Document Title: Document Number: QPMO-410-CT-02274 Design & Build Temporary Water Supply Project
Method Statement, ITP And Risk Assessment for Tankers Water Supply
Please align the resources with the Org Chart (ex. Project
5 5 Responsibilities Hazem Al Naser
Manager Vs Project Director, etc…) (Complied PM )
Status A: Accepted as is
Status B: Accepted with comments Restriction Level: ☐ Restricted ☐ Unrestricted
Status C: Not accepted Page 1 of 4
No labs in Riyadh were provided (2 in Dammam and 1 from
Attachment 1 ITP - E -
12 outside KSA). Is it possible to have an approved lab in Hazem Al Naser
Approved Testing Laboratories
Riyadh. (3rd Party ITL is ACES)
Status A: Accepted as is
Status B: Accepted with comments Restriction Level: ☐ Restricted ☐ Unrestricted
Status C: Not accepted Page 2 of 4
It’s important to adjust driving based on the road conditions.
Access road conditions on-site and on the road for any
24 Risk Assessment Allauddin Choudhry
issues. It’s best to avoid pothole-ridden, damaged, and old
roads. ( Incorporate with comment added into the section3)
Status A: Accepted as is
Status B: Accepted with comments Restriction Level: ☐ Restricted ☐ Unrestricted
Status C: Not accepted Page 3 of 4
An internal tracking system shall be described in this
method statement to make sure that all the water tankers are
34 Section8 sourcing water from legal sources. (complied in Sec. 8.2 & Bilel Alouani
8.4)
I dont see the recovery plan for tankers that may have
36 Tanker Recovery mechanical issues on Qiddiya.Is there point of contact in Logistics Manager
place for the duration of the project. (complied in Sec. 8.5)
Status A: Accepted as is
Status B: Accepted with comments Restriction Level: ☐ Restricted ☐ Unrestricted
Status C: Not accepted Page 4 of 4