ESTIMATION OF R.C.

C SLAB CULVERT
Item No. Description No. Length(m) Breadth(m) Height(m) Quantity Remark
1 Earthwork excavation
Abutment 2 5 0.7 0.6 4.2 L=4.8+0.15+0.15=5.1
Wing wall 4 1.2 0.7 0.6 2.016 L=1.2
2 Cemant concreting
Abutment 2 5.1 0.7 0.3 2.142 L=4.8+0.15+0.15=5.1
Wing wall 4 1.2 0.7 0.3 1.008 L=1.2
3 1st class brickwork
1:4 cement mortar
Abutment 2 4.8 0.4 1.5 5.76 L=4.8,B=0.4,H=1.30+20=1.5m
Wing wall 4 1.2 0.4 1.5 2.88 80-50=0.3

Parapet upto kerb 2 4.7 0.4 0.3 1.128


Paarapet above kerb 2 4.7 0.3 0.5 1.41
Coping 2 4.9 0.4 0.1 0.392 L=4.8+0.1=4.9,H=0.1
Total= 11.57
Deduction of bearing slab 2 4.8 0.3 0.2 0.576
11.57-0.576=10. 10.994
4 Slab 1:2:4 1 4.8 2.1 994 10019.52
5 Bar bending scheduling
No.straight bar 4.8/0.3+1=17
Main bar 17 2.38 40.46 2.1-2x0.04+2x9x0.02=2.38
No. Of bentup bar 4.8/0.3=16
2.38+0.16=2.54
Alternative bentup bar 16 2.4 38.4
D*D/162*L=20*20/162*78.6=1

940Kg =1.94 quintal


Total= 78.86

Distribution bar
Bottom bar 9 4.9 44.1
NAME- SUBHAM RAJU
SEM - 5TH
BRANCH - CIVIL
REGDNO - F21115001051
Top bar 4 4.9 19.6
D*D/162*L=10*10/162*L=39.
32Kg =0.39 quintal
Total= 63.7

6 Wearing coat 2 4 2.3 0.1 1.84 B=1.5+0.4+0.4=2.3,H=0.1


7 Cement pointing work
Face wall excluding coping 2 4.7 2.1 19.74 B=1.3+0.7+0.1=2.1
Inner side face wall 2 4.7 0.8 7.52 H=0.1+0.2+0.5=0.8
Coping 2 4.9 0.7 6.86
Side parapet wall upto kerb 4 0.4 0.2 0.32
Side parapet wall above kerb 4 0.5 0.4 0.8
Coping side wall 4 0.4 0.2 0.32
Total= 35.56
Deduction rectangle block 2 1.5 1.3 3.9
Triangle block 2 1.3 1.3 1.69 1/2x1.3x1.3=0.84
Deduction
Total= 5.59
Net Total 29.97 35.56-5.59=29.97