Professional Documents
Culture Documents
0 Egpc-Aud-001-Aprc Bowtie Voume 5
0 Egpc-Aud-001-Aprc Bowtie Voume 5
Volume 5
Bow Tie Analysis Report
Copyright
This document is a property of EGPC. It is non-transferable and must be surrendered on demand or upon
termination of employment to EGPC. This document cannot be used except in the purposes it is issued
for. It cannot be reproducing this report in whole or in part unless by the approval of EGPC CEO Assist for
HSE and according to EGPC document control procedure (EGPC.GEN.GL.001).
Disclaimer
This assessment report has been prepared by the team formulated by the ministerial decree #1484 of
year2020 solely for EGPC and is confidential. Neither EGPC nor any of its respective officers or employees
accept any responsibility or liability whatsoever (including negligence) with respect to the contents of
this assessment report. No warranties, representations or conditions of any kind either express or implied
are given or made in respect of the contents of this report. Accordingly, if any reader chooses to rely on
any aspect of this report they do so entirely at their own risk.
All administrative queries should be directed to the EGPC HSE Department utilizing feedback form
according to document control procedure (EGPC.GEN.GL.001)
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 3 of 111
Document No: EGPC-AUD-APRC-05
Table of Contents
Introduction ............................................................................................................................................... 5
Plant Overview ........................................................................................................................................... 6
Bow Tie Methodology ................................................................................................................................ 9
3.1 Bow Tie Concept .................................................................................................................................... 9
3.2 Study Recording ................................................................................................................................... 10
3.3 Barriers Effectiveness........................................................................................................................... 10
3.4 Priority Ratings Matrix ......................................................................................................................... 10
3.5 Team Composition ............................................................................................................................... 12
List of abbreviations ................................................................................................................................. 12
Bow Tie Recommendations ..................................................................................................................... 13
5.1 LPG in storage area .............................................................................................................................. 13
5.2 Gasoline in floating roof tank .............................................................................................................. 15
5.3 Floating roof in gasoline tanks ............................................................................................................. 17
5.4 Propane stored in bullets ..................................................................................................................... 19
5.5 HF in Alkylation unit ............................................................................................................................. 21
5.6 Hydrocarbon in VRU unit ..................................................................................................................... 24
: List of Attendees .......................................................................................................................... 28
: Bow Tie Diagrams ....................................................................................................................... 39
i. LPG in Storage Area ............................................................................................................................. 40
ii. Gasoline in Floating Roof Tanks ........................................................................................................... 51
iii. Roof in Gasoline Floating Roof Tanks .................................................................................................. 64
iv. Propane in bullets ................................................................................................................................ 75
v. HF in Alkylation unit ............................................................................................................................. 85
vi. Hydrocarbon release in VRU unit ........................................................................................................ 99
List of Figures
Figure 1: APRC Block Flow Diagram .................................................................................................................. 7
Figure 2: APRC Plot Plan.................................................................................................................................... 8
Figure 3: Bow tie analysis structure .................................................................................................................. 9
List of Tables
Table 1: Barriers effectiveness color code ....................................................................................................... 10
Table 2: Priority Ratings for Recommendations ............................................................................................. 11
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 4 of 111
Document No: EGPC-AUD-APRC-05
Introduction
Egyptian petroleum general corporate (EGPC) has established a committee to review the process safety
management system in Amreya Petroleum Refining Co. (APRC). Part of the assessment process was to
conduct Bow-Tie analysis workshops for major hazards were conducted by participation of personnel from
different departments in addition to committee team in the period between 9 th December and 15th
December 2020.
The Bow Tie is a risk assessment method that can be used to analyze and communicate how high risk
scenarios develop. The essence of Bow Tie consists of credible risk scenarios around a certain hazard and
the barriers that prevent or reduce the severity of these scenarios.
1. Fulfill the requirement of the ministry of petroleum to develop Bow Tie for major hazards.
2. Analyze the major hazards in a systematic and structured way.
3. Identifying the process safety barriers in place and evaluate their effectiveness.
4. Engaging the workforce in developing Bow Ties and increase their risk awareness.
5. Provide a model for Bow Tie analysis so APRC team could develop their own for the hazards that
didn’t cover during the sessions.
6. Develop recommendations to strengthen the barriers and reduce the plant's overall risk.
The following hazards have been analyzed during Bow Tie workshops:
However, it should be noted that the Bow Tie analysis doesn’t replace the HAZOP study and other risk
assessment studies that must be conducted by APRC.
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 6 of 111
Document No: EGPC-AUD-APRC-05
Plant Overview
AMREYA petroleum refining company (APRC) is EGPC owned company. It had been established in 1971.
It is considered as one of the biggest EGPC refining companies. According to the annual report
throughput with about 13% of country refining capacity.
Currently the refinery's capacity is 11000 -12000 metric ton/day of crude oil (3.8 million ton per year).
APRC produces high octane gasoline, naphtha, kerosene elemental sulfur, diesel oil, gas oil, lube oil,
linear alkyl benzene, asphalt, blown bitumen, fuel oil, benzene, toluene, LPG, wax, jet fuels ,technical
white oil, medicinal oil, spray oil and turbine oils. APRC play an important role in exporting some products
through (EGPC) as fuel oil, slack wax, and (LAB), to Italy, Greece, Malta, Germany, and England.
Key processing units installed include:
⚫ 2 x Crude Distillation Units (CDU 3 and CDU 5)
⚫ 1 x Vacuum Distillation Unit (VDU with Blown Bitumen)
⚫ 1 x Vapor Recovery/LPG Recovery Unit (VRU)
⚫ Kerosene, Naphtha, LPG and Gas Oil Hydro-desulphurization Units
⚫ Lubrication Oil Plant which includes;
➢ Propane De-Asphalting Unit (Unit 13 decommissioned / Unit 13A available)
➢ Phenol Extraction Unit
➢ De-waxing Unit
➢ Clay Treatment Unit
➢ Hydro-finishing Unit
➢ Specialty Oil Unit
➢ Medical Oil Unit
⚫ Naphtha Platforming and Aromatic Extraction Unit including:
➢ Naphtha Hydro treater
➢ Fixed Bed Catalytic Reformer
➢ Benzene/Toluene Extraction Unit
➢ Naphtha Isomerization Unit
⚫ Linear alkyl benzene (capacity 40,000 tons)
⚫ Storage facilities
⚫ Utilities
The block flow diagram of APRC is shown in Figure 1, while the APRC plot plan is shown in Figure 2.
Rev. 0
Bow Tie Analysis Report
Dec. 2020
Amreya Petroleum Refining Company
Page 7 of 111
Document No: EGPC-AUD-APRC-05
The followings steps were considered during the development of each bow tie diagram:
• Address the major accident hazard and top event;
• Define consequences and threats (initiating events);
• Define preventive and mitigation barriers;
• Define degradation factors and controls for barrier where specific concerns are highlighted by
the team
• Evaluate the effectiveness of barriers.
• Define the required actions to reduce the risk and to enhance barriers' effectiveness.
Effective
Partly Effective
Ineffective or Missing
Unknown
List of abbreviations
Item Definition
ALARP As Low As Reasonably Practicable
BFD Block Flow Diagram
BMS Burner Management System
CCTV Closed Circuit Television
CDU Crude Distillation Unit
DECT Digital Enhanced Cordless Telecommunications
EGPC Egyptian General Petroleum Corporation
ERP Emergency Response Plan
HAZID Hazard Identification
HSE Health, Safety, and Environment
HSE CB HSE Capacity Building
HVAC Heat Ventilation and Air Conditioning
ITPM Inspection, Testing and Preventive Maintenance
MAH Major Accident Hazards
NORM Naturally Occurring Radioactive Material
PFD Process Flow Diagram
P&ID Piping and Instrumentation Diagram
PPE Personal Protective Equipment
PSM Process Safety Management
PSSR Pre Startup Safety Review
PTW Permit to Work
RCFA Root Cause Failure Analysis
R&D Research and Development
SOP Standard Operating Procedures
RBI Risk-Based Inspection
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 13 of 111
Document No: EGPC-AUD-APRC-05
29 Study providing CCTV and proper access control for the bullets area. P4
Conduct a survey to check the condition of the concrete structures inside the facility.
30
Prioritize them and make the required repairs for the defected items.
P3
31 Study installing double block valves for all samples and drains with plugs or caps. P3
Assure providing the required EX walkie talkie devices to be used inside the operation units and tank farm
32 P2
areas
33 Study and review lightening and earthing system and assess them against the relevant standard. P2
34 Assure develop Hazard Area Classification layout and schedules for all the facility areas. P2
Assure availability of certified ATEX engineers to check the conditions of the EX-rating devices and
35 P3
connections and assess compliance with the ATEX requirements.
36 Expedite the implementation of the new FF and detection system for propane & LPG bullets. P2
37 Conduct HAZOP study for the LPG bullets to study the neediness for of installing ESD system. P2
38 Assure providing override management system for the existing detection system for the G06 LPG bullet. P3
Assure providing detailed specific LPG or propane release scenarios to the ERP with specific consideration
39
and procedures.
P3
Study and review the existing FF system and assess against the worst case scenario and the required flow
40
quantities and pressure needed.
P2
Build a rescue team and provide them with the required training, and ensure providing them with the proper
41
equipment/facilities, and check their physical fitness for work.
P3
42 Assure providing proper head counting system inside the facility. P3
43 Install proper number of fire alarm siren to ensure proper notification for the whole complex. P3
44 Conduct adequate and regular different level drills for all potential emergency scenarios. P2
45 Provide adequate number of first aid kits and conduct the required training for the medical team. P3
46 Assure providing adequate number of safety showers based on relevant standard. P3
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 15 of 111
Document No: EGPC-AUD-APRC-05
28 Assure creating Hazard Area Classification layout and schedules for all the facility areas. P2
Assure availability of certified ATEX engineers to check the conditions of the EX-rating devices and connections
29 P3
and assess compliance with the ATEX requirements.
Study and review the existing FF system and assess against the worst case scenario and the required flow
30 P2
quantities and pressure needed.
Assess and review the location of the firefighting manual valves and assure they are in safe location, locked
31 P2
open with proper labeling.
Assure updating the existing ERP to include a detailed emergency scenarios, then train all employees on it, and
32 P2
perform regular drills with different levels.
Build a rescue team and provide them with the required training, and ensure providing them with the proper
33 P3
equipment/facilities, and check their physical fitness for work.
34 Assure providing proper head counting system for the employees. P3
Install proper number of fire alarm siren to ensure proper notification for the whole complex in any emergency
35 P3
situation.
36 Provide adequate number of first aid kits and conduct the required training for the medical team. P3
37 Assure providing adequate number of safety showers based on relevant standards. P2
38 Improve and implement the existing waste management procedure. P3
39 Provide adequate housekeeping for storage tank area with adequate number of skilled contractor. P3
40 Study and review the existing drain system capacity and condition and upgrade the system accordingly P2
Study installing proper concrete base with proper slope towards proper destination waste management
41 P3
system
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 17 of 111
Document No: EGPC-AUD-APRC-05
Assess and review the location of the firefighting manual valves and assure they are in safe location, locked
29 P2
open with proper labeling.
Assure updating the existing ERP to include a detailed emergency scenarios, then train all employees on it,
30 P2
and perform regular drills with different levels.
Build a rescue team and provide them with the required training, and ensure providing them with the proper
31 P3
equipment/facilities, and check their physical fitness for work.
32 Assure providing proper head counting system for the employees. P3
Install proper number of fire alarm siren to ensure proper notification for the whole complex in any emergency
33 P3
situation.
34 Provide adequate number of first aid kits and conduct the required training for the medical team. P3
35 Assure providing adequate number of safety showers based on relevant standard. P2
36 Improve and implement the existing waste management procedure. P3
37 Provide adequate housekeeping for storage tank area with adequate number of skilled contractor. P3
38 Study and review the existing drain system capacity and condition and upgrade the system if needed P2
Study installing proper concrete base with proper slope towards proper destination waste management
39 P3
system
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 19 of 111
Document No: EGPC-AUD-APRC-05
Conduct QRA & FERA study for the company facilities and review the effect of the existing propane bullets on
28 the adjacent MEK and toluene bullets, ammonia tank, Natural gas vessel and oil tanks. Moreover, use the P2
outcomes for proper design of firefighting and fire & gas system.
29 Study and review providing proper passive fireproofing as per the required standard API 2218. P2
Study providing/ renting thermal/IR camera to conduct survey leaks as a temporary solution till the
30 P3
implementation Fire & gas detection system.
Study and review the existing condition of piping support to fix the regular vibration problem inside the
31 P2
rotating equipment.
Study replacing the single type mechanical seal with double type mechanical seal with proper plan as per API
32 P2
682.
33 Study and review installing automatic trip function for the Propane discharge pump. P3
34 Ensure that discharge pumps are working inside their characteristic curve. P2
Ensure proper selection of the pumps strainer mesh size for any new pumps as per the manufacturer
35 P3
recommendation.
Assess and review the existing discharge pumps for propane and LPG bullets and replace the old design pumps
36 P3
with new pumps as per the new standard and code.
37 Study providing CCTV and proper access control for the bullets area. P4
Conduct a survey to check the condition of the concrete structures inside the facility. Prioritize them and make
38 P2
the required repairs for the defected items.
39 Study installing double block valves for all samples and drains with plugs or caps. P3
40 Study and review lightening and earthing system and assess them against the relevant standard. P2
Conduct frequent gas testing during any hot working activities, and the testing frequency shall be
41 P2
proportionated to the associated risk.
42 Assure develop Hazard Area Classification layout and schedules for all the facility areas. P2
Assure availability of certified ATEX engineers to check the conditions of the EX-rating devices and connections
43 P3
and assess compliance with the ATEX requirements.
Assure providing detailed specific LPG or propane release scenarios to the ERP, then train all employees on it,
44 P2
and perform regular drills with different levels.
Study and review the existing FF system and assess against the worst case scenario and the required flow
45 P2
quantities and pressure needed.
Build a rescue team and provide them with the required training, and ensure providing them with the proper
46 P3
equipment/facilities, and check their physical fitness for work.
47 Assure providing proper head counting system P4
48 Install proper number of fire alarm siren to ensure proper notification for the whole complex. P3
49 Provide adequate number of first aid kits and conduct the required training for the medical team P3
50 Assure providing adequate number of safety showers based on relevant standard. P2
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 21 of 111
Document No: EGPC-AUD-APRC-05
Study replacing the single type mechanical seal with double type mechanical seal with proper plan as per API
29 P1
682
30 Study and review installing automatic trip signal for the suction pump. P2
31 Ensure that discharge pumps are working inside their characteristic curve P2
Assure creating warehouse stock philosophy considering the Min. and Max. stock philosophy for the required
32 P3
spare parts.
33 Study providing stop signal for HF pumps from the DCS P3
34 Asses the location of local start/stop button as per relevant code and standard. P2
35 Operating envelope to be identified for operating parameters in local reading sheet P3
36 Assure providing adequate training for operation staff regarding dealing with HF P3
37 Assure providing maintenance plan for the defected local devices P3
38 Assure providing adequate number of manpower that can cover all surveillance activities. P3
Conduct HAZOP study for LAB unit to check the need for Basic control system, remote Shutdown system for
39 P2
isolation of the critical HF loop in case of any emergency.
40 Assure providing alarm management study and alarm management software P3
Confirm that all changes for alarm setting priority are subjected to MOC process and to be studied by
41 P3
engineering
Conduct root cause analysis for repeated failures of PSVs internals to investigate its suitability for sour gases
42 P3
medium
43 Assure providing LO/TO at the open position for the manual valve up and down stream of PSV. P3
44 Ensure proper implementation of ITPM plan for the flare system downstream of the KOH system. P3
Assure that Inspection program shall include periodical radiographic survey for plugging due to fouling inside
45 P3
the relieving header.
Assure the compliance of the HF unit operators to the exposure time limits of the HF as per as the relevant
46 P2
code and HF MSDS.
47 Assure implementation of proper maintenance plan for all Level transmitters at HF storage tank P3
Study providing the ISO HF tank PSV with the proper connection to be connected to the flare system instead
48 P2
of the existing release to atmosphere during filling the lab unit with new HF catalyst.
49 Review the suitability for accessibility and escaping features on the HF ISO containers during filling process. P2
Assure implementation of hose management procedure and proper storage for flexible hoses with respect to
50 P3
their life time.
51 Study installing double block valves for all samples and drains with plugs or caps. P3
52 Expedite providing new HF suits compatible with the new applicable specifications P1
53 Assure Proper testing for HF PPE with proper inspection method P2
54 Assure providing PMI test for all received material P3
55 Assure including purging procedure in maintenance for HF instrumentation P3
56 Assure developing PSSR procedure with checklist and assure proper implementation. P3
Study the need for regular purging process for the instrumentation impulse lines to get rid of any precipitate
57 P3
scales as per the relevant standard.
Conduct a survey to check the condition of the concrete structures inside the facility. Prioritize them and make
58 P2
the required repairs for the defected items.
59 Assure including the inspection for steel structure and foundation inside the inspection plan of the HF unit. P3
60 Provide clear KPIs for Safety Critical Elements "SCE" inspection (Testing/ year) P3
61 Conduct QRA & FERA study for the facility. P2
62 Conduct periodic fire drill for the different release and fire scenarios inside the HF unit. P2
Expedite project for connection of new Firefighting system to the detection system to make it totally working
63 P2
on automatic mode.
64 Study and review providing proper passive fireproofing as per the required standard API 2218 P2
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 23 of 111
Document No: EGPC-AUD-APRC-05
65 Assess the existing gas detection system location and types according to gas mapping study. P2
66 Study replacing catalytic type detector with suitable reliable type for the HF unit. P2
67 Conduct regular HF gas leak survey using a permanent or rental camera/detector to detect any HF leaks. P3
68 Expedite implementation of the new drain system with the required capacity and proper slope P2
Assess and review the location of the firefighting manual valves and assure they are in safe location, locked
69 P2
open with proper labeling.
70 Study the replacement of HF catalyst (unit 1500) with licensor fixed bed safer catalyst. P2
Increase the number of drills in HF area considering all expected scenarios, and the recommendations from
71 drills to be shared with all concerned parties. Moreover, ensure that all workers are well trained on the P2
emergency response plan.
72 Assure providing adequate training for paramedic to deal with HF injuries. P3
Develop escape route layout, provide signs inside the access points, and define the routes by colour and
73 P2
arrows.
74 Provide discriminating tone for the siren signals "one for alarming and one for evacuation". P3
Study providing breathing apparatus with higher capacity to give suitable time for intervention and
75 P2
evacuation
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 24 of 111
Document No: EGPC-AUD-APRC-05
Build a rescue team and provide them with the required training, and ensure providing them with the proper
65 P3
equipment/facilities, and check their physical fitness for work.
66 Assure providing proper head counting system for the employees. P3
Install proper number of fire alarm siren to ensure proper notification for the whole complex in any emergency
67 P3
situation.
Assure providing adequate number of safety showers, first aid kits, escape breathing apparatus, based on
68 P3
relevant standards
Assure updating the existing ERP to include all the potential emergency scenarios especially H2S release,
69 conduct training for the employees on the emergency response plan, and perform regular drills considering all P2
potential scenarios and different emergency levels.
70 Assure providing adequate personnel H2S detectors for the VRU crew P3
71 Study installing permanent H2S detection system inside the VRU. P3
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 27 of 111
Document No: EGPC-AUD-APRC-05
Appendices
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 28 of 111
Document No: EGPC-AUD-APRC-05
: List of Attendees
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 29 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 30 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 31 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 32 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 33 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 34 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 35 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 36 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 37 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 38 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 39 of 111
Document No: EGPC-AUD-APRC-05
Threats
Threat 1: Internal Corrosion
Threat 3 : Overpressure
Consequences
Consequence 2: Equipment damage and loss of production due to fire & Explosion
Rev. 0
Bow Tie Analysis Report
Oct 2020
Amreya Petroleum Refining Company
Page 51 of 111
Document No: EGPC-AUD-APRC-05
Threats
Threat 1: Internal Corrosion
Threat 3: Overfilling
Rev. 0
Bow Tie Analysis Report
Oct 2020
Amreya Petroleum Refining Company
Page 55 of 111
Document No: EGPC-AUD-APRC-05
Consequences
Consequence 1: Fatalities due to fire / Explosion
Rev. 0
Bow Tie Analysis Report
Oct 2020
Amreya Petroleum Refining Company
Page 61 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Oct 2020
Amreya Petroleum Refining Company
Page 62 of 111
Document No: EGPC-AUD-APRC-05
Threats
Threat 1: Roof Corrosion
Consequences
Consequence 2: Fire / Explosion due to LOPC leads to Equipment damage and loss of production
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 73 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 74 of 111
Document No: EGPC-AUD-APRC-05
Threats
Threat 1: Internal corrosion
Threat 3: Overpressure
Threat 8: Horseplay
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 81 of 111
Document No: EGPC-AUD-APRC-05
Consequences
Consequence 2: Equipment damage and loss of production due to fire & Explosion
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 85 of 111
Document No: EGPC-AUD-APRC-05
v. HF in Alkylation unit
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 86 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 87 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 88 of 111
Document No: EGPC-AUD-APRC-05
Threats
Threat 1: Internal Corrosion Vessel
Threat 7: Overpressure
Consequences
Threats
Threat 1: Internal Corrosion
Threat 3: Overpressure
Consequences
Consequence 1: Fatalities due to Fire & Explosion
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 109 of 111
Document No: EGPC-AUD-APRC-05
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 110 of 111
Document No: EGPC-AUD-APRC-05
Consequence 2: Equipment damage and loss of production due to fire & Explosion
Rev. 0
Bow Tie Analysis Report
Dec 2020
Amreya Petroleum Refining Company
Page 111 of 111
Document No: EGPC-AUD-APRC-05
Consequences 4: Toxicity