6 Piping Materials Guide
2.3. Creating All Data Sheets for Process
and Utility Valves
All valves used within a process plant must have a dedicated valve
data sheet (VDS). This document is, effectively, the passport for the
component, and it must detail the size range, pressure rating, design
temperature, materials of construction, testing and inspection proce-
dures and quote all the necessary design codes relating to the valve
‘This VDS is essential for the efficient procurement and the possible
future maintenance of the valve.
2.4. Creating a List of Piping Specials and Data
Sheets
A piping system generally comprises common components such as
pipe, fittings, and valves; however, less common piping items may be
required, such as strainers, hoses and hose couplings, steam traps, or
interlocks. This second group, called piping specials, must carry an SP
number as an identifying tag
The piping material engineer must create and maintain a list of SP
numbers that makes the “special” unique, based on type, material, size,
and rating. This means that there could be several 2in. ASME 150,
ASTM A105 body strainers with the same mesh,
As with valves, each piping special must have its own data sheet, to
guarantee speedy procurement and future maintenance.
2.5. Assembling Piping Material Requisition
with All Additional Documents
When all the piping specifications have been defined and initial
quantities identified by the Material Take-off Group, the piping material
engineer is responsible for assembling the requisition packages.
‘The Procurement Department will break the piping requirements into
several requisitions, so that inquiry requisitions can be sent out to
manufacturers or dealers that specialize in that particular group of
piping components.
+ Pipe (seamless and welded)—carbon and stainless steel.
+ Pipe (exotic)—Inconel, Monel, titanium.The Piping Material Engineer 7
+ Pipe fittings (seamless and welded)—carbon and stainless steel
* Valves gate/globe/check (small bore, 1/in. and below)—carbon and
stainless steel.
* Valves gate/globe/check (2in. and above)—carbon and stainless stecl.
* Ball valves (all sizes)—carbon and stainless steel.
* Special valves (all sizes)—non-slam-check valves, butterfly valves.
+ Stud bolting—all materials.
* Gaskets—ilat, spiral wound, ring type.
* Special piping items (SPs)—strainers, hoses, hose couplings, sight glasses,
interlocks, and the like.
To get competitive bids, inquiries will go out to several manufacturers
for each group of piping components, and they will be invited to offer
their best price to satisfy the scope of supply for the requisition. This
includes not only supplying the item but also testing, certification,
marking, packing, and if required, shipment to the site
2.6. Reviewing Offers from Vendors and Create
a Technical Bid Evaluation
Many clients have an “approved bidders list,” which is a selection of
vendors considered suitable to supply material to the company. This
bidders list is based on a track record on the client’s previous projects
and reliable recommendations.
Prospective vendors are given a date by which they must submit a
price that covers the scope of supplies laid out in the requisition. The
number of vendors invited to tender a bid varies, based on the size and
complexity of the specific requisition.
To create a competitive environment, a short list of between three and
six suitable vendors should be considered, and it is essential that these
vendors think that, at all times, they are bidding against other
competitors. Even if, sometimes, vendors drop out and it becomes a
“one-horse race” for commercial and technical reasons, all vendors must
think that they are not bidding alone.
All vendors that deliver feasible bids should be evaluated, and it is the
responsibility of the piping material engineer to bring all vendors to the
same starting line and ensure that they are all offering material that
meets the specifications and they are “technically acceptable,” sometimes
called “fit for purpose.”8 Piping Materials Guide
Some vendors will find it difficult, for commercial or technical reasons,
to meet the requirements of the requisition. These vendors are deemed
technically unacceptable and not considered further in the evaluation.
‘The piping material engineer, during this evaluation, creates a bid
tabulation spreadsheet to illustrate and technically evaluate all vendors
invited to submit a bid for the requisition.
The tabulation lists the complete technical requirements for each item
on the requisition and evaluates each vendor to determine if t is technically
acceptable.
Technical requirements include not only the materials of construction
and design codes but also testing, certification, and painting. Non-
technical areas also are covered by the piping material engineer, such as
marking and packing. The delivery, required on site (ROS) date, is
supplied by the Material Control Group as part of the final commercial
negotiations.
The Procurement Department is responsible for all commercial and
logistical aspects of the requisition, and the Project Services Group
determines the ROS date and the delivery location. It is pointless to
award an order to a manufacturer that is technically acceptable and
commercially the cheapest if its delivery dates do not meet the
construction schedule.
When this technical bid evaluation (TBE) or technical bid analysis
(TBA) is complete, with all technically acceptable vendors identified,
then it is turned over to the Procurement Department, which enters into
negotiations with those vendors that can satisfy the project’s technical
and logistical requirements.
After negotiations, a vendoris selected that is both technically acceptable
and comes up with the most competitive commercial/logistical offer. The
successful vendor is not necessarily the cheapest but the one that
Procurement feels most confident with in all areas, What initially looks to
be the cheapest might, at the end of the day, prove more expensive.
2.7. After Placement of a Purchase Order,
Reviewing and Approving Documentation
Related to All Piping Components
‘The importance of vendor documentation after placement of an order
must not be underestimated. It is the vendor’s responsibility to supply
support documentation and drawings to back up the material it is
supplying. This documentation includes an inspection and testing plan,The Piping Material Engineer 9
general arrangement drawings, material certification, test certificates,
and production schedules.
All this documentation must be reviewed by the piping material
engineer, approved and signed off, before final payment can be released
to the vendor for the supply of the material.
2.8. Vendor Visits
The piping material engineer may be required to visit the vendor's
premises to witness the testing of piping components or attend clarification
meetings,
Certain piping items are more complex than others, either because of
their chemical composition and supplementary requirements or their
design, size, or pressure rating. In these cases, the relevant purchase
order requires a greater deal of attention from the piping material
engineer to ensure that no complications result in incorrect materials
being supplied or an unnecessary production delay
To avoid this, the following additional activities should be seriously
considered:
A bid clarification meeting to guarantee that the prospective vendor fully
understands the requisition and associated specification.
* After the order has been placed, a preinspection meeting to discuss
production, inspection, and quality control,
* Placing the requisition engineer in the vendor’s facilities during critical
manufacturing phases of the job to ensure that the specifications are
understood.
* Placing an inspector in the vendor's facilities, who is responsible for the
inspection and testing of the order and coordinates with the piping
material engineer in the home office to guarantee that the specifications
are understood and being applied.
The first two are low-cost activities and should be a formality for most
purchase orders, the last two are more-expensive activities and should be
considered based on the complexity of the order or the need for long lead
items.
No two requisitions are the same, and a relatively simple order with a
new and untried vendor may require more consideration than a complex
order with a vendor that is a known quantity. The decision to make
vendor visits also relates to the size of the inspection budget, which might