1. A roofing tile which has the shape of an "S" laid on its side
C Mission tile
2. That part of the building foundation which forms the permanent retaining wall of
the structure below grade
C Grad beam
C Block outs
4. A system of framing a building in which the studs are continuous to roof supporting
second floor joints
C Western framing
5. Rough plaster finish obtained by flinging plaster on a wall with a hand operated
machine
C Girt
A Alabaster B Casein
C Temperea
A Annealing B Alloy
C Built-up
9. The horizontal distance from the face of a lock or latch to the center of the knob or
lock cylinder
A Built-up B Backset
C Backfill
10. A commercially pure iron of fibrous nature, valued for its corrosion resistance and
ductility
C Wrought iron
A Tahilan B Pabalagbag
C Pilareta
12. Riser Filipino term
A Takip-silipan B Muldura
C Planehuelda
A Sinturon B Hardinera
C Guililan
A Suban B Poleva
C Espolon
A Pantilya B Asintada
C Hulog
A Tie B Continuous
C Cantilever
17. A wall (bearing or non-bearing) designed to resist lateral forces parallel to the wall
A Prefabricated B Shear
C Non-bearing
18. A modern method of installing wood parquet flooring on wooden boards sub-
flooring is by
C Gluing / pasting
19. The standard height of window sills for office rooms in upper floors
C 0.60 meters
20. The dimension of commercial acoustic boards for aluminum T-runners used for
dropped-ceiling in offices
21. In the design of a large shopping centers where space is required, intervals of
columns can be wider than the ordinary by adopting a structural method of
construction
A Pre-casting B Compressioning
C Post-tensioning
23. Heat gain through the structure of a habitable room occur in tropical region at walls
and roofs by conduction. This can be minimized by the use of
A Wood B Steel
C Concrete
C Wall paper
25. Dry walls do not require appreciable mount of moisture and they are customarily
finished with
C Plywood on studs
26. Wallboards or plywood maybe applied over studs. They can also be applied over
CHB masonry wall by using
A Furring B Sheathing
C Wood battens
27. To turn back water whenever joints occur in which dissimilar materials come
together, it is necessary to provide
C Counter flushing
28. The part of a foundation system which supports the exterior walls of a
superstructure and bears directly on the column footing is a
C Grade beam
29. A narrow strip of wood applied to cover a joint along the edges of two parallel
boards in the same plane
A Fillet B Batten
C Strip
C Pre-casting
31. The boxing in of covering a joist, beam or girder to give the appearance of a larger
beam
C Beam formworks
32. A system of framing a building on which floor joists of each storey rest on the top
plates of the storey below and teh bearing walls and partitions rest on the subfloor
of each storey
C Western framing
33. Pressure exerted against the underground portion of a building created by the
presence of water in the soil
C Hydrostatic pressure
34. A window which projects outside the main line of a building and the compartment
in which it is located extends to the floor
C Oriel window
35. A form of brick bond in which each course is alternately composed of entirely of
headers or of stretchers
C Flemish bond
36. A joint formed when a concrete surface hardens before the next batch of concrete
is placed against it
C Control joint
37. An iron alloy usually including carbon and silicon which has high compressive
strength but low tensile strength
C Pig iron
A Moneyka B Kusturada
C Lastilyas
A Barakilan B Estunyo
C Sibe
A Balangkas B Tahilan
C Reostra
A Tabike B Sibe
C Sopo
A Sinturon B Baytang
C Tahilan
43. Best material which will reduce moisture in a wall when used
A Cleaning B Re-painting
C Adequate insulation
45. Heat gain through the walls in buildings exposed to afternoon sun intensifies
discomfort of inhabitants because of conductivity. However, this can be minimized
by the use of
C Thick RC wall
46. Sound or noise between bedrooms may be reduced by using less expensive
materials with the application of construction techniques
47. One method of leveling batter boards without the transit is the use of
C Plumb bob
48. A manual method of squaring the corners of a building lines in building layout is
the use of
A 4-5-4 multiples and strings B 2-3-4 multiples with the use of transit
50. Due to temperature effects in materials, concrete walls, slabs of long buildings,
new building adjoining existing buildings should be provided with
C Flashing
Answer Key
1. b 2. a 3. a 4. a
5. a 6. b 7. b 8. b
49. a 50. a