Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 102

HARGA SATUAN UPAH DAN BAHAN

MATARAM TH. 2013

NO. JENIS UPAH/BAHAN HARGA SATUAN SATUAN


1 2 3 4
A HARGA SATUAN UPAH
1 Pekerja 44,000.00 Hari
2 Buruh Terampil 51,300.00 Hari
3 Mandor 55,000.00 Hari
4 Tukang batu 57,000.00 Hari
5 Kepala tukang batu 60,000.00 Hari
6 Tukang kayu 57,000.00 Hari
7 Kepala tukang kayu 60,000.00 Hari
8 Tukang besi 57,000.00 Hari
9 Kepala tukang besi 60,000.00 Hari
10 Tukang cat 57,000.00 Hari
11 Kepala tukang cat 60,000.00 Hari
12 Tukang las 57,000.00 Hari
13 Kepala tukang las 60,000.00 Hari
14 Tukang gypsum 57,000.00 Hari
15 Kepala tukang gypsum 60,000.00 Hari
16 Tukang alumunium 57,000.00 Hari
17 Kepala tukang alumunium 60,000.00 Hari
18 Tukang pipa 57,000.00 Hari
19 Kepala tukang pipa 60,000.00 Hari
20 Tukang listrik 57,000.00 Hari
21 Kepala tukang listrik 60,000.00 Hari
-
B. HARGA SATUAN BAHAN. DAN ALAT -
B.1 Bahan Pasangan -
1 Batu kali belah 90,000.00 m³
2 Tanah Urug 40,500.00 m³
3 Pasir pasang 80,000.00 m³
4 Pasir urug 81,000.00 m³
5 Pasir beton 90,000.00 m³
6 Pasir cor 64.29 kg
7 Sirtu diquarry 90,000.00 m³
8 Semen (Portland semen) = 50 kg 50,000.00 kg
9 Semen 1,000.00 kg
10 Semen warna 9,000.00 kg
11 Semen putih 9,000.00 kg
12 Bata merah 400.00 bh
13 Krikil alam 2-3cm - 1 m³ 150,000.00 m³
14 Krikil alam 2-3cm 129.63 kg
15 Batu pecah 5-7 cm 135,463.50 m³
16 Batu pecah 3-5 cm 207,450.00 m³
17 Batu pecah 2-3 cm 219,600.00 m³
-
B.2 Bahan Lantai -
### Batu tempel pola sisir 121,500.00 m²
2 Keramik 20 x 20 cm (motif biasa) 17,000.00 m²
3 Keramik dinding 20 x 25 cm (motif biasa) 38,250.00 m²
4 Keramik 30 x 30 cm (putih klas menengah) 34,650.00 m²
5 Keramik 40 x 40 cm (putih klas biasa) 40,000.00 m²
6 Keramik 40 x 40 cm (putih klas tinggi) 59,400.00 m²
7 Keramik 10 x 40 cm (motif) 3,650.40 bh
8 Batu paras 112,500.00 m²
-
B.3 Bahan Kayu -
1 Kayu klas I 6,750,000.00 m³
2 Papan kayu kls I 6,750,000.00 m³
3 Kayu klas II 3,000,000.00 m³
4 Papan kayu kls II 3,000,000.00 m³
5 Papan kayu kls III 2,000,000.00 m³
6 Kayu kelas III 2,000,000.00 m³
7 Kayu dolken ø 10cm - 4 m 17,000.00 btg
8 Kayu usuk/reng 2,000,000.00 m³
9 Kayu terentang 1,800,000.00 m³
-
B.4 Bahan Langit-langit -
1 Triplek 9 mm 90,000.00 lbr
2 Triplek aluminium 93,600.00 lbr
3 Calsiboard 120x240x3,5 mm 60,300.00 lbr
4 Kalsiboard 4,5 mm 60,300.00 lbr
5 Calsiboard 120x240x6 mm 66,150.00 lbr
6 Plester kalsiboard 2,340.00 m¹
7 Plasting claster 2,340.00 m¹
8 Tepung gypsum 2,340.00 kg
9 Gypsum board 74,430.00 lbr
10 List plafond gypsum C 17,865.00 m¹
11 List plafond gypsum C7 14,895.00 m¹
12 List plafond profil 1x4 cm 3,150.00 m¹
13 Playwood 3 mm 90,000.00 lbr
14 Playwood 4 mm 112,500.00 lbr
15 Playwood 6 mm 115,000.00 lbr
16 Teakwood 3 mm 95,400.00 lbr
17 Teakwood 4 mm 112,500.00 lbr
18 Formika 90,000.00 lbr
19 Asbes Gelombang Kecil 1 x 1,8 m 28,601.10 lbr
20 Asbes Gelombang Besar 1 x 2,5 m 94,500.00 lbr
21 Asbes Bubungan Glmb. Kecil 24,462.00 psng
22 Asbes Bubungan Glmb. Besar 51,930.00 lbr
-
B.5 Bahan Atap -
1 Genteng press kodok dicat 1,530.00 bh
2 Bubungan 3,150.00 bh
3 Genteng beton 4,500.00 bh
4 Bubungan Genteng beton 5,850.00 bh
5 Seng plat Bjls 18 27,000.00 lbr
6 Seng plat Bjls 20 46,800.00 lbr
7 Seng plat Bjls 25 67,500.00 lbr
8 Seng plat Bjls 30 76,500.00 lbr
9 Seng gelombang Bjls 20 40,500.00 lbr
10 Seng gelombang Bjls 25 54,000.00 lbr
11 Seng gelombang Bjls 30 64,800.00 lbr
-
B.6 Bahan Kaca -
1 Kaca bening 3 mm 67,500.00 m²
2 Kaca bening 5 mm 90,000.00 m²
3 Kaca ryben 3 mm 76,500.00 m²
4 Kaca ryben 5 mm 99,000.00 m²
5 Kaca es 3 mm/kaca buram 85,500.00 m²
6 Kaca es 5 mm/kaca buram 108,000.00 m²
7 Sealant 10,800.00 tube
8 Profil Kaca 63,000.00 m
9 Jendela nako + kaca 5 mm 135,000.00 m2
-
B.7 Bahan Alumunium -
1 Aluminium 4/8 85,500.00 m¹
2 Grendel aluminium 18,900.00 bh
3 List holow aluminium 1 x 3 7,560.00 m¹
4 Aluminium strip 22,680.00 m¹
5 Frime pintu aluminium 37,800.00 m¹
6 Metal furing 0.4x4 m ASTM - C 645 10,800.00 m¹
7 C Channel 0.8x4 m ASTM - C 645 6,750.00 m¹
8 Theaded rod 4 mm x 1000 mm 4,050.00 bh
9 Suspension braket 2,250.00 bh
10 Soffit clear 2,250.00 bh
11 Saddle clip 1,800.00 bh
12 Paku peluru 1,800.00 bh
13 Angle section 3m 4,950.00 bh
14 Screw 22,500.00 kg
15 Join compound ASTM - E 136 4,950.00 bh
16 Join tape 75 m 14,850.00 bh
17 Sand paper 2,475.00 bh
18 Paku 675.00 bh
19 Sunscreen Alluminium 90,000.00 m2
20 Rolling door Alluminium 135,000.00 m2
21 Profil Alluminium 22,500.00 m'
22 Pintu Alluminium 225,000.00 m
-
B.8 Bahan Besi & Pengunci -
1 Besi beton ulir 9,000.00 kg
2 Besi beton polos 9,000.00 kg
3 Besi strip 13,500.00 kg
4 Kawat beton 10,000.00 kg
5 Paku usuk/reng 15,000.00 kg
6 Paku 1-3 cm 15,000.00 kg
7 Paku 4-6 cm 15,000.00 kg
8 Paku khusus calsiboard 22,500.00 kg
9 Paku asbes 20,250.00 kg
10 Paku seng 18,000.00 kg
11 Paku piles 360.00 bh
12 Paku sekrup 9,900.00 dos
13 Begel plat 27,810.00 bh
14 Angker kuda - kuda ø 16 mm p = 40 cm 6,750.00 bh
15 Angker kuda - kuda ø 12 mm p = 30 cm 4,950.00 bh
16 Angker kusen pintu dan jendela 1,350.00 bh
17 Grendel besar klas biasa 6,930.00 bh
18 Grendel besar klas menengah 15,750.00 bh
19 Grendel besar klas tinggi 34,650.00 bh
20 Kait angin klas menengah 10,125.00 bh
21 Door Closer 135,000.00 bh
22 Expagnolett 49,500.00 bh
23 Engsel Jendela klas biasa 11,250.00 Bh
24 Engsel jendela klas tinggi 16,200.00 bh
25 Engsel pintu klas biasa 13,500.00 bh
26 Engsel pintu klas tinggi 27,270.00 bh
27 Kunci pintu 2 slaag klas menengah 100,000.00 bh
28 Kunci pintu 2 slaag klas tinggi 257,985.00 bh
29 Kunci tanam cylinder 225,000.00 bh
30 Kawat duri 16,200.00 kg
31 Besi profil siku ( EX KS ) 627,750.00 kg
32 Besi profil canal (EX KS) 17,460.00 kg
33 Besi Baja IWF 7,290.00 kg
34 Besi Siku 36,450.00 kg
35 Besi plat 16,200.00 kg
36 Kawat las 22,500.00 kg
37 Pintu besi gulung 112,500.00 m2
38 Pintu lipat 112,500.00 m2
39 Kawat Nyamuk Besi 18,000.00 m2
40 Kawat Nyamuk Plastik 13,500.00 m2
-
B.9 Bahan - bahan Listrik -
### Lampu pijar 4,950.00 bh
### Lampu down light 18 watt 135,000.00 bh
### Lampu SL 8 watt 35,000.00 bh
### Lampu SL 18 watt 50,000.00 bh
### Lampu baret 40 watt 202,500.00 bh
### Lampu TL 2x40 watt 180,000.00 bh
### Lampu TL bambu 40 watt 135,000.00 bh
### Saklar Tunggal 11,250.00 bh
### Saklar Ganda 11,250.00 bh
### Saklar tanam 90,000.00 bh
### Titik lampu baru 100,000.00 ttk
### Revisi titik lampu 90,000.00 ttk
### Revisi titik stop kontak 90,000.00 ttk
### Fitting lampu 6,750.00 bh
-
B.10 Bahan Sanitair -
1 Floor drain (Avour)/saringan air 27,000.00 bh
2 Kran air biasa GI ø 1/2" klas menengah 33,750.00 bh
3 Kran washtafel GI ø 1/2" 67,500.00 bh
4 Pipa PVC ø 1/2" 32,400.00 m¹
5 Pipa PVC ø 1 1/2" 36,000.00 m¹
6 Pipa PVC ø 2" 40,500.00 m¹
7 Pipa PVC ø 3" klas tinggi 61,200.00 m¹
8 Pipa PVC ø 4" 76,000.00 m¹
9 Pipa GI ø 3/4" 40,500.00 m¹
10 Pipa GI ø 1" 31,500.00 m¹
11 Closed jongkok porselint klas menengah 250,000.00 unit
12 Closed duduk monoblok klas menengah 1,350,000.00 unit
13 Saringan Air besi 53,100.00 bh
14 Saringan Air plastik 14,400.00 bh
15 Urinoir type muslim 478,800.00 unit
16 Asesories urinoir type muslim 392,400.00 set
17 Wastafeel +Acecories, kran + Miralset 922,050.00 unit
18 Bak stainless steel 2 lobang 405,000.00 unit
19 Water drain + accesoris 44,640.00 bh
20 Kran bebekan ø 1/2" 112,500.00 bh
21 Jetsowercloset ø 1/2" 121,500.00 bh
22 Handsower ø 1/2" 157,500.00 bh
-
B.11 Bahan Finishing -
### Cat tembok klas menengah 22,500.00 kg
### Cat tembok klas tinggi 67,500.00 kg
### Cat genteng 40,500.00 kg
### Cat kayu klas menengah 38,700.00 kg
### Cat besi klas tinggi 44,640.00 kg
### Meny kayu 20,700.00 kg
### Meny besi 23,400.00 kg
### Minyak cat klas menengah 14,850.00 ltr
### Amplas 3,150.00 lbr
### Kuas cat 7,650.00 bh
### Roll cat 13,500.00 bh
### Plamir tembok 8,100.00 kg
### Plamir Kayu 22,815.00 kg
### Residu/teer 11,250.00 ltr
15 Politur 31,230.00 ltr
16 Kape 5,400.00 bh
17 Vernis 32,940.00 ltr
18 Alkali (anti jamur) 41,580.00 kg
19 Tinner serbaguna 23,850.00 ltr
20 Wood filer 34,020.00 ltr
21 Seanding sealer 34,020.00 ltr
22 Wood steam 35,820.00 ltr
23 Clear glos 37,800.00 ltr
24 Lem kayu 16,920.00 kg
25 Lem silent 189,000.00 tbg
26 Seaflex 31,500.00 Kg
27 Sikat baja 13,500.00 bh
-
B.12 Bahan Lain - lain -
### Listrik 495.00 kw
### Air kerja 22.50 ltr
### Solar 4,050.00 ltr
### Minyak begesting 3,150.00 ltr
### Minyak tanah 10,800.00 ltr
### Oli mesin 22,050.00 ltr
### Mesin las (sewa) 9,000.00 jam
### Mesin bor (sewa) 14,175.00 jam
### Pompa air (sewa) 9,900.00 jam
### Sewa alat bantu granit 47,250.00 hari
### Alat bantu 31,500.00 hari
### Mesin potong plat ( sewa ) 13,500.00 jam
### Mesin Gergaji (sewa) 13,500.00 jam
### Mata Gergaji 47,250.00 bh
### Mata Bor 8,100.00 jam
### Dump Truk 3 - 4 M3 90,000.00 jam
### Water Tanker 3000 - 4500 L 45,000.00 jam
### Acytilyin 180,000.00 btl
### Oksigen 67,500.00 btl
### Sikat baja 10,800.00 bh
### Sewa kompresor 103,500.00 hari
### Bambu (dia.12,5 cm, P - 6 m) 22,500.00 btg
### Bambu (dia.10 cm, P- 6 m) 19,800.00 btg
### Bambu (dia.7 cm, P- 6 m) 19,800.00 btg
### Bedek kulitan 30,600.00 m²
### Bedek biasa 30,600.00 m²
### Bedek pagar 22,500.00 m²
### Tali ijuk 15,300.00 kg
DAFTAR ANALISA HARGA SATUAN UPAH DAN BAHAN
HARGA SATUAN JUMLAH HARGA
KODE ANALISA KOEFISIEN SAT. URAIAN
(Rp.) (Rp.)

A. PEKERJAAN PERSIAPAN
1 m³ Pagar Sementara dari seng gelombang tinggi 2 meter
RSNI T.12.2002.2
BAHAN
1.2500 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 21,250.00
2.5000 kg Semen Rp 1,000.00 Rp 2,500.00
1.2000 lbr Seng gelombang Bjls 25 Rp 54,000.00 Rp 64,800.00
0.0050 m³ Pasir beton Rp 90,000.00 Rp 450.00
0.0090 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 1,350.00
0.0600 kg Paku 4-6 cm Rp 15,000.00 Rp 900.00
0.0720 m³ Kayu usuk/reng Rp 2,000,000.00 Rp 144,000.00
0.4000 kg Meny besi Rp 23,400.00 Rp 9,360.00
Jumlah (I) Rp 244,610.00
TENAGA
0.2000 Hari Tukang kayu Rp 57,000.00 Rp 11,400.00
0.0200 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,200.00
0.4000 Hari Pekerja Rp 44,000.00 Rp 17,600.00
0.0200 Hari Mandor Rp 55,000.00 Rp 1,100.00
Jumlah (II) Rp 31,300.00
Jumlah (I) + (II) Rp 275,910.00
Over head / Keuntungan 10 % Rp 27,591.00
Rp 303,501.00

1 m³ Bongkaran beton bertulang


RSNI T.12.2002.13
TENAGA
6.6670 Hari Pekerja Rp 44,000.00 Rp 293,348.00
0.3330 Hari Mandor Rp 55,000.00 Rp 18,315.00
Jumlah (II) Rp 311,663.00
Jumlah (I) + (II) Rp 311,663.00
Over head / Keuntungan 10 % Rp 31,166.30
Rp 342,829.30

1 m³ Bongkaran dinding tembok bata merah


RSNI T.12.2002.14
TENAGA
6.6670 Hari Pekerja Rp 44,000.00 Rp 293,348.00
0.3330 Hari Mandor Rp 55,000.00 Rp 18,315.00
Jumlah (II) Rp 311,663.00
Jumlah (I) + (II) Rp 311,663.00
Over head / Keuntungan 10 % Rp 31,166.30
Rp 342,829.30

B. PEKERJAAN TANAH
1 M³ GALIAN TANAH BIASA SEDALAM 1M
SNI 2835.2008.1
0.7500 Hari Pekerja Rp 44,000.00 Rp 33,000.00
0.0250 Hari Mandor Rp 55,000.00 Rp 1,375.00
Jumlah Rp 34,375.00
Over head / Keuntungan 10 % Rp 3,437.50
Rp 37,812.50

1 M³ GALIAN TANAH BIASA SEDALAM 2M


SNI 2835.2008.2
0.9000 Hari Pekerja Rp 44,000.00 Rp 39,600.00
0.0450 Hari Mandor Rp 55,000.00 Rp 2,475.00
Jumlah Rp 42,075.00
Over head / Keuntungan 10 % Rp 4,207.50
Rp 46,282.50

1 M³ GALIAN TANAH BIASA SEDALAM 3M


SNI 2835.2008.3
1.0500 Hari Pekerja Rp 44,000.00 Rp 46,200.00
0.0670 Hari Mandor Rp 55,000.00 Rp 3,685.00
Jumlah Rp 49,885.00
Over head / Keuntungan 10 % Rp 4,988.50
Rp 54,873.50

1 M³ GALIAN TANAH KERAS SEDALAM 1 M


SNI 2835.2008.4
1.0000 Hari Pekerja Rp 44,000.00 Rp 44,000.00
0.0320 Hari Mandor Rp 55,000.00 Rp 1,760.00
Jumlah Rp 45,760.00
Over head / Keuntungan 10 % Rp 4,576.00
Rp 50,336.00
1 M³ GALIAN TANAH CADAS SEDALAM 1M
SNI 2835.2008.5
1.5000 Hari Pekerja Rp 44,000.00 Rp 66,000.00
0.0600 Hari Mandor Rp 55,000.00 Rp 3,300.00
Jumlah Rp 69,300.00
Over head / Keuntungan 10 % Rp 6,930.00
Rp 76,230.00

1 M³ GALIAN TANAH LUMPUR SEDALAM 1M


SNI 2835.2008.6
1.2000 Hari Pekerja Rp 44,000.00 Rp 52,800.00
0.0450 Hari Mandor Rp 55,000.00 Rp 2,475.00
Jumlah Rp 55,275.00
Over head / Keuntungan 10 % Rp 5,527.50
Rp 60,802.50

1 M² STRIPPING TEBING SETINGGI 1M


SNI 2835.2008.7
0.0500 Hari Pekerja Rp 44,000.00 Rp 2,200.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah Rp 2,475.00
Over head / Keuntungan 10 % Rp 247.50
Rp 2,722.50

1 M³ MEMBUANG TANAH SEJAUH 15 METER


SNI 2835.2008.8
0.3300 Hari Pekerja Rp 44,000.00 Rp 14,520.00
0.0100 Hari Mandor Rp 55,000.00 Rp 550.00
Jumlah Rp 15,070.00
Over head / Keuntungan 10 % Rp 1,507.00
Rp 16,577.00

1 M³ MENGURUG KEMBALI
SNI 2835.2008.9
Mengurug kembali 1m³ dihitung 1/3 kali dari indek pekerjaan galian

1 M³ PEMADATAN TANAH (Per 20 cm)


SNI 2835.2008.10
0.5000 Hari Pekerja Rp 44,000.00 Rp 22,000.00
0.0500 Hari Mandor Rp 55,000.00 Rp 2,750.00
Jumlah Rp 24,750.00
Over head / Keuntungan 10 % Rp 2,475.00
Rp 27,225.00

1 M³ URUGAN PASIR
SNI 2835.2008.11
1.2000 m³ Pasir urug Rp 81,000.00 Rp 97,200.00
0.3000 Hari Pekerja Rp 44,000.00 Rp 13,200.00
0.0100 Hari Mandor Rp 55,000.00 Rp 550.00
Jumlah Rp 110,950.00
Over head / Keuntungan 10 % Rp 11,095.00
Rp 122,045.00

1 M³ URUGAN TANAH
SNI 2835.2008.11a
1.2000 m³ Tanah Urug Rp 40,500.00 Rp 48,600.00
0.3000 Hari Pekerja Rp 44,000.00 Rp 13,200.00
0.0100 Hari Mandor Rp 55,000.00 Rp 550.00
Jumlah Rp 62,350.00
Over head / Keuntungan 10 % Rp 6,235.00
Rp 68,585.00

1 M³ URUGAN SIRTU
SNI 2835.2008.15
1.2000 m³ Sirtu diquarry Rp 90,000.00 Rp 108,000.00
0.2500 Hari Pekerja Rp 44,000.00 Rp 11,000.00
0.0250 Hari Mandor Rp 55,000.00 Rp 1,375.00
Jumlah Rp 120,375.00
Over head / Keuntungan 10 % Rp 12,037.50
Rp 132,412.50

C. PEKERJAAN PONDASI BATU BELAH


1 M³ PAS. BT. KALI 1Pc : 3Psr
SNI 2836.2008.1
BAHAN
1.2000 m³ Batu kali belah Rp 90,000.00 Rp 108,000.00
202.0000 kg Semen Rp 1,000.00 Rp 202,000.00
0.4850 m³ Pasir pasang Rp 80,000.00 Rp 38,800.00
Jumlah (I) Rp 348,800.00
TENAGA
0.6000 Hari Tukang batu Rp 57,000.00 Rp 34,200.00
0.0600 Hari Kepala tukang batu Rp 60,000.00 Rp 3,600.00
1.5000 Hari Pekerja Rp 44,000.00 Rp 66,000.00
0.0750 Hari Mandor Rp 55,000.00 Rp 4,125.00
Jumlah (II) Rp 107,925.00
Jumlah (I) + (II) Rp 456,725.00
Over head / Keuntungan 10 % Rp 45,672.50
Rp 502,397.50

1 M³ PAS. BT. KALI 1Pc : 4Psr


SNI 2836.2008.2
BAHAN
1.2000 m³ Batu kali belah Rp 90,000.00 Rp 108,000.00
163.0000 kg Semen Rp 1,000.00 Rp 163,000.00
0.4850 m³ Pasir pasang Rp 80,000.00 Rp 38,800.00
Jumlah (I) Rp 309,800.00
TENAGA
0.7500 Hari Tukang batu Rp 57,000.00 Rp 42,750.00
0.0750 Hari Kepala tukang batu Rp 60,000.00 Rp 4,500.00
1.5000 Hari Pekerja Rp 44,000.00 Rp 66,000.00
0.0750 Hari Mandor Rp 55,000.00 Rp 4,125.00
Jumlah (II) Rp 117,375.00
Jumlah (I) + (II) Rp 427,175.00
Over head / Keuntungan 10 % Rp 42,717.50
Rp 469,892.50

1 M³ PAS. BT. KALI 1Pc : 5Psr


SNI 2836.2008.3
BAHAN
1.2000 m³ Batu kali belah Rp 90,000.00 Rp 108,000.00
136.0000 kg Semen Rp 1,000.00 Rp 136,000.00
0.5440 m³ Pasir pasang Rp 80,000.00 Rp 43,520.00
Jumlah (I) Rp 287,520.00
TENAGA
0.7500 Hari Tukang batu Rp 57,000.00 Rp 42,750.00
0.0750 Hari Kepala tukang batu Rp 60,000.00 Rp 4,500.00
1.5000 Hari Pekerja Rp 44,000.00 Rp 66,000.00
0.0750 Hari Mandor Rp 55,000.00 Rp 4,125.00
Jumlah (II) Rp 117,375.00
Jumlah (I) + (II) Rp 404,895.00
Over head / Keuntungan 10 % Rp 40,489.50
Rp 445,384.50

1 M³ PAS. BATU KOSONG (Aanstamping)


SNI 2836.2008.9
BAHAN
1.2000 m³ Batu kali belah Rp 90,000.00 Rp 108,000.00
0.4320 m³ Pasir urug Rp 81,000.00 Rp 34,992.00
Jumlah (I) Rp 142,992.00
TENAGA
0.3900 Hari Tukang batu Rp 57,000.00 Rp 22,230.00
0.0390 Hari Kepala tukang batu Rp 60,000.00 Rp 2,340.00
0.7800 Hari Pekerja Rp 44,000.00 Rp 34,320.00
0.0390 Hari Mandor Rp 55,000.00 Rp 2,145.00
Jumlah (II) Rp 61,035.00
Jumlah (I) + (II) Rp 204,027.00
Over head / Keuntungan 10 % Rp 20,402.70
Rp 224,429.70

1 M³ Memasang Pondasi Siklop, 60% beton campuran 1PC : 2PB : 3 KR dan 40% batu belah
SNI 2836.2008.10
BAHAN
0.4800 m³ Batu kali belah Rp 90,000.00 Rp 43,200.00
194.0000 kg Semen Rp 1,000.00 Rp 194,000.00
0.3120 m³ Pasir beton Rp 90,000.00 Rp 28,080.00
0.4680 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 70,200.00
126.0000 kg Besi beton polos Rp 9,000.00 Rp 1,134,000.00
1.8000 kg Kawat beton Rp 10,000.00 Rp 18,000.00
Jumlah (I) Rp 1,487,480.00
TENAGA
0.8500 Hari Tukang batu Rp 57,000.00 Rp 48,450.00
0.0850 Hari Kepala tukang batu Rp 60,000.00 Rp 5,100.00
3.4000 Hari Pekerja Rp 44,000.00 Rp 149,600.00
0.1700 Hari Mandor Rp 55,000.00 Rp 9,350.00
Jumlah (II) Rp 212,500.00
Jumlah (I) + (II) Rp 1,699,980.00
Over head / Keuntungan 10 % Rp 169,998.00
Rp 1,869,978.00
D. PEKERJAAN BETON
1 M³ MEMBUAT BETON MUTU, FC = 7,4 MPA (K.100), SLUM (12±2) cm, wc = 0,87
SNI 7394.2008.1
BAHAN
247.0000 kg Semen Rp 1,000.00 Rp 247,000.00
869.0000 kg Pasir cor Rp 64.29 Rp 55,864.29
999.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 129,500.00
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 437,201.79
TENAGA
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
0.0280 Hari Kepala tukang batu Rp 60,000.00 Rp 1,680.00
1.6500 Hari Pekerja Rp 44,000.00 Rp 72,600.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 94,520.00
Jumlah (I) + (II) Rp 531,721.79
Over head / Keuntungan 10 % Rp 53,172.18
Rp 584,893.96

1 M³ MEMBUAT BETON MUTU, FC = 9,8 MPA (K.125), SLUM (12±2) cm, wc = 0,78
SNI 7394.2008.2
BAHAN
276.0000 kg Semen Rp 1,000.00 Rp 276,000.00
828.0000 kg Pasir cor Rp 64.29 Rp 53,228.57
1,012.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 131,185.19
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 465,251.26
TENAGA
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
0.0280 Hari Kepala tukang batu Rp 60,000.00 Rp 1,680.00
1.6500 Hari Pekerja Rp 44,000.00 Rp 72,600.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 94,520.00
Jumlah (I) + (II) Rp 559,771.26
Over head / Keuntungan 10 % Rp 55,977.13
Rp 615,748.38

Membuat 1 m3 beton mutu f’c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
SNI 7394.2008.3
BAHAN
299.0000 kg Semen Rp 1,000.00 Rp 299,000.00
799.0000 kg Pasir cor Rp 64.29 Rp 51,364.29
1,017.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 131,833.33
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 487,035.12
TENAGA
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
0.0280 Hari Kepala tukang batu Rp 60,000.00 Rp 1,680.00
1.6500 Hari Pekerja Rp 44,000.00 Rp 72,600.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 94,520.00
Jumlah (I) + (II) Rp 581,555.12
Over head / Keuntungan 10 % Rp 58,155.51
Rp 639,710.63

Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c=0,87
SNI 7394.2008.4
BAHAN
230.0000 kg Semen Rp 1,000.00 Rp 230,000.00
893.0000 kg Pasir cor Rp 64.29 Rp 57,407.14
1,027.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 133,129.63
200.0000 ltr Air kerja Rp 22.50 Rp 4,500.00
Jumlah (I) Rp 425,036.77
TENAGA
0.2000 Hari Tukang batu Rp 57,000.00 Rp 11,400.00
0.0200 Hari Kepala tukang batu Rp 60,000.00 Rp 1,200.00
1.2000 Hari Pekerja Rp 44,000.00 Rp 52,800.00
0.0600 Hari Mandor Rp 55,000.00 Rp 3,300.00
Jumlah (II) Rp 68,700.00
Jumlah (I) + (II) Rp 493,736.77
Over head / Keuntungan 10 % Rp 49,373.68
Rp 543,110.45
1 M³ MEMBUAT LANTAI BETON MUTU, FC = 14,5 MPA (K.175), SLUM (12±2) cm, wc = 0,66
SNI 7394.2008.5
BAHAN
326.0000 kg Semen Rp 1,000.00 Rp 326,000.00
760.0000 kg Pasir cor Rp 64.29 Rp 48,857.14
1,029.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 133,388.89
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 513,083.53
TENAGA
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
0.0280 Hari Kepala tukang batu Rp 60,000.00 Rp 1,680.00
1.6500 Hari Pekerja Rp 44,000.00 Rp 72,600.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 94,520.00
Jumlah (I) + (II) Rp 607,603.53
Over head / Keuntungan 10 % Rp 60,760.35
Rp 668,363.88

1 M³ MEMBUAT LANTAI BETON MUTU, FC = 16,9 MPA (K.200), SLUM (12±2) cm, wc = 0,61
SNI 7394.2008.6
BAHAN
352.0000 kg Semen Rp 1,000.00 Rp 352,000.00
731.0000 kg Pasir cor Rp 64.29 Rp 46,992.86
1,031.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 133,648.15
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 537,478.51
TENAGA
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
0.0280 Hari Kepala tukang batu Rp 60,000.00 Rp 1,680.00
1.6500 Hari Pekerja Rp 44,000.00 Rp 72,600.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 94,520.00
Jumlah (I) + (II) Rp 631,998.51
Over head / Keuntungan 10 % Rp 63,199.85
Rp 695,198.36

1 M³ MEMBUAT LANTAI BETON MUTU, FC = 19,3 MPA (K.225), SLUM (12±2) cm, wc = 0,58
SNI 7394.2008.7
BAHAN
371.0000 kg Semen Rp 1,000.00 Rp 371,000.00
698.0000 kg Pasir cor Rp 64.29 Rp 44,871.43
1,047.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 135,722.22
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 556,431.15
TENAGA
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
0.0280 Hari Kepala tukang batu Rp 60,000.00 Rp 1,680.00
1.6500 Hari Pekerja Rp 44,000.00 Rp 72,600.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 94,520.00
Jumlah (I) + (II) Rp 650,951.15
Over head / Keuntungan 10 % Rp 65,095.12
Rp 716,046.27

1 M³ MEMBUAT LANTAI BETON MUTU, FC = 21,7 MPA (K.250), SLUM (12±2) cm, wc = 0,56
SNI 7394.2008.8
BAHAN
384.0000 kg Semen Rp 1,000.00 Rp 384,000.00
692.0000 kg Pasir cor Rp 64.29 Rp 44,485.71
1,039.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 134,685.19
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 568,008.40
TENAGA
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
0.0280 Hari Kepala tukang batu Rp 60,000.00 Rp 1,680.00
1.6500 Hari Pekerja Rp 44,000.00 Rp 72,600.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 94,520.00
Jumlah (I) + (II) Rp 662,528.40
Over head / Keuntungan 10 % Rp 66,252.84
Rp 728,781.24

1 M³ MEMBUAT LANTAI BETON MUTU, FC = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
SNI 7394.2008.9
BAHAN
406.0000 kg Semen Rp 1,000.00 Rp 406,000.00
684.0000 kg Pasir cor Rp 64.29 Rp 43,971.43
1,026.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 133,000.00
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 587,808.93
TENAGA
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
0.0280 Hari Kepala tukang batu Rp 60,000.00 Rp 1,680.00
1.6500 Hari Pekerja Rp 44,000.00 Rp 72,600.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 94,520.00
Jumlah (I) + (II) Rp 682,328.93
Over head / Keuntungan 10 % Rp 68,232.89
Rp 750,561.82

1 M³ MEMBUAT LANTAI BETON MUTU, FC = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
SNI 7394.2008.10
BAHAN
413.0000 kg Semen Rp 1,000.00 Rp 413,000.00
681.0000 m³ Pasir beton Rp 90,000.00 Rp 61,290,000.00
1,021.0000 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 153,150,000.00
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 214,857,837.50
TENAGA
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
0.0280 Hari Kepala tukang batu Rp 60,000.00 Rp 1,680.00
1.6500 Hari Pekerja Rp 44,000.00 Rp 72,600.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 94,520.00
Jumlah (I) + (II) Rp 214,952,357.50
Over head / Keuntungan 10 % Rp 21,495,235.75
Rp 236,447,593.25

1 M³ MEMBUAT LANTAI BETON MUTU, FC = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
SNI 7394.2008.11
BAHAN
439.0000 kg Semen Rp 1,000.00 Rp 439,000.00
670.0000 kg Pasir cor Rp 64.29 Rp 43,071.43
1,006.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 130,407.41
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 617,316.34
TENAGA
0.3500 Hari Tukang batu Rp 57,000.00 Rp 19,950.00
0.0350 Hari Kepala tukang batu Rp 60,000.00 Rp 2,100.00
2.1000 Hari Pekerja Rp 44,000.00 Rp 92,400.00
0.1050 Hari Mandor Rp 55,000.00 Rp 5,775.00
Jumlah (II) Rp 120,225.00
Jumlah (I) + (II) Rp 737,541.34
Over head / Keuntungan 10 % Rp 73,754.13
Rp 811,295.47

1 M³ MEMBUAT LANTAI BETON MUTU, FC = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
SNI 7394.2008.12
BAHAN
448.0000 kg Semen Rp 1,000.00 Rp 448,000.00
667.0000 kg Pasir cor Rp 64.29 Rp 42,878.57
1,000.0000 kg Krikil alam 2-3cm Rp 129.63 Rp 129,629.63
215.0000 ltr Air kerja Rp 22.50 Rp 4,837.50
Jumlah (I) Rp 625,345.70
TENAGA
0.3500 Hari Tukang batu Rp 57,000.00 Rp 19,950.00
0.0350 Hari Kepala tukang batu Rp 60,000.00 Rp 2,100.00
2.1000 Hari Pekerja Rp 44,000.00 Rp 92,400.00
0.1050 Hari Mandor Rp 55,000.00 Rp 5,775.00
Jumlah (II) Rp 120,225.00
Jumlah (I) + (II) Rp 745,570.70
Over head / Keuntungan 10 % Rp 74,557.07
Rp 820,127.77

10 KG PEMBERSIAN DENGAN BESI POLOS


SNI 7394.2008.17
BAHAN
1.0500 kg Besi beton polos Rp 9,000.00 Rp 9,450.00
0.0150 kg Kawat beton Rp 10,000.00 Rp 150.00
Jumlah (I) Rp 9,600.00
TENAGA
0.0070 Hari Tukang besi Rp 57,000.00 Rp 399.00
0.0007 Hari Kepala tukang besi Rp 60,000.00 Rp 42.00
0.0070 Hari Pekerja Rp 44,000.00 Rp 308.00
0.0004 Hari Mandor Rp 55,000.00 Rp 22.00
Jumlah (II) Rp 771.00
Jumlah (I) + (II) Rp 10,371.00
Over head / Keuntungan 10 % Rp 1,037.10
Rp 11,408.10
10 KG PEMBESIAN DENGAN BESI ULIR
SNI 7394.2008.18
BAHAN
1.0500 kg Besi beton ulir Rp 9,000.00 Rp 9,450.00
0.0150 kg Kawat beton Rp 10,000.00 Rp 150.00
Jumlah (I) Rp 9,600.00
TENAGA
0.0070 Hari Tukang besi Rp 57,000.00 Rp 399.00
0.0007 Hari Kepala tukang besi Rp 60,000.00 Rp 42.00
0.0070 Hari Pekerja Rp 44,000.00 Rp 308.00
0.0004 Hari Mandor Rp 55,000.00 Rp 22.00
Jumlah (II) Rp 771.00
Jumlah (I) + (II) Rp 10,371.00
Over head / Keuntungan 10 % Rp 1,037.10
Rp 11,408.10

1 M² MEMASANG BEGISTING UNTUK PONDASI


SNI 7394.2008.20
BAHAN
0.0400 m³ Kayu kelas III Rp 2,000,000.00 Rp 80,000.00
0.3000 kg Paku usuk/reng Rp 15,000.00 Rp 4,500.00
0.1000 ltr Minyak begesting Rp 3,150.00 Rp 315.00
Jumlah (I) Rp 84,815.00
TENAGA
0.2600 Hari Tukang kayu Rp 57,000.00 Rp 14,820.00
0.0260 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,560.00
0.5200 Hari Pekerja Rp 44,000.00 Rp 22,880.00
0.0260 Hari Mandor Rp 55,000.00 Rp 1,430.00
Jumlah (II) Rp 40,690.00
Jumlah (I) + (II) Rp 125,505.00
Over head / Keuntungan 10 % Rp 12,550.50
Rp 138,055.50

1 M² MEMASANG BEGISTING UNTUK SLOOF


SNI 7394.2008.21
BAHAN
0.0450 m³ Kayu kelas III Rp 2,000,000.00 Rp 90,000.00
0.3000 kg Paku usuk/reng Rp 15,000.00 Rp 4,500.00
0.1000 ltr Minyak begesting Rp 3,150.00 Rp 315.00
Jumlah (I) Rp 94,815.00
TENAGA
0.2600 Hari Tukang kayu Rp 57,000.00 Rp 14,820.00
0.0260 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,560.00
0.5200 Hari Pekerja Rp 44,000.00 Rp 22,880.00
0.0260 Hari Mandor Rp 55,000.00 Rp 1,430.00
Jumlah (II) Rp 40,690.00
Jumlah (I) + (II) Rp 135,505.00
Over head / Keuntungan 10 % Rp 13,550.50
Rp 149,055.50

1 M² MEMASANG BEGISTING UNTUK KOLOM


SNI 7394.2008.22
BAHAN
0.0400 m³ Kayu kelas III Rp 2,000,000.00 Rp 80,000.00
0.4000 kg Paku usuk/reng Rp 15,000.00 Rp 6,000.00
0.2000 ltr Minyak begesting Rp 3,150.00 Rp 630.00
0.0150 m³ Kayu kelas III Rp 2,000,000.00 Rp 30,000.00
0.3500 lbr Triplek 9 mm Rp 90,000.00 Rp 31,500.00
2.0000 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 34,000.00
Jumlah (I) Rp 182,130.00
TENAGA
0.3300 Hari Tukang kayu Rp 57,000.00 Rp 18,810.00
0.0330 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,980.00
0.6600 Hari Pekerja Rp 44,000.00 Rp 29,040.00
0.0330 Hari Mandor Rp 55,000.00 Rp 1,815.00
Jumlah (II) Rp 51,645.00
Jumlah (I) + (II) Rp 233,775.00
Over head / Keuntungan 10 % Rp 23,377.50
Rp 257,152.50
1 M² MEMASANG BEGISTING UNTUK BALOK
SNI 7394.2008.23
BAHAN
0.0400 m³ Kayu kelas III Rp 2,000,000.00 Rp 80,000.00
0.4000 kg Paku usuk/reng Rp 15,000.00 Rp 6,000.00
0.2000 ltr Minyak begesting Rp 3,150.00 Rp 630.00
0.0180 m³ Kayu kelas III Rp 2,000,000.00 Rp 36,000.00
0.3500 lbr Triplek 9 mm Rp 90,000.00 Rp 31,500.00
2.0000 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 34,000.00
Jumlah (I) Rp 188,130.00
TENAGA
0.3300 Hari Tukang kayu Rp 57,000.00 Rp 18,810.00
0.0330 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,980.00
0.6600 Hari Pekerja Rp 44,000.00 Rp 29,040.00
0.0330 Hari Mandor Rp 55,000.00 Rp 1,815.00
Jumlah (II) Rp 51,645.00
Jumlah (I) + (II) Rp 239,775.00
Over head / Keuntungan 10 % Rp 23,977.50
Rp 263,752.50

1 M² MEMASANG BEGISTING UNTUK LANTAI


SNI 7394.2008.24
BAHAN
0.0400 m³ Kayu kelas III Rp 2,000,000.00 Rp 80,000.00
0.4000 kg Paku usuk/reng Rp 15,000.00 Rp 6,000.00
0.2000 ltr Minyak begesting Rp 3,150.00 Rp 630.00
0.0150 m³ Kayu kelas III Rp 2,000,000.00 Rp 30,000.00
0.3500 lbr Triplek 9 mm Rp 90,000.00 Rp 31,500.00
6.0000 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 102,000.00
Jumlah (I) Rp 250,130.00
TENAGA
0.3300 Hari Tukang kayu Rp 57,000.00 Rp 18,810.00
0.0330 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,980.00
0.6600 Hari Pekerja Rp 44,000.00 Rp 29,040.00
0.0330 Hari Mandor Rp 55,000.00 Rp 1,815.00
Jumlah (II) Rp 51,645.00
Jumlah (I) + (II) Rp 301,775.00
Over head / Keuntungan 10 % Rp 30,177.50
Rp 331,952.50

1 M² MEMASANG BEGISTING UNTUK DINDING


SNI 7394.2008.25
BAHAN
0.0300 m³ Kayu kelas III Rp 2,000,000.00 Rp 60,000.00
0.4000 kg Paku usuk/reng Rp 15,000.00 Rp 6,000.00
0.2000 ltr Minyak begesting Rp 3,150.00 Rp 630.00
0.0200 m³ Kayu kelas III Rp 2,000,000.00 Rp 40,000.00
0.3500 lbr Triplek 9 mm Rp 90,000.00 Rp 31,500.00
3.0000 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 51,000.00
Jumlah (I) Rp 189,130.00
TENAGA
0.3300 Hari Tukang kayu Rp 57,000.00 Rp 18,810.00
0.0330 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,980.00
0.6600 Hari Pekerja Rp 44,000.00 Rp 29,040.00
0.0330 Hari Mandor Rp 55,000.00 Rp 1,815.00
Jumlah (II) Rp 51,645.00
Jumlah (I) + (II) Rp 240,775.00
Over head / Keuntungan 10 % Rp 24,077.50
Rp 264,852.50

1 M² MEMASANG BEGISTING UNTUK TANGGA


SNI 7394.2008.26
BAHAN
0.0300 m³ Kayu kelas III Rp 2,000,000.00 Rp 60,000.00
0.4000 kg Paku usuk/reng Rp 15,000.00 Rp 6,000.00
0.1500 ltr Minyak begesting Rp 3,150.00 Rp 472.50
0.0150 m³ Kayu kelas III Rp 2,000,000.00 Rp 30,000.00
0.3500 lbr Triplek 9 mm Rp 90,000.00 Rp 31,500.00
2.0000 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 34,000.00
Jumlah (I) Rp 161,972.50
TENAGA
0.3300 Hari Tukang kayu Rp 57,000.00 Rp 18,810.00
0.0330 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,980.00
0.6600 Hari Pekerja Rp 44,000.00 Rp 29,040.00
0.0330 Hari Mandor Rp 55,000.00 Rp 1,815.00
Jumlah (II) Rp 51,645.00
Jumlah (I) + (II) Rp 213,617.50
Over head / Keuntungan 10 % Rp 21,361.75
Rp 234,979.25
1 M3 MEMASANG pondasi beton bertulang (150 kg besi + bekisting)
SNI 7394.2008.28
BAHAN
0.2000 m³ Kayu kelas III Rp 2,000,000.00 Rp 400,000.00
1.5000 kg Paku usuk/reng Rp 15,000.00 Rp 22,500.00
0.4000 ltr Minyak begesting Rp 3,150.00 Rp 1,260.00
157.5000 kg Besi beton polos Rp 9,000.00 Rp 1,417,500.00
2.2500 kg Kawat beton Rp 10,000.00 Rp 22,500.00
336.0000 kg Semen Rp 1,000.00 Rp 336,000.00
0.5400 m³ Pasir beton Rp 90,000.00 Rp 48,600.00
0.8100 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 121,500.00
Jumlah (I) Rp 2,369,860.00
TENAGA
1.3000 Hari Tukang kayu Rp 57,000.00 Rp 74,100.00
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
1.0500 Hari Tukang besi Rp 57,000.00 Rp 59,850.00
0.2620 Hari Kepala tukang besi Rp 60,000.00 Rp 15,720.00
5.3000 Hari Pekerja Rp 44,000.00 Rp 233,200.00
0.2650 Hari Mandor Rp 55,000.00 Rp 14,575.00
Jumlah (II) Rp 413,120.00
Jumlah (I) + (II) Rp 2,782,980.00
Over head / Keuntungan 10 % Rp 278,298.00
Rp 3,061,278.00

1 M3 MEMASANG PONDASI BETON FOOT PLATE (150x150x25)


SNI 7394.2008.28a

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


169.5960 kg PEMBESIAN POLOS Rp 11,408.10 Rp 1,934,768.13
1.0670 m2 BEKISTING PONDASI (2 Kali Pakai) Rp 138,055.50 Rp 147,305.22
Jumlah (I) Rp 2,750,437.23

1 M3 MEMASANG sloof beton bertulang (200 kg besi + bekisting)


SNI 7394.2008.29
BAHAN
0.2700 m³ Kayu kelas III Rp 2,000,000.00 Rp 540,000.00
2.0000 kg Paku usuk/reng Rp 15,000.00 Rp 30,000.00
0.6000 ltr Minyak begesting Rp 3,150.00 Rp 1,890.00
210.0000 kg Besi beton polos Rp 9,000.00 Rp 1,890,000.00
3.0000 kg Kawat beton Rp 10,000.00 Rp 30,000.00
336.0000 kg Semen Rp 1,000.00 Rp 336,000.00
0.5400 m³ Pasir beton Rp 90,000.00 Rp 48,600.00
0.8100 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 121,500.00
Jumlah (I) Rp 2,997,990.00
TENAGA
1.5600 Hari Tukang kayu Rp 57,000.00 Rp 88,920.00
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
1.4000 Hari Tukang besi Rp 57,000.00 Rp 79,800.00
0.3230 Hari Kepala tukang besi Rp 60,000.00 Rp 19,380.00
5.6500 Hari Pekerja Rp 44,000.00 Rp 248,600.00
0.2830 Hari Mandor Rp 55,000.00 Rp 15,565.00
Jumlah (II) Rp 467,940.00
Jumlah (I) + (II) Rp 3,465,930.00
Over head / Keuntungan 10 % Rp 346,593.00
Rp 3,812,523.00

1 M3 MEMBUAT SLOOF BETON 15/20 CM


SNI 7394.2008.29a

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


77.5010 kg PEMBESIAN POLOS Rp 11,408.10 Rp 884,139.16
6.6670 m2 BEKISTING SLOOF (2 Kali Pakai) Rp 149,055.50 Rp 993,753.02
Jumlah (I) Rp 2,546,256.06

1 M3 MEMBUAT SLOOF BETON 13/15 CM


SNI 7394.2008.29b

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


108.3910 kg PEMBESIAN POLOS Rp 11,408.10 Rp 1,236,535.37
7.6920 m2 BEKISTING SLOOF (2 Kali Pakai) Rp 149,055.50 Rp 1,146,534.91
Jumlah (I) Rp 3,051,434.16
1 M3 Membuat kolom beton bertulang (300 kg besi + bekisting)
SNI 7394.2008.30
BAHAN
0.4000 m³ Kayu kelas III Rp 2,000,000.00 Rp 800,000.00
4.0000 kg Paku usuk/reng Rp 15,000.00 Rp 60,000.00
2.0000 ltr Minyak begesting Rp 3,150.00 Rp 6,300.00
315.0000 kg Besi beton polos Rp 9,000.00 Rp 2,835,000.00
4.5000 kg Kawat beton Rp 10,000.00 Rp 45,000.00
336.0000 kg Semen Rp 1,000.00 Rp 336,000.00
0.5400 m³ Pasir beton Rp 90,000.00 Rp 48,600.00
0.8100 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 121,500.00
0.1500 m³ Kayu klas II Rp 3,000,000.00 Rp 450,000.00
3.5000 lbr Playwood 6 mm Rp 115,000.00 Rp 402,500.00
20.0000 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 340,000.00
Jumlah (I) Rp 5,444,900.00
TENAGA
1.6500 Hari Tukang kayu Rp 57,000.00 Rp 94,050.00
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
2.1000 Hari Tukang besi Rp 57,000.00 Rp 119,700.00
0.3230 Hari Kepala tukang besi Rp 60,000.00 Rp 19,380.00
7.0500 Hari Pekerja Rp 44,000.00 Rp 310,200.00
0.3530 Hari Mandor Rp 55,000.00 Rp 19,415.00
Jumlah (II) Rp 578,420.00
Jumlah (I) + (II) Rp 6,023,320.00
Over head / Keuntungan 10 % Rp 602,332.00
Rp 6,625,652.00

1 M3 MEMBUAT KOLOM BETON 15/15 CM


SNI 7394.2008.30a

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


96.6440 kg PEMBESIAN POLOS Rp 11,408.10 Rp 1,102,524.42
6.6670 m2 BEKISTING KOLOM Rp 257,152.50 Rp 1,714,435.72
Jumlah (I) Rp 3,485,324.02

1 M3 MEMASANG kolom beton bertulang (300 kg besi + bekisting)


SNI 7394.2008.31
BAHAN
0.3200 m³ Kayu kelas III Rp 2,000,000.00 Rp 640,000.00
3.2000 kg Paku usuk/reng Rp 15,000.00 Rp 48,000.00
1.6000 ltr Minyak begesting Rp 3,150.00 Rp 5,040.00
210.0000 kg Besi beton polos Rp 9,000.00 Rp 1,890,000.00
3.0000 kg Kawat beton Rp 10,000.00 Rp 30,000.00
336.0000 kg Semen Rp 1,000.00 Rp 336,000.00
0.5400 m³ Pasir beton Rp 90,000.00 Rp 48,600.00
0.8100 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 121,500.00
0.1400 m³ Kayu klas II Rp 3,000,000.00 Rp 420,000.00
2.8000 lbr Playwood 6 mm Rp 115,000.00 Rp 322,000.00
Jumlah (I) Rp 3,861,140.00
TENAGA
1.6500 Hari Tukang kayu Rp 57,000.00 Rp 94,050.00
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
1.4000 Hari Tukang besi Rp 57,000.00 Rp 79,800.00
0.3330 Hari Kepala tukang besi Rp 60,000.00 Rp 19,980.00
6.3500 Hari Pekerja Rp 44,000.00 Rp 279,400.00
0.3180 Hari Mandor Rp 55,000.00 Rp 17,490.00
Jumlah (II) Rp 506,395.00
Jumlah (I) + (II) Rp 4,367,535.00
Over head / Keuntungan 10 % Rp 436,753.50
Rp 4,804,288.50

1 M3 MEMBUAT BALOK BETON 20/25 CM (BALOK ANAK DAN BALOK ATAP)


SNI 7394.2008.31a

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


145.3270 kg PEMBESIAN POLOS Rp 11,408.10 Rp 1,657,904.95
7.0000 m2 BEKISTING BALOK Rp 263,752.50 Rp 1,846,267.50
Jumlah (I) Rp 4,172,536.33

1 M3 MEMBUAT BALOK RING BETON 15/20 CM


SNI 7394.2008.31b

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


107.1070 kg PEMBESIAN POLOS Rp 11,408.10 Rp 1,221,887.37
9.1670 m2 BEKISTING BALOK Rp 263,752.50 Rp 2,417,819.17
Jumlah (I) Rp 4,308,070.42
1 M3 MEMBUAT BALOK RING BETON 13/15 CM
SNI 7394.2008.31c

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


108.3910 kg PEMBESIAN POLOS Rp 11,408.10 Rp 1,236,535.37
5.5130 m2 BEKISTING BALOK Rp 263,752.50 Rp 1,454,067.53
Jumlah (I) Rp 3,358,966.78

1 M3 MEMBUAT BALOK LATEI BETON 13/15 CM


SNI 7394.2008.31d

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


108.3910 kg PEMBESIAN POLOS Rp 11,408.10 Rp 1,236,535.37
5.5130 m2 BEKISTING BALOK Rp 263,752.50 Rp 1,454,067.53
Jumlah (I) Rp 3,358,966.78

1 M3 MEMASANG plat beton bertulang (150 kg besi + bekisting)


SNI 7394.2008.32
BAHAN
0.3200 m³ Kayu kelas III Rp 2,000,000.00 Rp 640,000.00
3.2000 kg Paku usuk/reng Rp 15,000.00 Rp 48,000.00
1.6000 ltr Minyak begesting Rp 3,150.00 Rp 5,040.00
157.5000 kg Besi beton polos Rp 9,000.00 Rp 1,417,500.00
2.2500 kg Kawat beton Rp 10,000.00 Rp 22,500.00
336.0000 kg Semen Rp 1,000.00 Rp 336,000.00
0.5400 m³ Pasir beton Rp 90,000.00 Rp 48,600.00
0.8100 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 121,500.00
0.1200 m³ Kayu klas II Rp 3,000,000.00 Rp 360,000.00
2.8000 lbr Playwood 6 mm Rp 115,000.00 Rp 322,000.00
32.0000 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 544,000.00
Jumlah (I) Rp 3,865,140.00
TENAGA
1.3000 Hari Tukang kayu Rp 57,000.00 Rp 74,100.00
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
1.0500 Hari Tukang besi Rp 57,000.00 Rp 59,850.00
0.2650 Hari Kepala tukang besi Rp 60,000.00 Rp 15,900.00
5.3000 Hari Pekerja Rp 44,000.00 Rp 233,200.00
0.2650 Hari Mandor Rp 55,000.00 Rp 14,575.00
Jumlah (II) Rp 413,300.00
Jumlah (I) + (II) Rp 4,278,440.00
Over head / Keuntungan 10 % Rp 427,844.00
Rp 4,706,284.00

1 M3 MEMBUAT PLAT BETON TANGGA TEBAL = 15 CM


SNI 7394.2008.32a

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


143.6670 kg PEMBESIAN POLOS Rp 11,408.10 Rp 1,638,967.50
6.6670 m2 BEKISTING LANTAI Rp 331,952.50 Rp 2,213,127.32
Jumlah (I) Rp 4,520,458.71

1 M3 MEMBUAT PLAT BETON LANTAI TEBAL = 12 CM


SNI 7394.2008.32b

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


86.6600 kg PEMBESIAN POLOS Rp 11,408.10 Rp 988,625.95
8.3330 m2 BEKISTING LANTAI Rp 331,952.50 Rp 2,766,160.18
Jumlah (I) Rp 4,423,150.01

1 M3 MEMBUAT PLAT BETON ATAP TEBAL = 10 CM


SNI 7394.2008.32c

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


74.4540 kg PEMBESIAN POLOS Rp 11,408.10 Rp 849,378.68
10.0000 m2 BEKISTING LANTAI Rp 331,952.50 Rp 3,319,525.00
Jumlah (I) Rp 4,837,267.56

1 M3 MEMBUAT PLAT BETON SUNSCREEN TEBAL = 8 CM


SNI 7394.2008.32d

1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88


61.1400 kg PEMBESIAN POLOS Rp 11,408.10 Rp 697,491.23
12.5000 m2 BEKISTING LANTAI Rp 331,952.50 Rp 4,149,406.25
Jumlah (I) Rp 5,515,261.37

1 M3 MEMBUAT PLAT BETON LISTPLANK TEBAL = 8 CM


SNI 7394.2008.32e
1.0000 m³ BETON (K-175) Rp 668,363.88 Rp 668,363.88
58.6430 kg PEMBESIAN POLOS Rp 11,408.10 Rp 669,005.21
12.5000 m2 BEKISTING LANTAI Rp 331,952.50 Rp 4,149,406.25
Jumlah (I) Rp 5,486,775.34
1 M3 MEMASANG dinding beton bertulang (150 kg besi + bekisting)
SNI 7394.2008.33
BAHAN
0.2400 m³ Kayu kelas III Rp 2,000,000.00 Rp 480,000.00
3.2000 kg Paku usuk/reng Rp 15,000.00 Rp 48,000.00
1.6000 ltr Minyak begesting Rp 3,150.00 Rp 5,040.00
157.5000 kg Besi beton polos Rp 9,000.00 Rp 1,417,500.00
2.2500 kg Kawat beton Rp 10,000.00 Rp 22,500.00
336.0000 kg Semen Rp 1,000.00 Rp 336,000.00
0.5400 m³ Pasir beton Rp 90,000.00 Rp 48,600.00
0.8100 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 121,500.00
0.1600 m³ Kayu klas II Rp 3,000,000.00 Rp 480,000.00
2.8000 lbr Playwood 6 mm Rp 115,000.00 Rp 322,000.00
24.0000 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 408,000.00
Jumlah (I) Rp 3,689,140.00
TENAGA
1.3000 Hari Tukang kayu Rp 57,000.00 Rp 74,100.00
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
1.0500 Hari Tukang besi Rp 57,000.00 Rp 59,850.00
0.2620 Hari Kepala tukang besi Rp 60,000.00 Rp 15,720.00
5.3000 Hari Pekerja Rp 44,000.00 Rp 233,200.00
0.2650 Hari Mandor Rp 55,000.00 Rp 14,575.00
Jumlah (II) Rp 413,120.00
Jumlah (I) + (II) Rp 4,102,260.00
Over head / Keuntungan 10 % Rp 410,226.00
Rp 4,512,486.00

1 M3 MEMASANG dinding beton bertulang (200 kg besi + bekisting)


SNI 7394.2008.34
BAHAN
0.2500 m³ Kayu kelas III Rp 2,000,000.00 Rp 500,000.00
3.0000 kg Paku usuk/reng Rp 15,000.00 Rp 45,000.00
1.2000 ltr Minyak begesting Rp 3,150.00 Rp 3,780.00
210.0000 kg Besi beton polos Rp 9,000.00 Rp 1,890,000.00
3.0000 kg Kawat beton Rp 10,000.00 Rp 30,000.00
336.0000 kg Semen Rp 1,000.00 Rp 336,000.00
0.5400 m³ Pasir beton Rp 90,000.00 Rp 48,600.00
0.8100 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 121,500.00
0.1050 m³ Kayu klas II Rp 3,000,000.00 Rp 315,000.00
2.5000 lbr Playwood 6 mm Rp 115,000.00 Rp 287,500.00
14.0000 btg Kayu dolken ø 10cm - 4 m Rp 17,000.00 Rp 238,000.00
Jumlah (I) Rp 3,815,380.00
TENAGA
1.5600 Hari Tukang kayu Rp 57,000.00 Rp 88,920.00
0.2750 Hari Tukang batu Rp 57,000.00 Rp 15,675.00
1.4000 Hari Tukang besi Rp 57,000.00 Rp 79,800.00
0.3230 Hari Kepala tukang besi Rp 60,000.00 Rp 19,380.00
5.6500 Hari Pekerja Rp 44,000.00 Rp 248,600.00
0.2830 Hari Mandor Rp 55,000.00 Rp 15,565.00
Jumlah (II) Rp 467,940.00
Jumlah (I) + (II) Rp 4,283,320.00
Over head / Keuntungan 10 % Rp 428,332.00
Rp 4,711,652.00

1 M' MEMASANG kolom praktis beton bertulang (11 x 11) cm


SNI 7394.2008.35
BAHAN
0.0020 m³ Kayu kelas III Rp 2,000,000.00 Rp 4,000.00
0.0100 kg Paku usuk/reng Rp 15,000.00 Rp 150.00
3.0000 kg Besi beton polos Rp 9,000.00 Rp 27,000.00
0.0450 kg Kawat beton Rp 10,000.00 Rp 450.00
4.0000 kg Semen Rp 1,000.00 Rp 4,000.00
0.0060 m³ Pasir beton Rp 90,000.00 Rp 540.00
0.0090 m³ Krikil alam 2-3cm - 1 m³ Rp 150,000.00 Rp 1,350.00
Jumlah (I) Rp 37,490.00
TENAGA
0.0200 Hari Tukang kayu Rp 57,000.00 Rp 1,140.00
0.0200 Hari Tukang batu Rp 57,000.00 Rp 1,140.00
0.0200 Hari Tukang besi Rp 57,000.00 Rp 1,140.00
0.0060 Hari Kepala tukang besi Rp 60,000.00 Rp 360.00
0.1800 Hari Pekerja Rp 44,000.00 Rp 7,920.00
0.0090 Hari Mandor Rp 55,000.00 Rp 495.00
Jumlah (II) Rp 12,195.00
Jumlah (I) + (II) Rp 49,685.00
Over head / Keuntungan 10 % Rp 4,968.50
Rp 54,653.50

E. PEKERJAAN DINDING
1 M² PAS. BATA MERAH TEBAL 1 BATA 1Pc : 3Psr
SNI 6897.2008.2
BAHAN
140.0000 bh Bata merah Rp 400.00 Rp 56,000.00
32.9500 kg Semen Rp 1,000.00 Rp 32,950.00
0.0910 m³ Pasir pasang Rp 80,000.00 Rp 7,280.00
Jumlah (I) Rp 96,230.00
TENAGA
0.2000 Hari Tukang batu Rp 57,000.00 Rp 11,400.00
0.0200 Hari Kepala tukang batu Rp 60,000.00 Rp 1,200.00
0.6000 Hari Pekerja Rp 44,000.00 Rp 26,400.00
0.0300 Hari Mandor Rp 55,000.00 Rp 1,650.00
Jumlah (II) Rp 40,650.00
Jumlah (I) + (II) Rp 136,880.00
Over head / Keuntungan 10 % Rp 13,688.00
Rp 150,568.00

1 M² PAS. BATA MERAH TEBAL 1 BATA 1Pc : 5Psr


SNI 6897.2008.4
BAHAN
140.0000 bh Bata merah Rp 400.00 Rp 56,000.00
22.2000 kg Semen Rp 1,000.00 Rp 22,200.00
0.1020 m³ Pasir pasang Rp 80,000.00 Rp 8,160.00
Jumlah (I) Rp 86,360.00
TENAGA
0.2000 Hari Tukang batu Rp 57,000.00 Rp 11,400.00
0.0200 Hari Kepala tukang batu Rp 60,000.00 Rp 1,200.00
0.6000 Hari Pekerja Rp 44,000.00 Rp 26,400.00
0.0300 Hari Mandor Rp 55,000.00 Rp 1,650.00
Jumlah (II) Rp 40,650.00
Jumlah (I) + (II) Rp 127,010.00
Over head / Keuntungan 10 % Rp 12,701.00
Rp 139,711.00

1 M² PAS. BATA MERAH 1/2 BATA 1Pc : 3Psr


SNI 6897.2008.8
BAHAN
70.0000 bh Bata merah Rp 400.00 Rp 28,000.00
14.3700 kg Semen Rp 1,000.00 Rp 14,370.00
0.0400 m³ Pasir pasang Rp 80,000.00 Rp 3,200.00
Jumlah (I) Rp 45,570.00
TENAGA
0.1000 Hari Tukang batu Rp 57,000.00 Rp 5,700.00
0.0100 Hari Kepala tukang batu Rp 60,000.00 Rp 600.00
0.3000 Hari Pekerja Rp 44,000.00 Rp 13,200.00
0.0150 Hari Mandor Rp 55,000.00 Rp 825.00
Jumlah (II) Rp 20,325.00
Jumlah (I) + (II) Rp 65,895.00
Over head / Keuntungan 10 % Rp 6,589.50
Rp 72,484.50

1 M² PAS. BATA MERAH 1/2 BATA 1Pc : 5Psr


SNI 6897.2008.10
BAHAH
70.0000 bh Bata merah Rp 400.00 Rp 28,000.00
9.6800 kg Semen Rp 1,000.00 Rp 9,680.00
0.0450 m³ Pasir pasang Rp 80,000.00 Rp 3,600.00
Jumlah (I) Rp 41,280.00
TENAGA
0.1000 Hari Tukang batu Rp 57,000.00 Rp 5,700.00
0.0100 Hari Kepala tukang batu Rp 60,000.00 Rp 600.00
0.3000 Hari Pekerja Rp 44,000.00 Rp 13,200.00
0.0150 Hari Mandor Rp 55,000.00 Rp 825.00
Jumlah (II) Rp 20,325.00
Jumlah (I) + (II) Rp 61,605.00
Over head / Keuntungan 10 % Rp 6,160.50
Rp 67,765.50
F. PEKERJAAN PLESTERAN
1 M² PLESTERAN TRASRAM 1PC : 3Psr
SNI 2837.2008.3
BAHAN
7.7760 kg Semen Rp 1,000.00 Rp 7,776.00
0.0230 m³ Pasir pasang Rp 80,000.00 Rp 1,840.00
Jumlah (I) Rp 9,616.00
TENAGA
0.1500 Hari Tukang batu Rp 57,000.00 Rp 8,550.00
0.0150 Hari Kepala tukang batu Rp 60,000.00 Rp 900.00
0.3000 Hari Pekerja Rp 44,000.00 Rp 13,200.00
0.0150 Hari Mandor Rp 55,000.00 Rp 825.00
Jumlah (II) Rp 23,475.00
Jumlah (I) + (II) Rp 33,091.00
Over head / Keuntungan 10 % Rp 3,309.10
Rp 36,400.10

1 M² PLESTERAN BETON 1PC : 4Psr , Tebal 15 mm


SNI 2837.2008.4
BAHAN
6.2400 kg Semen Rp 1,000.00 Rp 6,240.00
0.0240 m³ Pasir pasang Rp 80,000.00 Rp 1,920.00
Jumlah (I) Rp 8,160.00
TENAGA
0.1500 Hari Tukang batu Rp 57,000.00 Rp 8,550.00
0.0150 Hari Kepala tukang batu Rp 60,000.00 Rp 900.00
0.3000 Hari Pekerja Rp 44,000.00 Rp 13,200.00
0.0150 Hari Mandor Rp 55,000.00 Rp 825.00
Jumlah (II) Rp 23,475.00
Jumlah (I) + (II) Rp 31,635.00
Over head / Keuntungan 10 % Rp 3,163.50
Rp 34,798.50

1 M² PLESTERAN 1PC : 5Psr


SNI 2837.2008.5
BAHAN
5.1480 kg Semen Rp 1,000.00 Rp 5,148.00
0.0260 m³ Pasir pasang Rp 80,000.00 Rp 2,080.00
Jumlah (I) Rp 7,228.00
TENAGA
0.1500 Hari Tukang batu Rp 57,000.00 Rp 8,550.00
0.0150 Hari Kepala tukang batu Rp 60,000.00 Rp 900.00
0.3000 Hari Pekerja Rp 44,000.00 Rp 13,200.00
0.0150 Hari Mandor Rp 55,000.00 Rp 825.00
Jumlah (II) Rp 23,475.00
Jumlah (I) + (II) Rp 30,703.00
Over head / Keuntungan 10 % Rp 3,070.30
Rp 33,773.30

1 M² PLESTERAN KALORAN 1PC : 3Psr


SNI 2837.2008.24
BAHAN
7.7760 kg Semen Rp 1,000.00 Rp 7,776.00
0.0263 m³ Pasir pasang Rp 80,000.00 Rp 2,104.00
Jumlah (I) Rp 9,880.00
TENAGA
0.3000 Hari Tukang batu Rp 57,000.00 Rp 17,100.00
0.0300 Hari Kepala tukang batu Rp 60,000.00 Rp 1,800.00
0.4000 Hari Pekerja Rp 44,000.00 Rp 17,600.00
0.0200 Hari Mandor Rp 55,000.00 Rp 1,100.00
Jumlah (II) Rp 37,600.00
Jumlah (I) + (II) Rp 47,480.00
Over head / Keuntungan 10 % Rp 4,748.00
Rp 52,228.00

1 M² SIARAN PONDASI 1PC : 2Psr


SNI 2837.2008.26
BAHAN
6.3400 kg Semen Rp 1,000.00 Rp 6,340.00
0.0120 m³ Pasir pasang Rp 80,000.00 Rp 960.00
Jumlah (I) Rp 7,300.00
TENAGA
0.1400 Hari Tukang batu Rp 57,000.00 Rp 7,980.00
0.0140 Hari Kepala tukang batu Rp 60,000.00 Rp 840.00
0.3000 Hari Pekerja Rp 44,000.00 Rp 13,200.00
0.0150 Hari Mandor Rp 55,000.00 Rp 825.00
Jumlah (II) Rp 22,845.00
Jumlah (I) + (II) Rp 30,145.00
Over head / Keuntungan 10 % Rp 3,014.50
Rp 33,159.50
1 M² PLESTERAN ACIAN
SNI 2837.2008.27
BAHAN
3.2500 kg Semen Rp 1,000.00 Rp 3,250.00
Jumlah (I) Rp 3,250.00
TENAGA
0.1000 Hari Tukang batu Rp 57,000.00 Rp 5,700.00
0.0100 Hari Kepala tukang batu Rp 60,000.00 Rp 600.00
0.2000 Hari Pekerja Rp 44,000.00 Rp 8,800.00
0.0100 Hari Mandor Rp 55,000.00 Rp 550.00
Jumlah (II) Rp 15,650.00
Jumlah (I) + (II) Rp 18,900.00
Over head / Keuntungan 10 % Rp 1,890.00
Rp 20,790.00

G. PEKERJAAN KAYU
1 M³ PEK.KAYU KUSEN PINTU/JENDELA KLS I
SNI 3434.2008.1 BAHAN
1.1000 m³ Kayu klas I Rp 6,750,000.00 Rp 7,425,000.00
1.2500 kg Paku usuk/reng Rp 15,000.00 Rp 18,750.00
1.0000 kg Lem kayu Rp 16,920.00 Rp 16,920.00
Jumlah (I) Rp 7,460,670.00
TENAGA
21.0000 Hari Tukang kayu Rp 57,000.00 Rp 1,197,000.00
2.1000 Hari Kepala tukang kayu Rp 60,000.00 Rp 126,000.00
7.0000 Hari Pekerja Rp 44,000.00 Rp 308,000.00
0.0350 Hari Mandor Rp 55,000.00 Rp 1,925.00
Jumlah (II) Rp 1,632,925.00
Jumlah (I) + (II) Rp 9,093,595.00
Over head / Keuntungan 10 % Rp 909,359.50
Rp 10,002,954.50

1 M³ PEK.KAYU KUSEN PINTU/JENDELA KLS II ATAU III


SNI 3434.2008.2 BAHAN
1.2000 m³ Kayu klas II Rp 3,000,000.00 Rp 3,600,000.00
1.2500 kg Paku usuk/reng Rp 15,000.00 Rp 18,750.00
1.0000 kg Lem kayu Rp 16,920.00 Rp 16,920.00
Jumlah (I) Rp 3,635,670.00
TENAGA
18.0000 Hari Tukang kayu Rp 57,000.00 Rp 1,026,000.00
1.8000 Hari Kepala tukang kayu Rp 60,000.00 Rp 108,000.00
6.0000 Hari Pekerja Rp 44,000.00 Rp 264,000.00
0.0300 Hari Mandor Rp 55,000.00 Rp 1,650.00
Jumlah (II) Rp 1,399,650.00
Jumlah (I) + (II) Rp 5,035,320.00
Over head / Keuntungan 10 % Rp 503,532.00
Rp 5,538,852.00

1 M² PEK. DAUN PINTU KLAM STANDAR KAYU KLAS II


SNI 3434.2008.3 BAHAN
0.0400 m³ Papan kayu kls II Rp 3,000,000.00 Rp 120,000.00
0.0500 kg Paku usuk/reng Rp 15,000.00 Rp 750.00
Jumlah (I) Rp 120,750.00
TENAGA
1.0500 Hari Tukang kayu Rp 57,000.00 Rp 59,850.00
0.1050 Hari Kepala tukang kayu Rp 60,000.00 Rp 6,300.00
0.3500 Hari Pekerja Rp 44,000.00 Rp 15,400.00
0.0180 Hari Mandor Rp 55,000.00 Rp 990.00
Jumlah (II) Rp 82,540.00
Jumlah (I) + (II) Rp 203,290.00
Over head / Keuntungan 10 % Rp 20,329.00
Rp 223,619.00

1 M² PEK. DAUN PINTU KLAM STANDAR KAYU KLAS III GUDANG SEMENTARA
SNI 3434.2008.4 BAHAN
0.0400 m³ Papan kayu kls III Rp 2,000,000.00 Rp 80,000.00
0.0500 kg Paku usuk/reng Rp 15,000.00 Rp 750.00
Jumlah (I) Rp 80,750.00
TENAGA
1.0500 Hari Tukang kayu Rp 57,000.00 Rp 59,850.00
0.1050 Hari Kepala tukang kayu Rp 60,000.00 Rp 6,300.00
0.3500 Hari Pekerja Rp 44,000.00 Rp 15,400.00
0.0180 Hari Mandor Rp 55,000.00 Rp 990.00
Jumlah (II) Rp 82,540.00
Jumlah (I) + (II) Rp 163,290.00
Over head / Keuntungan 10 % Rp 16,329.00
Rp 179,619.00
1 M² PEK. DAUN PINTU PINTU PANIL KAYU KLAS I ATAU II
SNI 3434.2008.5 BAHAN
0.0400 m³ Papan kayu kls II Rp 3,000,000.00 Rp 120,000.00
0.5000 kg Lem kayu Rp 16,920.00 Rp 8,460.00
Jumlah (I) Rp 128,460.00
TENAGA
3.0000 Hari Tukang kayu Rp 57,000.00 Rp 171,000.00
0.3000 Hari Kepala tukang kayu Rp 60,000.00 Rp 18,000.00
1.0000 Hari Pekerja Rp 44,000.00 Rp 44,000.00
0.0500 Hari Mandor Rp 55,000.00 Rp 2,750.00
Jumlah (II) Rp 235,750.00
Jumlah (I) + (II) Rp 364,210.00
Over head / Keuntungan 10 % Rp 36,421.00
Rp 400,631.00

1 M² PEK. DAUN PINTU PANIL MEMAKAI BINGKAI DALAM DILAPIS TRIPLEK ALUMINIUM
SNI 3434.2008.5a BAHAN
0.0400 m³ Papan kayu kls II Rp 3,000,000.00 Rp 120,000.00
0.5000 lbr Triplek aluminium Rp 93,600.00 Rp 46,800.00
0.5000 kg Lem kayu Rp 16,920.00 Rp 8,460.00
Jumlah (I) Rp 175,260.00
TENAGA
3.0000 Hari Tukang kayu Rp 57,000.00 Rp 171,000.00
0.3000 Hari Kepala tukang kayu Rp 60,000.00 Rp 18,000.00
1.0000 Hari Pekerja Rp 44,000.00 Rp 44,000.00
0.0500 Hari Mandor Rp 55,000.00 Rp 2,750.00
Jumlah (II) Rp 235,750.00
Jumlah (I) + (II) Rp 411,010.00
Over head / Keuntungan 10 % Rp 41,101.00
Rp 452,111.00

1 M² DAUN PINTU/JENDELA KACA 3 MM


SNI 3434.2008.6 BAHAN
0.0240 m³ Papan kayu kls I Rp 6,750,000.00 Rp 162,000.00
0.3000 kg Lem kayu Rp 16,920.00 Rp 5,076.00
0.8900 m² Kaca bening 3 mm Rp -
Jumlah (I) Rp 167,076.00
TENAGA
2.4000 Hari Tukang kayu Rp 57,000.00 Rp 136,800.00
0.2400 Hari Kepala tukang kayu Rp 60,000.00 Rp 14,400.00
0.8000 Hari Pekerja Rp 44,000.00 Rp 35,200.00
0.0400 Hari Mandor Rp 55,000.00 Rp 2,200.00
Jumlah (II) Rp 188,600.00
Jumlah (I) + (II) Rp 355,676.00
Over head / Keuntungan 10 % Rp 35,567.60
Rp 391,243.60

1 M² DAUN PINTU/JENDELA KACA 3 MM


SNI 3434.2008.6a BAHAN
0.0240 m³ Papan kayu kls II Rp 3,000,000.00 Rp 72,000.00
0.3000 kg Lem kayu Rp 16,920.00 Rp 5,076.00
0.8900 m² Kaca bening 3 mm Rp -
Jumlah (I) Rp 77,076.00
TENAGA
2.4000 Hari Tukang kayu Rp 57,000.00 Rp 136,800.00
0.2400 Hari Kepala tukang kayu Rp 60,000.00 Rp 14,400.00
0.8000 Hari Pekerja Rp 44,000.00 Rp 35,200.00
0.0400 Hari Mandor Rp 55,000.00 Rp 2,200.00
Jumlah (II) Rp 188,600.00
Jumlah (I) + (II) Rp 265,676.00
Over head / Keuntungan 10 % Rp 26,567.60
Rp 292,243.60

1 M² PEK. DAUN PINTU DAN JENDELA JALUSI KAYU KLAS I ATAU II


SNI 3434.2008.7 BAHAN
0.0640 m³ Papan kayu kls II Rp 3,000,000.00 Rp 192,000.00
0.5000 kg Lem kayu Rp 16,920.00 Rp 8,460.00
Jumlah (I) Rp 200,460.00
TENAGA
3.0000 Hari Tukang kayu Rp 57,000.00 Rp 171,000.00
0.3000 Hari Kepala tukang kayu Rp 60,000.00 Rp 18,000.00
1.0000 Hari Pekerja Rp 44,000.00 Rp 44,000.00
0.0500 Hari Mandor Rp 55,000.00 Rp 2,750.00
Jumlah (II) Rp 235,750.00
Jumlah (I) + (II) Rp 436,210.00
Over head / Keuntungan 10 % Rp 43,621.00
Rp 479,831.00
1 M¹ PEK. KUSEN PINTU/JENDELA ALUMUNIUM
SNI 3434.2008.6a BAHAN
1.1000 m¹ Aluminium 4/8 Rp 85,500.00 Rp 94,050.00
0.0600 tbg Lem silent Rp 189,000.00 Rp 11,340.00
2.0000 dos Paku sekrup Rp 9,900.00 Rp 19,800.00
Jumlah (I) Rp 125,190.00
TENAGA
0.0430 Hari Tukang alumunium Rp 57,000.00 Rp 2,451.00
0.0043 Hari Kepala tukang alumunium Rp 60,000.00 Rp 258.00
0.0130 Hari Pekerja Rp 44,000.00 Rp 572.00
0.0021 Hari Mandor Rp 55,000.00 Rp 115.50
Jumlah (II) Rp 3,396.50
Jumlah (I) + (II) Rp 128,586.50
Over head / Keuntungan 10 % Rp 12,858.65
Rp 141,445.15

1 M² PEK. MEMASANG JALUSI/KREPYAK KUSEN KAYU KLAS I ATAU II


SNI 3434.2008.10 BAHAN
0.0600 m³ Papan kayu kls II Rp 3,000,000.00 Rp 180,000.00
0.1500 kg Paku usuk/reng Rp 15,000.00 Rp 2,250.00
Jumlah (I) Rp 182,250.00
TENAGA
2.0000 Hari Tukang kayu Rp 57,000.00 Rp 114,000.00
0.2000 Hari Kepala tukang kayu Rp 60,000.00 Rp 12,000.00
0.6700 Hari Pekerja Rp 44,000.00 Rp 29,480.00
0.3350 Hari Mandor Rp 55,000.00 Rp 18,425.00
Jumlah (II) Rp 173,905.00
Jumlah (I) + (II) Rp 356,155.00
Over head / Keuntungan 10 % Rp 35,615.50
Rp 391,770.50

1 M² PEK. MEMASANG TEAKWOOD RANGKAP RANGKA EXPOSE KAYU KLAS I


SNI 3434.2008.11 BAHAN
0.0250 m³ Papan kayu kls I Rp 6,750,000.00 Rp 168,750.00
0.0300 kg Paku usuk/reng Rp 15,000.00 Rp 450.00
0.3000 kg Lem kayu Rp 16,920.00 Rp 5,076.00
1.0000 lbr Teakwood 4 mm Rp 112,500.00 Rp 112,500.00
Jumlah (I) Rp 286,776.00
TENAGA
2.4000 Hari Tukang kayu Rp 57,000.00 Rp 136,800.00
0.2400 Hari Kepala tukang kayu Rp 60,000.00 Rp 14,400.00
0.8000 Hari Pekerja Rp 44,000.00 Rp 35,200.00
0.0400 Hari Mandor Rp 55,000.00 Rp 2,200.00
Jumlah (II) Rp 188,600.00
Jumlah (I) + (II) Rp 475,376.00
Over head / Keuntungan 10 % Rp 47,537.60
Rp 522,913.60

1 M² PEK. MEMASANG TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE KAYU KLAS I
SNI 3434.2008.12 BAHAN
0.0250 m³ Papan kayu kls I Rp 6,750,000.00 Rp 168,750.00
0.0300 kg Paku usuk/reng Rp 15,000.00 Rp 450.00
0.8000 kg Lem kayu Rp 16,920.00 Rp 13,536.00
1.0000 lbr Teakwood 4 mm Rp 112,500.00 Rp 112,500.00
0.5000 lbr Formika Rp 90,000.00 Rp 45,000.00
Jumlah (I) Rp 295,236.00
TENAGA
2.5500 Hari Tukang kayu Rp 57,000.00 Rp 145,350.00
0.2550 Hari Kepala tukang kayu Rp 60,000.00 Rp 15,300.00
0.8500 Hari Pekerja Rp 44,000.00 Rp 37,400.00
0.0430 Hari Mandor Rp 55,000.00 Rp 2,365.00
Jumlah (II) Rp 200,415.00
Jumlah (I) + (II) Rp 495,651.00
Over head / Keuntungan 10 % Rp 49,565.10
Rp 545,216.10

1 M3 PAS. KONSTRUKSI KUDA - KUDA KONVENSIONAL KAYU KLS I, II DAN III


SNI 3434.2008.13 BAHAN
1.1000 m³ Kayu klas II Rp 3,000,000.00 Rp 3,300,000.00
5.6000 kg Paku usuk/reng Rp 15,000.00 Rp 84,000.00
15.0000 bh Begel plat Rp 27,810.00 Rp 417,150.00
Jumlah (I) Rp 3,801,150.00
TENAGA
12.0000 Hari Tukang kayu Rp 57,000.00 Rp 684,000.00
1.2000 Hari Kepala tukang kayu Rp 60,000.00 Rp 72,000.00
4.0000 Hari Pekerja Rp 44,000.00 Rp 176,000.00
0.2000 Hari Mandor Rp 55,000.00 Rp 11,000.00
Jumlah (II) Rp 943,000.00
Jumlah (I) + (II) Rp 4,744,150.00
Over head / Keuntungan 10 % Rp 474,415.00
Rp 5,218,565.00

1 M3 PAS. KONSTRUKSI KUDA - KUDA KONSOL/EXPOSE KAYU KLAS I


SNI 3434.2008.14 BAHAN
1.2000 m³ Kayu klas I Rp 6,750,000.00 Rp 8,100,000.00
5.6000 kg Paku usuk/reng Rp 15,000.00 Rp 84,000.00
15.0000 bh Begel plat Rp 27,810.00 Rp 417,150.00
Jumlah (I) Rp 8,601,150.00
TENAGA
20.0000 Hari Tukang kayu Rp 57,000.00 Rp 1,140,000.00
2.0100 Hari Kepala tukang kayu Rp 60,000.00 Rp 120,600.00
6.7000 Hari Pekerja Rp 44,000.00 Rp 294,800.00
0.3350 Hari Mandor Rp 55,000.00 Rp 18,425.00
Jumlah (II) Rp 1,573,825.00
Jumlah (I) + (II) Rp 10,174,975.00
Over head / Keuntungan 10 % Rp 1,017,497.50
Rp 11,192,472.50

1 M3 PAS.KAYU GORDING 8/12 KAYU KLAS II


SNI 3434.2008.15 BAHAN
1.1000 m³ Kayu klas II Rp 3,000,000.00 Rp 3,300,000.00
3.0000 kg Paku usuk/reng Rp 15,000.00 Rp 45,000.00
15.0000 bh Begel plat Rp 27,810.00 Rp 417,150.00
Jumlah (I) Rp 3,762,150.00
TENAGA
7.2000 Hari Tukang kayu Rp 57,000.00 Rp 410,400.00
0.7200 Hari Kepala tukang kayu Rp 60,000.00 Rp 43,200.00
2.4000 Hari Pekerja Rp 44,000.00 Rp 105,600.00
0.1200 Hari Mandor Rp 55,000.00 Rp 6,600.00
Jumlah (II) Rp 565,800.00
Jumlah (I) + (II) Rp 4,327,950.00
Over head / Keuntungan 10 % Rp 432,795.00
Rp 4,760,745.00

1 M² PEK. USUK 5/7 & RENG 2/3 UNTUK GENTENG KERAMIK


SNI 3434.2008.16 BAHAN
0.0140 m³ Kayu klas II Rp 3,000,000.00 Rp 42,000.00
0.0036 m³ Kayu klas I Rp 6,750,000.00 Rp 24,300.00
0.2500 kg Paku usuk/reng Rp 15,000.00 Rp 3,750.00
Jumlah (I) Rp 70,050.00
TENAGA
0.1000 Hari Tukang kayu Rp 57,000.00 Rp 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 Rp 600.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 10,975.00
Jumlah (I) + (II) Rp 81,025.00
Over head / Keuntungan 10 % Rp 8,102.50
Rp 89,127.50

1 M² PEK. USUK 5/7 & RENG 2/3 UNTUK GENTENG BETON


SNI 3434.2008.17 BAHAN
0.0140 m³ Kayu klas II Rp 3,000,000.00 Rp 42,000.00
0.0072 m³ Kayu klas I Rp 6,750,000.00 Rp 48,600.00
0.2500 kg Paku usuk/reng Rp 15,000.00 Rp 3,750.00
Jumlah (I) Rp 94,350.00
TENAGA
0.1000 Hari Tukang kayu Rp 57,000.00 Rp 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 Rp 600.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 10,975.00
Jumlah (I) + (II) Rp 105,325.00
Over head / Keuntungan 10 % Rp 10,532.50
Rp 115,857.50
1 M² PEK. USUK LAMA & RENG 2/3 BARU UNTUK GENTENG KODOK
SNI 3434.2008.17a BAHAN
0.0036 m³ Kayu klas I Rp 6,750,000.00 Rp 24,300.00
0.2500 kg Paku usuk/reng Rp 15,000.00 Rp 3,750.00
Jumlah (I) Rp 28,050.00
TENAGA
0.1000 Hari Tukang kayu Rp 57,000.00 Rp 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 Rp 600.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 10,975.00
Jumlah (I) + (II) Rp 39,025.00
Over head / Keuntungan 10 % Rp 3,902.50
Rp 42,927.50

1 M² PAS. RANGKA ATAP SIRAP


SNI 3434.2008.18 BAHAN
0.1650 m³ Kayu klas II Rp 3,000,000.00 Rp 495,000.00
0.2000 kg Paku usuk/reng Rp 15,000.00 Rp 3,000.00
Jumlah (I) Rp 498,000.00
TENAGA
0.1200 Hari Tukang kayu Rp 57,000.00 Rp 6,840.00
0.0120 Hari Kepala tukang kayu Rp 60,000.00 Rp 720.00
0.1200 Hari Pekerja Rp 44,000.00 Rp 5,280.00
0.0060 Hari Mandor Rp 55,000.00 Rp 330.00
Jumlah (II) Rp 13,170.00
Jumlah (I) + (II) Rp 511,170.00
Over head / Keuntungan 10 % Rp 51,117.00
Rp 562,287.00

1 M² PASANG RANGKA LANGIT-LANGIT (50x100)cm, KAYU KELAS II ATAU III


SNI 3434.2008.19 BAHAN
0.0154 m³ Kayu klas II Rp 3,000,000.00 Rp 46,200.00
0.2000 kg Paku usuk/reng Rp 15,000.00 Rp 3,000.00
Jumlah (I) Rp 49,200.00
TENAGA
0.3000 Hari Tukang kayu Rp 57,000.00 Rp 17,100.00
0.0300 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,800.00
0.1500 Hari Pekerja Rp 44,000.00 Rp 6,600.00
0.0750 Hari Mandor Rp 55,000.00 Rp 4,125.00
Jumlah (II) Rp 29,625.00
Jumlah (I) + (II) Rp 78,825.00
Over head / Keuntungan 10 % Rp 7,882.50
Rp 86,707.50

1 M² PASANG RANGKA LANGIT-LANGIT (60x60)cm, KAYU KELAS II ATAU III


SNI 3434.2008.20 BAHAN
0.0163 m³ Kayu klas II Rp 3,000,000.00 Rp 48,900.00
0.2500 kg Paku usuk/reng Rp 15,000.00 Rp 3,750.00
Jumlah (I) Rp 52,650.00
TENAGA
0.3000 Hari Tukang kayu Rp 57,000.00 Rp 17,100.00
0.0300 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,800.00
0.2000 Hari Pekerja Rp 44,000.00 Rp 8,800.00
0.0100 Hari Mandor Rp 55,000.00 Rp 550.00
Jumlah (II) Rp 28,250.00
Jumlah (I) + (II) Rp 80,900.00
Over head / Keuntungan 10 % Rp 8,090.00
Rp 88,990.00

1 M¹ PAS. PAPAN LIST PLANK KAYU KLAS I UK. 3/20 KAYU KLAS I ATAU II
SNI 3434.2008.21 BAHAN
0.0108 m³ Papan kayu kls II Rp 3,000,000.00 Rp 32,400.00
0.1000 kg Paku usuk/reng Rp 15,000.00 Rp 1,500.00
Jumlah (I) Rp 33,900.00
TENAGA
0.2000 Hari Tukang kayu Rp 57,000.00 Rp 11,400.00
0.0250 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,500.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 17,575.00
Jumlah (I) + (II) Rp 51,475.00
Over head / Keuntungan 10 % Rp 5,147.50
Rp 56,622.50
1 M¹ PAS. PAPAN LIST PLANK KAYU KLAS I UK. 3/30 KAYU KLAS I ATAU II
SNI 3434.2008.22 BAHAN
0.0110 m³ Papan kayu kls I Rp 6,750,000.00 Rp 74,250.00
0.0500 kg Paku usuk/reng Rp 15,000.00 Rp 750.00
Jumlah (I) Rp 75,000.00
TENAGA
0.2000 Hari Tukang kayu Rp 57,000.00 Rp 11,400.00
0.0200 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,200.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 17,275.00
Jumlah (I) + (II) Rp 92,275.00
Over head / Keuntungan 10 % Rp 9,227.50
Rp 101,502.50

1 M² PAS. RANGKA DINDING PEMISAH (60 x 120) KAYU KLAS II ATAU III
SNI 3434.2008.23 BAHAN
0.0280 m³ Kayu klas II Rp 3,000,000.00 Rp 84,000.00
0.1500 kg Paku usuk/reng Rp 15,000.00 Rp 2,250.00
Jumlah (I) Rp 86,250.00
TENAGA
0.4500 Hari Tukang kayu Rp 57,000.00 Rp 25,650.00
0.0450 Hari Kepala tukang kayu Rp 60,000.00 Rp 2,700.00
0.1500 Hari Pekerja Rp 44,000.00 Rp 6,600.00
0.0080 Hari Mandor Rp 55,000.00 Rp 440.00
Jumlah (II) Rp 35,390.00
Jumlah (I) + (II) Rp 121,640.00
Over head / Keuntungan 10 % Rp 12,164.00
Rp 133,804.00

1 M² PAS. DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KLAS II


SNI 3434.2008.24 BAHAN
0.0280 m³ Kayu klas II Rp 3,000,000.00 Rp 84,000.00
0.1500 kg Paku usuk/reng Rp 15,000.00 Rp 2,250.00
0.8600 lbr Teakwood 4 mm Rp 112,500.00 Rp 96,750.00
0.5600 kg Lem kayu Rp 16,920.00 Rp 9,475.20
Jumlah (I) Rp 192,475.20
TENAGA
0.4500 Hari Tukang kayu Rp 57,000.00 Rp 25,650.00
0.0450 Hari Kepala tukang kayu Rp 60,000.00 Rp 2,700.00
0.1500 Hari Pekerja Rp 44,000.00 Rp 6,600.00
0.0080 Hari Mandor Rp 55,000.00 Rp 440.00
Jumlah (II) Rp 35,390.00
Jumlah (I) + (II) Rp 227,865.20
Over head / Keuntungan 10 % Rp 22,786.52
Rp 250,651.72

1 M² PAS. DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KLAS II


SNI 3434.2008.25 BAHAN
0.0280 m³ Kayu klas II Rp 3,000,000.00 Rp 84,000.00
0.1500 kg Paku usuk/reng Rp 15,000.00 Rp 2,250.00
0.8600 lbr Playwood 4 mm Rp 112,500.00 Rp 96,750.00
0.5600 kg Lem kayu Rp 16,920.00 Rp 9,475.20
Jumlah (I) Rp 192,475.20
TENAGA
0.6000 Hari Tukang kayu Rp 57,000.00 Rp 34,200.00
0.0600 Hari Kepala tukang kayu Rp 60,000.00 Rp 3,600.00
0.2000 Hari Pekerja Rp 44,000.00 Rp 8,800.00
0.0100 Hari Mandor Rp 55,000.00 Rp 550.00
Jumlah (II) Rp 47,150.00
Jumlah (I) + (II) Rp 239,625.20
Over head / Keuntungan 10 % Rp 23,962.52
Rp 263,587.72

1 M² PAS. DINDING LAMBRIZIRING PAPAN KAYU KLAS I


SNI 3434.2008.26 BAHAN
0.0070 m³ Papan kayu kls I Rp 6,750,000.00 Rp 47,250.00
0.1000 kg Paku usuk/reng Rp 15,000.00 Rp 1,500.00
0.1500 dos Paku sekrup Rp 9,900.00 Rp 1,485.00
Jumlah (I) Rp 50,235.00
TENAGA
1.8000 Hari Tukang kayu Rp 57,000.00 Rp 102,600.00
0.1800 Hari Kepala tukang kayu Rp 60,000.00 Rp 10,800.00
0.6000 Hari Pekerja Rp 44,000.00 Rp 26,400.00
0.0300 Hari Mandor Rp 55,000.00 Rp 1,650.00
Jumlah (II) Rp 141,450.00
Jumlah (I) + (II) Rp 191,685.00
Over head / Keuntungan 10 % Rp 19,168.50
Rp 210,853.50

H. PEKERJAAN PENUTUP ATAP


1 M² PEKERJAAN ATAP GENTENG KODOK
SNI 03.3436.2002.2 BAHAN
25.0000 bh Genteng press kodok dicat Rp 1,530.00 Rp 38,250.00
Jumlah (I) Rp 38,250.00
TENAGA
0.0750 Hari Tukang kayu Rp 57,000.00 Rp 4,275.00
0.0075 Hari Kepala tukang kayu Rp 60,000.00 Rp 450.00
0.1500 Hari Pekerja Rp 44,000.00 Rp 6,600.00
0.0080 Hari Mandor Rp 55,000.00 Rp 440.00
Jumlah (II) Rp 11,765.00
Jumlah (I) + (II) Rp 50,015.00
Over head / Keuntungan 10 % Rp 5,001.50
Rp 55,016.50

1 M² PEKERJAAN PASANGAN ATAP GENTENG LAMA


SNI 03.3436.2002.1a 0.0750 Hari Tukang kayu Rp 57,000.00Rp 4,275.00
0.0075 Hari Kepala tukang kayu Rp 60,000.00Rp 450.00
0.1500 Hari Pekerja Rp 44,000.00Rp 6,600.00
0.0075 Hari Mandor Rp 55,000.00Rp 412.50
Jumlah Rp 11,737.50
Over head / Keuntungan 10 % Rp 1,173.75
Rp 12,911.25

1 M¹ PEKERJAAN BUBUNGAN GENTENG KODOK


SNI 03.3436.2002.5 BAHAN
5.0000 bh Bubungan Rp 3,150.00 Rp 15,750.00
8.0000 kg Semen Rp 1,000.00 Rp 8,000.00
0.0320 m³ Pasir pasang Rp 80,000.00 Rp 2,560.00
Jumlah (I) Rp 26,310.00
TENAGA
0.2000 Hari Tukang batu Rp 57,000.00 Rp 11,400.00
0.0200 Hari Kepala tukang batu Rp 60,000.00 Rp 1,200.00
0.4000 Hari Pekerja Rp 44,000.00 Rp 17,600.00
0.0020 Hari Mandor Rp 55,000.00 Rp 110.00
Jumlah (II) Rp 30,310.00
Jumlah (I) + (II) Rp 56,620.00
Over head / Keuntungan 10 % Rp 5,662.00
Rp 62,282.00

1 M² PEKERJAAN ATAP GENTENG BETON


SNI 03.3436.2002.30 BAHAN
11.0000 bh Genteng beton Rp 4,500.00 Rp 49,500.00
0.0300 kg Paku 4-6 cm Rp 15,000.00 Rp 450.00
Jumlah (I) Rp 49,950.00
TENAGA
0.1000 Hari Tukang kayu Rp 57,000.00 Rp 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 Rp 600.00
0.2000 Hari Pekerja Rp 44,000.00 Rp 8,800.00
0.0100 Hari Mandor Rp 55,000.00 Rp 550.00
Jumlah (II) Rp 15,650.00
Jumlah (I) + (II) Rp 65,600.00
Over head / Keuntungan 10 % Rp 6,560.00
Rp 72,160.00

SNI 1 M² PEKERJAAN ATAP GENTENG BETON LAMA


03.3436.2002.30a BAHAN
bh Genteng beton Rp 4,500.00 Rp -
0.0300 kg Paku 4-6 cm Rp 15,000.00 Rp 450.00
Jumlah (I) Rp 450.00
TENAGA
0.1000 Hari Tukang kayu Rp 57,000.00 Rp 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 Rp 600.00
0.2000 Hari Pekerja Rp 44,000.00 Rp 8,800.00
0.0100 Hari Mandor Rp 55,000.00 Rp 550.00
Jumlah (II) Rp 15,650.00
Jumlah (I) + (II) Rp 16,100.00
Over head / Keuntungan 10 % Rp 1,610.00
Rp 17,710.00

1 M² PEKERJAAN BUBUNGAN ATAP GENTENG BETON


SNI 03.3436.2002.34 BAHAN
3.5000 bh Bubungan Genteng beton Rp 5,850.00 Rp 20,475.00
10.8000 kg Semen Rp 1,000.00 Rp 10,800.00
0.0320 m³ Pasir pasang Rp 80,000.00 Rp 2,560.00
0.0500 kg Paku 4-6 cm Rp 15,000.00 Rp 750.00
1.0000 kg Semen warna Rp 9,000.00 Rp 9,000.00
Jumlah (I) Rp 33,835.00
TENAGA
0.2000 Hari Tukang kayu Rp 57,000.00 Rp 11,400.00
0.0200 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,200.00
0.4000 Hari Pekerja Rp 44,000.00 Rp 17,600.00
0.0200 Hari Mandor Rp 55,000.00 Rp 1,100.00
Jumlah (II) Rp 31,300.00
Jumlah (I) + (II) Rp 65,135.00
Over head / Keuntungan 10 % Rp 6,513.50
Rp 71,648.50

1 M² PEKERJAAN ATAP SENG GELOMBANG bjls 30


SNI 03.3436.2002.38 BAHAN
0.7000 lbr Seng gelombang Bjls 25 Rp 54,000.00 Rp 37,800.00
0.0200 kg Paku seng Rp 18,000.00 Rp 360.00
Jumlah (I) Rp 38,160.00
TENAGA
0.0600 Hari Tukang kayu Rp 57,000.00 Rp 3,420.00
0.0060 Hari Kepala tukang kayu Rp 60,000.00 Rp 360.00
0.1200 Hari Pekerja Rp 44,000.00 Rp 5,280.00
0.0060 Hari Mandor Rp 55,000.00 Rp 330.00
Jumlah (II) Rp 9,390.00
Jumlah (I) + (II) Rp 47,550.00
Over head / Keuntungan 10 % Rp 4,755.00
Rp 52,305.00

1 M¹ PEKERJAAN BUBUNGAN SENG PLAT BJLS 30


SNI 03.3436.2002.39 BAHAN
0.3000 lbr Seng plat Bjls 30 Rp 76,500.00 Rp 22,950.00
0.0400 kg Paku seng Rp 18,000.00 Rp 720.00
Jumlah (I) Rp 23,670.00
TENAGA
0.0700 Hari Tukang kayu Rp 57,000.00 Rp 3,990.00
0.0080 Hari Kepala tukang kayu Rp 60,000.00 Rp 480.00
0.1500 Hari Pekerja Rp 44,000.00 Rp 6,600.00
0.0060 Hari Mandor Rp 55,000.00 Rp 330.00
Jumlah (II) Rp 11,400.00
Jumlah (I) + (II) Rp 35,070.00
Over head / Keuntungan 10 % Rp 3,507.00
Rp 38,577.00

1 M¹ PEKERJAAN TALANG MIRING


SNI 03.3436.2002.40 BAHAN
0.5000 lbr Seng plat Bjls 30 Rp 76,500.00 Rp 38,250.00
0.0150 kg Paku usuk/reng Rp 15,000.00 Rp 225.00
0.0132 m³ Papan kayu kls II Rp 3,000,000.00 Rp 39,600.00
0.0190 kg Meny besi Rp 23,400.00 Rp 444.60
Jumlah (I) Rp 78,519.60
TENAGA
0.4000 Hari Tukang kayu Rp 57,000.00 Rp 22,800.00
0.0250 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,500.00
0.0400 Hari Pekerja Rp 44,000.00 Rp 1,760.00
0.0013 Hari Mandor Rp 55,000.00 Rp 68.75
Jumlah (II) Rp 26,128.75
Jumlah (I) + (II) Rp 104,648.35
Over head / Keuntungan 10 % Rp 10,464.84
Rp 115,113.19
I. PEKERJAAN BESI DAN ALUMINIUM
SNI 7393-2008.1 1 KG MEMASANG BESI PROFIL
BAHAN
1.1500 kg Besi profil siku ( EX KS ) Rp 627,750.00 Rp 721,912.50
Jumlah (I) Rp 721,912.50
TENAGA
0.0600 Hari Tukang las Rp 57,000.00 Rp 3,420.00
0.0060 Hari Kepala tukang kayu Rp 60,000.00 Rp 360.00
0.0600 Hari Pekerja Rp 44,000.00 Rp 2,640.00
0.0030 Hari Mandor Rp 55,000.00 Rp 165.00
Jumlah (II) Rp 6,585.00
Jumlah (I) + (II) Rp 728,497.50
Over head / Keuntungan 10 % Rp 72,849.75
Rp 801,347.25

SNI 7393-2008.2 1 KG MEMASANG RANGKA KUDA-KUDA BAJA IWF


BAHAN
1.1500 kg Besi Baja IWF Rp 7,290.00 Rp 8,383.50
Jumlah (I) Rp 8,383.50
TENAGA
0.0600 Hari Tukang las Rp 57,000.00 Rp 3,420.00
0.0060 Hari Kepala tukang kayu Rp 60,000.00 Rp 360.00
0.0600 Hari Pekerja Rp 44,000.00 Rp 2,640.00
0.0030 Hari Mandor Rp 55,000.00 Rp 165.00
Jumlah (II) Rp 6,585.00
Jumlah (I) + (II) Rp 14,968.50
Over head / Keuntungan 10 % Rp 1,496.85
Rp 16,465.35

SNI 7393-2008.3 100 KG MENGERJAKAN PERAKITAN


BAHAN
1.0000 ltr Solar Rp 4,050.00 Rp 4,050.00
0.1000 ltr Minyak begesting Rp 3,150.00 Rp 315.00
Jumlah (I) Rp 4,365.00
TENAGA
0.1000 Hari Tukang besi Rp 57,000.00 Rp 5,700.00
0.0010 Hari Kepala tukang besi Rp 60,000.00 Rp 60.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
0.8000 Jam Sewa alat Rp 100,000.00 Rp 80,000.00
Jumlah (II) Rp 90,435.00
Jumlah (I) + (II) Rp 94,800.00
Over head / Keuntungan 10 % Rp 9,480.00
Rp 104,280.00

SNI 7393-2008.4 1 m2 PEKERJAAN PINTU BESI PLAT BAJA T=2 MM RANGKAP ,RANGKA BAJA SIKU
BAHAN
15.0000 kg Besi Siku Rp 36,450.00 Rp 546,750.00
32.8000 kg Besi plat Rp 16,200.00 Rp 531,360.00
0.0500 kg Kawat las Rp 22,500.00 Rp 1,125.00
Jumlah (I) Rp 1,079,235.00
TENAGA
1.0500 Hari Tukang las Rp 57,000.00 Rp 59,850.00
0.1050 Hari Kepala tukang besi Rp 60,000.00 Rp 6,300.00
1.0500 Hari Pekerja Rp 44,000.00 Rp 46,200.00
0.0520 Hari Mandor Rp 55,000.00 Rp 2,860.00
Jumlah (II) Rp 115,210.00
Jumlah (I) + (II) Rp 1,194,445.00
Over head / Keuntungan 10 % Rp 119,444.50
Rp 1,313,889.50

SNI 7393-2008.5 10 CM MENGERJAKAN PENGELASAN DENGAN LAS LISTRIK


BAHAN
0.3000 ltr Solar Rp 4,050.00 Rp 1,215.00
0.0400 ltr Minyak begesting Rp 3,150.00 Rp 126.00
0.4000 kg Kawat las Rp 22,500.00 Rp 9,000.00
Jumlah (I) Rp 10,341.00
TENAGA
0.0200 Hari Tukang besi Rp 57,000.00 Rp 1,140.00
0.0020 Hari Kepala tukang besi Rp 60,000.00 Rp 120.00
0.0400 Hari Pekerja Rp 44,000.00 Rp 1,760.00
0.0020 Hari Mandor Rp 55,000.00 Rp 110.00
0.1700 Jam Sewa alat Rp 100,000.00 Rp 17,000.00
Jumlah (II) Rp 20,130.00
Jumlah (I) + (II) Rp 30,471.00
Over head / Keuntungan 10 % Rp 3,047.10
Rp 33,518.10
SNI 7393-2008.7 1M2 MENGERJAKAN PINTU ROLLING DOOR BESI
BAHAN
1.0000 m2 Pintu besi gulung Rp 112,500.00 Rp 112,500.00
Jumlah (I) Rp 112,500.00
TENAGA
1.2000 Hari Tukang las Rp 57,000.00 Rp 68,400.00
0.1200 Hari Kepala tukang las Rp 60,000.00 Rp 7,200.00
1.2000 Hari Pekerja Rp 44,000.00 Rp 52,800.00
0.0060 Hari Mandor Rp 55,000.00 Rp 330.00
Jumlah (II) Rp 128,730.00
Jumlah (I) + (II) Rp 241,230.00
Over head / Keuntungan 10 % Rp 24,123.00
Rp 265,353.00

SNI 7393-2008.8 1M2 MENGERJAKAN PINTU LIPAT (FOLDING DOOR) BAHAN PLASTIK/PVC
BAHAN
1.0000 m2 Pintu lipat Rp 112,500.00 Rp 112,500.00
Jumlah (I) Rp 112,500.00
TENAGA
0.4400 Hari Tukang las Rp 57,000.00 Rp 25,080.00
0.0440 Hari Kepala tukang las Rp 60,000.00 Rp 2,640.00
0.4400 Hari Pekerja Rp 44,000.00 Rp 19,360.00
0.0220 Hari Mandor Rp 55,000.00 Rp 1,210.00
Jumlah (II) Rp 48,290.00
Jumlah (I) + (II) Rp 160,790.00
Over head / Keuntungan 10 % Rp 16,079.00
Rp 176,869.00

SNI 7393-2008.9 1M2 MENGERJAKAN SUNSCREEN ALLUMINIUM


BAHAN
1.0000 m2 Sunscreen Alluminium Rp 90,000.00 Rp 90,000.00
Jumlah (I) Rp 90,000.00
TENAGA
0.8000 Hari Tukang alumunium Rp 57,000.00 Rp 45,600.00
0.0800 Hari Kepala tukang alumunium Rp 60,000.00 Rp 4,800.00
0.0800 Hari Pekerja Rp 44,000.00 Rp 3,520.00
0.0040 Hari Mandor Rp 55,000.00 Rp 220.00
Jumlah (II) Rp 54,140.00
Jumlah (I) + (II) Rp 144,140.00
Over head / Keuntungan 10 % Rp 14,414.00
Rp 158,554.00

SNI 7393-2008.10 1M2 MEMASANG ROLLING DOOR ALLUMINIUM


BAHAN
1.0000 m2 Rolling door Alluminium Rp 135,000.00 Rp 135,000.00
Jumlah (I) Rp 135,000.00
TENAGA
1.0000 Hari Tukang alumunium Rp 57,000.00 Rp 57,000.00
0.1000 Hari Kepala tukang alumunium Rp 60,000.00 Rp 6,000.00
1.0000 Hari Pekerja Rp 44,000.00 Rp 44,000.00
0.0500 Hari Mandor Rp 55,000.00 Rp 2,750.00
Jumlah (II) Rp 109,750.00
Jumlah (I) + (II) Rp 244,750.00
Over head / Keuntungan 10 % Rp 24,475.00
Rp 269,225.00

SNI 7393-2008.11 1M MEMASANG KUSEN PNTU ALLUMINIUM


BAHAN
1.1000 m2 Rolling door Alluminium Rp 135,000.00 Rp 148,500.00
2.0000 dos Paku sekrup Rp 9,900.00 Rp 19,800.00
0.0600 tube Sealant Rp 10,800.00 Rp 648.00
Jumlah (I) Rp 168,948.00
TENAGA
0.0430 Hari Tukang alumunium Rp 57,000.00 Rp 2,451.00
0.0043 Hari Kepala tukang alumunium Rp 60,000.00 Rp 258.00
0.0430 Hari Pekerja Rp 44,000.00 Rp 1,892.00
0.0021 Hari Mandor Rp 55,000.00 Rp 115.50
Jumlah (II) Rp 4,716.50
Jumlah (I) + (II) Rp 173,664.50
Over head / Keuntungan 10 % Rp 17,366.45
Rp 191,030.95
SNI 7393-2008.12 1 M2 MEMASANG PINTU ALLUMINIUM STRIP LEBAR 8 CM
BAHAN
4.4000 m' Profil Alluminium Rp 22,500.00 Rp 99,000.00
14.6000 m¹ Aluminium strip Rp 22,680.00 Rp 331,128.00
Jumlah (I) Rp 430,128.00
TENAGA
0.0850 Hari Tukang alumunium Rp 57,000.00 Rp 4,845.00
0.0085 Hari Kepala tukang alumunium Rp 60,000.00 Rp 510.00
0.0850 Hari Pekerja Rp 44,000.00 Rp 3,740.00
0.0042 Hari Mandor Rp 55,000.00 Rp 231.00
Jumlah (II) Rp 9,326.00
Jumlah (I) + (II) Rp 439,454.00
Over head / Keuntungan 10 % Rp 43,945.40
Rp 483,399.40

SNI 7393-2008.13 1 M2 MEMASANG PINTU KACA RANGK ALUMINIUM


BAHAN
4.4000 m Pintu Alluminium Rp 225,000.00 Rp 990,000.00
4.5000 m Profil Kaca Rp 63,000.00 Rp 283,500.00
0.2700 tube Sealant Rp 10,800.00 Rp 2,916.00
Jumlah (I) Rp 1,276,416.00
TENAGA
0.0850 Hari Tukang alumunium Rp 57,000.00 Rp 4,845.00
0.0090 Hari Kepala tukang alumunium Rp 60,000.00 Rp 540.00
0.0850 Hari Pekerja Rp 44,000.00 Rp 3,740.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 9,400.00
Jumlah (I) + (II) Rp 1,285,816.00
Over head / Keuntungan 10 % Rp 128,581.60
Rp 1,414,397.60

SNI 7393-2008.15 1 M2 MEMASANG TRALI BESI STRIP (2 x 3) MM


BAHAN
6.1770 kg Besi strip Rp 13,500.00 Rp 83,389.50
27.0800 cm Pengelasan Rp 33,518.10 Rp 907,670.15
Jumlah (I) Rp 991,059.65
TENAGA
1.6700 Hari Tukang las Rp 57,000.00 Rp 95,190.00
0.1670 Hari Kepala tukang las Rp 60,000.00 Rp 10,020.00
1.6700 Hari Pekerja Rp 44,000.00 Rp 73,480.00
0.0830 Hari Mandor Rp 55,000.00 Rp 4,565.00
Jumlah (II) Rp 183,255.00
Jumlah (I) + (II) Rp 1,174,314.65
Over head / Keuntungan 10 % Rp 117,431.46
Rp 1,291,746.11

SNI 7393-2008.16 1 M2 MEMASANG KAWAT NYAMUK


BAHAN
1.1000 m2 Kawat Nyamuk Besi Rp 18,000.00 Rp 19,800.00
11.1100 cm Pengelasan Rp 33,518.10 Rp 372,386.09
1.7160 kg Besi strip Rp 13,500.00 Rp 23,166.00
Jumlah (I) Rp 415,352.09
TENAGA
0.1000 Hari Tukang las Rp 57,000.00 Rp 5,700.00
0.0010 Hari Kepala tukang las Rp 60,000.00 Rp 60.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 10,435.00
Jumlah (I) + (II) Rp 425,787.09
Over head / Keuntungan 10 % Rp 42,578.71
Rp 468,365.80

SNI 7393-2008.17 1 M2 MEMASANG JENDELA NAKO DAN TRASLIS


BAHAN
1.1000 m2 Jendela nako + kaca 5 mm Rp 135,000.00 Rp 148,500.00
10.0000 dos Paku sekrup Rp 9,900.00 Rp 99,000.00
7.0000 kg Besi strip Rp 13,500.00 Rp 94,500.00
Jumlah (I) Rp 342,000.00
TENAGA
0.2000 Hari Tukang kayu Rp 57,000.00 Rp 11,400.00
0.0020 Hari Kepala tukang kayu Rp 60,000.00 Rp 120.00
0.2000 Hari Pekerja Rp 44,000.00 Rp 8,800.00
0.0010 Hari Mandor Rp 55,000.00 Rp 55.00
Jumlah (II) Rp 20,375.00
Jumlah (I) + (II) Rp 362,375.00
Over head / Keuntungan 10 % Rp 36,237.50
Rp 398,612.50

SNI 7393-2008.18 1 M1 MEMASANG TALANG DATAR/JURAI SENG BJLS 28 LEBAR 90 CM


BAHAN
1.0500 lbr Seng plat Bjls 25 Rp 67,500.00 Rp 70,875.00
0.0150 kg Paku 1-3 cm Rp 15,000.00 Rp 225.00
0.0190 m³ Papan kayu kls II Rp 3,000,000.00 Rp 57,000.00
Jumlah (I) Rp 128,100.00
TENAGA
0.4000 Hari Tukang kayu Rp 57,000.00 Rp 22,800.00
0.0250 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,500.00
0.2000 Hari Pekerja Rp 44,000.00 Rp 8,800.00
0.0100 Hari Mandor Rp 55,000.00 Rp 550.00
Jumlah (II) Rp 33,650.00
Jumlah (I) + (II) Rp 161,750.00
Over head / Keuntungan 10 % Rp 16,175.00
Rp 177,925.00

SNI 7393-2008.19 1 M1 MEMASANG TALANG 1/2 LINGKARAN D-15 CM, SENG PLAT BJLS 30 LEBAR 45 CM
BAHAN
1.0500 lbr Seng plat Bjls 30 Rp 76,500.00 Rp 80,325.00
0.0100 dos Paku sekrup Rp 9,900.00 Rp 99.00
0.5000 kg Besi strip Rp 13,500.00 Rp 6,750.00
Jumlah (I) Rp 87,174.00
TENAGA
0.3000 Hari Tukang kayu Rp 57,000.00 Rp 17,100.00
0.0300 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,800.00
0.1500 Hari Pekerja Rp 44,000.00 Rp 6,600.00
0.0080 Hari Mandor Rp 55,000.00 Rp 440.00
Jumlah (II) Rp 25,940.00
Jumlah (I) + (II) Rp 113,114.00
Over head / Keuntungan 10 % Rp 11,311.40
Rp 124,425.40

J. PEKERJAAN PLAFOND/LANGIT - LANGIT

SNI 2839.2008.1 1 M² MEMASANG PLAFOND ASBES SEMEN, TEBAL 4 MM, 5MM DAN 6 MM
BAHAN
1.1000 lbr Asbes Gelombang Besar 1 x 2,5 m Rp 94,500.00 Rp 103,950.00
0.0100 kg Paku asbes Rp 20,250.00 Rp 202.50
Jumlah (I) Rp 104,152.50
TENAGA
0.0700 Hari Tukang kayu Rp 57,000.00 Rp 3,990.00
0.0070 Hari Kepala tukang kayu Rp 60,000.00 Rp 420.00
0.0300 Hari Pekerja Rp 44,000.00 Rp 1,320.00
0.0040 Hari Mandor Rp 55,000.00 Rp 220.00
Jumlah (II) Rp 5,950.00
Jumlah (I) + (II) Rp 110,102.50
Over head / Keuntungan 10 % Rp 11,010.25
Rp 121,112.75

SNI 2839.2008.5 1 M² MEMASANG PLAFOND CALSIBOARD


BAHAN
0.3750 lbr Calsiboard 120x240x3,5 mm Rp 60,300.00 Rp 22,612.50
0.0300 kg Paku khusus calsiboard Rp 22,500.00 Rp 675.00
Jumlah (I) Rp 23,287.50
TENAGA
0.1000 Hari Tukang kayu Rp 57,000.00 Rp 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 Rp 600.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 10,975.00
Jumlah (I) + (II) Rp 34,262.50
Over head / Keuntungan 10 % Rp 3,426.25
Rp 37,688.75
SNI 2839.2008.5a 1 M² MEMASANG PLAFOND CALSIBOARD + RANGKA KAYU
BAHAN
0.0163 m³ Kayu klas II Rp 3,000,000.00 Rp 48,900.00
0.2500 kg Paku usuk/reng Rp 15,000.00 Rp 3,750.00
0.1100 kg Paku khusus calsiboard Rp 22,500.00 Rp 2,475.00
0.3600 lbr Kalsiboard 4,5 mm Rp 60,300.00 Rp 21,708.00
Jumlah (I) Rp 76,833.00
TENAGA
0.4200 Hari Tukang kayu Rp 57,000.00 Rp 23,940.00
0.0420 Hari Kepala tukang kayu Rp 60,000.00 Rp 2,520.00
0.2600 Hari Pekerja Rp 44,000.00 Rp 11,440.00
0.0130 Hari Mandor Rp 55,000.00 Rp 715.00
Jumlah (II) Rp 38,615.00
Jumlah (I) + (II) Rp 115,448.00
Over head / Keuntungan 10 % Rp 11,544.80
Rp 126,992.80

SNI 2839.2008.5b 1 M² MEMASANG LAPISAN CALSIBOARD + RANGKA LAMA TETAP


BAHAN
0.1100 kg Paku khusus calsiboard Rp 22,500.00 Rp 2,475.00
0.3600 lbr Kalsiboard 4,5 mm Rp 60,300.00 Rp 21,708.00
Jumlah (I) Rp 24,183.00
TENAGA
0.2100 Hari Tukang kayu Rp 57,000.00 Rp 11,970.00
0.0210 Hari Kepala tukang kayu Rp 60,000.00 Rp 1,260.00
0.1300 Hari Pekerja Rp 44,000.00 Rp 5,720.00
0.0065 Hari Mandor Rp 55,000.00 Rp 357.50
Jumlah (II) Rp 19,307.50
Jumlah (I) + (II) Rp 43,490.50
Over head / Keuntungan 10 % Rp 4,349.05
Rp 47,839.55

SNI 2839.2008.6 1 M² MEMASANG PLAFOND LAMBRIZIRING KAYU, TEBAL 9 MM


BAHAN
0.0150 m³ Papan kayu kls II Rp 3,000,000.00 Rp 45,000.00
0.0100 kg Paku asbes Rp 20,250.00 Rp 202.50
Jumlah (I) Rp 45,202.50
TENAGA
0.8000 Hari Tukang kayu Rp 57,000.00 Rp 45,600.00
0.0800 Hari Kepala tukang kayu Rp 60,000.00 Rp 4,800.00
0.8000 Hari Pekerja Rp 44,000.00 Rp 35,200.00
0.0400 Hari Mandor Rp 55,000.00 Rp 2,200.00
Jumlah (II) Rp 87,800.00
Jumlah (I) + (II) Rp 133,002.50
Over head / Keuntungan 10 % Rp 13,300.25
Rp 146,302.75

SNI 2839.2008.6 1 M² MEMASANG PLAFOND LAMBRIZIRING KAYU, TEBAL 9 MM


BAHAN
0.0150 m³ Papan kayu kls I Rp 6,750,000.00 Rp 101,250.00
0.0100 kg Paku asbes Rp 20,250.00 Rp 202.50
Jumlah (I) Rp 101,452.50
TENAGA
0.8000 Hari Tukang kayu Rp 57,000.00 Rp 45,600.00
0.0800 Hari Kepala tukang kayu Rp 60,000.00 Rp 4,800.00
0.8000 Hari Pekerja Rp 44,000.00 Rp 35,200.00
0.0400 Hari Mandor Rp 55,000.00 Rp 2,200.00
Jumlah (II) Rp 87,800.00
Jumlah (I) + (II) Rp 189,252.50
Over head / Keuntungan 10 % Rp 18,925.25
Rp 208,177.75

SNI 2839.2008.7 1 M² MEMASANG PLAFOND GYPSUM BOARD UKURAN (1200x2400x9) MM


BAHAN
0.3640 lbr Gypsum board Rp 74,430.00 Rp 27,092.52
0.1100 dos Paku sekrup Rp 9,900.00 Rp 1,089.00
Jumlah (I) Rp 28,181.52
TENAGA
0.0500 Hari Tukang kayu Rp 57,000.00 Rp 2,850.00
0.0050 Hari Kepala tukang kayu Rp 60,000.00 Rp 300.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 7,825.00
Jumlah (I) + (II) Rp 36,006.52
Over head / Keuntungan 10 % Rp 3,600.65
Rp 39,607.17
SNI 2839.2008.8 1M¹ PASANG LIST PROFIL PLAFOND GYPSUM
BAHAN
1.0500 m¹ List plafond gypsum C7 Rp 14,895.00 Rp 15,639.75
2.0000 bh Paku piles Rp 360.00 Rp 720.00
Jumlah (I) Rp 16,359.75
TENAGA
0.0500 Hari Tukang gypsum Rp 57,000.00 Rp 2,850.00
0.0050 Hari Kepala tukang gypsum Rp 60,000.00 Rp 300.00
0.1000 Hari Pekerja Rp 44,000.00 Rp 4,400.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 7,825.00
Jumlah (I) + (II) Rp 24,184.75
Over head / Keuntungan 10 % Rp 2,418.48
Rp 26,603.23

SNI 2839.2008.10 1M¹ PASANG LIST PROFIL PLAFOND KAYU


BAHAN
1.0500 m¹ List plafond profil 1x4 cm Rp 3,150.00 Rp 3,307.50
0.0500 kg Paku usuk/reng Rp 15,000.00 Rp 750.00
Jumlah (I) Rp 4,057.50
TENAGA
0.0500 Hari Tukang kayu Rp 57,000.00 Rp 2,850.00
0.0050 Hari Kepala tukang kayu Rp 60,000.00 Rp 300.00
0.0500 Hari Pekerja Rp 44,000.00 Rp 2,200.00
0.0050 Hari Mandor Rp 55,000.00 Rp 275.00
Jumlah (II) Rp 5,625.00
Jumlah (I) + (II) Rp 9,682.50
Over head / Keuntungan 10 % Rp 968.25
Rp 10,650.75

K. PEKERJAAN PENUTUP LANTAI


SNI 7395.2008.35 1 M2PAS. LANTAI KERAMIK 30 x 30 CM CAMP 1PC : 3PS
BAHAN
1.0500 m² Keramik 30 x 30 cm (putih klas menengah) Rp 34,650.00 Rp 36,382.50
10.0000 kg Semen Rp 1,000.00 Rp 10,000.00
1.5000 kg Semen warna Rp 9,000.00 Rp 13,500.00
0.0450 m³ Pasir pasang Rp 80,000.00 Rp 3,600.00
Jumlah (I) Rp 63,482.50
TENAGA
0.3500 Hari Tukang batu Rp 57,000.00 Rp 19,950.00
0.0350 Hari Kepala tukang batu Rp 60,000.00 Rp 2,100.00
0.7000 Hari Pekerja Rp 44,000.00 Rp 30,800.00
0.0350 Hari Mandor Rp 55,000.00 Rp 1,925.00
Jumlah (II) Rp 54,775.00
Jumlah (I) + (II) Rp 118,257.50
Over head / Keuntungan 10 % Rp 11,825.75
Rp 130,083.25

1 M² PAS. KERAMIK LANTAI 40 x 40 CM CAMP 1PC : 2PS


SNI 7395.2008.34a BAHAN
1.0500 m² Keramik 40 x 40 cm (putih klas biasa) Rp 40,000.00 Rp 42,000.00
8.8000 kg Semen Rp 1,000.00 Rp 8,800.00
1.3000 kg Semen warna Rp 9,000.00 Rp 11,700.00
0.0215 m³ Pasir pasang Rp 80,000.00 Rp 1,720.00
Jumlah (I) Rp 64,220.00
TENAGA
0.3500 Hari Tukang batu Rp 57,000.00 Rp 19,950.00
0.0350 Hari Kepala tukang batu Rp 60,000.00 Rp 2,100.00
0.6200 Hari Pekerja Rp 44,000.00 Rp 27,280.00
0.0300 Hari Mandor Rp 55,000.00 Rp 1,650.00
Jumlah (II) Rp 50,980.00
Jumlah (I) + (II) Rp 115,200.00
Over head / Keuntungan 10 % Rp 11,520.00
Rp 126,720.00

SNI 7395.2008.54a 1 M² PAS. KERAMIK LANTAI KM/WC 20 x 20 CM CAMP 1PC : 2PS


BAHAN
1.0000 m² Keramik 20 x 20 cm (motif biasa) Rp 17,000.00 Rp 17,000.00
9.3000 kg Semen Rp 1,000.00 Rp 9,300.00
1.9400 kg Semen warna Rp 9,000.00 Rp 17,460.00
0.0180 m³ Pasir pasang Rp 80,000.00 Rp 1,440.00
Jumlah (I) Rp 45,200.00
TENAGA
0.4500 Hari Tukang batu Rp 57,000.00 Rp 25,650.00
0.0450 Hari K` Rp 60,000.00 Rp 2,700.00
0.9000 Hari Pekerja Rp 44,000.00 Rp 39,600.00
0.0450 Hari Mandor Rp 55,000.00 Rp 2,475.00
Jumlah (II) Rp 70,425.00
Jumlah (I) + (II) Rp 115,625.00
Over head / Keuntungan 10 % Rp 11,562.50
Rp 127,187.50

SNI 7395.2008.54 1 M² PAS. DINDING KERAMIK 20 x 20 CM


BAHAN
1.0000 m² Keramik 20 x 20 cm (motif biasa) Rp 17,000.00 Rp 17,000.00
9.3000 kg Semen Rp 1,000.00 Rp 9,300.00
1.9400 kg Semen warna Rp 9,000.00 Rp 17,460.00
0.0180 m³ Pasir pasang Rp 80,000.00 Rp 1,440.00
Jumlah (I) Rp 45,200.00
TENAGA
0.4500 Hari Tukang batu Rp 57,000.00 Rp 25,650.00
0.0450 Hari Kepala tukang batu Rp 60,000.00 Rp 2,700.00
0.9000 Hari Pekerja Rp 44,000.00 Rp 39,600.00
0.0450 Hari Mandor Rp 55,000.00 Rp 2,475.00
Jumlah (II) Rp 70,425.00
Jumlah (I) + (II) Rp 115,625.00
Over head / Keuntungan 10 % Rp 11,562.50
Rp 127,187.50

SNI 7395.2008.57 1 M² PAS. DINDING BATU PARAS


BAHAN
1.1000 m² Batu paras Rp 112,500.00 Rp 123,750.00
11.7500 kg Semen Rp 1,000.00 Rp 11,750.00
0.0350 m³ Pasir pasang Rp 80,000.00 Rp 2,800.00
Jumlah (I) Rp 138,300.00
TENAGA
0.3500 Hari Tukang batu Rp 57,000.00 Rp 19,950.00
0.0350 Hari Kepala tukang batu Rp 60,000.00 Rp 2,100.00
0.7000 Hari Pekerja Rp 44,000.00 Rp 30,800.00
0.0350 Hari Mandor Rp 55,000.00 Rp 1,925.00
Jumlah (II) Rp 54,775.00
Jumlah (I) + (II) Rp 193,075.00
Over head / Keuntungan 10 % Rp 19,307.50
Rp 212,382.50

SNI 7395.2008.58 1 M² PAS. DINDING BATU TEMPEL


BAHAN
1.1000 m² Batu tempel pola sisir Rp 121,500.00 Rp 133,650.00
11.7500 kg Semen Rp 1,000.00 Rp 11,750.00
0.0350 m³ Pasir pasang Rp 80,000.00 Rp 2,800.00
Jumlah (I) Rp 148,200.00
TENAGA
0.3500 Hari Tukang batu Rp 57,000.00 Rp 19,950.00
0.0350 Hari Kepala tukang batu Rp 60,000.00 Rp 2,100.00
0.7000 Hari Pekerja Rp 44,000.00 Rp 30,800.00
0.0350 Hari Mandor Rp 55,000.00 Rp 1,925.00
Jumlah (II) Rp 54,775.00
Jumlah (I) + (II) Rp 202,975.00
Over head / Keuntungan 10 % Rp 20,297.50
Rp 223,272.50

J.6.41 1 M¹ PAS. KERAMIK PLINT 10 x 40 CM CAMP 1PC : 2PS


BAHAN
2.5000 bh Keramik 10 x 40 cm (motif) Rp 3,650.40 Rp 9,126.00
1.6500 kg Semen Rp 1,000.00 Rp 1,650.00
0.1000 kg Semen warna Rp 9,000.00 Rp 900.00
0.0320 m³ Pasir pasang Rp 80,000.00 Rp 2,560.00
Jumlah (I) Rp 14,236.00
TENAGA
0.0900 Hari Tukang batu Rp 57,000.00 Rp 5,130.00
0.0090 Hari Kepala tukang batu Rp 60,000.00 Rp 540.00
0.0900 Hari Pekerja Rp 44,000.00 Rp 3,960.00
0.0045 Hari Mandor Rp 55,000.00 Rp 247.50
Jumlah (II) Rp 9,877.50
Jumlah (I) + (II) Rp 24,113.50
Over head / Keuntungan 10 % Rp 2,411.35
Rp 26,524.85
J.6.43 1 M² PAS. KERAMIK DINDING 20 x 25 CM CAMP 1PC : 2PS
1.0500 m² Keramik dinding 20 x 25 cm (motif biasa) Rp 38,250.00 40,162.50
9.3000 kg Semen Rp 1,000.00 9,300.00
1.9400 kg Semen warna Rp 9,000.00 17,460.00
0.0180 m³ Pasir pasang Rp 80,000.00 1,440.00
0.4500 Hari Tukang batu Rp 57,000.00 25,650.00
0.0450 Hari Kepala tukang batu Rp 60,000.00 2,700.00
0.6000 Hari Pekerja Rp 44,000.00 26,400.00
0.0300 Hari Mandor Rp 55,000.00 1,650.00
Jumlah 124,762.50
Over head / Keuntungan 10 % 12,476.25
137,238.75
K. PEKERJAAN PENGUNCI & KACA
Pt T-30-2000-C.1. 1 BH PEKERJAAN MEMASANG KUNCI TANAM
1.0000 bh Kunci pintu 2 slaag klas tinggi Rp 257,985.00 257,985.00
0.6000 Hari Tukang kayu Rp 57,000.00 34,200.00
0.0600 Hari Kepala tukang kayu Rp 60,000.00 3,600.00
Jumlah 295,785.00
Over head / Keuntungan 10 % 29,578.50
325,363.50

Pt T-30-2000-C.2. 1 BH PEKERJAAN MEMASANG KUNCI TANAM


1.0000 bh Kunci pintu 2 slaag klas menengah Rp 100,000.00 100,000.00
0.5000 Hari Tukang kayu Rp 57,000.00 28,500.00
0.0500 Hari Kepala tukang kayu Rp 60,000.00 3,000.00
Jumlah 131,500.00
Over head / Keuntungan 10 % 13,150.00
144,650.00

Pt T-30-2000-C.3. 1 BH PEKERJAAN MEMASANG KUNCI SILINDER


1.0000 bh Kunci tanam cylinder Rp 225,000.00 225,000.00
0.6000 Hari Tukang kayu Rp 57,000.00 34,200.00
0.0600 Hari Kepala tukang kayu Rp 60,000.00 3,600.00
Jumlah 262,800.00
Over head / Keuntungan 10 % 26,280.00
289,080.00

Pt T-30-2000-C.4. 1 BH PEKERJAAN MEMASANG ENGSEL PINTU KUALITAS TINGGI


1.0000 bh Engsel pintu klas tinggi Rp 27,270.00 27,270.00
0.1500 Hari Tukang kayu Rp 57,000.00 8,550.00
0.0150 Hari Kepala tukang kayu Rp 60,000.00 900.00
Jumlah 36,720.00
Over head / Keuntungan 10 % 3,672.00
40,392.00

Pt T-30-2000-C.5. 1 BH PEKERJAAN MEMASANG ENGSEL PINTU


1.0000 bh Engsel pintu klas biasa Rp 13,500.00 13,500.00
0.1250 Hari Tukang kayu Rp 57,000.00 7,125.00
0.013 Hari Kepala tukang kayu Rp 60,000.00 750.00
Jumlah 21,375.00
Over head / Keuntungan 10 % 2,137.50
23,512.50

Pt T-30-2000-C.6. 1 BH PEKERJAAN MEMASANG ENGSEL JENDELA


1.0000 Bh Engsel Jendela klas biasa Rp 11,250.00 11,250.00
0.1000 Hari Tukang kayu Rp 57,000.00 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 600.00
Jumlah 17,550.00
Over head / Keuntungan 10 % 1,755.00
19,305.00

Pt T-30-2000-C.7. 1 BH PEKERJAAN MEMASANG KAIT ANGIN


1.0000 bh Kait angin klas menengah Rp 10,125.00 10,125.00
0.1000 Hari Tukang kayu Rp 57,000.00 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 600.00
Jumlah 16,425.00
Over head / Keuntungan 10 % 1,642.50
18,067.50

Pt T-30-2000-C.8. 1 BH PEKERJAAN MEMASANG DOOR CLOSER


1.0000 bh Door Closer Rp 135,000.00 135,000.00
0.2000 Hari Tukang kayu Rp 57,000.00 11,400.00
0.0200 Hari Kepala tukang kayu Rp 60,000.00 1,200.00
Jumlah 147,600.00
Over head / Keuntungan 10 % 14,760.00
162,360.00
Pt T-30-2000-C.11. 1 BH PEKERJAAN MEMASANG GRENDEL TANAM EXPANYOLET
1.0000 bh Expagnolett Rp 49,500.00 49,500.00
0.1000 Hari Tukang kayu Rp 57,000.00 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 600.00
Jumlah 55,800.00
Over head / Keuntungan 10 % 5,580.00
61,380.00

Pt T-30-2000-C.12. 1 BH PEKERJAAN MEMASANG GRENDEL PINTU


1.0000 bh Grendel besar klas menengah Rp 15,750.00 15,750.00
0.1000 Hari Tukang kayu Rp 57,000.00 5,700.00
0.0100 Hari Kepala tukang kayu Rp 60,000.00 600.00
Jumlah 22,050.00
Over head / Keuntungan 10 % 2,205.00
24,255.00

Pt T-30-2000-C.13. 1 M² PEKERJAAN MEMASANG KACA POLOS 3MM


1.1000 m² Kaca bening 3 mm Rp 67,500.00 74,250.00
0.1600 Hari Tukang kayu Rp 57,000.00 9,120.00
0.0160 Hari Kepala tukang kayu Rp 60,000.00 960.00
0.1600 Hari Pekerja Rp 44,000.00 7,040.00
0.00800 Hari Mandor Rp 55,000.00 440.00
Jumlah 91,370.00
Over head / Keuntungan 10 % 9,137.00
100,507.00

Pt T-30-2000-C.14. 1 M² PEKERJAAN MEMASANG KACA 5MM


1.1000 m² Kaca bening 5 mm Rp 90,000.00 99,000.00
0.1600 Hari Tukang kayu Rp 57,000.00 9,120.00
0.0160 Hari Kepala tukang kayu Rp 60,000.00 960.00
0.1600 Hari Pekerja Rp 44,000.00 7,040.00
0.00800 Hari Mandor Rp 55,000.00 440.00
Jumlah 116,120.00
Over head / Keuntungan 10 % 11,612.00
127,732.00

L. PEKERJAAN SANITAIR
L.6.1 1 BH PEKERJAAN MEMASANG JONGKOK PORSELINT
1.0000 Unit Closed jongkok porselint klas menengah Rp 250,000.00 250,000.00
6.0000 kg Semen Rp 1,000.00 6,000.00
0.0010 m³ Pasir pasang Rp 80,000.00 80.00
1.5000 Hari Tukang batu Rp 57,000.00 85,500.00
0.0150 Hari Kepala tukang batu Rp 60,000.00 900.00
1.0000 Hari Pekerja Rp 44,000.00 44,000.00
0.1600 Hari Mandor Rp 55,000.00 8,800.00
Jumlah 395,280.00
Over head / Keuntungan 10 % 39,528.00
434,808.00
L.6.2 1 BH PEKERJAAN MEMASANG DUDUK MONOBLOK
1.0000 Unit Closed duduk monoblok klas menengah Rp 1,350,000.00 1,350,000.00
6% Hk Perlengkapan Rp 1,350,000.00 81,000.00
1.1000 Hari Tukang batu Rp 57,000.00 62,700.00
0.0010 Hari Kepala tukang batu Rp 60,000.00 60.00
3.3000 Hari Pekerja Rp 44,000.00 145,200.00
0.1600 Hari Mandor Rp 55,000.00 8,800.00
Jumlah 1,647,760.00
Over head / Keuntungan 10 % 164,776.00
1,812,536.00
L.6.4 1 BH PEKERJAAN MEMASANG WASHTAFEL
1.0000 Unit Wastafeel +Acecories, kran + Miralset Rp 922,050.00 922,050.00
12% Hk Perlengkapan Rp 922,050.00 110,646.00
6.0000 kg Semen Rp 1,000.00 6,000.00
0.0100 m³ Pasir pasang Rp 80,000.00 800.00
1.4500 Hari Tukang batu Rp 57,000.00 82,650.00
0.1500 Hari Kepala tukang batu Rp 60,000.00 9,000.00
1.2000 Hari Pekerja Rp 44,000.00 52,800.00
0.1000 Hari Mandor Rp 55,000.00 5,500.00
Jumlah 1,189,446.00
Over head / Keuntungan 10 % 118,944.60
1,308,390.60
L.6.5 1 BH PEKERJAAN MEMASANG BAK STAINLESS STEEL
1.0000 Unit Bak stainless steel 2 lobang Rp 405,000.00 405,000.00
0.3000 Hari Tukang batu Rp 57,000.00 17,100.00
0.0300 Hari Kepala tukang batu Rp 60,000.00 1,800.00
0.0300 Hari Pekerja Rp 44,000.00 1,320.00
0.0015 Hari Mandor Rp 55,000.00 82.50
Jumlah 425,302.50
Over head / Keuntungan 10 % 42,530.25
467,832.75
L.6.6 1 BH PEKERJAAN MEMASANG FLOOR DRAIN
1.0000 Unit Floor drain (Avour)/saringan air Rp 27,000.00 27,000.00
0.1000 Hari Tukang pipa Rp 57,000.00 5,700.00
0.0100 Hari Kepala tukang pipa Rp 60,000.00 600.00
0.0100 Hari Pekerja Rp 44,000.00 440.00
0.0050 Hari Mandor Rp 55,000.00 275.00
Jumlah 34,015.00
Over head / Keuntungan 10 % 3,401.50
37,416.50
L.6.7 1 M¹ PEKERJAAN MEMASANG PIPA PVC Ø 1 1/2''
1.2000 m¹ Pipa PVC ø 1 1/2" Rp 36,000.00 43,200.00
35% hk Perlengkapan Rp 36,000.00 12,600.00
0.1080 Hari Tukang pipa Rp 57,000.00 6,156.00
0.0180 Hari Kepala tukang pipa Rp 60,000.00 1,080.00
0.1080 Hari Pekerja Rp 44,000.00 4,752.00
0.0054 Hari Mandor Rp 55,000.00 297.00
Jumlah 68,085.00
Over head / Keuntungan 10 % 6,808.50
74,893.50
L.6.8 1 M¹ PEKERJAAN MEMASANG PIPA PVC Ø 3''
1.2000 m¹ Pipa PVC ø 3" klas tinggi Rp 61,200.00 73,440.00
35% hk Perlengkapan Rp 61,200.00 21,420.00
0.1800 Hari Tukang pipa Rp 57,000.00 10,260.00
0.0180 Hari Kepala tukang pipa Rp 60,000.00 1,080.00
0.1080 Hari Pekerja Rp 44,000.00 4,752.00
0.0054 Hari Mandor Rp 55,000.00 297.00
Jumlah 111,249.00
Over head / Keuntungan 10 % 11,124.90
122,373.90
L.6.9 1 M¹ PEKERJAAN MEMASANG PIPA PVC Ø 4''
1.2000 m¹ Pipa PVC ø 4" Rp 76,000.00 91,200.00
35% hk Perlengkapan Rp 76,000.00 26,600.00
0.0900 Hari Tukang pipa Rp 57,000.00 5,130.00
0.0090 Hari Kepala tukang pipa Rp 60,000.00 540.00
0.0540 Hari Pekerja Rp 44,000.00 2,376.00
0.0070 Hari Mandor Rp 55,000.00 385.00
Jumlah 126,231.00
Over head / Keuntungan 10 % 12,623.10
138,854.10
L.6.10 1 M¹ PEKERJAAN MEMASANG PIPA GI Ø 3/4''
1.1000 m¹ Pipa GI ø 3/4" Rp 40,500.00 44,550.00
35% hk Perlengkapan Rp 40,500.00 14,175.00
0.0900 Hari Tukang pipa Rp 57,000.00 5,130.00
0.0090 Hari Kepala tukang pipa Rp 60,000.00 540.00
0.0540 Hari Pekerja Rp 44,000.00 2,376.00
0.0270 Hari Mandor Rp 55,000.00 1,485.00
Jumlah 68,256.00
Over head / Keuntungan 10 % 6,825.60
75,081.60
L.6.11 1 M¹ PEKERJAAN MEMASANG PIPA GI Ø 1''
1.1000 m¹ Pipa GI ø 1" Rp 31,500.00 34,650.00
35% hk Perlengkapan Rp 31,500.00 11,025.00
0.0900 Hari Tukang pipa Rp 57,000.00 5,130.00
0.0090 Hari Kepala tukang pipa Rp 60,000.00 540.00
0.0540 Hari Pekerja Rp 44,000.00 2,376.00
0.0270 Hari Mandor Rp 55,000.00 1,485.00
Jumlah 51,345.00
Over head / Keuntungan 10 % 5,134.50
56,479.50

M. PEKERJAAN PENGECATAN
Pt T-38-2000-C.1. 1 M² PEK. CAT KAYU
0.050 bh Kape Rp 5,400.00 270.00
0.150 Hari Pekerja Rp 44,000.00 6,600.00
0.0080 Hari Mandor Rp 55,000.00 440.00
Jumlah 7,310.00
Over head / Keuntungan 10 % 731.00
8,041.00
Pt T-38-2000-C.2. 1 M² LAPIS PLAMIR TEMBOK
0.100 kg Plamir Kayu Rp 22,815.00 2,281.50
0.500 lbr Amplas Rp 3,150.00 1,575.00
0.050 bh Kape Rp 5,400.00 270.00
0.020 Hari Pekerja Rp 44,000.00 880.00
0.030 Hari Tukang cat Rp 57,000.00 1,710.00
0.003 Hari Kepala tukang cat Rp 60,000.00 180.00
0.0010 Hari Mandor Rp 55,000.00 55.00
Jumlah 6,951.50
Over head / Keuntungan 10 % 695.15
7,646.65

Pt T-38-2000-C.4. 1 M² PENGECATAN TEMBOK LAMA 2 LAPIS DENGAN KUAS


0.240 kg Cat tembok klas menengah Rp 22,500.00 5,400.00
0.015 bh Kuas cat Rp 7,650.00 114.75
0.060 Hari Pekerja Rp 44,000.00 2,640.00
0.050 Hari Tukang cat Rp 57,000.00 2,850.00
0.005 Hari Kepala tukang cat Rp 60,000.00 300.00
0.0030 Hari Mandor Rp 55,000.00 165.00
Jumlah 11,469.75
Over head / Keuntungan 10 % 1,146.98
12,616.73

Pt T-38-2000-C.5. 1 M² PENGECATAN TEMBOK LAMA 2 LAPIS DENGAN ROLL


0.470 kg Cat tembok klas menengah Rp 22,500.00 10,575.00
0.010 bh Roll cat Rp 13,500.00 135.00
0.040 Hari Pekerja Rp 44,000.00 1,760.00
0.030 Hari Tukang cat Rp 57,000.00 1,710.00
0.003 Hari Kepala tukang cat Rp 60,000.00 180.00
0.0020 Hari Mandor Rp 55,000.00 110.00
Jumlah 14,470.00
Over head / Keuntungan 10 % 1,447.00
15,917.00

Pt T-38-2000-C.6. 1 M² PENGECATAN TEMBOK BARU 2 LAPIS DENGAN KUAS


0.100 kg Plamir tembok Rp 8,100.00 810.00
0.240 kg Cat tembok klas menengah Rp 22,500.00 5,400.00
0.500 lbr Amplas Rp 3,150.00 1,575.00
0.015 bh Kuas cat Rp 7,650.00 114.75
0.050 bh Kape Rp 5,400.00 270.00
0.080 Hari Pekerja Rp 44,000.00 3,520.00
0.060 Hari Tukang cat Rp 57,000.00 3,420.00
0.006 Hari Kepala tukang cat Rp 60,000.00 360.00
0.0060 Hari Mandor Rp 55,000.00 330.00
Jumlah 15,799.75
Over head / Keuntungan 10 % 1,579.98
17,379.73

Pt T-38-2000-C.7. 1 M² PENGECATAN TEMBOK BARU 2 LAPIS DENGAN ROLL


0.100 kg Plamir tembok Rp 8,100.00 810.00
0.470 kg Cat tembok klas menengah Rp 22,500.00 10,575.00
0.500 lbr Amplas Rp 3,150.00 1,575.00
0.010 bh Roll cat Rp 13,500.00 135.00
0.050 bh Kape Rp 5,400.00 270.00
0.060 Hari Pekerja Rp 44,000.00 2,640.00
0.040 Hari Tukang cat Rp 57,000.00 2,280.00
0.004 Hari Kepala tukang cat Rp 60,000.00 240.00
0.0030 Hari Mandor Rp 55,000.00 165.00
Jumlah 18,690.00
Over head / Keuntungan 10 % 1,869.00
20,559.00
Pt T-38-2000-C.12. 1 M² PEK. CAT KAYU (PLAMIR, 1 LAPIS CAT DASAR DAN 2 LAPIS CAT PENUTUP)
0.080 kg Plamir Kayu Rp 22,815.00 1,825.20
0.170 kg Cat kayu klas menengah Rp 38,700.00 6,579.00
0.300 kg Cat kayu klas menengah Rp 38,700.00 11,610.00
0.200 ltr Minyak cat klas menengah Rp 14,850.00 2,970.00
0.020 bh Kuas cat Rp 7,650.00 153.00
1.000 lbr Amplas Rp 3,150.00 3,150.00
0.150 Hari Pekerja Rp 44,000.00 6,600.00
0.150 Hari Tukang cat Rp 57,000.00 8,550.00
0.015 Hari Kepala tukang cat Rp 60,000.00 900.00
0.0080 Hari Mandor Rp 55,000.00 440.00
Jumlah 42,777.20
Over head / Keuntungan 10 % 4,277.72
47,054.92
Pt T-38-2000-C.12a. 1 M² PEK. CAT ULANG KAYU
0.300 kg Cat kayu klas menengah Rp 38,700.00 11,610.00
0.200 ltr Minyak cat klas menengah Rp 14,850.00 2,970.00
0.020 bh Kuas cat Rp 7,650.00 153.00
1.000 lbr Amplas Rp 3,150.00 3,150.00
0.150 Hari Pekerja Rp 44,000.00 6,600.00
0.150 Hari Tukang cat Rp 57,000.00 8,550.00
0.015 Hari Kepala tukang cat Rp 60,000.00 900.00
0.0080 Hari Mandor Rp 55,000.00 440.00
Jumlah 34,373.00
Over head / Keuntungan 10 % 3,437.30
37,810.30

Pt T-38-2000-C.13. 1 M² PEK. CAT GENTENG


0.120 kg Cat genteng Rp 40,500.00 4,860.00
0.180 kg Cat genteng Rp 40,500.00 7,290.00
0.028 Hari Pekerja Rp 44,000.00 1,232.00
0.042 Hari Tukang cat Rp 57,000.00 2,394.00
0.004 Hari Kepala tukang cat Rp 60,000.00 240.00
0.0030 Hari Mandor Rp 55,000.00 165.00
Jumlah 16,181.00
Over head / Keuntungan 10 % 1,618.10
17,799.10

Pt T-38-2000-C.14. 1 M² PELAPISAN BIDANG KAYU DENGAN PELITUR 2 LAPIS


0.100 ltr Wood filer Rp 34,020.00 3,402.00
0.200 ltr Politur Rp 31,230.00 6,246.00
0.020 bh Kuas cat Rp 7,650.00 153.00
1.000 lbr Amplas Rp 3,150.00 3,150.00
0.250 Hari Pekerja Rp 44,000.00 11,000.00
0.250 Hari Tukang cat Rp 57,000.00 14,250.00
0.025 Hari Kepala tukang cat Rp 60,000.00 1,500.00
0.0130 Hari Mandor Rp 55,000.00 715.00
Jumlah 40,416.00
Over head / Keuntungan 10 % 4,041.60
44,457.60

Pt T-38-2000-C.15. 1 M² PELAPISAN BIDANG KAYU DENGAN VERNIS 2 LAPIS


0.300 ltr Vernis Rp 32,940.00 9,882.00
0.020 bh Kuas cat Rp 7,650.00 153.00
0.500 lbr Amplas Rp 3,150.00 1,575.00
0.100 Hari Tukang cat Rp 57,000.00 5,700.00
0.010 Hari Kepala tukang cat Rp 60,000.00 600.00
Jumlah 17,910.00
Over head / Keuntungan 10 % 1,791.00
19,701.00

Pt T-38-2000-C.16. 1 M² PELAPISAN BIDANG KAYU DENGAN RESIDU (TEER)


0.350 ltr Residu/teer Rp 11,250.00 3,937.50
0.020 bh Kuas cat Rp 7,650.00 153.00
0.030 ltr Minyak tanah Rp 10,800.00 324.00
0.100 Hari Tukang cat Rp 57,000.00 5,700.00
0.010 Hari Kepala tukang cat Rp 60,000.00 600.00
Jumlah 10,714.50
Over head / Keuntungan 10 % 1,071.45
11,785.95
RENCANA ANGGARAN BIAYA (RAB)
SATUAN KERJA : BADAN KOORDINASI PENYULUHAN PERTANIAN, PERIKANAN DAN KEHUTANAN PROVINSI NTB
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PEMBANGUNAN LANJUTAN (TAHAP II) ASRAMA UTARA SMKPP NEGERI MATARAM
PAKET PEKERJAAN : PEMBANGUNAN LANJUTAN (TAHAP II) ASRAMA UTARA SMKPP NEGERI MATARAM
LOKASI : JL. TGH LOPAN NO X KM 7 LABUAPI - LOMBOK BARAT.
TAHUN : 2013

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT. KODE ANALISA
(Rp.) (Rp.)
1 2 3 4 5 6 7
PEKERJAAN LANTAI I
I. PEKERJAAN PENDAHULUAN/PERSIAPAN
1 Pengukuran/Pemasangan bouwplank 1.00 Keg Ls 1,200,000.00 1,200,000.00
2 Pembersihan bekas material dan Mobilisasi 1.00 Keg Ls 1,300,000.00 1,300,000.00
JUMLAH 2,500,000.00

II. PEKERJAAN TANAH DAN PASIR


1 Galian tanah pondasi tangga 1.80 m3 SNI 2835.2008.1 37,812.50 68,062.50
2 Urugan tanah peninggian lantai 103.91 m3 SNI 2835.2008.11a 68,585.00 7,126,667.35
JUMLAH 7,194,729.85

III. PEKERJAAN PASANGAN DAN PLESTERAN


1 Pas. Pondasi Batu Kali trap tangga 1PC : 5 PS 9.50 m3 SNI 2836.2008.3 445,384.50 4,231,152.75
2 Pas. Dinding 1/2 Bata 1Pc : 5 Ps 318.25 m2 SNI 6897.2008.10 67,765.50 21,566,370.38
3 Pas. Bata Anak Tangga 1Pc : 3 Ps 8.25 m2 SNI 6897.2008.8 72,484.50 597,997.13
4 Plesteran Dinding 1Pc : 5Ps 510.84 m2 SNI 2837.2008.5 33,773.30 17,252,752.57
5 Plesteran Beton 1Pc : 3Ps 146.84 m2 SNI 2837.2008.3 36,400.10 5,344,990.68
6 Acian Dinding + Acian Beton 696.10 m2 SNI 2837.2008.27 20,790.00 14,471,919.00
7 Pasangan Keramik Lantai dan tangga 40 x 40 165.25 m2 SNI 7395.2008.34a 126,720.00 20,940,480.00
8 Pasangan Dinding Keramik dinding KM/WC 20x40 15.66 m2 SNI 7395.2008.54 127,187.50 1,991,756.25
9 Pasangan Keramik Lantai KM/WC 20x20 9.00 m2 SNI 7395.2008.54a 127,187.50 1,144,687.50
10 Paving Blok segi enam dan pasir Urug 10 cm Kel 62.00 m2 Ls 90,000.00 5,580,000.00
11 Pasangan bata pada pinggir paving blok dalam 20 cm 24.80 m2 SNI 6897.2008.10 67,765.50 1,680,584.40
JUMLAH 94,802,690.66

IV. PEKERJAAN BETON BERTULANG


1 Beton Rabat lantai 8.31 m3 SNI 7394.2008.1 584,893.96 4,860,468.84
2 Pondasi tangga 0.20 m3 SNI 7394.2008.28a 2,750,437.23 550,087.45
3 Beton Kolom K1 30x40 4.86 m3 SNI 7394.2008.30 6,625,652.00 32,200,668.72
4 Beton Kolom K2 30x30 1.82 m3 SNI 7394.2008.30 6,625,652.00 12,058,686.64
5 Beton Kolom K3 10x25 0.44 m3 SNI 7394.2008.30a 3,485,324.02 1,533,542.57
6 Beton Kolom Praktis (Kp) 10x10 0.39 m3 SNI 7394.2008.30a 3,485,324.02 1,359,276.37
7 Beton Balok B1 30x60 5.40 m3 SNI 7394.2008.31 4,804,288.50 25,943,157.90
8 Beton Balok B2 30x50 1.13 m3 SNI 7394.2008.31 4,804,288.50 5,428,846.01
9 Beton Balok B3 30x40 4.20 m3 SNI 7394.2008.31 4,804,288.50 20,178,011.70
10 Beton Balok B4 25x35 3.89 m3 SNI 7394.2008.31 4,804,288.50 18,688,682.27
11 Beton Balok Latai 12x20 0.72 m3 SNI 7394.2008.31d 3,358,966.78 2,418,456.08
12 Plat Lantai tebal 12 cm 15.56 m3 SNI 7394.2008.32c 4,837,267.56 75,267,883.27
13 Beton Balok Bordes 20x25 0.23 m3 SNI 7394.2008.31a 4,172,536.33 959,683.36
14 Beton Plat Sunscreen tebal 8 cm 1.58 m3 SNI 7394.2008.32c 4,837,267.56 7,642,882.75
15 Beton Plat Tangga tebal 12 cm 1.12 m3 SNI 7394.2008.32c 4,837,267.56 5,417,739.67
JUMLAH 214,508,073.58

V. PEKERJAAN KAYU/BESI, PINTU, JENDELA DAN PENGUNCI


1 Kusen Pintu dan Jendela Kayu Klas II 0.82 m3 SNI 3434.2008.2 5,538,852.00 4,541,858.64
2 Daun Pintu Panel Kayu Klas II 14.11 m2 SNI 3434.2008.5 400,631.00 5,652,903.41
3 Daun Jendela Kaca 3 mm 7.40 m2 SNI 3434.2008.6a 292,243.60 2,162,602.64
4 Daun Fentilasi Kaca 3 mm 0.63 m2 SNI 3434.2008.6a 292,243.60 184,113.47
5 Daun Pintu Tripleks 1.00 bh Ls 425,000.00 425,000.00
6 Kusen Aluminium 4 in Warna Coklat 14.70 m2 Ls 85,000.00 1,249,500.00
7 Daun Pintu Aluminium 3.00 bh Ls 1,000,000.00 3,000,000.00
8 Kunci Pintu 6.00 bh Pt T-30-2000-C.2. 144,650.00 867,900.00
9 Engsel Pintu 18.00 bh Pt T-30-2000-C.5. 23,512.50 423,225.00
10 Engsel Jendela dan Fentilasi 88.00 bh SNI 2835.2008.5 76,230.00 6,708,240.00
11 Kait angin Jendela dan Fentilasi 88.00 bh Pt T-30-2000-C.7. 18,067.50 1,589,940.00
12 Expagnolet 3.00 bh Pt T-30-2000-C.11. 61,380.00 184,140.00
13 Grendel Jendela dan Fentilasi 44.00 bh Pt T-30-2000-C.12. 24,255.00 1,067,220.00
14 Plafond Kalsiboard rangka Kayu 4/6 cm 193.00 m2 Ls 157,000.00 30,301,000.00
JUMLAH 58,357,643.16

VI. PEKERJAAN PENGECATAN


1 Cat Dinding, Plat, Kolom dan Balok 696.10 m² Pt T-38-2000-C.7. 20,559.00 14,311,119.90
2 Cat Kayu, Daun Pintu dan Jendela 54.89 m² Pt T-38-2000-C.12. 47,054.92 2,582,844.56
3 List Plafond Gypsum 12x12 cm 130.00 m Ls 25,000.00 3,250,000.00
JUMLAH 20,143,964.46
VII. PEKERJAAN INSTALASI LISTRIK
1 Instalasi Titik Lampu 18.00 bh Ls 100,000.00 1,800,000.00
2 Lampu Philip 8 watt 12.00 bh Ls 35,000.00 420,000.00
3 Lampu tl 20 watt 6.00 bh Ls 180,000.00 1,080,000.00
4 Stop kontak 6.00 bh Ls 30,000.00 180,000.00
5 Saklar Double 4.00 bh Ls 11,250.00 45,000.00
6 Saklar Tunggal 7.00 bh Ls 11,250.00 78,750.00
7 MCB 4 Grup 1.00 Unit Ls 50,000.00 50,000.00
8 Meteran Listrik 2400 watt 1.00 Unit Ls 2,000,000.00 2,000,000.00
9 Penangkal Petir 1.00 Unit Ls 1,000,000.00 1,000,000.00
JUMLAH 6,653,750.00

VIII. PEKERJAAN INSTALASI AIR


1 Klouset Jongkok porselin ex Toto 3.00 bh Ls 250,000.00 750,000.00
2 Kran air Ø 1/2" 6.00 m Ls 33,750.00 202,500.00
3 Avoor 3.00 bh Ls 53,100.00 159,300.00
4 Pipa Air Paralon 1/2 in & Accessories 42.00 m Ls 32,400.00 1,360,800.00
5 Pipa Paralon Pembuang Kotoran 4 in & Accessories 24.00 m Ls 76,000.00 1,824,000.00
6 Ember Besar 3.00 bh Ls 45,000.00 135,000.00
7 Septik tank dan Sumur Resapan 1.00 unit Ls 4,000,000.00 4,000,000.00
8 Pembuangan Sumur Buis Beton 80 cm Kedalaman 2m 1.00 unit Ls 100,000.00 100,000.00
9 Mesin pompa air simitsu/sejenis 1.00 bh Ls 450,000.00 450,000.00
10 Tangga besi pipa Galvanis Diameter 1,5 in T 9m 1.00 bh Ls 1,000,000.00 1,000,000.00
11 Saluran Air Keliling Bangunan 1/2 diameter 30 cm 62.00 m Ls 45,000.00 2,790,000.00
JUMLAH 12,771,600.00
PEKERJAAN LANTAI II
IX. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. Dinding 1/2 Bata 1Pc : 5Ps 318.25 m² SNI 6897.2008.10 67,765.50 21,566,370.38
2 Plesteran Dinding 1Pc : 5Ps 410.61 m² SNI 2837.2008.5 33,773.30 13,867,654.71
3 Plesteran Beton 1Pc : 3Ps 121.20 m² SNI 2837.2008.3 36,400.10 4,411,692.12
4 Acian Dinding 531.81 m² SNI 2837.2008.27 20,790.00 11,056,329.90
5 Pasangan Keramik Lantai 40x40 155.75 m² SNI 7395.2008.34a 126,720.00 19,736,640.00
6 Pasangan Dinding Keramik KM/WC 20x40 15.66 m² SNI 7395.2008.54 127,187.50 1,991,756.25
7 Pasangan Keramik Lantai 20x20 9.00 m² SNI 7395.2008.54a 127,187.50 1,144,687.50
8 Pasangan Glass Blook dinding tangga 22.00 bh Ls 25,000.00 550,000.00
JUMLAH 74,325,130.86

X. PEKERJAAN BETON BERTULANG


1 Beton Kolom K1 30x40 4.80 m3 SNI 7394.2008.30 6,625,652.00 31,803,129.60
2 Beton Kolom K2 30x30 1.80 m3 SNI 7394.2008.30 6,625,652.00 11,926,173.60
3 Beton Kolom K3 10x25 0.50 m3 SNI 7394.2008.30a 3,485,324.02 1,742,662.01
4 Beton Kolom Praktis (Kp) 10x10 0.44 m3 SNI 7394.2008.30a 3,485,324.02 1,533,542.57
5 Beton Ring Balok 20x30 7.41 m3 SNI 7394.2008.31 4,804,288.50 35,599,777.79
6 Beton Ring Balok 30x40 0.90 m3 SNI 7394.2008.31 4,804,288.50 4,323,859.65
7 Beton Balok Sun Screen 12/20 0.65 m3 SNI 7394.2008.31d 3,358,966.78 2,183,328.41
8 Beton Plat Dak 8 cm 2.10 m3 SNI 7394.2008.32c 4,837,267.56 10,158,261.88
9 Plat Sunscreen tebal 8 cm 1.58 m3 SNI 7394.2008.32c 4,837,267.56 7,642,882.75
JUMLAH 106,913,618.25

XI. PEKERJAAN KAYU/BESI, PINTU, JENDELA DAN PENGUNCI


1 Kusen Pintu dan Jendela Kayu Klas II 0.82 m3 SNI 3434.2008.2 5,538,852.00 4,541,858.64
2 Daun Pintu Panel Kayu Klas II 14.11 m2 SNI 3434.2008.5 400,631.00 5,652,903.41
3 Daun Jendela Kaca 3 mm 7.40 m2 SNI 3434.2008.6a 292,243.60 2,162,602.64
4 Daun Fentilasi Kaca 3 mm 0.63 m2 SNI 3434.2008.6a 292,243.60 184,113.47
5 Kusen Aluminium 4 in 14.70 m2 Ls 85,000.00 1,249,500.00
6 Daun Pintu Aluminium 3.00 bh Ls 1,000,000.00 3,000,000.00
7 Kunci Pintu 6.00 bh Pt T-30-2000-C.2. 144,650.00 867,900.00
8 Engsel Pintu 18.00 bh Pt T-30-2000-C.5. 23,512.50 423,225.00
9 Engsel Jendela dan Fentilasi 88.00 bh Pt T-30-2000-C.6. 76,230.00 6,708,240.00
10 Kait angin Jendela dan Fentilasi 88.00 bh Pt T-30-2000-C.7. 18,067.50 1,589,940.00
11 Expagnolet 3.00 bh Pt T-30-2000-C.11. 61,380.00 184,140.00
12 Grendel Jendela dan Fentilasi 44.00 bh Pt T-30-2000-C.12. 24,255.00 1,067,220.00
JUMLAH 27,631,643.16

XII. PEKERJAAN RANGKA ATAP, ATAP, PLAFOND


1 Plafond Kalsiboard rangka kayu 4/6 cm 193.00 m2 Ls 140,000.00 27,020,000.00
2 Rangka Baja Ringan C 80 244.40 m2 Ls 75,000.00 18,330,000.00
3 Atap Genteng Pres Beton Flat 244.40 m2 SNI 03.3436.2002.30 72,160.00 17,635,904.00
4 Bubungan Genteng Beton Flat 34.05 m2 SNI 03.3436.2002.34 71,648.50 2,439,631.43
5 List Plank Kayu bersusun 2/20 dan 2/10 31.20 m2 SNI 3434.2008.21 56,622.50 1,766,622.00
JUMLAH 67,192,157.43

XIII. PEKERJAAN PENGECATAN


1 Cat Dinding, Plat, Kolom, Balok dan Plafond 531.81 m² Pt T-38-2000-C.7. 20,559.00 10,933,481.79
2 Cat Kusen, Daun Pintu, Jendela dan list Plank 86.09 m² Pt T-38-2000-C.12. 47,054.92 4,050,958.06
3 List Plafond Gypsum 12x12 cm 130.00 m Ls 25,000.00 3,250,000.00
JUMLAH 18,234,439.85
XIV. PEKERJAAN INSTALASI LISTRIK
1 Instalasi Titik Lampu 18.00 bh Ls 100,000.00 1,800,000.00
2 Lampu Philip 18 watt 12.00 bh Ls 35,000.00 420,000.00
3 Lampu tl 20 watt 6.00 bh Ls 180,000.00 1,080,000.00
4 Stop kontak 6.00 bh Ls 50,000.00 300,000.00
5 Saklar Double 4.00 bh Ls 11,250.00 45,000.00
6 Saklar Tunggal 6.00 bh Ls 11,250.00 67,500.00
JUMLAH 3,712,500.00

XV. PEKERJAAN INSTALASI AIR


1 Klouset Jongkok porselin ex Toto 3.00 bh Ls 250,000.00 750,000.00
2 Kran air Ø 1/2" 6.00 m Ls 33,750.00 202,500.00
3 Avoor 3.00 bh Ls 53,100.00 159,300.00
4 Pipa Air Paralon 1/2 in & Accessories 42.00 m Ls 32,400.00 1,360,800.00
5 Pipa Pembuang Kotoran 4 in & Accessories 24.00 m Ls 76,000.00 1,824,000.00
6 Pipa diameter 1 in pipa penguras dari tengki Air 20.00 m Ls 30,000.00 600,000.00
7 Ember Besar 3.00 bh Ls 55,000.00 165,000.00
8 Tengki Air Fiber 1000 L 2.00 bh Ls 4,000,000.00 8,000,000.00
JUMLAH 13,061,600.00
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
SATUAN KERJA : BADAN KOORDINASI PENYULUHAN PERTANIAN, PERIKANAN DAN KEHUTANAN PROVINSI NTB
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PEMBANGUNAN LANJUTAN (TAHAP II) ASRAMA UTARA SMKPP NEGERI MATARAM
PAKET PEKERJAAN : PEMBANGUNAN LANJUTAN (TAHAP II) ASRAMA UTARA SMKPP NEGERI MATARAM
LOKASI : JL. TGH LOPAN NO X KM 7 LABUAPI - LOMBOK BARAT.
TAHUN : 2013

NO URAIAN PEKERJAAN JUMLAH

1 2 3
PEKERJAAN LANTAI I
I. PEKERJAAN PENDAHULUAN/PERSIAPAN Rp. 2,500,000.00
II. PEKERJAAN TANAH DAN PASIR Rp. 7,194,729.85
III. PEKERJAAN PASANGAN DAN PLESTERAN Rp. 94,802,690.66
IV. PEKERJAAN BETON BERTULANG Rp. 214,508,073.58
V. PEKERJAAN KAYU/BESI, PINTU, JENDELA DAN PENGUNCI Rp. 58,357,643.16
VI. PEKERJAAN PENGECATAN Rp. 20,143,964.46
VII. PEKERJAAN INSTALASI LISTRIK Rp. 6,653,750.00
VIII. PEKERJAAN INSTALASI AIR Rp. 12,771,600.00
PEKERJAAN LANTAI II
IX. PEKERJAAN PASANGAN DAN PLESTERAN Rp. 74,325,130.86
X. PEKERJAAN BETON BERTULANG Rp. 106,913,618.25
XI. PEKERJAAN KAYU/BESI, PINTU, JENDELA DAN PENGUNCI Rp. 27,631,643.16
XII. PEKERJAAN RANGKA ATAP, ATAP, PLAFOND Rp. 67,192,157.43
XIII. PEKERJAAN PENGECATAN Rp. 18,234,439.85
XIV. PEKERJAAN INSTALASI LISTRIK Rp. 3,712,500.00
XV. PEKERJAAN INSTALASI AIR Rp. 13,061,600.00

JUMLAH REAL COST Rp. 728,003,541.25


PAJAK/PPN 10 % Rp. 72,800,354.13
TOTAL JUMLAH BIAYA Rp. 800,803,895.38
DIBULATKAN Rp. 800,803,000.00

TERBILANG : DELAPAN RATUS JUTA DELAPAN RATUS TIGA RIBU RUPIAH.

Mataram, 16 April 2013


Dibuat Oleh :
CV. AGUNG JAYA

NARTO
Direktur
TIME SCHEDULE
SATUAN KERJA : BADAN KOORDINASI PENYULUHAN PERTANIAN, PERIKANAN DAN KEHUTANAN PROVINSI NTB
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PEMBANGUNAN LANJUTAN (TAHAP II) ASRAMA UTARA SMKPP NEGERI MATARAM
PAKET PEKERJAAN : PEMBANGUNAN LANJUTAN (TAHAP II) ASRAMA UTARA SMKPP NEGERI MATARAM
LOKASI : JL. TGH LOPAN NO X KM 7 LABUAPI - LOMBOK BARAT.
TAHUN : 2013

JANGKA WAKTU PELAKSANAAN 120 HARI KALENDER


NO URAIAN PEKERJAAN VOLUME BOBOT
M.1 M.2 M.3 M.4 M.5 M.6 M.7 M.8 M.9 M.10 M.11 M.12 M.13 M.14 M.15 M.16 M.17 M18. KET.
1HK
PEKERJAAN LANTAI I
I. PEKERJAAN PENDAHULUAN/PERSIAPAN
1 Pengukuran/Pemasangan bouwplank 1.00 Keg 0.165 0.165
2 Pembersihan bekas material dan Mobilisasi 1.00 Keg 0.179 0.179

II. PEKERJAAN TANAH DAN PASIR


1 Galian tanah pondasi tangga 1.80 m3 0.009 0.009
2 Urugan tanah peninggian lantai 103.91 m3 0.979 0.979

III. PEKERJAAN PASANGAN DAN PLESTERAN


1 Pas. Pondasi Batu Kali trap tangga 1PC : 5 PS 9.50 m3 0.581 0.581
2 Pas. Dinding 1/2 Bata 1Pc : 5 Ps 318.25 m2 2.962 1.481 1.481
3 Pas. Bata Anak Tangga 1Pc : 3 Ps 8.25 m2 0.082 0.082
4 Plesteran Dinding 1Pc : 5Ps 510.84 m2 2.370 1.185 1.185
5 Plesteran Beton 1Pc : 3Ps 146.84 m2 0.734 0.734
6 Acian Dinding + Acian Beton 696.10 m2 1.988 0.994 0.994
7 Pasangan Keramik Lantai dan tangga 40 x 40 165.25 m2 2.876 1.438 1.438
8 Pasangan Dinding Keramik dinding KM/WC 20x40 15.66 m2 0.274 0.274
9 Pasangan Keramik Lantai KM/WC 20x20 9.00 m2 0.157 0.157
10 Paving Blok segi enam dan pasir Urug 10 cm Kel 62.00 m2 0.766 0.766
11 Pasangan bata pada pinggir paving blok dalam 20 cm 24.80 m2 0.231 0.231

IV. PEKERJAAN BETON BERTULANG


1 Beton Rabat lantai 8.31 m3 0.668 0.668
2 Pondasi tangga 0.20 m3 0.076 0.076
3 Beton Kolom K1 30x40 4.86 m3 4.423 4.423
4 Beton Kolom K2 30x30 1.82 m3 1.656 1.656
5 Beton Kolom K3 10x25 0.44 m3 0.211 0.211
6 Beton Kolom Praktis (Kp) 10x10 0.39 m3 0.187 0.187
7 Beton Balok B1 30x60 5.40 m3 3.564 3.564
8 Beton Balok B2 30x50 1.13 m3 0.746 0.746
9 Beton Balok B3 30x40 4.20 m3 2.772 2.772
10 Beton Balok B4 25x35 3.89 m3 2.567 2.567
11 Beton Balok Latai 12x20 0.72 m3 0.332 0.332
12 Plat Lantai tebal 12 cm 15.56 m3 10.339 5.169 5.169
13 Beton Balok Bordes 20x25 0.23 m3 0.132 0.132
14 Beton Plat Sunscreen tebal 8 cm 1.58 m3 1.050 1.050
15 Beton Plat Tangga tebal 12 cm 1.12 m3 0.744 0.744
V. PEKERJAAN KAYU/BESI, PINTU, JENDELA DAN PENGUNCI
1 Kusen Pintu dan Jendela Kayu Klas II 0.82 m3 0.624 0.624
2 Daun Pintu Panel Kayu Klas II 14.11 m2 0.776 0.776
3 Daun Jendela Kaca 3 mm 7.40 m2 0.297 0.297
4 Daun Fentilasi Kaca 3 mm 0.63 m2 0.025 0.025
5 Daun Pintu Tripleks 1.00 bh 0.058 0.058
6 Kusen Aluminium 4 in Warna Coklat 14.70 m2 0.172 0.172
7 Daun Pintu Aluminium 3.00 bh 0.412 0.412
8 Kunci Pintu 6.00 bh 0.119 0.119
9 Engsel Pintu 18.00 bh 0.058 0.058
10 Engsel Jendela dan Fentilasi 88.00 bh 0.921 0.921
11 Kait angin Jendela dan Fentilasi 88.00 bh 0.218 0.218
12 Expagnolet 3.00 bh 0.025 0.025
13 Grendel Jendela dan Fentilasi 44.00 bh 0.147 0.147
14 Plafond Kalsiboard rangka Kayu 4/6 cm 193.00 m2 4.162 2.081 2.081

VI. PEKERJAAN PENGECATAN


1 Cat Dinding, Plat, Kolom dan Balok 696.10 m² 1.966 0.983 0.983
2 Cat Kayu, Daun Pintu dan Jendela 54.89 m² 0.355 0.355
3 List Plafond Gypsum 12x12 cm 130.00 m 0.446 0.446

VII. PEKERJAAN INSTALASI LISTRIK


1 Instalasi Titik Lampu 18.00 bh 0.247 0.247
2 Lampu Philip 8 watt 12.00 bh 0.058 0.058
3 Lampu tl 20 watt 6.00 bh 0.148 0.148
4 Stop kontak 6.00 bh 0.025 0.025
5 Saklar Double 4.00 bh 0.006 0.006
6 Saklar Tunggal 7.00 bh 0.011 0.011
7 MCB 4 Grup 1.00 Unit 0.007 0.007
8 Meteran Listrik 2400 watt 1.00 Unit 0.275 0.275
9 Penangkal Petir 1.00 Unit 0.137 0.137

VIII. PEKERJAAN INSTALASI AIR


1 Klouset Jongkok porselin ex Toto 3.00 bh 0.103 0.103
2 Kran air Ø 1/2" 6.00 m 0.028 0.028
3 Avoor 3.00 bh 0.022 0.022
4 Pipa Air Paralon 1/2 in & Accessories 42.00 m 0.187 0.187
5 Pipa Paralon Pembuang Kotoran 4 in & Accessories 24.00 m 0.251 0.251
6 Ember Besar 3.00 bh 0.019 0.019
7 Septik tank dan Sumur Resapan 1.00 unit 0.549 0.549
8 Pembuangan Sumur Buis Beton 80 cm Kedalaman 2m 1.00 unit 0.014 0.014
9 Mesin pompa air simitsu/sejenis 1.00 bh 0.062 0.062
10 Tangga besi pipa Galvanis Diameter 1,5 in T 9m 1.00 bh 0.137 0.137
11 Saluran Air Keliling Bangunan 1/2 diameter 30 cm 62.00 m 0.383 0.383
PEKERJAAN LANTAI II
IX. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. Dinding 1/2 Bata 1Pc : 5Ps 318.25 m² 2.962 1.481 1.481
2 Plesteran Dinding 1Pc : 5Ps 410.61 m² 1.905 1.905
3 Plesteran Beton 1Pc : 3Ps 121.20 m² 0.606 0.606
4 Acian Dinding 531.81 m² 1.519 0.759 0.759
5 Pasangan Keramik Lantai 40x40 155.75 m² 2.711 1.356 1.356
6 Pasangan Dinding Keramik KM/WC 20x40 15.66 m² 0.274 0.274
7 Pasangan Keramik Lantai 20x20 9.00 m² 0.157 0.157
8 Pasangan Glass Blook dinding tangga 22.00 bh 0.076 0.076
X. PEKERJAAN BETON BERTULANG
1 Beton Kolom K1 30x40 4.80 m3 4.369 2.184 2.184
2 Beton Kolom K2 30x30 1.80 m3 1.638 1.638
3 Beton Kolom K3 10x25 0.50 m3 0.239 0.239
4 Beton Kolom Praktis (Kp) 10x10 0.44 m3 0.211 0.105 0.105
5 Beton Ring Balok 20x30 7.41 m3 4.890 2.445 2.445
6 Beton Ring Balok 30x40 0.90 m3 0.594 0.594
7 Beton Balok Sun Screen 12/20 0.65 m3 0.300 0.300
8 Beton Plat Dak 8 cm 2.10 m3 1.395 1.395
9 Plat Sunscreen tebal 8 cm 1.58 m3 1.050 1.050

XI. PEKERJAAN KAYU/BESI, PINTU, JENDELA DAN PENGUNCI


1 Kusen Pintu dan Jendela Kayu Klas II 0.82 m3 0.624 0.624
2 Daun Pintu Panel Kayu Klas II 14.11 m2 0.776 0.776
3 Daun Jendela Kaca 3 mm 7.40 m2 0.297 0.297
4 Daun Fentilasi Kaca 3 mm 0.63 m2 0.025 0.025
5 Kusen Aluminium 4 in 14.70 m2 0.172 0.172
6 Daun Pintu Aluminium 3.00 bh 0.412 0.412
7 Kunci Pintu 6.00 bh 0.119 0.119
8 Engsel Pintu 18.00 bh 0.058 0.058
9 Engsel Jendela dan Fentilasi 88.00 bh 0.921 0.921
10 Kait angin Jendela dan Fentilasi 88.00 bh 0.218 0.218
11 Expagnolet 3.00 bh 0.025 0.025
12 Grendel Jendela dan Fentilasi 44.00 bh 0.147 0.147

XII. PEKERJAAN RANGKA ATAP, ATAP, PLAFOND


1 Plafond Kalsiboard rangka kayu 4/6 cm 193.00 m2 3.712 1.856 1.856
2 Rangka Baja Ringan C 80 244.40 m2 2.518 1.259 1.259
3 Atap Genteng Pres Beton Flat 244.40 m2 2.423 1.211 1.211
4 Bubungan Genteng Beton Flat 34.05 m2 0.335 0.335
5 List Plank Kayu bersusun 2/20 dan 2/10 31.20 m2 0.243 0.243

XIII. PEKERJAAN PENGECATAN


1 Cat Dinding, Plat, Kolom, Balok dan Plafond 531.81 m² 1.502 0.751 0.751
2 Cat Kusen, Daun Pintu, Jendela dan list Plank 86.09 m² 0.556 0.556
3 List Plafond Gypsum 12x12 cm 130.00 m 0.446 0.446

XIV. PEKERJAAN INSTALASI LISTRIK


1 Instalasi Titik Lampu 18.00 bh 0.247 0.247
2 Lampu Philip 18 watt 12.00 bh 0.058 0.058
3 Lampu tl 20 watt 6.00 bh 0.148 0.148
4 Stop kontak 6.00 bh 0.041 0.041
5 Saklar Double 4.00 bh 0.006 0.006
6 Saklar Tunggal 6.00 bh 0.009 0.009

XV. PEKERJAAN INSTALASI AIR


1 Klouset Jongkok porselin ex Toto 3.00 bh 0.103 0.103
2 Kran air Ø 1/2" 6.00 m 0.028 0.028
3 Avoor 3.00 bh 0.022 0.022
4 Pipa Air Paralon 1/2 in & Accessories 42.00 m 0.187 0.187
5 Pipa Pembuang Kotoran 4 in & Accessories 24.00 m 0.251 0.251
6 Pipa diameter 1 in pipa penguras dari tengki Air 20.00 m 0.082 0.082
7 Ember Besar 3.00 bh 0.023 0.023
8 Tengki Air Fiber 1000 L 2.00 bh 1.099 1.099
JUMLAH BOBOT : 100.000
RENCANA KEMAJUAN FISIK MINGGU KE- : 0.8 1.6 2.7 8.4 17.9 10.2 6.3 3.5 4.8 3.7 9.4 7.6 9.7 5.4 4.3 2.4 1.5 0.0
RENCANA KUMULATIF KEMAJUAN FISIK MINGGU KE- : 0.8 2.3 5.1 13.5 31.3 41.5 47.8 51.3 56.0 59.7 69.1 76.7 86.4 91.7 96.1 98.5 100.0 100.0
Mataram, 16 April 2013
Dibuat Oleh :
CV. AGUNG JAYA

NARTO
Direktur
JADWAL PENGGUNAAN BAHAN DAN TENAGA
SATUAN KERJA : BADAN KOORDINASI PENYULUHAN PERTANIAN, PERIKANAN DAN KEHUTANAN PROVINSI NTB
KEGIATAN : PEMBANGUNAN GEDUNG KANTOR
PEKERJAAN : PEMBANGUNAN LANJUTAN (TAHAP II) ASRAMA UTARA SMKPP NEGERI MATARAM
PAKET PEKERJAAN : PEMBANGUNAN LANJUTAN (TAHAP II) ASRAMA UTARA SMKPP NEGERI MATARAM
LOKASI : JL. TGH LOPAN NO X KM 7 LABUAPI - LOMBOK BARAT.
TAHUN ANGGARAN : 2013

JANGKA WAKTU PELAKSANAAN 120 HARI KALENDER


NO URAIAN PEKERJAAN VOLUME
M.1 M.2 M.3 M.4 M.5 M.6 M.7 M.8 M.9 M.10 M.11 M.12 M.13 M.14 M.15 M.16 M.17 M18. KET.
1HK
PEKERJAAN LANTAI I
I. PEKERJAAN PENDAHULUAN/PERSIAPAN
1 Pengukuran/Pemasangan bouwplank 1.00 1.00
2 Pembersihan bekas material dan Mobilisasi 1.00 1.00

II. PEKERJAAN TANAH DAN PASIR


1 Galian tanah pondasi tangga 1.80
Pekerja 1.35 1.35
Mandor 0.05 0.05

2 Urugan tanah peninggian lantai 103.91


BAHAN
Tanah Urug 124.69 124.692

TENAGA
Pekerja 31.17 31.173
Mandor 1.04 1.039

III. PEKERJAAN PASANGAN DAN PLESTERAN


1 Pas. Pondasi Batu Kali trap tangga 1PC : 5 PS 9.50
Bahan
Batu kali belah 11.40 11.4
Semen 1,292.00 1292
Pasir pasang 5.17 5.2

TENAGA
Tukang batu 7.13 7.1
Kepala tukang batu 0.71 0.7
Pekerja 14.25 14.3
Mandor 0.71 0.7

2 Pas. Dinding 1/2 Bata 1Pc : 5 Ps 318.25


BAHAH
Bata merah 22,277.5 11138.8 11138.8
Semen 3,080.7 1540.3 1540.3
Pasir pasang 14.3 7.2 7.2

TENAGA
Tukang batu 31.8 15.9 15.9
Kepala tukang batu 3.2 1.6 1.6
Pekerja 95.5 47.7 47.7
Mandor 4.8 2.4 2.4

3 Pas. Bata Anak Tangga 1Pc : 3 Ps 8.25


BAHAN
Bata merah 577.50 577.5
Semen 118.55 118.6
Pasir pasang 0.33 0.33

TENAGA
Tukang batu 0.83 0.83
Kepala tukang batu 0.08 0.08
Pekerja 2.48 2.48
Mandor 0.12 0.12
4 Plesteran Dinding 1Pc : 5Ps 510.84
BAHAN
Semen 2,629.80 1314.9 1314.9
Pasir pasang 13.28 6.6 6.6

TENAGA
Tukang batu 76.63 38.3 38.3
Kepala tukang batu 7.66 3.8 3.8
Pekerja 153.25 76.6 76.6
Mandor 7.66 3.8 3.8

5 Plesteran Beton 1Pc : 3Ps 146.84


BAHAN
Semen 1,141.83 1141.8
Pasir pasang 3.38 3.4

TENAGA
Tukang batu 22.03 22.0
Kepala tukang batu 2.20 2.2
Pekerja 44.05 44.1
Mandor 2.20 2.2

6 Acian Dinding + Acian Beton 696.10


BAHAN
Semen 2,262.33 1131.2 1131.2

TENAGA
Tukang batu 69.61 34.8 34.8
Kepala tukang batu 6.96 3.5 3.5
Pekerja 139.22 69.6 69.6
Mandor 6.96 3.5 3.5

7 Pasangan Keramik Lantai dan tangga 40 x 40 165.25


BAHAN
Keramik 40 x 40 cm (putih klas biasa) 173.51 86.8 86.8
Semen 1,454.20 727.1 727.1
Semen warna 214.83 107.4 107.4
Pasir pasang 3.55 1.8 1.8

TENAGA
Tukang batu 57.84 28.9 28.9
Kepala tukang batu 5.78 2.9 2.9
Pekerja 102.46 51.2 51.2
Mandor 4.96 2.5 2.5

8 Pasangan Dinding Keramik dinding KM/WC 20x40 15.66


BAHAN
Keramik 20 x 20 cm (motif biasa) 15.66 15.7
Semen 145.64 145.6
Semen warna 30.38 30.4
Pasir pasang 0.28 0.3

TENAGA
Tukang batu 7.05 7.0
Kepala tukang batu 0.70 0.7
Pekerja 14.09 14.1
Mandor 0.70 0.7

9 Pasangan Keramik Lantai KM/WC 20x20 9.00


BAHAN
Keramik 20 x 20 cm (motif biasa) 9.00 9.0
Semen 83.70 83.7
Semen warna 17.46 17.5
Pasir pasang 0.16 0.2

TENAGA
Tukang batu 4.05 4.1
Kepala tukang batu 0.41 0.4
Pekerja 8.10 8.1
Mandor 0.40 0.4
10 Paving Blok segi enam dan pasir Urug 10 cm Kel 62.00 62.0

11 Pasangan bata pada pinggir paving blok dalam 20 cm 24.80


BAHAH
Bata merah 1,736.00 1736.00
Semen 240.06 240.06
Pasir pasang 1.12 1.12

TENAGA
Tukang batu 2.48 2.48
Kepala tukang batu 0.25 0.25
Pekerja 7.44 7.44
Mandor 0.37 0.37

IV. PEKERJAAN BETON BERTULANG


1 Beton Rabat lantai 8.310
BAHAN
Semen 2,052.570 2052.6
Pasir cor 7,221.390 7221.4
Krikil alam 2-3cm 8,301.690 8301.7
Air kerja 1,786.650 1786.7

TENAGA
Tukang batu 2.285 2.3
Kepala tukang batu 0.233 0.2
Pekerja 13.712 13.7
Mandor 0.690 0.7

2 Pondasi tangga 0.20


BETON (K-175)
BAHAN
Semen 65.20 65.2
Pasir cor 152.00 152.0
Krikil alam 2-3cm 205.80 205.8
Air kerja 43.00 43.0

TENAGA
Tukang batu 0.06 0.06
Kepala tukang batu 0.01 0.01
Pekerja 0.33 0.33
Mandor 0.02 0.02

PEMBESIAN POLOS
BAHAN
Besi beton polos 0.21 0.210
Kawat beton 0.003 0.003

TENAGA
Tukang besi 0.0014 0.001
Kepala tukang besi 0.0001 0.000
Pekerja 0.0014 0.001
Mandor 0.0001 0.000

BEKISTING PONDASI (2 Kali Pakai)


BAHAN
Kayu kelas III 0.01 0.008
Paku usuk/reng 0.06 0.060
Minyak begesting 0.02 0.020

TENAGA
Tukang kayu 0.05 0.052
Kepala tukang kayu 0.01 0.005
Pekerja 0.10 0.104
Mandor 0.01 0.005
3 Beton Kolom K1 30x40 4.86
BAHAN
Kayu kelas III 1.94 1.9
Paku usuk/reng 19.44 19.4
Minyak begesting 9.72 9.7
Besi beton polos 1,530.90 1530.9
Kawat beton 21.87 21.9
Semen 1,632.96 1633.0
Pasir beton 2.62 2.6
Krikil alam 2-3cm - 1 m³ 3.94 3.9
Kayu klas II 0.73 0.7
Playwood 6 mm 17.01 17.0
Kayu dolken ø 10cm - 4 m 97.20 97.2

TENAGA
Tukang kayu 8.02 8.0
Tukang batu 1.34 1.3
Tukang besi 10.21 10.2
Kepala tukang besi 1.57 1.6
Pekerja 34.26 34.3
Mandor 1.72 1.7

4 Beton Kolom K2 30x30 1.82


BAHAN
Kayu kelas III 0.73 0.7
Paku usuk/reng 7.28 7.3
Minyak begesting 3.64 3.6
Besi beton polos 573.30 573.3
Kawat beton 8.19 8.2
Semen 611.52 611.5
Pasir beton 0.98 1.0
Krikil alam 2-3cm - 1 m³ 1.47 1.5
Kayu klas II 0.27 0.3
Playwood 6 mm 6.37 6.4
Kayu dolken ø 10cm - 4 m 36.40 36.4

TENAGA
Tukang kayu 3.00 3.0
Tukang batu 0.50 0.5
Tukang besi 3.82 3.8
Kepala tukang besi 0.59 0.6
Pekerja 12.83 12.8
Mandor 0.64 0.6

5 Beton Kolom K3 10x25 0.44


BETON (K-175)
BAHAN
Semen 143.44 143.4
Pasir cor 334.40 334.4
Krikil alam 2-3cm 452.76 452.8
Air kerja 94.60 94.6

TENAGA
Tukang batu 0.12 0.12
Kepala tukang batu 0.01 0.01
Pekerja 0.73 0.73
Mandor 0.04 0.04

PEMBESIAN POLOS
BAHAN
Besi beton polos 0.46 0.4620
Kawat beton 0.01 0.0066
TENAGA
Tukang besi 0.0031 0.0031
Kepala tukang besi 0.0003 0.0003
Pekerja 0.0031 0.0031
Mandor 0.0002 0.0002

BEKISTING KOLOM
BAHAN
Kayu kelas III 0.02 0.02
Paku usuk/reng 0.18 0.18
Minyak begesting 0.09 0.09
Kayu kelas III 0.01 0.01
Triplek 9 mm 0.15 0.15
Kayu dolken ø 10cm - 4 m 0.88 0.88

TENAGA
Tukang kayu 0.15 0.15
Kepala tukang kayu 0.01 0.01
Pekerja 0.29 0.29
Mandor 0.01 0.01

6 Beton Kolom Praktis (Kp) 10x10 0.39


BETON (K-175)
BAHAN
Semen 127.14 127.140
Pasir cor 296.40 296.400
Krikil alam 2-3cm 401.31 401.310
Air kerja 83.85 83.850

TENAGA
Tukang batu 0.107 0.107
Kepala tukang batu 0.011 0.011
Pekerja 0.644 0.644
Mandor 0.032 0.032

PEMBESIAN POLOS
BAHAN
Besi beton polos 0.41 0.410
Kawat beton 0.01 0.006

TENAGA
Tukang besi 0.0027 0.003
Kepala tukang besi 0.0003 0.000
Pekerja 0.0027 0.003
Mandor 0.0002 0.000

BEKISTING KOLOM
BAHAN
Kayu kelas III 0.02 0.016
Paku usuk/reng 0.16 0.156
Minyak begesting 0.08 0.078
Kayu kelas III 0.01 0.006
Triplek 9 mm 0.14 0.136
Kayu dolken ø 10cm - 4 m 0.78 0.780

TENAGA
Tukang kayu 0.13 0.129
Kepala tukang kayu 0.01 0.013
Pekerja 0.26 0.257
Mandor 0.01 0.013

7 Beton Balok B1 30x60 5.40


BAHAN
Kayu kelas III 1.73 1.7
Paku usuk/reng 17.28 17.3
Minyak begesting 8.64 8.6
Besi beton polos 1,134.00 1134.0
Kawat beton 16.20 16.2
Semen 1,814.40 1814.4
Pasir beton 2.92 2.9
Krikil alam 2-3cm - 1 m³ 4.37 4.4
Kayu klas II 0.76 0.8
Playwood 6 mm 15.12 15.1

TENAGA
Tukang kayu 8.91 8.9
Tukang batu 1.49 1.5
Tukang besi 7.56 7.6
Kepala tukang besi 1.80 1.8
Pekerja 34.29 34.3
Mandor 1.72 1.7

8 Beton Balok B2 30x50 1.13


BAHAN
Kayu kelas III 0.36 0.4
Paku usuk/reng 3.62 3.6
Minyak begesting 1.81 1.8
Besi beton polos 237.30 237.3
Kawat beton 3.39 3.4
Semen 379.68 379.7
Pasir beton 0.61 0.6
Krikil alam 2-3cm - 1 m³ 0.92 0.9
Kayu klas II 0.16 0.2
Playwood 6 mm 3.16 3.2

TENAGA
Tukang kayu 1.86 1.9
Tukang batu 0.31 0.3
Tukang besi 1.58 1.6
Kepala tukang besi 0.38 0.4
Pekerja 7.18 7.2
Mandor 0.36 0.4

9 Beton Balok B3 30x40 4.20


BAHAN
Kayu kelas III 1.34 1.3
Paku usuk/reng 13.44 13.4
Minyak begesting 6.72 6.7
Besi beton polos 882.00 882.0
Kawat beton 12.60 12.6
Semen 1,411.20 1411.2
Pasir beton 2.27 2.3
Krikil alam 2-3cm - 1 m³ 3.40 3.4
Kayu klas II 0.59 0.6
Playwood 6 mm 11.76 11.8

TENAGA
Tukang kayu 6.93 6.9
Tukang batu 1.16 1.2
Tukang besi 5.88 5.9
Kepala tukang besi 1.40 1.4
Pekerja 26.67 26.7
Mandor 1.34 1.3

10 Beton Balok B4 25x35 3.89


BAHAN
Kayu kelas III 1.24 1.2
Paku usuk/reng 12.45 12.4
Minyak begesting 6.22 6.2
Besi beton polos 816.90 816.9
Kawat beton 11.67 11.7
Semen 1,307.04 1307.0
Pasir beton 2.10 2.1
Krikil alam 2-3cm - 1 m³ 3.15 3.2
Kayu klas II 0.54 0.5
Playwood 6 mm 10.89 10.9
TENAGA
Tukang kayu 6.42 6.4
Tukang batu 1.07 1.1
Tukang besi 5.45 5.4
Kepala tukang besi 1.30 1.3
Pekerja 24.70 24.7
Mandor 1.24 1.2

11 Beton Balok Latai 12x20 0.72


BETON (K-175)
BAHAN
Semen 234.72 234.72
Pasir cor 547.20 547.20
Krikil alam 2-3cm 740.88 740.88
Air kerja 154.80 154.80

TENAGA
Tukang batu 0.20 0.20
Kepala tukang batu 0.02 0.02
Pekerja 1.19 1.19
Mandor 0.06 0.06

PEMBESIAN POLOS
BAHAN
Besi beton polos 0.76 0.76
Kawat beton 0.01 0.01

TENAGA
Tukang besi 0.01 0.01
Kepala tukang besi 0.00 0.00
Pekerja 0.01 0.01
Mandor 0.00 0.00

BEKISTING BALOK
BAHAN
Kayu kelas III 0.03 0.03
Paku usuk/reng 0.29 0.29
Minyak begesting 0.14 0.14
Kayu kelas III 0.01 0.01
Triplek 9 mm 0.25 0.25
Kayu dolken ø 10cm - 4 m 1.44 1.44

TENAGA
Tukang kayu 0.238 0.24
Kepala tukang kayu 0.024 0.02
Pekerja 0.475 0.48
Mandor 0.024 0.02

12 Plat Lantai tebal 12 cm 15.56


BETON (K-175)
BAHAN
Semen 5,072.56 2536.3 2536.3
Pasir cor 11,825.60 5912.8 5912.8
Krikil alam 2-3cm 16,011.24 8005.6 8005.6
Air kerja 3,345.40 1672.7 1672.7

TENAGA
Tukang batu 4.28 2.1 2.1
Kepala tukang batu 0.44 0.2 0.2
Pekerja 25.67 12.8 12.8
Mandor 1.29 0.6 0.6

PEMBESIAN POLOS
BAHAN
Besi beton polos 16.34 8.2 8.2
Kawat beton 0.23 0.1 0.1
TENAGA
Tukang besi 0.11 0.1 0.1
Kepala tukang besi 0.01 0.0 0.0
Pekerja 0.11 0.1 0.1
Mandor 0.01 0.0 0.0

BEKISTING LANTAI
BAHAN
Kayu kelas III 0.62 0.3 0.3
Paku usuk/reng 6.22 3.1 3.1
Minyak begesting 3.11 1.6 1.6
Kayu kelas III 0.23 0.1 0.1
Triplek 9 mm 5.45 2.7 2.7
Kayu dolken ø 10cm - 4 m 93.36 46.7 46.7

TENAGA -
Tukang kayu 5.13 2.6 2.6
Kepala tukang kayu 0.51 0.3 0.3
Pekerja 10.27 5.1 5.1
Mandor 0.51 0.3 0.3

13 Beton Balok Bordes 20x25 0.23


BETON (K-175)
BAHAN
Semen 74.98 74.9800
Pasir cor 174.80 174.8000
Krikil alam 2-3cm 236.67 236.6700
Air kerja 49.45 49.4500

TENAGA
Tukang batu 0.06 0.0633
Kepala tukang batu 0.01 0.0064
Pekerja 0.38 0.3795
Mandor 0.02 0.0191

PEMBESIAN POLOS
BAHAN
Besi beton polos 0.24 0.2415
Kawat beton 0.0035 0.0035

TENAGA
Tukang besi 0.0016 0.0016
Kepala tukang besi 0.0002 0.0002
Pekerja 0.0016 0.0016
Mandor 0.0001 0.0001

BEKISTING BALOK
BAHAN
Kayu kelas III 0.009 0.009
Paku usuk/reng 0.092 0.092
Minyak begesting 0.046 0.046
Kayu kelas III 0.004 0.004
Triplek 9 mm 0.081 0.081
Kayu dolken ø 10cm - 4 m 0.460 0.460

TENAGA
Tukang kayu 0.076 0.076
Kepala tukang kayu 0.008 0.008
Pekerja 0.152 0.152
Mandor 0.008 0.008

14 Beton Plat Sunscreen tebal 8 cm 1.58


BETON (K-175)
BAHAN
Semen 515.08 515.1
Pasir cor 1,200.80 1200.8
Krikil alam 2-3cm 1,625.82 1625.8
Air kerja 339.70 339.7
TENAGA
Tukang batu 0.43 0.43
Kepala tukang batu 0.04 0.04
Pekerja 2.61 2.61
Mandor 0.13 0.13

PEMBESIAN POLOS
BAHAN
Besi beton polos 1.66 1.66
Kawat beton 0.02 0.02

TENAGA
Tukang besi 0.01 0.011
Kepala tukang besi 0.00 0.001
Pekerja 0.01 0.011
Mandor 0.00 0.001

BEKISTING LANTAI
BAHAN
Kayu kelas III 0.06 0.06
Paku usuk/reng 0.63 0.63
Minyak begesting 0.32 0.32
Kayu kelas III 0.02 0.02
Triplek 9 mm 0.55 0.55
Kayu dolken ø 10cm - 4 m 9.48 9.48

TENAGA
Tukang kayu 0.52 0.52
Kepala tukang kayu 0.05 0.05
Pekerja 1.04 1.04
Mandor 0.05 0.05

15 Beton Plat Tangga tebal 12 cm 1.12


BETON (K-175)
BAHAN
Semen 365.12 365.1
Pasir cor 851.20 851.2
Krikil alam 2-3cm 1,152.48 1152.5
Air kerja 240.80 240.8

TENAGA
Tukang batu 0.31 0.3
Kepala tukang batu 0.03 0.0
Pekerja 1.85 1.8
Mandor 0.09 0.1

PEMBESIAN POLOS
BAHAN
Besi beton polos 1.18 1.1760
Kawat beton 0.02 0.0168

TENAGA
Tukang besi 0.01 0.0078
Kepala tukang besi 0.00 0.0008
Pekerja 0.01 0.0078
Mandor 0.00 0.0004

BEKISTING LANTAI
BAHAN
Kayu kelas III 0.04 0.04
Paku usuk/reng 0.45 0.45
Minyak begesting 0.22 0.22
Kayu kelas III 0.02 0.02
Triplek 9 mm 0.39 0.39
Kayu dolken ø 10cm - 4 m 6.72 6.72
TENAGA
Tukang kayu 0.37 0.37
Kepala tukang kayu 0.04 0.04
Pekerja 0.74 0.74
Mandor 0.04 0.04

V. PEKERJAAN KAYU/BESI, PINTU, JENDELA DAN PENGUNCI


1 Kusen Pintu dan Jendela Kayu Klas II 0.82
BAHAN
Kayu klas II 0.98 1.0
Paku usuk/reng 1.03 1.0
Lem kayu 0.82 0.8

TENAGA
Tukang kayu 14.76 14.8
Kepala tukang kayu 1.48 1.5
Pekerja 4.92 4.9
Mandor 0.02 0.02

2 Daun Pintu Panel Kayu Klas II 14.11


BAHAN
Papan kayu kls II 0.56 0.6
Lem kayu 7.06 7.1

TENAGA
Tukang kayu 42.33 42.3
Kepala tukang kayu 4.23 4.2
Pekerja 14.11 14.1
Mandor 0.71 0.7

3 Daun Jendela Kaca 3 mm 7.40


BAHAN
Papan kayu kls II 0.18 0.2
Lem kayu 2.22 2.2
Kaca bening 3 mm 6.59 6.6

TENAGA
Tukang kayu 17.76 17.8
Kepala tukang kayu 1.78 1.8
Pekerja 5.92 5.9
Mandor 0.30 0.3

4 Daun Fentilasi Kaca 3 mm 0.63


BAHAN
Papan kayu kls II 0.02 0.02
Lem kayu 0.19 0.19
Kaca bening 3 mm 0.56 0.56

TENAGA
Tukang kayu 1.51 1.51
Kepala tukang kayu 0.15 0.15
Pekerja 0.50 0.50
Mandor 0.03 0.03

5 Daun Pintu Tripleks 1.00 1.00

6 Kusen Aluminium 4 in Warna Coklat 14.70 14.7

7 Daun Pintu Aluminium 3.00 3.0

8 Kunci Pintu 6.00


BAHAN
Kunci pintu 2 slaag klas menengah 6.00 6.0

TENAGA
Tukang kayu 3.00 3.0
Kepala tukang kayu 0.30 0.3
9 Engsel Pintu 18.00
BAHAN
Engsel pintu klas biasa 18.00 18.0

TENAGA
Tukang kayu 2.25 2.3
Kepala tukang kayu 0.23 0.2

10 Engsel Jendela dan Fentilasi 88.00


BAHAN
Engsel Jendela klas biasa 88.00 88.0

TENAGA
Tukang kayu 8.80 8.8
Kepala tukang kayu 0.88 0.9

11 Kait angin Jendela dan Fentilasi 88.00


BAHAN
Kait angin klas menengah 88.00 88.0

TENAGA
Tukang kayu 8.80 8.8
Kepala tukang kayu 0.88 0.9

12 Expagnolet 3.00
BAHAN
Expagnolett 3.00 3.0

TENAGA
Tukang kayu 0.30 0.3
Kepala tukang kayu 0.03 0.0

13 Grendel Jendela dan Fentilasi 44.00


BAHAN
Grendel besar klas menengah 44.00 44.0

TENAGA
Tukang kayu 4.40 4.4
Kepala tukang kayu 0.44 0.4

14 Plafond Kalsiboard rangka Kayu 4/6 cm 193.00 96.5 96.5

VI. PEKERJAAN PENGECATAN


1 Cat Dinding, Plat, Kolom dan Balok 696.10
BAHAN
Plamir tembok 69.61 34.8 34.8
Cat tembok klas menengah 327.17 163.6 163.6
Amplas 348.05 174.0 174.0
Roll cat 6.96 3.5 3.5
Kape 34.81 17.4 17.4

TENAGA
Pekerja 41.77 20.9 20.9
Tukang cat 27.84 13.9 13.9
Kepala tukang cat 2.78 1.4 1.4
Mandor 2.09 1.0 1.0

2 Cat Kayu, Daun Pintu dan Jendela 54.89


BAHAN
Plamir Kayu 4.39 4.4
Cat kayu klas menengah 9.33 9.3
Cat kayu klas menengah 16.47 16.5
Minyak cat klas menengah 10.98 11.0
Kuas cat 1.10 1.1
Amplas 54.89 54.9
TENAGA
Pekerja 8.23 8.2
Tukang cat 8.23 8.2
Kepala tukang cat 0.82 0.8
Mandor 0.44 0.4

3 List Plafond Gypsum 12x12 cm 130.00 130.0

VII. PEKERJAAN INSTALASI LISTRIK


1 Instalasi Titik Lampu 18.00 18.0
2 Lampu Philip 8 watt 12.00 12.0
3 Lampu tl 20 watt 6.00 6.0
4 Stop kontak 6.00 6.0
5 Saklar Double 4.00 4.0
6 Saklar Tunggal 7.00 7.0
7 MCB 4 Grup 1.00 1.0
8 Meteran Listrik 2400 watt 1.00 1.0
9 Penangkal Petir 1.00 1.0

VIII. PEKERJAAN SANITAIR


1 Klouset Jongkok porselin ex Toto 3.00 3.0
2 Kran air Ø 1/2" 6.00 6.0
3 Avoor 3.00 3.0
4 Pipa Air Paralon 1/2 in & Accessories 42.00 42.0
5 Pipa Paralon Pembuang Kotoran 4 in & Accessories 24.00 24.0
6 Ember Besar 3.00 3.0
7 Septik tank dan Sumur Resapan 1.00 1.0
8 Pembuangan Sumur Buis Beton 80 cm Kedalaman 2m 1.00 1.0
9 Mesin pompa air simitsu/sejenis 1.00 1.0
10 Tangga besi pipa Galvanis Diameter 1,5 in T 9m 1.00 1.0
11 Saluran Air Keliling Bangunan 1/2 diameter 30 cm 62.00 62.0

PEKERJAAN LANTAI II
IX. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. Dinding 1/2 Bata 1Pc : 5Ps 318.25
BAHAN
Bata merah 22,277.50 11138.8 11138.8
Semen 3,080.66 1540.3 1540.3
Pasir pasang 14.32 7.2 7.2

TENAGA
Tukang batu 31.83 15.9 15.9
Kepala tukang batu 3.18 1.6 1.6
Pekerja 95.48 47.7 47.7
Mandor 4.77 2.4 2.4

2 Plesteran Dinding 1Pc : 5Ps 410.61


BAHAN
Semen 2,113.82 2113.8
Pasir pasang 10.68 10.7

TENAGA
Tukang batu 61.59 61.6
Kepala tukang batu 6.16 6.2
Pekerja 123.18 123.2
Mandor 6.16 6.2

3 Plesteran Beton 1Pc : 3Ps 121.20


BAHAN
Semen 942.45 942.5
Pasir pasang 2.79 2.8

TENAGA
Tukang batu 18.18 18.2
Kepala tukang batu 1.82 1.8
Pekerja 36.36 36.4
Mandor 1.82 1.8
4 Acian Dinding 531.81
BAHAN
Semen 1,728.38 864.2 864.2

TENAGA
Tukang batu 53.18 26.6 26.6
Kepala tukang batu 5.32 2.7 2.7
Pekerja 106.36 53.2 53.2
Mandor 5.32 2.7 2.7

5 Pasangan Keramik Lantai 40x40 155.75


BAHAN
Keramik 40 x 40 cm (putih klas biasa) 163.54 81.8 81.8
Semen 1,370.60 685.3 685.3
Semen warna 202.48 101.2 101.2
Pasir pasang 3.35 1.7 1.7

TENAGA
Tukang batu 54.51 27.3 27.3
Kepala tukang batu 5.45 2.7 2.7
Pekerja 96.57 48.3 48.3
Mandor 4.67 2.3 2.3

6 Pasangan Dinding Keramik KM/WC 20x40 15.66


BAHAN
Keramik 20 x 20 cm (motif biasa) 15.66 15.7
Semen 145.64 145.6
Semen warna 30.38 30.4
Pasir pasang 0.28 0.3

TENAGA
Tukang batu 7.05 7.0
Kepala tukang batu 0.70 0.7
Pekerja 14.09 14.1
Mandor 0.70 0.7

7 Pasangan Keramik Lantai 20x20 9.00


BAHAN
Keramik 20 x 20 cm (motif biasa) 9.00 9.0
Semen 83.70 83.7
Semen warna 17.46 17.5
Pasir pasang 0.16 0.2

TENAGA
Tukang batu 4.05 4.1
Kepala tukang batu 0.41 0.4
Pekerja 8.10 8.1
Mandor 0.40 0.4

8 Pasangan Glass Blook dinding tangga 22.00 22.0

X. PEKERJAAN BETON BERTULANG


1 Beton Kolom K1 30x40 4.80
BAHAN
Kayu kelas III 1.92 0.96 0.96
Paku usuk/reng 19.20 9.6 9.6
Minyak begesting 9.60 4.8 4.8
Besi beton polos 1,512.00 756.00 756.00
Kawat beton 21.60 10.8 10.8
Semen 1,612.80 1612.8 1612.8
Pasir beton 2.59 2.6 2.6
Krikil alam 2-3cm - 1 m³ 3.89 1.9 1.9
Kayu klas II 0.72 0.4 0.4
Playwood 6 mm 16.80 8.4 8.4
Kayu dolken ø 10cm - 4 m 96.00 48.0 48.0
TENAGA
Tukang kayu 7.92 4.0 4.0
Tukang batu 1.32 0.7 0.7
Tukang besi 10.08 5.0 5.0
Kepala tukang besi 1.55 0.8 0.8
Pekerja 33.84 16.9 16.9
Mandor 1.69 1.7 1.7

2 Beton Kolom K2 30x30 1.80


BAHAN
Kayu kelas III 0.72 0.7
Paku usuk/reng 7.20 7.2
Minyak begesting 3.60 3.6
Besi beton polos 567.00 567.0
Kawat beton 8.10 8.1
Semen 604.80 604.8
Pasir beton 0.97 0.97
Krikil alam 2-3cm - 1 m³ 1.46 1.5
Kayu klas II 0.27 0.3
Playwood 6 mm 6.30 6.3
Kayu dolken ø 10cm - 4 m 36.00 36.0

TENAGA
Tukang kayu 2.97 3.0
Tukang batu 0.50 0.5
Tukang besi 3.78 3.8
Kepala tukang besi 0.58 0.6
Pekerja 12.69 12.7
Mandor 0.64 0.6

3 Beton Kolom K3 10x25 0.50


BETON (K-175)
BAHAN
Semen 163.00 163.0
Pasir cor 380.00 380.0
Krikil alam 2-3cm 514.50 514.5
Air kerja 107.50 107.5

TENAGA
Tukang batu 0.14 0.14
Kepala tukang batu 0.01 0.01
Pekerja 0.83 0.83
Mandor 0.04 0.04

PEMBESIAN POLOS
BAHAN
Besi beton polos 0.53 0.53
Kawat beton 0.01 0.01

TENAGA
Tukang besi 0.0035 0.0035
Kepala tukang besi 0.0004 0.0004
Pekerja 0.0035 0.0035
Mandor 0.0002 0.0002

BEKISTING KOLOM
BAHAN
Kayu kelas III 0.02 0.020
Paku usuk/reng 0.20 0.200
Minyak begesting 0.10 0.100
Kayu kelas III 0.01 0.008
Triplek 9 mm 0.18 0.175
Kayu dolken ø 10cm - 4 m 1.00 1.000

TENAGA
Tukang kayu 0.17 0.17
Kepala tukang kayu 0.02 0.02
Pekerja 0.33 0.33
Mandor 0.02 0.02
4 Beton Kolom Praktis (Kp) 10x10 0.44
BETON (K-175)
BAHAN
Semen 143.44 71.7 71.7
Pasir cor 334.40 167.2 167.2
Krikil alam 2-3cm 452.76 226.4 226.4
Air kerja 94.60 47.3 47.3

TENAGA
Tukang batu 0.12 0.1 0.1
Kepala tukang batu 0.01 0.006 0.006
Pekerja 0.73 0.363 0.363
Mandor 0.04 0.018 0.018

PEMBESIAN POLOS
BAHAN
Besi beton polos 0.46 0.2 0.2
Kawat beton 0.01 0.003 0.003

TENAGA
Tukang besi 0.0031 0.0015 0.0015
Kepala tukang besi 0.0003 0.0002 0.0002
Pekerja 0.0031 0.0015 0.0015
Mandor 0.0002 0.0001 0.0001

BEKISTING KOLOM
BAHAN
Kayu kelas III 0.02 0.009 0.009
Paku usuk/reng 0.18 0.088 0.088
Minyak begesting 0.09 0.044 0.044
Kayu kelas III 0.01 0.003 0.003
Triplek 9 mm 0.15 0.077 0.077
Kayu dolken ø 10cm - 4 m 0.88 0.880 0.880

TENAGA
Tukang kayu 0.15 0.073 0.073
Kepala tukang kayu 0.01 0.007 0.007
Pekerja 0.29 0.145 0.145
Mandor 0.01 0.007 0.007

5 Beton Ring Balok 20x30 7.41


BAHAN
Kayu kelas III 2.37 1.2 1.2
Paku usuk/reng 23.71 11.9 11.9
Minyak begesting 11.86 5.9 5.9
Besi beton polos 1,556.10 778.1 778.1
Kawat beton 22.23 11.1 11.1
Semen 2,489.76 1244.9 1244.9
Pasir beton 4.00 2.0 2.0
Krikil alam 2-3cm - 1 m³ 6.00 3.0 3.0
Kayu klas II 1.04 0.5 0.5
Playwood 6 mm 20.75 10.4 10.4

TENAGA
Tukang kayu 12.23 6.1 6.1
Tukang batu 2.04 1.0 1.0
Tukang besi 10.37 5.2 5.2
Kepala tukang besi 2.47 1.2 1.2
Pekerja 47.05 23.5 23.5
Mandor 2.36 1.2 1.2

6 Beton Ring Balok 30x40 0.90


BAHAN
Kayu kelas III 0.29 0.3
Paku usuk/reng 2.88 2.9
Minyak begesting 1.44 1.4
Besi beton polos 189.00 189.0
Kawat beton 2.70 2.7
Semen 302.40 302.4
Pasir beton 0.49 0.5
Krikil alam 2-3cm - 1 m³ 0.73 0.7
Kayu klas II 0.13 0.1
Playwood 6 mm 2.52 2.5

TENAGA
Tukang kayu 1.48 1.5
Tukang batu 0.25 0.2
Tukang besi 1.26 1.3
Kepala tukang besi 0.30 0.3
Pekerja 5.72 5.7
Mandor 0.29 0.3

7 Beton Balok Sun Screen 12/20 0.65


BAHAN
Kayu kelas III 0.21 0.2
Paku usuk/reng 2.08 2.1
Minyak begesting 1.04 1.0
Besi beton polos 136.50 136.5
Kawat beton 1.95 2.0
Semen 218.40 218.4
Pasir beton 0.35 0.4
Krikil alam 2-3cm - 1 m³ 0.53 0.5
Kayu klas II 0.09 0.1
Playwood 6 mm 1.82 1.8

TENAGA
Tukang kayu 1.07 1.1
Tukang batu 0.18 0.2
Tukang besi 0.91 0.9
Kepala tukang besi 0.22 0.2
Pekerja 4.13 4.1
Mandor 0.21 0.2

8 Beton Plat Dak 8 cm 2.10


BETON (K-175)
BAHAN
Semen 684.60 684.6
Pasir cor 1,596.00 1596.0
Krikil alam 2-3cm 2,160.90 2160.9
Air kerja 451.50 451.5

TENAGA
Tukang batu 0.578 0.58
Kepala tukang batu 0.059 0.06
Pekerja 3.465 3.47
Mandor 0.174 0.17

PEMBESIAN POLOS
BAHAN
Besi beton polos 2.21 2.21
Kawat beton 0.03 0.03

TENAGA
Tukang besi 0.015 0.015
Kepala tukang besi 0.001 0.001
Pekerja 0.015 0.015
Mandor 0.001 0.001

BEKISTING LANTAI
BAHAN
Kayu kelas III 0.08 0.08
Paku usuk/reng 0.84 0.84
Minyak begesting 0.42 0.42
Kayu kelas III 0.03 0.03
Triplek 9 mm 0.74 0.74
Kayu dolken ø 10cm - 4 m 12.60 12.60
TENAGA
Tukang kayu 0.693 0.693
Kepala tukang kayu 0.069 0.069
Pekerja 1.386 1.386
Mandor 0.069 0.069

9 Plat Sunscreen tebal 8 cm 1.58


BETON (K-175)
BAHAN
Semen 515.08 515.1
Pasir cor 1,200.80 1200.8
Krikil alam 2-3cm 1,625.82 1625.8
Air kerja 339.70 339.7

TENAGA
Tukang batu 0.43 0.43
Kepala tukang batu 0.04 0.04
Pekerja 2.61 2.61
Mandor 0.13 0.13

PEMBESIAN POLOS
BAHAN
Besi beton polos 1.66 1.7
Kawat beton 0.02 0.02

TENAGA
Tukang besi 0.011 0.011
Kepala tukang besi 0.001 0.001
Pekerja 0.011 0.011
Mandor 0.001 0.001

BEKISTING LANTAI
BAHAN
Kayu kelas III 0.06 0.063
Paku usuk/reng 0.63 0.632
Minyak begesting 0.32 0.316
Kayu kelas III 0.02 0.024
Triplek 9 mm 0.55 0.553
Kayu dolken ø 10cm - 4 m 9.48 9.480

TENAGA
Tukang kayu 0.52 0.521
Kepala tukang kayu 0.05 0.052
Pekerja 1.04 1.043
Mandor 0.05 0.052

XI. PEKERJAAN KAYU/BESI, PINTU, JENDELA DAN PENGUNCI


1 Kusen Pintu dan Jendela Kayu Klas II 0.82
BAHAN
Kayu klas II 0.98 1.0
Paku usuk/reng 1.03 1.0
Lem kayu 0.82 0.8

TENAGA
Tukang kayu 14.76 14.8
Kepala tukang kayu 1.48 1.5
Pekerja 4.92 4.9
Mandor 0.02 0.0

2 Daun Pintu Panel Kayu Klas II 14.11


BAHAN
Papan kayu kls II 0.56 0.6
Lem kayu 7.06 7.1

TENAGA
Tukang kayu 42.33 42.3
Kepala tukang kayu 4.23 4.2
Pekerja 14.11 14.1
Mandor 0.71 0.7
3 Daun Jendela Kaca 3 mm 7.40
BAHAN
Papan kayu kls II 0.18 0.2
Lem kayu 2.22 2.2
Kaca bening 3 mm 6.59 6.6

TENAGA
Tukang kayu 17.76 17.8
Kepala tukang kayu 1.78 1.8
Pekerja 5.92 5.9
Mandor 0.30 0.3

4 Daun Fentilasi Kaca 3 mm 0.63


BAHAN
Papan kayu kls II 0.02 0.0
Lem kayu 0.19 0.2
Kaca bening 3 mm 0.56 0.6

TENAGA
Tukang kayu 1.51 1.5
Kepala tukang kayu 0.15 0.2
Pekerja 0.50 0.5
Mandor 0.03 0.0

5 Kusen Aluminium 4 in 14.70 14.7


6 Daun Pintu Aluminium 3.00 3.0

7 Kunci Pintu 6.00


BAHAN
Kunci pintu 2 slaag klas menengah 6.00 6.0

TENAGA
Tukang kayu 3.00 3.0
Kepala tukang kayu 0.30 0.3

8 Engsel Pintu 18.00


BAHAN
Engsel pintu klas biasa 18.00 18.0

TENAGA
Tukang kayu 2.25 2.3
Kepala tukang kayu 0.23 0.2

9 Engsel Jendela dan Fentilasi 88.00


BAHAN
Engsel Jendela klas biasa 88.00 88.0

TENAGA
Tukang kayu 8.80 8.8
Kepala tukang kayu 0.88 0.9

10 Kait angin Jendela dan Fentilasi 88.00


BAHAN
Kait angin klas menengah 88.00 88.0

TENAGA
Tukang kayu 8.80 8.8
Kepala tukang kayu 0.88 0.9

11 Expagnolet 3.00
BAHAN
Expagnolett 3.00 3.0

TENAGA
Tukang kayu 0.30 0.3
Kepala tukang kayu 0.03 0.0
12 Grendel Jendela dan Fentilasi 44.00
BAHAN
Grendel besar klas menengah 44.00 44.0

TENAGA
Tukang kayu 4.40 4.4
Kepala tukang kayu 0.44 0.4

XII. PEKERJAAN RANGKA ATAP, ATAP, PLAFOND


1 Plafond Kalsiboard rangka kayu 4/6 cm 193.00 96.5 96.5
2 Rangka Baja Ringan C 80 244.40 122.2 122.2

3 Atap Genteng Pres Beton Flat 244.40


BAHAN
Genteng beton 2,688.40 1344.2 1344.2
Paku 4-6 cm 7.33 3.7 3.7

TENAGA
Tukang kayu 24.44 12.2 12.2
Kepala tukang kayu 2.44 1.2 1.2
Pekerja 48.88 24.4 24.4
Mandor 2.44 1.2 1.2

4 Bubungan Genteng Beton Flat 34.05


BAHAN
Bubungan Genteng beton 119.17 119.2
Semen 367.74 367.7
Pasir pasang 1.09 1.1
Paku 4-6 cm 1.70 1.7
Semen warna 34.05 34.1

TENAGA
Tukang kayu 6.81 6.8
Kepala tukang kayu 0.68 0.7
Pekerja 13.62 13.6
Mandor 0.68 0.7

5 List Plank Kayu bersusun 2/20 dan 2/10 31.20


BAHAN
Papan kayu kls II 0.34 0.3
Paku usuk/reng 3.12 3.1

TENAGA -
Tukang kayu 6.24 6.2
Kepala tukang kayu 0.78 0.8
Pekerja 3.12 3.1
Mandor 0.16 0.2

XIII. PEKERJAAN PENGECATAN


1 Cat Dinding, Plat, Kolom, Balok dan Plafond 531.81
BAHAN
Plamir tembok 53.18 26.6 26.6
Cat tembok klas menengah 249.95 125.0 125.0
Amplas 265.91 133.0 133.0
Roll cat 5.32 2.7 2.7
Kape 26.59 13.3 13.3

TENAGA
Pekerja 31.91 16.0 16.0
Tukang cat 21.27 10.6 10.6
Kepala tukang cat 2.13 1.1 1.1
Mandor 1.60 0.8 0.8

2 Cat Kusen, Daun Pintu, Jendela dan list Plank 86.09


BAHAN
Plamir Kayu 6.89 6.9
Cat kayu klas menengah 14.64 14.6
Cat kayu klas menengah 25.83 25.8
Minyak cat klas menengah 17.22 17.2
Kuas cat 1.72 1.7
Amplas 86.09 86.1

TENAGA
Pekerja 12.91 12.9
Tukang cat 12.91 12.9
Kepala tukang cat 1.29 1.3
Mandor 0.69 0.7

3 List Plafond Gypsum 12x12 cm 130.00 130.0

XIV. PEKERJAAN INSTALASI LISTRIK


1 Instalasi Titik Lampu 18.00 18.0
2 Lampu Philip 18 watt 12.00 12.0
3 Lampu tl 20 watt 6.00 6.0
4 Stop kontak 6.00 6.0
5 Saklar Double 4.00 4.0
6 Saklar Tunggal 6.00 6.0
7 Penangkal Petir 1.00 1.0

XV. PEKERJAAN INSTALASI AIR


1 Klouset Jongkok porselin ex Toto 3.00 3.0
2 Kran air Ø 1/2" 6.00 6.0
3 Avoor 3.00 3.0
4 Pipa Air Paralon 1/2 in & Accessories 42.00 42.0
5 Pipa Paralon Pembuang Kotoran 4 in & Accessories 24.00 24.0
6 Pipa diameter 1 in pipa penguras dari tengki Air 20.00 20.0
7 Ember Besar 3.00 3.0
8 Tengki Air Fiber 1000 L 2.00 2.0

Mataram, 16 April 2013


Dibuat Oleh :
CV. AGUNG JAYA

NARTO
Direktur

You might also like