electric power supply for all the individual customers Electric distribution network
is usually radial system that exposed to frequent electric power interruption.
Radial main distribution systems: There are several configurations of distribution systems.
Most distribution circuits are radial (both primary and secondary). Radial circuits have many
advantages over networked circuits including [9].
Lower fault currents over most of the circuit
Easier voltage control
Easier prediction and control of power flows
Lower cost
A radial system is connected to only one source of supply and is exposed to many interruption
possibilities. The most important of which are those due to overhead line or underground cable
failures or transformer failures. Each event may be accompanied by a long interruption. A radial
system is characterized with by having only one path for the power to flow from the source
(substation) to the customer.
This is the simplest distribution circuit and has the lowest initial cost. However, it suffers from
the following drawbacks.
The end of the distributors nearest to the feeder point will be heavily loaded.
[14]
The customers at the distant end of the distribution would be subjected to serious voltage
fluctuations when the load on the distributor is changed.
The customers are dependent on a single feeder and single distributor. Therefore, any fault
on the feeder distributor cuts off supply to the customers who are on the side of the fault
away from the substation. The reliability of this system is low.
Ring main distribution system:
In this system the primaries of the transformers form a loop as shown in figure. In this
configuration alternative path for services feeder must be installed. The loop circuit starts from the
substation bus bars, make a loop through the area to be served, and returned to the substation. The
figure below shows the single line diagram of ring main system for a.c distribution where a
substation supplies to the closed feeder LMNOPQRS. The distributors are tapped from M, O, &
Q of the feeders through distribution transformer.
[15]
When the feeder ring is energized by two or more than two generating stations or substations, it
is called inter connected system [10]. The inter-connected system has the following advantages:
Fuzzy logic controller is a decision mechanism represented by a set of fuzzy rules. The alternative
for probability modeling of the reliability is advanced to the fuzzy logic system [11]. And the
possibility theory is characterized by [12].
T. Juhana Hashim and A. Mohamed [13] this paper discussed the implementation of a fuzzy logic
based coordinated voltage control for a distribution system connected with distributed generations
(DGs). The connection of DGs has created a challenge for the distribution network operators to
keep the voltage in the system within its acceptable limits. Intelligent centralized or coordinated
voltage control schemes have proven to be more reliable due to its ability to provide more control
and coordination with the communication with other network devices.
[16]
2.5.2. Simulated Annealing Method
Young-Jae Jeon, Jae-Chul Kim [15] presented an efficient algorithm for loss minimization by
using an automatic switching operation in large scale distribution systems. Simulated annealing is
particularly well suited for a large combinatorial optimization problem since it can avoid local
minima by accepting improvements in cost. However, it often requires a meaningful cooling
schedule and a special strategy, which makes use of the property of distribution systems in finding
the optimal solution
Khalil and Alexander v. Gorpinich [15] presented a new simple algorithm for solving the
distribution network reconfiguration (DNR) problem. This algorithm is a simple modification to
the binary particle swarm optimization (BPSO) called selective particle swarm optimization
(SPSO). The search space for proposed algorithm is a set of branches (switches) which are
normally closed or normally opened, this search space may be dissimilar for different
dimensions.
V.Selve, Dr.G.Baskar,B. Rampradheeba [16], this paper presented about network reconfiguration
is aimed at maximizing the reliability of power supplied to the customers. Binary particle swarm
optimization (BPSO) is used to determine optimal configuration of switches in network in order
to maximize reliability at load points. In the presented work, probabilistic reliability models of the
components are used to estimate the future behavior of the distribution system in terms of the
reliability of supplying power to its customers.
2.5.4. Metaheuristic Algorithms
Sourabh Katoch1 & Sumit Singh Chauhan1 & Vijay Kumar, in this reaaerch paper diffenet gentic
algorism domains were properly covered [15].
Heuristic and Meta-heuristic techniques are the randomized searching procedures. It is described
that swarm optimization techniques and evolutionary techniques are the parts of it. In next section,
and Genetic Algorithms, fuzzy logic, and artificial neural network are described in details. Several
methods have been proposed to solve the reconfiguration problem.
[17]
Figure. Classification of metaheuristic algorithms [15]
[18]
[19]
CHAPTER THREE
[20]
s.no Feeders Major cause of power outage
Earth Short circuit Open Over load of Fallen Unknown
fault fault circuit transformer tree
1 Feeder-1
2 Feeder-2
3 Feeder-3
4 Feeder-4
5 Feeder-5
6 Feeder-6
7 Feeder-7
8 Feeder-8
9 Feeder-9
10 Feeder-10
11 Feeder-11
12 Feeder-12
13 Feeder-13
Table 3.2 the major causes of power interruption for each three feeders
[21]
decrease the failure rate of the equipments proper installation and timely maintenance of the
equipments are highly equipments.
3.5.2. Human Factors/Errors
There are many ways in which the people can cause interruption in an electric distribution system.
These are vehicle contact fallen the poles by humans.
3.5.3. GG
3.6. Load Point Indices
Load point indices are conventional which typically represent the data each connected individual
customer. The load point indices [8] are:
a. Average failure rate, λ(f/yr)
λ𝑖 = λ1 + λ2 + λ3 + λ4 + ⋯ + λ𝑚 = ∑n𝑖=1 λ𝑗 ( 3.1)
where
n= total number of customers connected at load point, i
λ𝑗= average failure rate of the loads at point, i
λ𝑖= average failure rate of the loads at point, i
b. Average outage time, r (hr.)
𝑛
𝑟𝑖1λ𝑖+𝑟𝑖2λ𝑖+𝑟13λ𝑖+𝑟𝑖4λ𝑖+⋯+𝑟𝑖𝑚λ𝑚 𝑟𝑖,𝑗1λ𝑖
r𝑖 = =∑ (3.2)
λ𝑖 𝑖,𝑗=1 λ𝑖
where
n= total number of feeder at load point, i
ri𝑗= average outage time of feeder due to failure rate segment, i
λ𝑖= average failure rate of each segment, i
c. the average outage time(hr./yr.)
Ui= 𝑟𝑖λ𝑖 (3.3)
3.7. System Reliability Indices
System planners and operators use the reliability indices as a tool to improve the level of service
to electric power consumers. According to the requirements for generation, transmission and
distribution capacity additions can be determined by the planners. Operators use these indices to
emphasize the system robustness and withstanding possible failures without catastrophic
[22]
consequences. Sustained interruption indices are distribution indices [6, 9]. The most common
distribution indices include the System Average Interruption Duration Index (SAIDI), Customer
Average Interruption Duration Index (CAIDI), System Average Interruption Frequency Index
(SAIFI), Momentary Average Interruption Frequency Index (MAIFI), Customer Average
Interruption Frequency Index (CAIFI) Customers Interrupted per Interruption Index (CIII), and
the Average Service Availability Index (ASAI).
where, λi is the failure rate and Ni is the number of customers at load points i.
Where ri is the restoration time , Ni total number of customers interrupted and NT is the total
number of customers connected at load point i. SAIDI can be improved by reducing the number
of interruptions or the duration of the interruptions.
[23]
3) Customer Average Interruption Duration Index (CAIDI) (h/interruption)
Customer Average Interruption Duration Index (CAIDI) is the average interruption duration for
those customers interrupted during a year. It is determined by dividing the sum of all customer
interruption durations by the number of customers experiencing one or more interruptions over a
one-year period. The index is the ratio of SAIDI to SAIFI as given in Equations (3.6). It represents
the average time taken to restore service to the customers when a sustained interruption occurs.
Where λi is the failure rate, Ui is the annual outage time and Ni is the number of customers at load
point i.
8760 Hours/year−CAIDI
ASAI = ( 3.7)
8760 Hours/year
The first five indices are customer-oriented indices and the last two are load and energy-oriented
indices. These indices can be used not only to assess the past performance of a distribution system
[24]
3.8. Harmonics
Harmonics is arising problem for both the electric power utility and customers. Harmonics is
defined as a sinusoidal component of a period wave or quantity having a frequency that is an
integral part of multiple of a fundamental frequency usually 50Hz or 60Hz. Distorted waves can
be split into a sum of fundamental frequency and the harmonics. Harmonics voltages are occurred
as the result of harmonics current as the result of harmonics currents which is created by the
nonlinear electronics loads. These nonlinear loads will draw the distorted current wave from the
supply side. Using Fourier series expansion it can be represented by a distorted wave as follows
[16].
U(t)=𝑈𝑑𝑐 + ∑∞
𝑛=1 𝑈(𝑛)𝑠 sin(𝑛𝜔𝑡) +U(n)c cos(𝑛𝜔𝑡) (3.11)
1 2𝜋
U(n)s=𝜋 ∫0 𝑈(𝑡)𝑠 sin(𝑛𝜔𝑡)d 𝜔𝑡 (3.12)
1 2𝜋
U(n)c=𝜋 ∫0 𝑈(𝑡)𝑠 cos(𝑛𝜔𝑡)d 𝜔𝑡 (3.13)
Where n is an integer and ω=2T/π, T is the fundamental period of the time. It is also common to
use a single quantity, the total harmonic distortion, THD, as the measure of the effective value of harmonic
distortion. The THDU and THDI can be calculated as
𝑇𝐻𝐷𝑢 = √∑∞ 2
𝑛=2 𝑈(𝑛) ⁄
𝑈(1) *100 (3.14)
𝑇𝐻𝐷𝐼 = √∑∞ 2
𝑛=2 𝐼(𝑛) ⁄
𝐼(1) *100 (3.15)
Table 2: Summary of interruption frequency and duration for the year 2019
[25]
Feeders Name SAIFI SAIDI CAIDI ASAI ASUI
Table 2 Summary of interruption frequency and duration for the year 2020
[26]
Feeder 12 279.4 351.39 1.25765927 0.999856432 0.000143568
Feeder 13 108.4 198.75 1.833487085 0.999790698 0.000209302
The occurrence of failures of a component will vary during its lifetime and is often being
visualized using a “bathtub curve” (see illustration in Figure 7)
h (t)= λ 3.12
Wear-out period or increasing failure rate period
h (t)= λt 3.13
Many components in power systems exhibit constant failure rate during their lifetimes, this occurs
at the end of the early failure region. Burn-in is performed by subjecting components to stress
slightly higher than the expected operating stress for a short period in order to weed out the failure
due to manufacturing defects.
[27]
The CDF of the life of a component is represented by:
F (t) =P [T≤T] 3.14
And
[28]
[29]
3.12. Capacitor Switching
One of the most common cause of electrical transient is switching of capacitor bank in power
system. Electric utility switching capacitor banks during peak hours to offset the lagging kvar
demand of the load. One common symptom of power quality problems related to capacitor
switching over voltages is that the problems appear ant nearly the same time each day. On
distribution feeders with industrial loads, capacitors are frequently switched by time lock
anticipation of an increase load with the beginning of working day. common problems are
adjustable speed derive trips and malfunction of other electronically controlled loads.
[30]
CHAPTER FOUR
Simulation Result and Discussion of the Distribution System
4.1. Simulation Result for Existing System
Sebeta substation has 13 feeders with having the total transformers of 230. from the
recorded two-year data
4.1.1. Analytical Result
Table 4.1. analytical reliability assessment for 2019
Feeder 13 435.46
378.4
Feeder 12 597.58
382.4
Feeder 11 622.77
479.8
Feeder 10 478.31
244.3
Feeder 9 518.73
241.5
Feeder 8 531.34
154
Feeder 7 684.85
371.3
Feeder 6 662.33
249.6
Feeder 5 550.09
164
Feeder 4 561.18
245.8
Feeder 3 661.36
451.7
Feeder 2 835.3
666.4
Feeder1 515.26
319.2
0 100 200 300 400 500 600 700 800 900
[31]
RELIABLITY ASSESMENT FOR THE 2019
Feeder 13 198.75
108.4
Feeder 12 351.39
279.4
Feeder 11 319.87
316.1
Feeder 10 501.52
469.3
Feeder 9 262.89
190.4
Feeder 8
218.8253.37
Feeder 7 245.41
189
Feeder 6 561.57
393.4
Feeder 5 296.67
215
Feeder 4 299.49
182.5
Feeder 3
320.5357.69
Feeder 2 812.53
604.3
Feeder1 753.77
597.1
0 100 200 300 400 500 600 700 800 900
[32]
[33]
Sector Interruption Cost
Interruption
Duration Cost
Sector Name minutes $/kW
Agricultural 1.00 0.06
20.00 0.34
60.00 0.65
240.00 2.06
480.00 4.12
Commercial 1.00 0.38
20.00 2.97
60.00 8.55
240.00 31.32
480.00 83.01
Govt. & Inst. 1.00 0.04
20.00 0.37
60.00 1.49
240.00 6.56
480.00 26.04
Industrial 1.00 1.63
20.00 3.87
60.00 9.09
240.00 25.16
480.00 55.81
Office & bldg 1.00 4.78
20.00 9.88
60.00 21.06
240.00 68.83
480.00 119.20
Residential 1.00 0.00
20.00 0.09
60.00 0.48
240.00 4.91
15.69
[34]
AENS 962.9512 MW hr / customer.yr
ASAI 0.9255 pu
ASUI 0.07445 pu
ECOST 3,093,816.00 $ / yr
EENS 78962.000 MW hr / yr
IEAR 0.039 $ / kW hr
[35]
4.4. Optimaziaon Result of the System
For improving of distribution system reliability of distribution system fuzzy logic controller has
been used. The optimal reclosers and switch placement on the distribution system has been
selected.
[36]
[37]
[38]
Appendix
Table 1: Causes of Interruption and peak load of each line for the Year 2019 (January 01/01/2019 - December
31/12/2019)
January February March
[39]
Feeder 11 10.6 11 13 14 35.13 10.7 12 4 24 1 22.92 10.9 14 8 12 1 40.25
Feeder 12 11 17 2 11 12.55 10.8 19 4 4 28.88 10.5 21 1 5 17.28
Feeder 13 4.4 12 22 6 21.92 4.5 17 15 5 22.15 10.2 7 15 7 6.7
[40]
Line 3.8 9 3 11 46.1 3.9 10 8 14 22.43 4.12 8 9 26 53.12
13
Line 2.3 2 2 0.57 2.3 3 5 2.11 2.4 3 1 5 5.58
14
Table 2: Summary of Interruption Frequency and Duration for the Year 2019
[41]
Feeder 12 13.6 152 72 141 4 597.58
382.4
Feeder 13 21.92 121 112 119 5 435.46
378.4
Table 3: Causes of Interruption and peak load of each line for the Year 2020 (January 01/01/2020
- December 31/12/2020)
January February March
Peak Interruption Peak Interruption Peak Interruption
Line Name (MW) (MW) (MW)
[42]
Feeder 11 11 10.7 10.2
9 14 8 32.25 13 12 5 1 24.93 18 13 12 39.73
Feeder 12 13.1 11.8 11.9
11 6 11 28.65 4 13 6 17.65 9 8 6 38.73
Feeder 13 4.8 8.1 6.74
4 4 5 13.5 7 8 5 21.75 12 12 18 51.63
[43]
Feeder 11 10.9 11.3 10.7
10 26 12 2 14.4 10 8 8 1 21.5 7 12 14 17.2
Feeder 12 10.9 11.6 11.7
7 2 12 16.6 5 4 12 13.48 2 10 10 31.6
Feeder 13 8.4 6.6 6.7
8 10 4 13.7 11 7 8 13.45 6 5 4 9.02
Table 4: Summary of interruption frequency and duration for the year 2020
Table 5: Monthly load report for the years 2019 and 2020
[44]
12.02 20:00 12/1/2020 0.76 2:00 24/01/20
L15
27/02/19 2:00 27/02/19 13.3 19:00 8/2/2020 2.80 4:00 11/2/2020
L1 10.1 20:00 2.1
23/02/19 15:00 3/2/2019 12.7 10:00 16/2/20 1.70 16:00 22/2/20
L2 12.6 12:00 1.2
25/02/19 15:00 28/02/19 10.3 19:00 1/2/2020 1.80 3:00 26/2/20
L3 10.4 20:00 1
20/02/19 2:00 18/02/19 13.4 14:00 29/2/20 1.20 8:00 23/2/20
L4 9.4 20:00 1.7
8/2/2019 8:00 3/2/2019 1.2 11:00 1/2/2020 0.10 20:00 1/2/2020
L5 0.7 16:00 0.1
11:00 28/02/19 2:00 4/2/2019 0.8 10:00 20/2/20 0.30 03:00 5/2/2020
L6 9.6 0.2
February 11:00 28/02/19 2:00 25/02/19 9.4 10:00 15/2/20 1.10 4:00 17/2/20
L7 6.9 1.4
4/2/2019 8:00 24/02/19 4.2 15:00 26/2/20 0.70 3:00 9/2/2020
L8 4 20:00 0.3
12:00 13/02/19 1:00 18/02/19 6.9 12:00 15/2/20 0.70 3:00 9/2/2020
L9 6.1 1.3
13:00 19/02/19 3:00 20/02/19 8.5 15:00 26/2/20 1.40 3:00 24/2/20
L10 4.1 1
2/2/2019 3:00 25/02/19 10.1 9:00 1/2/2020 0.90 2:00 10/2/2020
L11 10.7 9:00 2.3
11/2/2019 4:00 23/02/19 11.5 20:00 8/2/2020 2.40 3:00 5/2/2020
L12 10.8 20:00 1.3
1/2/2019 15:00 11/2/2019 4 19:00 25/2/20 0.50 8:00 17/2/20
L13 4.5 12:00 0.6
18/3/19 2:00 8/3/2019 14.6 19:00 16/03/20 2.30 3:00 13/3/20
L1 9.6 20:00 2.3
9/3/2019 20:00 7/3/2019 13.9 11:00 20/3/20 0.02 15:00 5/3/2020
L2 12.9 9:00 0.1
9/3/2019 0:00 9/3/2019 10.9 19:00 28/3/20 1.80 15:00 1/3/2020
L3 9.1 20:00 0.4
28/3/19 3:00 6/3/2019 15.5 19:00 17/3/20 2.60 3:00 17/3/20
L4 10.8 19:00 0.5
26/3/19 12:00 2/3/2019 1.5 16:00 17/3/20 0.04 20:00 5/3/2020
L5 1.5 14:00 0.1
6:00 31/3/19 14:00 20/3/2019 0.9 9:00 23/3/20 0.04 2:00 6/3/2020
L6 2.6 0.2
March 14:00 12/3/2019 3:00 18/3/2019 8.3 11:00 21/3/20 0.80 15:00 21/3/20
L7 7.1 1.4
8/3/2019 3:00 10/3/2019 3.6 13:00 22/3/20 0.60 3:00 15/3/20
L8 3.8 16:00 0.5
14:00 6/3/2019 3:00 4/3/2019 7.1 10:00 16/3/20 0.70 3:00 9/3/2020
L9 7.8 1.2
16:00 8/3/2019 1:00 11/3/2019 6.4 20:00 16/3/20 1.30 3:00 18/3/20
L10 7.2 0.95
27/3/19 3:00 30/3/2019 10.9 12:00 18/3/20 1.70 3:00 9/3/2020
L11 10.9 11:00 0.72
13/3/19 3:00 9/3/2019 11.1 13:00 21/3/20 0.60 2:00 17/3/20
L12 10.5 19:00 2.7
20/3/19 1:00 25/3/2019 4.5 9:00 9/3/2020 0.60 3:00 9/3/2020
L13 10.2 20:00 0.9
20/4/2019 2:00 23/4/2019 7.3 21:00 17/04/20 0.14 10:00 16/04/20
L1 9.8 19:00 1.16
6/4/2019 16:00 13/4/2019 14.1 13:00 3/4/2020 0.50 3:00 27/04/20
L2 12.7 11:00 0.9
7/4/2019 9:00 3/4/2019 10.8 12:00 18/04/20 1.40 3:00 3/4/2020
L3 9.5 9:00 0.14
10/4/2019 3:00 10/4/2019 15.4 18:00 30/04/20 1.30 14:00 8/4/2020
L4 11 20:00 0.57
13/4/2019 12:00 2/4/2019 8.5 16:00 30/04/20 0.02 20:00 3/4/2020
L5 1.5 9:00 0
11:00 2/4/2019 2:00 28/4/209 0.81 10:00 9/4/2020 0.23 01:00 6/4/2020
L6 2.6 0.21
April 20:00 24/4/2019 2:00 29/4/2019 7.5 11:00 23/04/20 0.90 4:00 27/04/20
L7 8.7 1.16
27/4/2019 3:00 15/4/2019 4 13:00 18/04/20 0.50 3:00 3/4/2020
L8 2.5 12:00 0.42
11:00 25/4/2019 4:00 28/4/2019 6 14:00 24/04/20 0.50 3:00 18/04/20
L9 6.3 0.59
17:00 20/4/2019 3:00 28/4/2019 9.4 13:00 15/04/20 0.95 1:00 20/04/20
L10 4.1 0.64
11/4/2019 3:00 29/4/2019 11 13:00 18/04/20 1.54 2:00 20/04/20
L11 10.2 11:00 1.3
27/4/2019 15:00 17/4/2019 13.1 12:00 18/04/20 1.80 3:00 15/04/20
L12 11.2 12:00 0.78
6/4/2019 3:00 29/4/2019 4.8 19:00 18/04/20 0.40 4:00 19/04/20
L13 4.4 12:00 0.69
May 9.8 20:00 4/9/2019 0.16 20:00 8/5/2019 5.9 11:00 20/5/20 0.30 2:00 20/5/20
L1
[45]
13.4 14:00 6/9/2019 0.8 23:00 7/5/2019 12.6 11:00 8/5/2020 0.02 12:00 21/5/20
L2
11.3 19:00 19/09/19 1.16 18:00 20/5/19 10.8 20:00 27/05/20 0.90 18:00 13/5/20
L3
10.9 19:00 11/9/2019 0.97 15:00 5/5/2019 16.4 18:00 22/05/20 1.90 4:00 11/5/2020
L4
1.16 14:00 17/09/19 0.09 14:00 2/5/2019 1.6 10:00 16/05/20 0.02 3:00 17/5/20
L5
0.9 8:00 6/9/2019 0.3 01:00 24/5/19 0.7 10:00 28/05/20 0.07 11:00 3/5/2020
L6
8.2 11:00 20/09/19 1.04 2:00 9/5/2019 9.2 15:00 3/5/2020 1.02 11:00 3/5/2020
L7
3.9 12:00 3/9/2019 0.6 02;00 9/5/2019 5.6 14:00 2/5/2020 0.04 2:00 30/5/20
L8
6.3 14:00 18/09/19 0.5 3:00 13/5/19 8.1 16:00 8/5/2020 0.70 3:00 18/5/20
L9
4.4 19:00 6/9/2019 0.5 2:00 13/5/19 6.8 16:00 4/5/2020 0.80 4:00 7/5/2020
L10
9.9 14:00 16/09/19 1.5 4:00 13/5/19 10.7 4/5/2020 1.40 9:00 18/5/20
L11 16:00
13.02 20:00 7/9/2019 1.7 3:00 29/5/19 11.8 18:00 18/5/20 2.02 3:00 13/5/20
L12
4.12 20:00 22/09/19 0.6 3:00 3/5/2019 8.1 12:00 19/5/20 0.70 11:00 3/5/2020
L13
11.3 12:00 22/06/19 1.9 4:00 30/06/19 7 19:00 19/6/20 0.64 18:00 19/6/20
L1
13.4 19:00 26/06/19 0.3 14:00 16/06/19 13.1 11:00 6/6/20 1.02 16:00 20/6/20
L2
10.1 16:00 18/06/19 0.14 20:00 22/06/19 10.9 15:00 22/6/20 0.02 3:00 1/6/2020
L3
11.7 16:00 8/6/2019 1.5 1:00 27/06/19 16.2 13:00 25/6/20 2.43 2:00 12/6/20
L4
0.9 15:00 27/06/19 0.1 20:00 1/6/2019 0.8 14:00 16/6/20 0.01 2:00 23/6/20
L5
6.5 12:00 18/06/19 0.3 24:00:00 28/06/19 0.9 2:00 23/6/20 0.02 4:00 5/6/2020
L6
June 9 11:00 21/06/19 0.2 3:00 24/06/19 9 11:00 12/6/20 0.83 0:00 30/6/20
L7
6.2 18:00 26/06/19 0.6 3:00 2/6/2019 4.3 4:00 12/6/20 0.07 1:00 1/6/2020
L8
8 11:00 27/06/19 0.95 14:00 20/06/19 8.8 13:00 1/6/20 0.48 0:00 30/6/20
L9
4.8 12:00 27/06/19 0.95 4:00 11/6/2019 6.4 13:00 3/6/20 1.07 0:00 30/6/20
L10
11.4 11:00 28/06/19 0.83 2:00 5/6/2019 10.24 13:00 12/6/20 1.26 0:00 30/6/20
L11
12.5 16:00 8/6/2019 1.7 3:00 14/06/19 11.88 12:00 25/6/20 2.34 2:00 1/6/2020
L12
4.6 17:00 3/6/2019 0.05 2:00 17/06/19 6.74 18:00 1/6/20 0.31 2:00 27/6/20
L13
10.7 10:00 6/7/2019 2.4 2:00 29/7/19 8.4 13:00 8/7/2020 0.80 1:00 18/7/20
L1
12.7 9:00 13/7/19 0.3 12:00 16/7/19 12.4 15:00 17/7/20 0.70 4:00 3/7/2020
L2
10.6 17:00 4/7/2019 0.3 3:00 18/7/19 11.2 20:00 25/7/20 0.60 4:00 3/7/2020
L3
11.4 20:00 4/7/2019 0.1 11:00 10/7/2019 15.2 13:00 2/7/2020 0.20 11:00 25/7/20
L4
1.4 14:00 10/7/2019 0.02 8:00 2/7/2019 1.3 9:00 17/7/20 0.20 7:00 1/7/2020
L5
3.8 11:00 31/7/19 0.3 1:00:00 8/7/2019 0.7 11:00 30/7/20 0.20 3:00 10/7/20
L6
July 8.2 10:00 3/7/2019 0.3 3:00 1/7/2019 9.3 10:00 18/7/20 0.70 1:00 1/7/2020
L7
3.8 20:00 5/7/2019 0.5 2:00 5/7/2019 5 13:00 13/7/20 0.60 4:00 3/7/2020
L8
6.7 10:00 19/7/19 1.2 3:00 29/7/19 6.8 10:00 17/7/20 0.30 4:00 3/7/2020
L9
4.9 19:00 2/7/2019 0.9 2:00 8/7/2019 9 19:00 19/7/20 0.70 4:00 1/7/2020
L10
10.3 11:00 4/7/2019 1.2 3:00 17/7/19 11 10:00 10/7/2020 0.80 2:00 1/7/2020
L11
12.4 17:00 19/7/19 2.6 11:00 14/7/19 12.2 12:00 13/7/20 0.20 1:00 4/7/2020
L12
3.8 13:00 6/7/2019 0.6 3:00 5/7/2019 4.3 19:00 22/7/20 0.60 2:00 4/7/2020
L13
10.3 20:00 21/08/19 0.7 15:00 22/08/19 6.5 19:00 26/8/20 0.40 6:00 26/8/20
L1
August 12.9 19:00 10/8/2019 1.1 12:00 28/08/19 12.5 10:00 21/6/8/20 0.01 10:00 27/8/20
L2
9.04 13:00 31/08/19 1.2 2:00 07/08/19/ 10.8 20:00 7/8/2020 0.35 5:00 28/8/20
L3
[46]
10.24 13:00 31/08/19 1.1 15:00 9/8/2019 15.9 19:00 18/7/20 0.02 17:00 25/8/20
L4
1.5 16:00 26/08/19 0.09 3:00 3/8/2019 0.5 10:00 22/8/20 0.02 1:00 1/8/2020
L5
4.7 2:00 10/8/2019 0.3 12:00 16/08/19 0.6 12:00 7/8/2020 0.16 3:00 6/8/2020
L6
8.2 11:00 24/08/19 0.7 14:00 22/08/19 9 11:00 18/8/20 0.50 8:00 12/8/20
L7
2.2 20:00 14/08/19 0.5 3:00 19/08/19 4.2 3:00 9/8/2020 0.69 3:00 6/8/2020
L8
6.3 13:00 8/8/2019 0.9 3:00 12/8/2019 6.9 11:00 4/8/2020 0.69 3:00 12/8/20
L9
4.6 12:00 3/8/2019 7 3:00 19/08/19 6.5 12:00 7/8/2020 0.97 3:00 3/8/2020
L10
9.4 11:00 24/08/19 1.9 3:00 12/8/2019 10.6 13:00 27/8/20 1.30 3:00 3/8/2020
L11
13.6 12:00 11/8/2019 2.1 6:00 10/8/2019 13.1 14:00 31/8/20 1.80 3:00 3/8/2020
L12
3.9 13:00 31/08/19 0.2 1:00 6/8/2019 5.8 13:00 31/8/20 0.16 7:00 25/8/20
L13
9.8 20:00 4/9/2019 0.16 20:00 8/9/2019 6.47 9:00 11/9/2020 0.80 15:00 8/9/2020
L1
13.4 14:00 6/9/2019 0.8 23:00 7/9/2019 12.19 9:00 0109/20 1.28 3:00 13/09/20
L2
11.3 19:00 19/09/19 1.16 18:00 20/09/19 9.76 9:00 11/9/2020 1.04 8:00 8/9/2020
L3
10.9 19:00 11/9/2019 0.97 15:00 5/9/2019 15.35 12:00 11/9/2020 1.50 2:00 4/9/2020
L4
1.16 14:00 17/09/19 0.09 14:00 2/9/2019 0.57 14:00 1/9/2020 0.02 1:00 2/9/2020
L5
0.9 8:00 6/9/2019 0.3 01:00 24/09/19 0.9 12:00 16/09/20 0.21 24:00 1/9/2020
L6
September 8.2 11:00 20/09/19 1.04 2:00 9/9/2019 9.3 11:00 21/09/20 0.73 2:00 28/09/20
L7
3.9 12:00 3/9/2019 0.6 02;00 9/9/2019 4.66 7:00 18/09/20 0.71 2:00 3/9/2020
L8
6.3 14:00 18/09/19 0.5 3:00 13/09/19 6.59 11:00 4/9/2020 0.42 3:00 28/09/20
L9
4.4 19:00 6/9/2019 0.5 2:00 13/09/19 7.47 11:00 8/9/2020 0.76 3:00 14/09/20
L10
9.9 14:00 16/09/19 1.5 4:00 13/09/19 11.04 14:00 17/09/20 0.83 0:00 2/9/2020
L11
13.02 20:00 7/9/2019 1.7 3:00 29/09/19 10.66 19:00 19/09/20 1.61 3:00 16/09/20
L12
4.12 20:00 22/09/19 0.6 3:00 3/9/2019 6.19 12:00 8/9/2020 0.88 2:00 14/09/20
L13
7.9 11:00 27/10/19 0.17 15:00 8/10/2019 6.4 19:00 3010/20 0.90 3:00 17/10/20
L1
12.3 11:00 12/10/2019 0.57 16:00 7/10/2019 12.04 11:00 28/10/20 1.14 14:00 31/10/20
L2
10.6 19:00 7/10/2019 1.00 3:00 22/10/19 10.5 19:00 30/10/20 0.70 16:00 8/10/2020
L3
10.7 19:00 22/10/19 1.12 15:00 1/10/2019 15.28 13:00 3/10/20 2.30 1:00 20/10/20
L4
1 14:00 11/10/2019 0.10 20:00 21/10/19 0.6 15:00 16/10/20 0.02 21:00 20/10/20
L5
0.8 10:00 8/10/2019 0.24 04:00 27/10/19 0.9 13:00 25/10/20 0.28 2:00 22/10/20
L6
October 8 15:00 9/10/2019 0.93 3:00 25/10/19 5.95 10:00 5/10/20 0.19 2:00 22/10/20
L7
2.4 12:00 5/10/2019 0.53 2:00 12/10/2019 3.64 19:00 21/10/20 0.66 3:00 17/10/20
L8
8.1 15:00 11/10/2019 0.31 2:00 25/10/19 6.8 11:00 7/10/20 0.50 4:00 11/10/20
L9
4.4 19:00 4/10/2019 0.67 3:00 27/10/19 7.04 17:00 14/10/20 0.20 1:00 26/10/20
L10
9.2 19:00 16/10/19 1.19 3:00 25/10/19 10.9 11:00 9/10/20 1.30 4:00 12/10/20
L11
12 13:00 20/10/19 1.05 1:00 24/10/19 10.9 19:00 23/10/20 1.70 3:00 1/10/2020
L12
4.5 6:00 15/10/19 0.17 2:00 6/10/2019 8.4 15:00 31/10/20 0.50 16:00 11/10/20
L13
7.9 11:00 27/10/19 0.17 15:00 8/11/2019 7 19:00 9/11/20 0.78 15:00 9/11/2020
L1
12.3 11:00 12/10/2019 0.57 16:00 7/11/2019 12.7 9:00 0.12 15:00 2/11/2020
L2 12/11/20
November 10.6 19:00 7/10/2019 1.00 3:00 22/11/19 11.7 19:00 20/11/20 0.76 6:00 5/11/2020
L3
10.7 19:00 22/10/19 1.12 15:00 1/11/2019 15.4 20:00 20/11/20 1.55 2:00 11/11/20
L4
1 14:00 11/10/2019 0.10 20:00 21/11/19 1.1 15:00 23/11/20 0.02 1:00 23/11/20
L5
[47]
0.8 10:00 8/10/2019 0.24 04:00 27/11/19 0.95 13:00 16/11/20 0.09 3:00 20/11/20
L6
8 15:00 9/10/2019 0.93 3:00 25/11/19 8.64 11:00 28/11/20 0.67 16:00 1/11/2020
L7
2.4 12:00 5/10/2019 0.53 2:00 12/11/2019 5.31 20:00 25/11/20 0.62 1:00 23/11/20
L8
8.1 15:00 11/10/2019 0.31 2:00 25/11/19 6.5 10:00 18/11/20 1.07 3:00 16/11/20
L9
4.4 19:00 4/10/2019 0.67 3:00 27/11/19 8.8 19:00 9/11/20 1.31 3:00 2/11/2020
L10
9.2 19:00 16/10/19 1.19 3:00 25/11/19 11.3 19:00 18/11/20 1.80 3:00 2/11/2020
L11
12 13:00 20/10/19 1.05 1:00 24/11/19 11.62 19:00 13/11/20 2.43 2:00 5/11/2020
L12
4.5 6:00 15/10/19 0.17 2:00 6/11/2019 6.6 11:00 28/11/20 0.90 3:00 2/11/2020
L13
2.3 14:00 29/10/19 0.40 17:00 29/11/19 2.4 18:00 0.40 9:00 28/11/20
L14 12/11/20
12.1 20:00 20/11/20 0.50 16:00 9/11/2020
L15
15.2 19:00 6/12/2019 1.30 2:00 3/12/2019 7.1 19:00 9/11/20 0.78 15:00
L1
13.1 10:00 21/12/19 1.60 17:00 5/12/2019 12.1 12:00 0.50 20:00 20/12/20
L2 2/12/20
13.3 8:00 19/12/19 1.10 2:00 16/12/19 12.3 19:00 20/12/20 2.30 3:00 9/12/2020
L3
15.4 19:00 3/12/2019 1.60 4:00 2/12/2019 16.5 19:00 24/12/20 1.20 3:00 22/12/20
L4
1.5 15:00 16/12/19 0.10 17:00 31/12/19 1.1 10:00 24/12/20 0.02 1:00 24/12/20
L5
0.8 12:00 27/12/19 0.20 3:00 2/12/2019 1 13:00 2/12/20 0.30 3:00 11/12/20
L6
8.7 11:00 27/12/19 0.20 1:00 26/12/19 6.2 11:00 22/12/20 0.89 3:00 7/12/2020
L7
December
3.9 20:00 31/12/19 0.50 2:00 1/12/2019 3.5 19:00 2/12/20 0.70 5:00 2/12/2020
L8
6.7 10:00 27/12/19 0.60 3:00 18/12/19 7.4 17:00 16/12/20 0.90 0:00 20/12/20
L9
7.1 18:00 3/12/2019 0.80 3:00 2/12/2019 6.5 19:00 17/12/20 1.70 2:00 17/12/20
L10
9.3 19:00 5/12/2019 1.40 3:00 2/12/2019 10.7 19:00 22/12/20 1.96 3:00 28/12/20
L11
11.4 19:00 9/12/2019 2.30 4:00 8/12/2019 11.7 20:00 29/12/202/12/20 2.30 2:00 12/12/20
L12
4.1 19:00 12/12/2019 0.60 3:00 23/12/19 6.7 12:00 2/12/20 1.05 3:00 28/12/20
L13
2.7 6:00 14/12/19 0.40 10:00 13/12/19 2.3 19:00 0.26 14:00 24/12/20
L14 8/12/20
References
[1] Turan Gonnen, electrical power distribution engineering, second edition, hand book,, 2006.
[3] K. TESFAY, "STUDY AND EVALUATION OF THE RELIABILITY AND DESIGN OF POWER DISTRIBUTION
SYSTEM : CASE STUDY ADDIS ABABA POWER DISTRIBUTION," ADDIS ABABA INSTITUTE OF
TECHNOLOGY, 2014.
[48]
[4] B. Abebe, "Designing of an Improved Distribution Substation to Mitigate the Power Reliability at
Bishoftu City," M-Tech Thesis, Defense Engineering College, 2014.
[5] Tempa Dorji, " reliability assessment of distribution systems”, including a case study on wang due
distribution system in Bhutan,," January 2009.
[9] T. Dorji, reliability assessment of distribution systems including a case study on wang due
distribution system in Bhutan, January 2009.
[11] L. Zadeh, "The concept of a linguistic variable and its applicationtion to approximate reasoning—I–
III," Information Sciences,, vol. 8, no. 3, p. 199–251, 1975, no. 4, pp. 301–357, 1975—no.
[12] L. A. Zadeh, "Fuzzy sets as a basis for a theory of possibility," Fuzzy Sets and Systems, vol. 1, no. 1,
pp. 3–28, , 1978.
[13] T. J. H. a. A. Mohamed, "Fuzzy Logic Based Coordinated Voltage Control for Distribution Network
with Distributed Generation," World Academy of Science,Engineering and Technology International
Journal of Electrical, Computer, Energetic, Electronic and Communication Engineering Vol: 7, No: 7,
2013.
[14] H. A.-A. H. H.-K. H. Hashemi-Dezaki, "Reliability optimization of electrical distribution systems using
internal loops to minimize energy not-supplied (ENS)," Journal of Applied Research and
Technology, vol. 13, no. 3, pp. 416-424, (2015).
[15] A. A. S. O. P. MALIK, ELECTRIC DISTRIBUTION SYSTEMS, Canada.: John Wiley & Sons, Inc., Hoboken,
New Jersey., 2019.
[16] T. Dorji, reliability assessment of distribution systems”, including a case study on wang due
distribution system in Bhutan, January 2009.
[17] S. Mishra, Power Quality Improvement Using Unified Power Quality Conditioner, Power Electronics
and Drives, 2016.
[49]
[50]