Professional Documents
Culture Documents
Annex C - Project Risk Register Section 1
Annex C - Project Risk Register Section 1
Guildhall
Section 1 - Risk Register
Risk
Ref Category Risk Description Impact Chance Cost Time RAG Mitigation
Index
Design team and contractor to collate
Failure to discharge planning and listed
3 Planning 2 1 1 2 Green initial pack of information for discharge
building conditions
of conditions
Extent of conditions known and to be
4 Planning Planning conditions impact on budget Increase project budget 4 3 4 14 Red
reviewed and managed
Works to provide new supply are
delayed / not in accordance with the Orders for the electrical services have
10 Legislation Stats Electricity provider 2 2 2 4 Green
programme to save having to provide a been placed by CYC direct.
sub-station.
Building Control Sign Off delay due to Revisit design to address concerns of
11 Legislation 2 2 2 4 Green Continue liaison with the BC Officer
lack of resources building control
12 Adjoining Owners Impact of boat companies (City Cruises) Impact delivery/ site servicing strategy. 2 1 1 2 Green Legal agreements are in place
22 Surveys Unidentified archaeology Further evaluation required. Cost impact 2 2 2 4 Green Evaluation of site undertaken.
23 Surveys Additional surveys required Cost impact 1 1 1 1 Green Undertake outstanding surveys
Unrealistic programme submitted by
26 Programme 1 3 2 2.5 Green Market tested
contractor
Review historic flood data, and issue to
Programme delays; due to flood levels Works stop, cost and programme
27 Programme 6 5 3 24 Red Contractor. Contingency plan to be
impacting construction implications
developed.
Risk
Ref Category Risk Description Impact Chance Cost Time RAG Mitigation
Index
Undertake surveys early to determine
unknowns. Allow suitable contingency
Costs of additional surveys and
32 Design Discovering structural unknowns 5 4 3 17.5 Red for remediation.
remediation works.
Biggest concerns being the tower
underpinning and South Range
62 Adjoining Owners Rights of Light 1 4 1 2.5 Green Title Report does not identify any issues
Risk
Ref Category Risk Description Impact Chance Cost Time RAG Mitigation
Index
Delay to design programme as a result Recovery of cost / time included within
Operator changes impacting on cost /
72 Design of tenant/operator requirements 3 3 3 9 Amber the Agreements for Lease should late or
programme
(restaurant) significant changes be made
Design changes (including client Traditional contract - risk remains with
73 Financial changes/ variations / EOT & loss & Construction cost overrun 6 5 5 30 Red CYC - Adequate contingency to be
expense claims) and unforeseen items secured
Delay to programme - Wind, Temp, Contractor to provide impact through
75 Construction Weather delays 5 3 2 12.5 Amber
Rain contract mechanisms
Underpinning, piling and crack repairs Cracks may appear elsewhere. Detailed dilapidations surveys, crack
76 Design 2 5 5 10 Amber
to be considered to 3rd parties Remediation costs monitors
Additional bore hole surveys indertaken,
no foundatons / obstructions found
albeit at relatively shallow depth. (near
tower)
Proposed piling designs impacted by
Ground conditions - Borehole survey
77 Surveys this and require altering - Time & Cost 3 3 3 9 Amber Bullivants / Arup to review surveys and
depth insufficient
impact confirm they are happy with findings.