Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Engineering Structures 201 (2019) 109813

Contents lists available at ScienceDirect

Engineering Structures
journal homepage: www.elsevier.com/locate/engstruct

Cable force optimization of a curved cable-stayed bridge with combined T


simulated annealing method and cubic B-Spline interpolation curves
Junjun Guoa,b, Wancheng Yuana, Xinzhi Danga, , M. Shahria Alamb,
⁎ ⁎

a
State Key Laboratory of Disaster Reduction in Civil Engineering, Tongji University, 1239, Siping Road, Shanghai 200092, PR China
b
School of Engineering, The University of British Columbia, Kelowna, BC, Canada

ARTICLE INFO ABSTRACT

Keywords: Cable-stayed bridges have been extensively constructed in China in the recent two decades. This type of bridge is
Cable-stayed bridge characterized by flexible cables that transfer the deck loads to pylons. This study focuses on the cable force
Optimum cable forces optimization of a curved cable-stayed bridge based on the proposed method where simulated annealing and
Simulated annealing cubic B-Spline interpolation curves are combined for the optimization. Firstly, the numerical model of a curved
Cubic B-Spline interpolation curves
cable-stayed bridge is generated in OpenSees platform. Secondly, the proposed method is elaborately described,
OpenSees
including the establishment of cubic B-Spline interpolation curves based on four interpolation points, the flow
chart of simulated annealing algorithm, objective function, design variables, and design load cases. Finally, the
static responses of the bridge deck, pylons, and cables are calculated and discussed under the obtained optimum
cable forces. The results reveal that the currently proposed method can efficiently generate a number of values
for the objective function, and the optimum solution can be selected as the minimum of the generated objective
function values. In addition, cable forces obtained by the proposed method change gradually. The proposed
method for determining the optimum cable forces can be easily implemented in practice.

1. Introduction takes the zero displacement deck profile at cable anchorage points as a
target where the optimum cable forces are obtained through the
Cable-stayed bridges have been extensively constructed in China iterative process. Zhang and Au [2] further improved this method be-
during the past twenty years. Such bridges are favored by bridge de- cause of its earlier intensive computation and convergence difficulty. In
signers because of the efficient use of materials, aesthetics, and the the case of improved zero displacement method, the uniform design is
economy. Thus, cable-stayed bridges have become a competitive bridge used and the displacement at control points are obtained based on finite
type for long-span bridges, especially for spans between 500 m and element analysis. Then, the Kriging model [3] was adopted to establish
1000 m. The cable-stayed bridge is mainly comprised of three compo- the relationship between the geometry of the bridge deck and the pre-
nents: bridge deck that provides vehicle lanes, stay-cables that transfer tensioning cable forces. Finally, optimal cable forces were obtained
loads from deck to pylons, and bridge pylons that transfer cable forces through optimization analysis on the established Kriging model. This
to the foundation and resist unbalanced bending moments. Stay-cables improved method converges easily and saves time. Nevertheless, the
play an important role in the design procedure and erection stages of a cable forces usually change abruptly for the aforementioned zero dis-
cable-stayed bridge. On one hand, the force distribution of bridge deck placement method.
and pylons can be adjusted by differing tension forces in stay-cables, on Chen and Au [4] proposed the force equilibrium method that can
the other hand, stay-cables make this type bridge a highly redundant easily take the vertical profile of the bridge deck and cable forces into
structure. The deck and pylons of a cable-stayed bridge should be de- consideration. In this method, firstly, the target bending moment of the
signed such that their vertical and horizontal displacements, respec- bridge deck is established by the deck model that is rigidly supported at
tively are minimized during service loads. This purpose can be achieved each cable anchorage point. Then, cable forces are applied to each
by the optimization of pre-tensioning cable forces. This topic has been anchorage point, and iteration is conducted for cable forces to obtain
investigated extensively, and the details are presented in the following the target bending moments of the bridge deck. However, this method
paragraphs. is more complicated and the nonlinearity effects are not considered.
Wang and Tseng [1] presented the zero displacement method that Janjic and Pircher [5] demonstrated the basic principle of unit load


Corresponding authors.
E-mail addresses: leodangxz@163.com (X. Dang), shahria.alam@ubc.ca (M.S. Alam).

https://doi.org/10.1016/j.engstruct.2019.109813
Received 18 March 2019; Received in revised form 5 September 2019; Accepted 15 October 2019
Available online 22 October 2019
0141-0296/ © 2019 Elsevier Ltd. All rights reserved.
J. Guo, et al. Engineering Structures 201 (2019) 109813

method. Each cable force is regarded as an independent variable, and (a). The piers of the bridge are consecutively numbered for convenience
the unit load is applied to one of them to obtain the bending moment at (Fig. 1(a)). Auxiliary piers (2, 5 and 6) are provided to increase the
each anchor point of the bridge deck. By repeating this process, the stiffness of the considered bridge, and counterweights are applied to
relationship between the cable forces and optimal bending moments both side spans to balance the self-weight of the main span. The cables
can be established. Finally, the optimum cable forces can be obtained are arranged in two inclined planes, and semi-harp cable pattern is
by solving the linear equations. The advantage of this method is that the adopted because of its efficiency[16]. The tensile strength of the cables
construction sequence, large displacements, time-dependency, and is 1770 MPa. The cable numbering is presented in Fig. 1(b), and the left
cable sag effects can be taken into account. Lee and Kim [6] proposed a pylon of the bridge is situated on a curve that has the curvature radius
“two-step approach” based on the unit load method. The upper and of 600 m. The pylons of the bridge are asymmetrical, and the height of
lower bounds of cable forces are introduced in the second step and then the shorter pylon and higher pylon are 102 m and 118.5 m, respec-
the global minimum is obtained. However, unit load method is only tively, as can be seen in Fig. 1(a) and (c). The bridge has four lanes of
suitable for linear systems, and it is unreasonable for a large span cable- traffic having a streamlined steel box girder, and the yield strength of
stayed bridge characterized by geometric nonlinearity. the steel box girder is 345 MPa. The pylons, transition piers and aux-
In recent years, a number of optimization algorithms that determine iliary piers are made of concrete. The tensile and compressive strengths
the optimal cable forces of cable-stayed bridges have been proposed. of the concrete are 2.65 MPa and 32.4 MPa, respectively. The cross-
Baldomir and Hernandez [7] conducted an optimum process that can sections of the pylons and auxiliary piers are presented in Fig. 1(d), and
account for cable stress and deck displacement, and the optimized cable the cross-sectional properties of the girder and the pylon bottom are
forces can be obtained after a certain number of iterations. Hassan [8,9] summarized in Table 1.
proposed a new method that combines Genetic Algorithms (GAs) and B-
spline curves to determine the optimum post-tensioning cable forces for
cable-stayed bridges under dead load. This new method can minimize 2.2. Numerical model of the bridge
the vertical displacement of the deck and the horizontal deflection of
the pylon’s tops. Martins and Simões [10–12] computed the cable forces The three dimensional (3D) numerical model of the curved cable-
based on an entropy-based approach that can account for the con- stayed bridge is generated in OpenSees platform[18], as shown in
struction sequence and the time-dependent effects of cable-stayed Fig. 2. The bridge deck is simulated with linear-elastic beam-column
bridges. Fabbrocino and Modano [13] proposed a procedure that can elements passing through its shear center, and the stiffness properties
determine the optimum cable forces of composite cable-stayed bridges, and mass of the deck section are concentrated in the spine beams. It is
and this method pertains to “force equilibrium methods”. Ha and Vu expected that the transition piers, auxiliary piers, and pylons will ex-
[14] developed a generalized method to obtain the optimum cable perience plastic deformation when subjected to extreme loads, such as
forces based on nonlinear inelastic analysis and a micro-genetic algo- strong earthquakes. Thus, they are modelled with fiber sections that are
rithm. The advantage of this method is that both the initial cable ten- comprised of confined concrete, unconfined concrete, and reinforce-
sioning forces and the total weight of cables can be optimized. Song and ment bar. The yield stress, modulus of elasticity and hardening ratio of
Xiao [15] presented an optimization procedure for determining initial the rebar are 400 MPa, 2 × 105 MPa and 0.05, respectively. The rebar is
cable forces of long-span cable-stayed bridges considering the coun- simulated with Steel01 Material in OpenSees. The confined and un-
terweight. confined concrete behaviors are modelled with the nonlinear con-
Although many works for determining the tensioning forces of stitutive relationship proposed by Mander [19]. The maximum com-
cable-stayed bridges have been done based on the above-mentioned pressive strength, strain at maximum strength, crushing strength and
studies, most of them are more complicated for bridge designers. strain at crushing strength of the confined and unconfined concrete are
Meanwhile, cable-stayed bridges are high statically indeterminate, the 36.5 MPa and 32.4 MPa, 2.2 × 10 3 and 2.0 × 10 3 , 7.3 MPa and
solution to cable tensioning forces for this type of bridge is not unique 6.5 MPa, and 1.6 × 10 2 and 3.5 × 10 3 , respectively. The advantage of
[17]. Thus, it is essential to develop a new procedure that can easily the fiber section is that the P-delta effect can be accounted in the static
determine the optimum cable forces. In the current study, a method analysis. The inclined stay cables are assumed to remain elastic during
combing simulated annealing algorithm and cubic B-Spline interpola- its whole service life, and these flexible stay cables can only resist
tion curves is proposed. Compared to the aforementioned methods, the tensile force. Thus, stay cables are modelled with large-displacement
proposed new algorithm can achieve a balance between the accuracy truss elements with pre-defined tension-only uniaxial material. The
and computational cost, i.e. the reasonable cable forces can be obtained sagging effect of stay cables due to its self-weight is considered by the
after a certain number of iterations. This method can be used to facil- equivalent modulus of elasticity or Ernst modulus [20]. The large dis-
itate the preliminary design of cable-stayed bridges. More importantly, placement truss element in OpenSees is adopted to model the stay
the obtained cable forces will not change abruptly but smoothly. The cables. First, the allowable stress of the cable is taken as one-third of its
numerical model of a curved cable-stayed bridge is established by design strength (1770 ÷ 3= 590 MPa ), and the areas of each cable can be
OpenSees software, and an optimization algorithm is programmed in calculated. Second, Ernst method is used to obtain the equivalent
Python language. The static responses of the bridge deck, the pylons, modulus of elasticity. Then, the cable forces are applied to the bridge by
and the cables are calculated and discussed under the obtained op- truss elements that include tension only materials with initial strain.
timum cable forces. The two ends of stay cables are rigidly connected with the corre-
sponding deck nodes and pylon nodes, respectively. The transition
2. Description and numerical model of the bridge piers, auxiliary piers, and pylons are connected with bridge deck by
bearings. These bearings are restrained in the transverse direction and
2.1. Description of the bridge can move freely in the longitudinal direction. In the vertical direction,
the bearings are assumed to resist only compressive force, thus elastic
The illustrative example bridge has been chosen in the current study no-tension material is adopted to simulate the force-displacement re-
based on a three-span curved cable-stayed bridge under construction. lationship of the bearings. Lumped linear springs including three
The length of the main span is 364 m, and the length of the left and translational springs and three rotational springs are used to model the
right side spans are 96 m and 138.8 m, respectively, as shown in Fig. 1 pier foundations.

2
J. Guo, et al. Engineering Structures 201 (2019) 109813

Fig. 1. Description of the bridge: (a) elevation view; (b) plan view; (c) side view; (d) cross-sections of pylons and auxiliary piers.

Table 1 cable-stayed bridge has asymmetrical pylons and side spans, thus the
Cross-sectional properties. cable forces in each side have to be taken as design variables for pre-
Cross-section
vious optimization techniques. Thus, a total of 56 design variables
A (m2) Iz (m4) Iy (m4) J (m4)
should be considered in the example bridge. The main disadvantage of
Girder 1.779 246.207 2.620 3.800 a large number of design variables is that it is difficult to obtain the
Pylon bottom 104.238 20,553 641 1680 optimum solution, meanwhile, the cable forces in some intervals may
change sharply. In order to avoid these disadvantages, Cubic B-Spline
Note: A = cross section area; Iz = moment of inertia to the global z-axis;
interpolation curve is adopted to represent the cable force distribution
Iy = moment of inertia to the global y-axis; J = torsion resistance.
in the current research, as shown in Fig. 3. The cubic B-Spline curve can
be defined as below[21]:
3. Formulation of the optimization problem 3
Pk,3 (t ) = Pi + k Gi,3 (t ), t [0, 1]
3.1. Cubic B-Spline interpolation curve i=0 (1)

In most previous optimization procedure, the design variables are where Pi (i = 0, 1, ...,5) are the control points, Gi,3 (t ) are the third-order
equal to the number of stay cables. For example, the current curved B-Spline basis functions given as:

3
J. Guo, et al. Engineering Structures 201 (2019) 109813

Fig. 2. Numerical model of the bridge.

conditions of cubic B-Spline curve given as:


1
P0,3 (0) = 6 (P0 + 4P1 + P2) = f (x 0)
1
P0,3 (1) = 6 (P1 + 4P2 + P3) = f (x1)
1
P1,3 (1) = 6 (P2 + 4P3 + P4 ) = f (x2 )
1
P2,3 (1) = 6 (P3 + 4P4 + P5) = f (x3) (3)

P0,3 (0) = P2 2P1 + P0 = 0


P3,3 (1) = P5 2P4 + P3 = 0 (4)

Eq. (3) reflects the values at the ends of the first curve segment,
which are equal to the corresponding interpolation point values. Eq. (4)
Fig. 3. Cubic B-Spline interpolation curve.
presents the second derivative of the first curve segment at the end-
points. In the same way, the boundary conditions for the other two
1
G0,3 (t ) = 6 ( t 3 + 3t 2 3t + 1) curve segments can be established. It should be noted that some of the
1 aforementioned equations are correlated due to the continuity condi-
G1,3 (t ) = (3t 3 6t 2 + 4) t [0, 1]
6 tions of internal interpolation points. Finally, a total of 6 independent
G2,3 (t ) =
1
6
( 3t 3 + 3t 2 + 3t + 1) equations are established, and the 6 control points can be determined
1 3 by solving the independent equations under given interpolation points.
G3,3 (t ) = t (2)
6 In the current study, cubic B-Spline interpolation curves are obtained by
using the functions (interpolate.splrep () and interpolate.splev ()) in
The relationship between the control points and the interpolation Python programming [22]. The advantage of cubic-B spline interpola-
points (design variables) can be established based on boundary tion curve is that it can accommodate various shapes with only four

Fig. 4. Cable forces represented by cubic B-Spline interpolation curves.

4
J. Guo, et al. Engineering Structures 201 (2019) 109813

Start

Randomly generate initial solution x, and


calculate objective function f(x_old)

Random walk to generate new


solution x_new, and calculate new
objective function f(x_new)

dE=f(x_new)-f(x_old)

Calculate probability
dE<0? No
p=exp(-dE/T)

No Yes

Accept new solution x=x_new


Yes
P>Random(0,1)?

Reach total number


No
of random walk ?

Yes

Decrease iterative Reach minimum


No
value T=maxT*α^k iterative value Tmin ?

Yes

End

Fig. 5. Flow chart of the simulated annealing method.

parameters, in addition, this curve changes smoothly. However, for 2. Calculate the old objective function value ( f (x old ) ) based on the
polynomial, the lower degree polynomial cannot provide adequate generated initial solution x . Randomly walk based on below for-
shapes, and the high degree polynomial usually makes curves change mulation:
abruptly. The authors tried to adopt polynomial and exponential
x new =x - old + T × sigFun (u 0.5) × ((1 + 1/ T )|2 × u 1| 1) × x
functions, but the results are not as good as those based on the cubic B-
Spline interpolation curve. (5)
In the current study, four cubic B-Spline interpolation curves are T = Tmax × k
(6)
used to represent the cable force distributions due to the asymmetry of
the example bridge, as shown in Fig. 4. For each interpolation curve, 1 if x > 0
the interpolation points are equally spaced along its horizontal axis. The sigFun (x ) = 0 if x = 0
first and fourth interpolation points are located at the first and last 1 if x < 0 (7)
anchor points, respectively. As a result, the vertical coordinate values of
interpolation points are taken as design variables. where T is the current iterative value level, and can be obtained
based on expression (6); x is the change of variable value; is a
3.2. Simulated annealing method constant usually varying from 0.8 to 1; k is the iteration number;
sigFun (x ) is signal function, as defined in formula (7); u is a random
Simulated annealing (SA) method is a probabilistic technique for value generated based on uniform distribution between 0 and 1
approximating the global optimization in a large search space for an (u = random . uniform (0, 1) ). In the current study, the tensile
optimization problem [23–25]. Implementation of the simulated an- strength of the cable is 1770 MPa, and the allowable stress of the
nealing is presented in Fig. 5, and can be summarized as below: cable under dead load case is taken as the one-third of its tensile
strength. As a result, the cross-sectional area of each cable can be
1. Determine the solution space, maximum iterative value Tmax , calculated using equation (8):
minimum iterative value Tmin , and the total number of random walk
for each iterative level.

5
J. Guo, et al. Engineering Structures 201 (2019) 109813

F Fobj = (d12 + d 22 + ) + (p12 + p22 + )


A= (11)
[ ] (8)
where di is the vertical displacement of the bridge deck node; pi is the
where A is the cross-sectional area, F is the cable force, and horizontal displacement of the pylon node.
[ ] = 1770 ÷ 3= 590 MPa is the allowable stress. The purpose of taking all the bridge deck and pylon nodes into
3. Calculate the new objective function value ( f (x new ) ) based on the account in establishing the objective function is to achieve small ver-
generated new solution x new . Then compare f (x new ) with f (x old ) : tical displacements of the bridge deck and horizontal displacements of
the pylons in the process of cable force optimization.
dE = f (x new ) f (x old ) (9)
3.4. Optimization implementation
if dE < 0 , replace the current old solution x old with the current new
solution x new . Otherwise, accept x new based on formulas (10): The optimization procedure of the example cable-stayed bridge can
be implemented based on the above-mentioned algorithm. In the cur-
exp( dE / T ) > random . uniform (0, 1) (10)
rent study, the maximum and minimum iterative values are set to 20
and 5.0 × 10 5, respectively. is set to 0.95, which can guarantee the
where exp(x ) is an exponential function; random . uniform (0, 1) iterative value decreases gradually. The total number of random walks
generates a random value between 0 and 1. in each iterative value is set to 2. In the current study, the lower and
4. Repeat steps 2 and 3 until reaching the total number of random upper bounds of the cable forces are set to 1000 kN and 5500 kN, re-
walks in the current iterative value level (T ), and record the op- spectively. In case, the lower and upper bound values are different, and
timum solution at this iterative value level. Then, update iteration those bound values can be set in the program. These bound constraints
number k, and decrease the iterative value based on formula (6). are set to narrow the search space, thus, a number of values of the
5. Repeat step 4 until reaching the termination condition (Tmin ). objective function can be obtained quickly. In practice, the cable forces
near the ends and middle of the girder are larger than those in the other
SA method can avoid the local optimal solution. However, for some positions, which can increase the global stiffness of the cable-stayed
complicated problems, it is difficult to obtain the global optimal solu- bridge. Thus, the values of design variables are designed to satisfy the
tion. For such situations, it is preferred to obtain a reasonable solution following constraint:
from a set of generated solutions. On one hand, finding a global optimal
solution is time-consuming, and for some problems, it is difficult to 1000 kN < f (x 0 ) < f (x1 ) < f (x2 ) < f (x3 ) < 5500 kN (12)
obtain the global optimum. On the other hand, some accepted solutions The change of variable value ( x ) is set to 1000 kN, and a total of
can be generated after a certain number of iterations. In the current two random walks are conducted for each iteration level. In the current
study, the number of iterations depends on the maximum value (Tmax ), study, cable force optimization is conducted under dead load, and dif-
minimum value (Tmin ), the magnitude of variable change ( x ) in Eq. (5), ferent variable initial values are considered to evaluate their effects on
and in Eq. (6). After running many simulations with many trials and the responses of the bridge, as shown in Fig. 6. Fig. 6(a) depicts the
errors, the authors’ gained valuable experiences, and found that x can objective function values of two different initial values. It is found that
be set to 1000 kN, the Tmax and Tmin can be varied from 10 to 50 and a number of the values of the objective function can be obtained, and
1.0 × 10 - 4 to 1.0 × 10 - 5 , respectively. Where, can range from 0.85 to approximately equal optimum values generate for two different initial
0.95. Then, Eq. (6) can be used to calculate the number of iterations. It conditions. This is verified by the maximum vertical displacement of
should be noted that the suggested iterative parameter values may not the bridge deck and the maximum horizontal displacement of the py-
be suitable for other cable-stayed bridges, and some numerical trials lons, as shown in Fig. 6(b) and (c). In the following case study, the
can be conducted to select the appropriate values. In general, there variable initial value (2000, 3000, 4000, 5000) kN is taken, and the
should be a large range at the earlier iteration, and a small range at the cable forces based on the minimum value of the objective function are
end of iteration. For example, taking x as 1000 kN, Tmax and Tmin as 10 taken in the following study.
and 1.0 × 10 - 4 , respectively, and as 0.9. Based on equation (5), the In the current study, the short side spans are supported by auxiliary
maximum and minimum changes of the control points are 10,000 kN piers, thus the stiffness of the side spans is larger than that of the middle
and 0.1 kN, respectively. The total number of iterations is 110 ac- span. As a result, compared to the whole deck length, applying live load
cording to Eq. (6). in the middle span is more critical to the whole bridge system, and will
In the following optimization, optimal solutions at each iterative generate more conservative estimate for the cable forces. Three live
value level will be recorded, and the final solution can be selected from load cases are considered, as can be seen in Fig. 7. According to Chinese
the iterations. bridge design specification[26], the live load for each traffic lane is
composed of distributed load (DLL) and concentrated load (CLL), and
3.3. Design variables and objective function 10.5 kN/m and 360 kN kN are taken for distributed and concentrated
loads, respectively. A total of 4 lanes are designed in the current cable-
In the current study, the y-coordinates of the cubic B-Spline inter- stayed bridge. For live load case 1, the distributed and concentrated live
polation points are taken as design variables ( f (x i ) in Fig. 3) that de- loads are applied to the main span and to the interaction position of the
termine the shape of the cubic B-Spline interpolation curve. Stay cable two cable planes, respectively. The other two live load cases can be seen
forces can be obtained based on the determined curve. A total of 16 in Fig. 7.
design variables defining 4 cubic B-Spline interpolation curves are
considered in the current optimization problem. The x-coordinates of 4. Results and discussion
the interpolation points are uniformly spaced and do not change during
the optimization process. According to the optimization in Section 3, the cable responses
The objective function (Fobj ) to be considered in the current study is under four load cases are illustrated in Fig. 8. The cable forces for each
the square root of the sum of the squares (SRSS) of the vertical dis- cable plane change smoothly from the first stay cable to the last. The
placement of the nodal points of the bridge deck and the squares of the cable forces increased for live load cases compared to those for the dead
horizontal displacements of the nodal points of the pylons. The use of load, and it can be seen that the cables near the end of the cable plane
the SRSS smoothes out the objective function and does not induce false are more easily affected by the live loads. It is found that the cable
local optima [8]. The objective function is presented in Eq. (11): forces for four load cases (dead load and three live load cases) are

6
J. Guo, et al. Engineering Structures 201 (2019) 109813

Fig. 6. Results of optimization under variable initial value (2000, 3000, 4000, 5000) kN and (1000, 2500, 4000, 5500) kN: (a) objective function; (b) maximum
vertical displacement of the bridge deck; (c) maximum horizontal displacement of the pylons.

within the upper and lower bounds as predefined. main span) as per the Chinese cable-stayed bridge design specification
Fig. 9 presents the vertical displacement, axial force and bending [27]. In the current research, the optimization is conducted under dead
moment along the bridge deck under the dead load and other three live load, and optimization can also be implemented with the consideration
load cases. The maximum vertical displacements of the bridge deck of dead load and live load. The vertical displacements in the side spans
under dead load and live load case 1 are 0.02 m and 0.27 m, respec- are very small compared to those in the main span because of the
tively. These vertical displacements are within the allowable displace- auxiliary piers. Fig. 9(b) presents the axial forces of the bridge deck, it is
ment (Lmain/400 = 364/400 = 0.91 m, and Lmain is the length of the found that the maximum axial force is located at the intersection

Fig. 7. Live load cases: concentrated live load (CLL) and distributed live load (DLL).

7
J. Guo, et al. Engineering Structures 201 (2019) 109813

Fig. 8. Cable forces under different design loads.

between the deck and the taller pylon. The maximum bending moments much smaller than the corresponding normal stresses. Fig. 11(a) pre-
of the bridge deck in the main and side spans are 6870 kN·m and sents the maximum and minimum normal stresses of the steel box
52,087 kN·m, respectively when subjected to the dead load. Large girder under different loading conditions (dead load case, live load 1
bending moments of the bridge deck exist in side-span due to the case, live load 2 case and live load 3 case). The normal stress is cal-
counterweights. Counterweights at the side spans can increase the culated based on the axial force and bending moment at each cross-
global stiffness of the bridge, meanwhile, large bending moments exist section. It is found that the maximum normal stress is 63.4 MPa oc-
in side-spans. However, the stresses induced by these large bending curring in live load 3 (Live3-Max), which is about 22.6% of the al-
moments and the corresponding axial forces are far less than the yield lowable maximum compressive stress (280 MPa). In addition, the
strength of the girder. More detailed information is provided in the minimum normal stress is −26.8 MPa which is about 9.6% of the al-
following section. The maximum bending moments of the bridge deck lowable maximum tensile stress (−280 MPa). The maximum and
under live load case 1 is 49,870 kN·m, and this means that the cable minimum normal stresses of the steel girder under the four load con-
forces obtained based on the proposed method are reasonable with ditions are far less than their corresponding allowable values. Fig. 11(b)
respect to the responses of the bridge deck under dead and live load demonstrates the maximum and minimum normal stresses along the
cases. height of the short pylon. The allowable maximum compressive and
Fig. 10 depicts the static responses of the shorter pylon under dead tensile stress of the concrete is 22.4 MPa and −1.8 MPa, respectively. It
and live load cases. The maximum horizontal displacement of the top of is found that all the sections experience stresses where the maximum
the short pylon under dead load and live load case 1 are 0.02 m and compressive stress is 8.2 MPa that is 36.6% of the allowable compres-
0.069 m, respectively, as can be seen in Fig. 10(a). The bending moment sive stress. It should be noted that the allowable maximum stresses for
distribution along the pylon height is described in Fig. 10(c), and the the concrete and steel refer to their corresponding design strength va-
maximum bending moment is located at the bottom of the pylon. lues according to Chinese reinforced and prestressed concrete bridges
In order to validate the effectiveness of the proposed cable force design specification [28], for example, the compressive strength stan-
optimization method, the stresses along the steel girder length and dard value of concrete C50 is 32.4 MPa, and its design strength value
pylon height are calculated, as can be seen in Fig. 11. In the current (allowable maximum value) is 22.4 MPa.
study, the shear stresses are not considered because they are usually The current study shows that optimum cable forces can be obtained

8
J. Guo, et al. Engineering Structures 201 (2019) 109813

Fig. 9. Responses of the bridge deck under different load cases: (a) vertical displacement; (b) axial force; (c) bending moment.

based on the proposed method. The objective function usually cannot method can be used to solve equation (13), then the tensioning cable
directly converge to the global minimum. However, a set of rational forces can be updated as below:
results can be obtained, such as displacements of the bridge deck, py-
{T } = {T0} + {x } (14)
lons, and cable forces. Hence, the new algorithm is efficient in de-
termining the initial cable forces of cable-stayed bridges. Another im- Repeating step one and two, until the errors between the target and
portant aspect is that, the cable force distribution of each cable plane iterated critical responses satisfy the predefined threshold. The ad-
can be specified, for example, in the current study, the values for each vantage of the forward iteration method is that shrinkage and creep
cable plane are assumed to increase from the start till the end. effects of concrete can be taken into consideration during the con-
For convenience, the cable-stayed bridge design is divided into two struction process. More details about the forward iteration method to
stages: completion stage and construction stage. For completion stage, determine the tensioning cable forces at construction stage can refer to
there is no need to consider the construction stage. At the notional Wang et al. [29].
completion state, the cable forces are optimized, which are later used in
the construction stage. The optimized final state is considered as target 5. Conclusions
cable forces, and forward iteration method can be adapted to determine
the cable forces at each construction step. The main purpose of this This study determines the optimum cable forces of a curved cable-
manuscript is to determine the optimal final stage of the cable-stayed stayed bridge based on the combination of the simulated annealing
bridge, which can be used as target values in the construction process. method and cubic B-Spline interpolation curves. The finite element
After determining the optimal cable forces at the completion stage, model of the example bridge is established in OpenSees platform, and
the forward iteration method [4] can be adopted to generate the ten- the proposed algorithm is programmed by Python language. The pro-
sioning cable forces at their corresponding construction steps. In the posed algorithm is independent of numerical models, and it can be
forward iteration method first a set of tensioning cable forces ({T0} ) are easily applied to other finite element software, such as SAP2000, S-
assumed to generate a completion state based on the forward method. FRAME, ANSYS, ABAQUAS, et al. The main conclusions can be drawn
Secondly, by comparing the generated and optimized completion stages as below:
(cable forces, girder vertical displacements et.al.), the cable forces are
adjusted based on the following expression: 1. The cable force distribution of each cable plane can be represented
by a cubic B-Spline interpolation curve that can make the cable
[A]{x } = {F0 F} (13)
forces change smoothly. In the current study, the obtained cable
where [A] is the influence matrix, {x } is the cable force increment forces gradually increase from the start of each cable plane.
vector, F0 , F are the critical responses at the optimized completion 2. It is difficult for the objective function of the proposed method to
stage and the generated completion stage, respectively. The least square converge to a global minimum, but a number of reasonable values of

9
J. Guo, et al. Engineering Structures 201 (2019) 109813

Fig. 10. Responses of the short pylon under different load cases: (a) horizontal displacement; (b) axial force; (c) bending moment.

the objective function can be generated from the proposed method. load can also be taken into account in the process of optimization.
The optimum solution can be selected as the minimum of the gen- 4. Although bridge response constraints are not applied in the opti-
erated objective function values. mization, the peak responses, such as the maximum vertical dis-
3. Reasonable static responses of the bridge deck, the pylons, and the placement of the deck and the maximum stresses of the girder and
cable forces are obtained under different load cases. The current pylons have been checked to make sure that they are within the
optimization is conducted under the dead load only, where the live corresponding allowable ranges.

Fig. 11. Cross-sectional maximum (Max) and minimum (Min) normal stresses along (a) deck length, and (b) pylon height.

10
J. Guo, et al. Engineering Structures 201 (2019) 109813

In the current study, the cable forces are optimized under the dead [9] Hassan MM. Optimization of stay cables in cable-stayed bridges using finite ele-
load, and only the live load is considered to verify the effectiveness of ment, genetic algorithm, and B-spline combined technique. Eng Struct
2013;49(2):643–54.
the proposed method. In practical design, temperature effect, steel [10] Martins AMB, Simões LMC, Negrão JHJO. Cable stretching force optimization of
girder fatigue effect, and shrinkage and creep effects of concrete should concrete cable-stayed bridges including construction stages and time-dependent
be considered to check whether the critical responses are within their effects. Struct Multidiscip Optim 2015;51(3):757–72.
[11] Martins AM, Simões LM, Negrão JH. Optimum design of concrete cable-stayed
corresponding limits. It should be noted that the proposed algorithm bridges. Eng Optim 2016;48(5):772–91.
does not take the construction sequence into consideration. It is used to [12] Martins AMB, Simões LMC, Negrão JHJO. Optimization of cable forces on concrete
determine the cable forces at the final stage of construction. Hence, the cable-stayed bridges including geometrical nonlinearities. Comput Struct
2015;155(C):18–27.
proposed method will be useful to practicing engineers for the pre- [13] Fabbrocino F, Modano M, Farina I, Carpentieri G, Fraternali F. Optimal prestress
liminary design of cable-stayed bridges. design of composite cable-stayed bridges. Compos Struct 2017;169:167–72.
[14] Ha M-H, Vu Q-A, Truong V-H, editors. Optimum design of stay cables of steel cable-
stayed bridges using nonlinear inelastic analysis and genetic algorithm. Structures.
Acknowledgment
Elsevier; 2018.
[15] Song C, Xiao R, Sun B. Optimization of cable pre-tension forces in long-span cable-
This research was supported by the China Scholarship Council stayed bridges considering the counterweight. Eng Struct 2018;172:919–28.
under Grant No. 201806260168; the Ministry of Science and [16] Calvi GM, Sullivan TJ, Villani A. Conceptual seismic design of cable-stayed bridges.
J Earthquake Eng 2010;14(8):1139–71. https://doi.org/10.1080/13632469. 2010.
Technology of China under Grant No. SLDRCE19-B-19; the National 505275.
Natural Science Foundation of China under Grant No. 51778471, [17] Sung YC, Chang DW, Teo EH. Optimum post-tensioning cable forces of Mau-Lo Hsi
51978512; and Transportation science and technology plan of cable-stayed bridge. Eng Struct 2006;28(10):1407–17.
[18] McKenna F, Scott MH, Fenves GL. Nonlinear finite-element analysis software ar-
Shandong province (2017B75). The first author would like to ac- chitecture using object composition. J Comput Civil Eng 2010;24(1):95–107.
knowledge the Faculty of Applied Science, the University of British [19] Mander JB, Priestley MJ, Park R. Theoretical stress-strain model for confined
Columbia for their support during the UBC visit and complete the study. concrete. J Struct Eng 1988;114(8):1804–26.
[20] Ernst JH. Der E-Modul von Seilen unter berucksichtigung des Durchhanges. Der
Bauingenieur 1965;40(2):52–5. [in German].
References [21] Caglar H, Caglar N, Elfaituri K. B-spline interpolation compared with finite differ-
ence, finite element and finite volume methods which applied to two-point
boundary value problems. Appl Math Comput 2006;175(1):72–9.
[1] Wang PH, Tseng TC, Yang CG. Initial shape of cable-stayed bridges. Comput Struct
[22] Oliphant TE. Python for scientific computing. Comput Sci Eng 2007;9(3):10–20.
1993;46(6):1095–106.
[23] Ingber L. Simulated annealing: practice versus theory. Math Comput Model
[2] Zhang J, Au FTK. Calibration of initial cable forces in cable-stayed bridge based on
1993;18(11):29–57.
Krigingapproach. Finite Elem Anal Des 2014;92(24):80–92.
[24] Junior HAEO, Ingber L, Petraglia A, Petraglia MR, Machado MAS. Stochastic global
[3] Lophaven SN, Nielsen HB, Sondergaard J. DACE a Matlab Kring toolbox[EB/OL].
optimization and its applications with fuzzy adaptive simulated annealing. Springer
http://www2.imm.dtu.dk/~hbn/dace/ [19.02.2005].
Berlin Heidelberg; 2012.
[4] Chen DW, Au FTK, Tham LG, Lee PKK. Determination of initial cable forces in
[25] Lin SW, Lee ZJ, Chen SC, Tseng TY. Parameter determination of support vector
prestressed concrete cable-stayed bridges for given design deck profiles using the
machine and feature selection using simulated annealing approach. Appl Soft
force equilibrium method. Comput Struct 2000;74(1):1–9.
Comput 2008;8(4):1505–12.
[5] Janjic D, Pircher M, Pircher H. Optimization of cable tensioning in cable-stayed
[26] General specifications for design of highway bridges and culverts. JTG D60-2015;
bridges. J Bridge Eng 2003;8(3):131–7.
2015.
[6] Lee TY, Kim YH, Kang SW. Optimization of tensioning strategy for asymmetric
[27] Guidelines for design of highway cable-stayed bridge. JTG/T D65-01-2007; 2007.
cable-stayed bridge and its effect on construction process. Struct Multidiscip Optim
[28] Code for design of highway reinforced concrete and prestressed concrete bridges
2008;35(6):623–9.
and culverts. JTG D62-2004; 2004.
[7] Baldomir A, Hernandez S, Nieto F, Jurado JA. Cable optimization of a long span
[29] Wang P-H, Tang T-Y, Zheng H-N. Analysis of cable-stayed bridges during con-
cable stayed bridge in La Coruña (Spain). Adv Eng Softw 2010;41(7–8):931–8.
struction by cantilever methods. Comput Struct 2004;82(4–5):329–46.
[8] Hassan MM, Nassef AO, Damatty AAE. Determination of optimum post-tensioning
cable forces of cable-stayed bridges. Eng Struct 2012;44(6):248–59.

11

You might also like