Professional Documents
Culture Documents
(BusinessPro Collection) Dobson, Michael Singer - Successful Project Management - How To Complete Projects On Time, On Budget, and On Target-Ama Self-Study - American Management Association (2015)
(BusinessPro Collection) Dobson, Michael Singer - Successful Project Management - How To Complete Projects On Time, On Budget, and On Target-Ama Self-Study - American Management Association (2015)
Fourth Edition
Michael S. Dobson
Successful Project Management, Fourth Edition
How to Complete Projects on Time, on Budget, and on Target
© 2015 American Management Association. All rights reserved. This material may not be reproduced, stored in a retrieval system,
or transmitted in whole or in part, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise,
without the prior written permission of the publisher.
ISBN 13: 978-0-7612-1567-7
ISBN 10: 0-7612-1567-0
AMACOM Self-Study Program
http://www.amaselfstudy.org
AMERICAN MANAGEMENT ASSOCIATION
http://www.amanet.org
Contents
About This Course xiii
How to Take This Course xv
Pre-Test xvii
Common Stakeholders
Other Stakeholders
Issues in Stakeholder Management
Constraints
Hierarchy of Constraints
Ranking Constraints
Assumptions
Project Charter
Obtaining Approval and Buy-In
Progressive Elaboration and the Project Objective
Recap
Review Questions
Recap
Review Questions
List of Exhibits
Exhibit 1–1 Case Study: Establishing a Project Management Office (PMO)
Exhibit 1–2 The Five Project Management Process Groups
Exhibit 1–3 The Ten Project Management Knowledge Areas
Exhibit 2–1 Phases
Exhibit 2–2 Analyzing Stakeholders
Exhibit 2–3 The Triple Constraint
Exhibit 2–4 Hierarchy of Constraints
Exhibit 3–1 Statement of Work
Exhibit 3–2 Guidelines for Writing Requirements
Exhibit 3–3 Work Breakdown Structure in “Org Chart” and Outline Format
Exhibit 3–4 Department Based vs. Phase Based WBS
Exhibit 3–5 Network Diagram
Exhibit 3–6 Critical Path
Exhibit 3–7 Forward Pass
Exhibit 3–8 Forward Pass Summary
Exhibit 3–9 Backward Pass
Exhibit 3–10 Backward Pass Summary
Exhibit 3–11 Critical Path and Float
Exhibit 3–12 Critical Path and Float Summary
Exhibit 3–13 Gantt Chart
Exhibit 3–14 Gantt Chart Data
Exhibit 3–15 Completed Gantt Chart
Exhibit 4–1 PERT Formulas
Exhibit 4–2 Standard Deviation Diagram
Exhibit 4–3 Z Table
Exhibit 5–1 Skill Requirements
Exhibit 5–2 Team Skills
Exhibit 5–3 Responsibility Assignment Matrix
Exhibit 5–4 Crashing a Project Using CPM
Exhibit 5–5 Summary of Crashing Activities
Exhibit 5–6 Communications and Stakeholder Management Plan Template
Exhibit 6–1 The Project Environment
Exhibit 6–2 Risk Identification
Exhibit 6–3 Sample Risk Register
Exhibit 6–4 Risk Triage Flowchart
Exhibit 6–5 Probability and Impact Matrix
Exhibit 6–6 Expected Monetary Value
The management of projects is often vital to the success and growth of organ-
izations. Unlike ongoing operations, projects are both temporary and unique.
Because they are temporary, they often do not have the benefit of fully devel-
oped, mature, and permanent organizations devoted to their success. Because
they are at least in some respects unique, they each involve special problems,
issues, and considerations.
Project management, in a nutshell, is the art, craft, and science of manag-
ing projects. It is a wide-ranging and complex discipline that incorporates and
uses elements from many different disciplines. Although project management
was once considered just an aspect of such fields as architecture or engineering,
today project management is considered to be a discipline in its own right.
In a fast-moving and fast-changing world, project management skills are
often a vital element in your career growth and ultimate success. Even when
managing projects is only an element of your overall job, success in managing
projects often has a disproportionate impact on your career.
Successful Project Management, Fourth Edition, is an introductory course in
project management. In this course, you will learn the fundamental concepts,
strategies, techniques, and approaches of modern project management. The
course is designed for active project managers, technical team members who
need to understand the overall project approach in order to perform their roles
effectively, and senior managers and executives who must hire, supervise, and
evaluate project managers in their employ.
We will follow the basic project management approach as laid out in A
Guide to the Project Management Body of Knowledge (PMBOK® Guide), 5th Edition,
popularly known as the PMBOK® Guide, along with other sources listed in
the Bibliography and Recommended Reading section at the end of the course.
We strongly encourage you to read and study widely.
This course consists of text material for you to read and three types of activ-
ities (the Pre- and Post-Test, in-text exercises, and end-of-chapter Review
Questions) for you to complete. These activities are designed to reinforce the
concepts brought out in the text portion of the course and to enable you to
evaluate your progress.
Certificate
Once you have taken your post-test, you will receive an email with your grade
and a certificate if you have passed the course successfully (70% or higher).
All tests are reviewed thoroughly by our instructors, and your grade and a
certificate will be returned to you promptly.
The Text
The most important component of this course is the text, for it is here that
the concepts and methods are first presented. Reading each chapter twice will
increase the likelihood of your understanding the text fully.
We recommend that you work on this course in a systematic way. Only
by reading the text and working through the exercises at a regular and steady
pace will you get the most out of this course and retain what you have learned.
In your first reading, concentrate on getting an overview of the chapter’s con-
tents. Read the learning objectives at the beginning of each chapter first. They
serve as guidelines to the major topics of the chapter and enumerate the skills
you should master as you study the text. As you read the chapter, pay attention
to the heading and subheadings. Find the general theme of the section and
see how that theme relates to others. Don’t let yourself get bogged down with
details during the first reading; simply concentrate on remembering and un-
derstanding the major themes.
In your second reading, look for the details that underlie the themes.
Read the entire chapter carefully and methodically, underlining key points,
working out the details of the examples, and making marginal notations as
you go. Complete the exercises.
FOR QUESTIONS AND COMMENTS: You can also contact Self Study at 1-800-225-3215
or visit the website at www.amaselfstudy.org.
10. Look at the WBS that follows this question. How is it organized?
(a) By department or work group
(b) By phase
(c) By cost account
(d) By difficulty or risk
Develop a Course
Instructional Systems
Production Operations Marketing
Design
Ship Materials to
Develop Exercises Conduct Beta Test Approve New Course
Seminar Location
Finalize Course
13. The extent to which the project’s product, service, and result satisfy the
needs for which it was undertaken is known as:
(a) quality.
(b) scope.
(c) risk.
(d) WBS.
14. Look at the following network diagram. What is the critical path?
(a) A→B→D→H
(b) A→E→C→D→H
(c) A→E→F→G→H
(d) A→C→H
Activity B Activity D
4 days 3 days
15. Today, we were supposed to have completed four activities that were
planned to cost $2,500 each. We have actually accomplished only three
of those activities and we have spent $7,000 to date. In earned value
method terms, what is our cost performance index, rounded to the
nearest whole percent?
(a) 93%
(b) 107%
(c) 75%
(d) 133%
18. What performance measurement baseline can serve as a metric for all
three triple constraints?
(a) Cost baseline
(b) Responsibility assignment matrix
(c) Tracking Gantt chart
(d) Weekly status reports
20. How frequently should you hold status meetings or require status
reports?
(a) Preferably weekly, but no less often than monthly
(b) Whenever a problem or issue arises
(c) When the project sponsor or customer need an update
(d) Varies based on the speed of change within the project
25. You have identified a risk that the price of raw materials you need for
the project could potentially double in price by the time you would
normally purchase them. You decide you will buy the materials far in
advance of need to lock in the price. What risk response strategy have
you used?
(a) Avoid
(b) Mitigate
(c) Transfer
(d) Contingency plan
Learning Objectives
By the end of this chapter, you should be able
to:
• Describe the origins and growth of project
management as a discipline.
• Define projects and project management and
explain the concepts of progressive elabora-
tion and iterative activity as they apply to proj-
ect management.
• Describe the relationship between projects
and the organization, including the roles of
programs and portfolios, the function of a
Project Management Office (PMO), and the
characteristics of functional, projectized, and
matrix organizations.
• Identify and describe the five fundamental
processes of project management.
• List and define the ten knowledge areas of
project management.
In the United States, the largest and best-known project management or-
ganization is the Project Management Institute (PMI), established in 1984. Its
standard terminology and guidelines for project management are contained
in A Guide to the Project Management Body of Knowledge (PMBOK® Guide), currently
in its fifth edition. The PMBOK® Guide is used by both the American National
Standards Institute (ANSI) and the Institute of Electrical and Electronics En-
gineers (IEEE) as its official standard. The PMI offers a range of credentials
for project managers, most famously the Project Management Professional
(PMP®) designation. This course is designed to be compatible with the fifth
edition of the PMBOK® Guide.
xhibit 1–1
Case Study: Establishing a Project Management Office (PMO)
You’ve learned that many organizations establish a Project Management Office (PMO) to provide
guidance, leadership, resources, and technical support to individual projects throughout the organ-
ization, and your CEO has expressed a desire to establish a PMO function in your own organization.
Because you are studying project management, you’ve been asked to lead this project.
In your initial discussions, you discover that the organization has relatively little understanding
of what a PMO is or what it does, and that some managers are skeptical of it. There is a concern
that managers may lose power and authority to the new PMO. On the other hand, several recent
projects have ended up failing, and there is a fear that your competitors, many of whom already
have PMOs, may pull ahead in the marketplace.
You have been directed to establish a PMO in time for the annual stockholders’ meeting, which
will take place in nine months.
Exercise 1–1
Getting Started
Instructions: We will use the Exhibit 1–1 case study, “Establishing a PMO,” throughout this book to
practice the skills we are learning.
When you are first given a project, it’s often the case that the project is not fully fleshed out,
and that’s okay. You normally must go through a process of gaining additional understanding and
insight about the project before you can manage it effectively. Read the following series of ques-
tions. Some of the answers are contained in the case study description, but not all of them. Answer
the questions to the best of your ability. Don’t worry if you can’t answer every question fully—that’s
quite normal at the beginning of a project.
When you have finished, turn to Appendix A: Answers to Exercises and Case Studies at the end
of this course to compare your responses with ours.
2. Why are we doing this project? How will the project benefit us if it is successful?
6. Who are the stakeholders—the people who will be affected by our project?
7. Does our project face opposition? What is the nature of that opposition? Why are some people
opposed? Can their issues be addressed?
8. Are there any major known risks that we can see at the beginning of the project?
special effects, transportation, and craft services. This gives maximum control
to the project manager (director or producer) at the expense of significant du-
plication of effort.
Matrix organizations seek to have the best of both worlds (and occasion-
ally end up with the worst of both worlds) by combining elements of func-
tional and projectized based on the needs of the individual organization. In
weak matrix organizations, project managers have limited cross-departmental
authority and primarily coordinate and persuade. Strong matrix organizations
give project managers substantial authority to direct and control resources
even though they live in functional departments, and balanced matrix organ-
izations operate somewhere in between.
No organizational structure is right for all situations; each contains both
advantages and disadvantages. As a project manager, you need to understand
your own organizational environment (which may include unofficial as well
as official characteristics) in order to operate effectively. It’s never the case
that every decision and element will be optimized for your specific project
needs (nor should it be), so you will always need to adapt your project to its
environment.
Is your organization primarily functional, projectized, or matrix? Do you have a PMO, and if so,
what type is it? What do you see as the advantages and disadvantages as far as your projects are
concerned?
Project Initiation
Before there is a project, there is some sort of need—a gap between where
we are and where we want to be. There may be more than one way to bridge
xhibit 1–2
The Five Project Management Process Groups
that gap, but eventually someone in authority (customer, project sponsor, ex-
ecutive) decides on the basic direction, and that leads to a project.
A project is not only temporary and unique, but also purposeful. Even if
the project is accomplished on time, on budget, and meets requirements, it’s
hard to call it successful if it doesn’t achieve its goal.
The process of project initiation involves defining this potential project,
determining how much it is likely to cost and how long it is likely to take, and
deciding who will lead the project and who will staff it. Though it’s ideal if
you’re involved in that process if you will eventually be the project manager,
it’s quite common for most of these major decisions to be made by other peo-
ple before you receive the project assignment.
Whether or not you were part of the process of defining the project, when
you get the assignment it’s a good idea to perform your own due diligence be-
fore committing yourself to the work. In particular, it’s desirable to take a good
hard look at assumptions and constraints.
Assumptions are things we believe to be true though we don’t actually have
any proof. It’s often necessary to make assumptions. In a research project, you
must assume that an answer actually exists—even though you may discover
later that it doesn’t, or that it isn’t at all what you expected or wanted. Often,
such factors as the budget and deadline rest on the assumption that there won’t
be any other important projects or emergencies that will interrupt you. Some
assumptions are more realistic or likely than others, but all assumptions need
to be out in the open where people can examine them properly.
Constraints are things that limit your choices. A deadline is a constraint;
so is a budget. Rules, laws, and policies are constraints. The particular skill
sets and talents available to you for the project are constraints. Sometimes
constraints are negotiable; other times they are not. The nature and extent of
constraints has a major effect on your ability to accomplish the project. Un-
derstanding them from the beginning is a crucial element in your eventual
success.
The project initiation phase ends with a project charter. That’s the formal,
written document that authorizes the project. The project charter takes many
different forms in different organizations, and often isn’t called by that name.
Still, it’s vital to have a clear, bright line that separates just talking about a
project from a formal directive to get started on it.
How is a new project established in your organization? Is there a formal project charter? Is there
another document that accomplishes the same thing? What works well or needs improvement in
how you start a project?
Project Planning
Project planning includes all the tools and processes necessary to define, or-
ganize, and develop the course of action that will accomplish the project goals.
It includes plans to manage schedule, cost, scope, risk, procurement, quality,
human resources, and stakeholders.
It is often said that failing to plan is planning to fail. Most of the tools
and techniques generally thought of as “project management” are actually
tools for planning: the work breakdown structure, Gantt charts, network dia-
grams, and the like. If project management is an “iterative process of progres-
sive elaboration,” as we’ve said, then project planning is the methodology to
accomplish this.
Many people confuse a project schedule with a project plan. Although
clearly a schedule is part of a plan, so is the budget, the communications strat-
egy, the risk management approach, and many other elements. Because proj-
ects differ, individual project plans may emphasize one of these elements more
than another.
Unless the project is fairly simple, planning doesn’t end just because
you’ve started work. Often, important parts of the project remain obscure until
some preliminary activities are complete. If you’re going to test a prototype
of whatever you’re building, the outcome of the test will reveal what corrective
actions are necessary. Until the test is performed, you don’t know what those
actions might be, and therefore you can’t do a whole lot of detailed planning
until you reach that point. Often, you begin with a plan that is detailed in its
opening phases but becomes increasingly sketchy as it extends into the future,
and you fill in the details (iterate and progressively elaborate) as you gain new
information.
Project Execution
The project plan describes what you are supposed to do, and project execution
is the process of actually doing it. In project execution, you assign project ac-
tivities to people, allocate resources (including, but not limited to, money),
and work with customers and other stakeholders. Although project execution
usually takes the majority of the total project schedule, budget, and other re-
sources, it doesn’t involve many specific “project management” techniques
and thus tends to get relatively little space in a book/course such as this.
Project Closing
Because projects end, they need to be closed. Project closing is the process of
ensuring that the project deliverables have been accomplished and are satis-
factory in the eyes of the customer, that they have been transferred to their
appropriate destinations or new owners, that any contracts or procurement
actions have been completed, that project team members and other resources
are released to do other work, and that the necessary paperwork is done and
archived. The closing process also includes the process of lessons learned.
What if a project is cancelled before it is completed? Sometimes projects
fail, customer needs change, or other demands require the resources allocated
to your project. No matter why the project ends, there’s still paperwork, doc-
umentation, releasing resources, and preparing lessons learned. Therefore,
you must conduct project closeout for every project, regardless of the circum-
stances of its end.
Strangely, many project plans—even those done by highly experienced
project managers—often neglect the closeout process and allocate no time or
resources to its performance. This is an embarrassing mistake, but one that is
easily corrected. The project deadline and the actual end of the project aren’t nec-
essarily the same thing. The deadline usually refers to the point in time at which
you complete the actual work of the project; many closeout activities, such as
lessons learned and archiving, must necessarily happen after the deadline.
Do you have a formal closing out process for projects? Does it include “lessons learned”? What
works well or needs improvement when it comes to completing projects in your organization?
xhibit 1–3
The Ten Project Management Knowledge Areas
Core Constraints
Project
Project Time Project Cost
Scope
Management Management
Management
People
Project Project
Project
Communi- Human
Stakeholder
cations Resources
Management
Management Management
Issues
Project Project
Project Risk
Quality Procurement
Management
Management Management
time management also includes the process of monitoring and controlling the
schedule to ensure the project stays on track.
members may be assigned full-time to your project for its duration, but may
also be available to you only on a part-time basis.
Developing a project plan involves assigning the appropriate people to
accomplish activities, making sure people aren’t inadvertently double-booked
on multiple assignments, overseeing and managing their work, and handling
the associated documentation, such as time reporting.
Exercise 1–2
Knowledge Areas
Instructions: In this exercise, we build on the case study first defined in Exhibit 1–1 and Exercise
1–1, fleshing out what we currently know about each of the ten knowledge areas as they apply to
this project. For each knowledge area, record all available information you have learned to this
point.
As before, you normally (both in the exercise and in real life) have limited information and will
not be able to answer questions fully at this stage. We will continue the process of progressive
elaboration in an iterative process as the project moves forward.
1. Project Integration Management. What we know about our role as project manager in bringing
this project together and leading it to a successful conclusion.
2. Project Time Management. What we know about the schedule and any time constraints.
3. Project Scope Management. What we know about the work that must be done, and the work
that is not included in this project.
4. Project Cost Management. What we know about the budget, resource availability, and anything
else we might spend to accomplish the project.
5. Project Communications Management. What we know about the need to report and com-
municate with others during the project.
6. Project Stakeholder Management. What we know about people affected by the project, their
interests, and their issues.
7. Project Human Resources Management. What we know about the people and skills we need
to accomplish the work.
8. Project Quality Management. What we know about factors that determine whether this project
will meet the needs for which it was established.
9. Project Procurement Management. What we know about any products or services to be ac-
quired outside the organization.
10. Project Risk Management. What we know about project threats and opportunities.
Review Questions
INSTRUCTIONS: Here is the first set of review questions in this course. Answering the questions fol-
lowing each chapter will give you a chance to check your comprehension of the concepts as they are presented
and will reinforce your understanding of them.
As you can see below, the answer to each numbered question is printed to the side of the question.
Before beginning, you should conceal the answers in some way, either by folding the page vertically or by
placing a sheet of paper over the answers. Then read and answer each question. Compare your answers
with those given. For any questions you answer incorrectly, make an effort to understand why the answer
given is the correct one. You may find it helpful to turn back to the appropriate section of the chapter and
review the material of which you are unsure. At any rate, be sure you understand all the review questions
before going on to the next chapter.
5. The project process that links to all other project processes is known as: 5. (d)
(a) project planning.
(b) project intiation.
(c) project management office.
(d) project monitoring and control.
Take a real-life project you’re involved in and define the problem, opportunity, or issue it is intended
to address. Do you think the project as defined will properly address the issue?
PROJECT INITIATION
The PMBOK Guide® defines project initiation as “the processes performed to
define a new project or a new phase of an existing project.” These include
defining initial scope, budget, and time parameters, although they may evolve
significantly in the planning process. The major stakeholders are defined and
their interests and goals are identified. And somewhere in that process the
project manager is selected.
We normally think of a project as something with a defined beginning
and an end. From a technical perspective, that’s correct. We’ve just seen, how-
ever, that there’s a discussion process that precedes the project. Because a proj-
ect is a means to an end, there’s also an aftermath of a project, in which the
product, service, or result provides the benefit for which we did it in the first
place. Whereas project management as a discipline focuses on the project it-
self, a wider management perspective includes awareness of what comes be-
fore and after.
Some of the specific elements in project initiation include:
• Definition of the initial scope of work
• Preparation of the business case for the project
• Consideration of alternatives
• Consultation with stakeholders
• Preparation of the project charter
• Approval of the project
PROJECT OR PHASE
Notice that the PMBOK® Guide definition mentions both a new project and a
“new phase of an existing project.” Let’s imagine that our reason for upgrading
the trade show exhibit is based on a competitive analysis study. Of course, a
trade show exhibit isn’t a means to an end either. If we’re launching a major
new product line, the new trade show exhibit is part of the marketing push.
And let’s not forget the development of the new product line, which might
include engineering, industrial design, manufacturing, market testing, and
many other activities.
Each of these can be thought of as a separate, independent project, or as
a phase of an overall project, “bringing a new product to market.” Developing
a new pharmaceutical drug normally involves pure research, in which many
different compounds are studied, followed by initial testing, followed by fur-
ther testing, followed by the FDA approval process, followed by marketing.
Large and complex projects frequently take a phased approach. At the end
of each phase, there’s an opportunity to decide whether the project should con-
tinue, or whether it should be modified in light of what has been learned pre-
viously. Sometimes, the lead role on the project moves from one department or
team to another: the chemists working on a new drug turn it over to testers who
hand it to the people who manage the approval process, who turn it over to the
marketing team. There may be an executive overseeing the entire process, but
different individual project managers are responsible for specific phases.
If your project actually is a phase in some other, larger project, you need
to have at least a general understanding of the overall flow and how your par-
ticular section fits in. Whether or not your project is also a phase, it’s still a proj-
ect: a temporary and unique activity with a defined beginning and an end.
Exhibit 2–1 shows how a phased approach to a large project works for new prod-
uct development, a new shopping center, and a new IT system. Notice that each
phase contains the basic processes of a project, first shown in Exhibit 1–1.
Is your project complete in itself, or is it a phase in some larger project? Describe the larger project
and identify the phases that precede and follow yours.
STAKEHOLDERS
Stakeholders, as you’ll remember, are people or groups who are affected by
the project or who have an effect on the project. It can be the outcome of the
project, a particular task or activity of the project, the resources used by the
project, or decisions related to the project.
Stakeholders can be aligned with your project (positive stakeholders), be
opposed to your project (negative stakeholders), or have an unrelated second-
ary interest in your project (tangential stakeholders). Stakeholders can also
be mixed: positively aligned in some areas and opposed in others.
Stakeholders can have varying levels of impact on your project, and your
project can have varying levels of impact on stakeholders. Stakeholders can have
a stake in the entire life cycle of the project, or only in part of it. Some stake-
holders are hugely important in the project, and deserve a great deal of your
time, effort, and attention. Others are relatively minor, and require much less.
During project initiation, you should identify as many stakeholders as you
can, and determine their characteristics with respect to your project. However,
the stakeholder environment can change. You should keep a continuing eye on
your stakeholders and adjust your plan and approach as necessary.
Common Stakeholders
Some stakeholders commonly exist on almost every project. These include:
• Project sponsor: The manager or executive, usually internal, with over-
sight responsibility for the project. The project sponsor is usually the one
who makes major policy decisions.
• Customer: The person or group that has requested or purchased the prod-
uct, service, or result. Customers may be external to the organization or
internal. If internal, they may overlap with the project sponsor.
• Project manager: The person directly charged with managing and leading
the project. Though this is most often you, in a phased project, there may
be other project managers working before, after, or in parallel on elements
of the same overall project.
• Project team members: Project team members are those people responsi-
ble for performing specific project activities. Team members can work full
time on your project throughout the length of the project, but can also work
part-time or only on specific activities. They may or may not (more often
not) report to you in a formal supervisory relationship. Although they are
usually part of your organization, they may also be consultants or tempo-
rary hires. Team members may support several projects simultaneously,
and may also have regular, permanent jobs.
• Your own supervisor or manager: Though your supervisor or manager
may also be the project sponsor, this is not always the case. You may have a
permanent organizational home and job responsibilities, and you may need
xhibit 2–1
Phases
Each phase is a project in its own right, using the process approach shown in Exhibit 1–1.
Project Monitoring and Control Project Monitoring and Control Project Monitoring and Control Project Monitoring and Control
Project Project Project Project Project Project Project Project Project Project Project Project Project Project Project Project
Initiation Planning Execution Closeout Initiation Planning Execution Closeout Initiation Planning Execution Closeout Initiation Planning Execution Closeout
Project Monitoring and Control Project Monitoring and Control Project Monitoring and Control Project Monitoring and Control
New IT System
Project Project Project Project Project Project Project Project Project Project Project Project Project Project Project Project
Initiation Planning Execution Closeout Initiation Planning Execution Closeout Initiation Planning Execution Closeout Initiation Planning Execution Closeout
Project Monitoring and Control Project Monitoring and Control Project Monitoring and Control Project Monitoring and Control
There may be some overlap among these roles. The customer may also
be the project sponsor, who may or may not also be in your management chain.
Other Stakeholders
You shouldn’t confine your search for stakeholders to these common cate-
gories. Some projects have great public visibility and may engender contro-
versy. If your project uses outside vendors, they too are stakeholders. While
on one hand, vendors are positive stakeholders with a strong interest in the
success of your project, they also have a potential conflict of interest: their
business ends with your project.
Earlier, we mentioned a pharmaceutical project, which requires regula-
tory approval. The regulators are project stakeholders as well. People man-
aging other projects in your organization are stakeholders in your project if
you all draw your resources from the same pool: more for you can mean less
for them. If assigning credit for success or blame for failure can be given to
different people or groups, they become stakeholders as well. Your competi-
tors are stakeholders in your project, because your success or failure has a di-
rect impact on them.
In one sense, there’s an almost unlimited universe of potential stakehold-
ers, but fortunately they aren’t all equally important. Some stakeholders re-
quire significant attention, but you may be able to ignore others with little or
no consequences.
Exercise 2–1
Stakeholder Register
Instructions: Complete the stakeholder register for any stakeholders you can identify for the PMO
project we began in Chapter 1. The first stakeholder, the CEO, has been completed as an example.
xhibit 2–2
Analyzing Stakeholders
1. Define the stakeholder. Name and title if an individual; or the group if collective. Beware of
groups that may not all think the same way: the “general public” may contain both supporters
and opponents of your project. What is the major interest of each stakeholder?
Possible choices:
• Top management/CEO: Overall look and feel
• Marketing and sales executive and team: How well it works for their needs
• Exhibit vendors: Their capabilities, time constraints, and resources
• The trade show organization: Rules and standards for exhibits
• Trade show attendees: Does the exhibit attract them?
2. Impact of your project on the stakeholder. Impact can include both the work of the project
(consumption of resources, taking people away from other work, cost) and the outcome of the
project (what it does or doesn’t do, how well it works).
For the marketing and sales team, potential impact issues may include:
• Does the cost of the new exhibit come out of their budget?
• Will they have to supply team members to work on the project, taking them away from other
work?
• Will the final exhibit be easy to work in? Comfortable? Attractive?
• Will it attract the right customers?
• Will it look at least as good if not better than the competition?
• How much work will it be to set it up and take it down?
• Is is complicated to operate or prone to break down (fancy electronics, displays, computers)?
3. Impact of the stakeholder on you. What power does the stakeholder have over your project?
Is their cooperation and support necessary to your success? Must you do what they say? Do
they control access to resources, staff, and money?
For the marketing and sales team, potential issues may include:
• Are they driving the project or is it coming from the CEO/executive team?
• Do they really want a new exhibit?
• Do they decide how much money and which resources you get?
• What authority do they have to set requirements for the project?
• If they ask for something you believe is not feasible within the time and cost constraints, must
you accommodate them, or do you have the authority to refuse?
• If they are not pleased with the final result, even though you have met the requirements, what
will the consequences be for you?
4. Timing. Will this stakeholder be a stakeholder for the entire project, for specific phases of the
project, or for a single aspect of the project?
For the marketing and sales team, potential issues may include:
• Are they part of the decision whether to do the new exhibit?
• Do they get to approve the design?
• Will they be involved in vendor selection?
• Will they be involved in the actual work of the project?
• Will they approve the final result?
CONSTRAINTS
A project constraint limits your choices. If you have a budget of $50,000, you
aren’t supposed to spend $60,000. If you need to get the project done in time
for the stockholders’ meeting, there’s a consequence if you get it done three
weeks after the meeting. If your product must conform to a regulatory stan-
dard, it’s not successful if it fails to do so.
Every project has constraints. Depending on the constraints, the identical
project can be very easy or operationally impossible—or anything in between.
At the beginning of the project, it’s vital to get a handle on the constraints.
Some constraints may be negotiable, and others are fixed in stone.
Everyone’s heard the classic management joke: “Did you want it good,
fast, or cheap? Pick two.” This reveals one of the key concepts in project man-
agement: the triple constraint. Although projects can have many constraints, al-
most every project has the same three at the core, as shown in Exhibit 2–3.
xhibit 2–3
The Triple Constraint
It’s usually not a problem to be ahead of schedule, under budget, and exceeding performance.
Therefore, the triple constraints represent the least you can do and still call yourself successful.
All three constraints are not necessarily defined at the outset. When John
F. Kennedy said, “I believe that this nation should commit itself to achieving
the goal, before this decade is out, of landing a man on the moon and returning
him safely to the Earth,” he defined the time constraint (“before this decade
is out”) and the performance goal (“landing a man on the moon and returning
him safely to Earth”), but the cost constraint is nowhere to be found. That, of
course, doesn’t mean there wasn’t going to be a cost constraint, but merely
that it was still in the process of being analyzed and negotiated.
The “pick two” joke also reminds us that constraints are not always cre-
ated equal. Is it more important to bring the astronauts back alive or to stay
within the budget? What about “before the decade is out”?
Hierarchy of Constraints
Each project has its own priority. Sometimes the deadline is literal. Across it,
the project fails. If you lose, being on time and on budget may be scant com-
fort. Cost issues rule when the money or other resources just don’t exist, or
aren’t available to you. If you don’t have it, you can’t spend it and you can’t
use it. Finally, there are times when “good enough” isn’t. Achieving less than
the performance standard is failure. Sometimes saying “partial success” is like
saying “a little bit pregnant.”
There are a lot of different ways of looking at a project, and the triple
constraint approach is only one of those ways. Its special value comes when
you recognize that the triple constraints have a priority. In order, they are
driver, middle constraint, and weak constraint.
In a war, you can’t very well go back to your boss and say, “I lost, but in
my defense, I’m ahead of schedule and under budget.” Performance is the
driver. In some wars, there’s a pressure to get it done, which would make time
the middle constraint and cost the weak one. The best project management
approach is to use money and resources and overpower the enemy. Cost can
be the middle constraint, too.
If you’re a poor and small country, you simply might not be able to raise
a strong enough force no matter what you do. In that case, the best project
management approach is to play the long game, try to wear down the more
powerful adversary in hopes they will eventually get tired and go home.
In a rescue, time is usually the driver. The earlier someone can be recov-
ered, the greater the chance he or she will survive, and the clock is ticking for
some victims more rapidly than others. Performance is most often the middle
constraint. Although clearly it’s not a success if the victim doesn’t make it,
time pressure may justify taking a few extra risks when seconds are precious.
Cost is the weak constraint, because you can fund improved emergency re-
sponse if you’re willing to pay for it.
But sometimes cost can be the driver. The first rescue truck arrives on
the scene and what it carries is all you have to work with. Are there five pa-
tients and only three rescuers? Well, until another truck gets here, three res-
cuers are all you have. It doesn’t matter if there are ten more back at the
station, at least not until they can make it to the scene.
By the way, although the hierarchy of constraints usually stays the same
throughout the project, any major changes that impact your project may also
reorient your driver. Stay alert. Exhibit 2–4 shows the relationship between
the triple constraints and the hierarchy of constraints.
Ranking Constraints
How do you determine driver, middle, and weak constraints? Asking the proj-
ect sponsor or customer may or may not work. Often, the answer they care
about is, “All three.” But you can also frame it from the point of view of suc-
cess. “If I could finish early, and meet the cost and time constraints, or I could
finish on time and be under budget, or I could finish on time and on budget
but exceed the performance goals, which would you prefer?” Be careful,
though: what is true in one direction (success) isn’t automatically true in the
other (failure).
It may help to think of the hierarchy of constraints not as something that’s
chosen, but as something that flows naturally from the conception of the proj-
ect. It’s the reason for the project that establishes the hierarchy of constraints
for the project.
By the way, remember that although the hierarchy of constraints usually
stays the same throughout the project, any major changes that impact your
project may also reorient your driver. This is an important skill to master. In
Exercise 2–2, you’ll take a project and figure out its hierarchy of constraints.
xhibit 2–4
Hierarchy of Constraints
In a project, the triple constraints typically array themselves in a hierarchy, based not on how im-
portant they are, but how flexible they are: how much they can be stretched before we’re forced to
declare failure. The driver is least flexible. Failing the driver means failing the project. The middle
and weak constraints follow. You can use the extra flexibility (especially in the weak constraint).
Exercise 2–2
Hierarchy of Constraints
Instructions: Based on the following excerpt from JFK’s speech to Congress on going to the moon,
identify the triple constraints and rank them in the order of driver, middle, and weak constraint.
Finally, if we are to win the battle that is now going on around the world between free-
dom and tyranny, the dramatic achievements in space which occurred in recent weeks
should have made clear to us all, as did the Sputnik in 1957, the impact of this adven-
ture on the minds of men everywhere, who are attempting to make a determination of
which road they should take . . . . Now it is time to take longer strides—time for a great
new American enterprise—time for this nation to take a clearly leading role in space
achievement, which in many ways may hold the key to our future on earth.
I believe we possess all the resources and talents necessary. . . [but]. . . have never
specified long-range goals on an urgent time schedule, or managed our resources
and our time so as to insure their fulfillment.
Recognizing the head start obtained by the Soviets with their large rocket engines,
which gives them many months of lead-time, and recognizing the likelihood that they
will exploit this lead for some time to come in still more impressive successes, we nev-
ertheless are required to make new efforts on our own. For while we cannot guarantee
that we shall one day be first, we can guarantee that any failure to make this effort will
make us last . . . .
I therefore ask the Congress, above and beyond the increases I have earlier re-
quested for space activities, to provide the funds which are needed to meet the fol-
lowing national goals:
First, I believe that this nation should commit itself to achieving the goal, before this
decade is out, of landing a man on the moon and returning him safely to the Earth . . . .
Let it be clear—and this is a judgment which the Members of the Congress must fi-
nally make—let it be clear that I am asking the Congress and the country to accept a
firm commitment to a new course of action, a course which will last for many years and
carry very heavy costs: 531 million dollars in fiscal ‘62—an estimated 7 to 9 billion dollars
additional over the next five years . . . .
It is a most important decision that we make as a nation . . .
Triple Constraints
Time: ____________________________________________________________________
Cost:_____________________________________________________________________
Performance: ______________________________________________________________
Hierarchy of Constraints
Driver: ___________________________________________________________________
Middle: ___________________________________________________________________
Weak:____________________________________________________________________
ASSUMPTIONS
You may have heard the warning about assumptions: “assume” makes an “ass”
out of “u” and “me.” But that’s not always the best way to look at it. Some as-
sumptions are very useful. For example, you should assume that any weapon
you see is loaded—even if you’re pretty sure it isn’t. Treating a empty firearm
with care does no harm; treating a loaded firearm as empty can kill someone.
It’s not always necessary—or possible—to turn every assumption into a
fact or a falsehood. However, it is necessary to recognize assumptions for what
they are, and not confuse them with reality. You can make assumptions, the
project sponsor and customer make assumptions, and your team makes as-
sumptions. All of them need to be brought into the open. That’s not always
easy. We don’t always recognize the assumptions we are making. Try some of
the following techniques:
1. Document review. Go through any memos, directives, or requirements
and check each statement listed as fact. Do you know that it is true, or
could it be an assumption?
2. Brainstorm. Brainstorm everything you think you know about the project,
then look at each listed item to see if it’s really a fact or actually an as-
sumption.
3. Think about common assumptions. “If this project is successful, the prob-
lem or issue that led to it will be resolved.” “Everybody is in basic agree-
ment with this course of action.” “No major problems or surprises will
occur that will force us to modify resources or priorities.” All of these state-
ments might be true, but it’s probably wise to verify.
Exercise 2–3
PMO Project Constraints and Assumptions
In this exercise, we return to the PMO project first discussed in Exhibit 1–1. You have already com-
pleted two previous exercises (Exercises 1–1 and 1–2) that built on the initial project description.
Instructions: Use the material you wrote for the two previous exercises along with the following ad-
ditional guidance to develop a list of constraints and assumptions for the project. Then rank the
constraints using the triple constraints paradigm.
After your first meeting with the CEO, you go away and do some studying about PMOs, and talk
to several managers whose opinions and candor you value. You have further discussions with the
CEO as well, and now you have additional information.
• The CEO wants to cap the cost of the project at $50,000, and the cost of running the PMO at less
than $200,000 per year. However, the detailed scope of the project has not yet been established.
Triple Constraints
Time: ____________________________________________________________________
Cost:_____________________________________________________________________
Performance: ______________________________________________________________
Hierarchy of Constraints
Driver: ___________________________________________________________________
Middle: ___________________________________________________________________
Weak:____________________________________________________________________
Assumptions
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
PROJECT CHARTER
In our summary of the project management knowledge areas and processes,
we described the project charter : the document that formally authorizes the ex-
istence of a project and gives the project manager working authority to pro-
ceed. Although a project charter may not actually be called “project charter,”
it’s vitally important that you get a written agreement that describes what you
have to do, when you have to do it, and how much you can spend in the
process.
Exercise 2–4
PMO Project Charter Outline
Instructions: In this exercise, you will describe what you know about each of the project charter el-
ements discussed previously. Note that some of them (the list of constraints and assumptions; the
list of stakeholders) were already done in previous exercises, and there’s no need to repeat the in-
formation here.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
Description of the product, service, or result that the project is supposed to deliver, prefer-
ably expressed as measurable objectives.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
High-level requirements of the project, along with boundaries—what the project isn’t ex-
pected to accomplish.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
Assignment of a project manager, a statement of the project manager’s authority and respon-
sibility, and a list of people who must approve elements of the project or its final outcome.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
Other organizations that must support the project and what they are expected to provide.
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
Review Questions
ITERATIVE PLANNING
There’s a bit of a chicken-and-egg problem in project planning: you can’t, for
example, make a good project plan without knowing the risks, and in order to
find all the risks, you need a good project plan. You need the plan to guide
your estimating, and you need your estimates to have a plan.
Here’s where progressive elaboration and the iterative nature of projects
comes back into play. Remember, progressive elaboration means that you
break the large project into smaller pieces, define each piece fully, and use
that expanded, more detailed information to support your planning and proj-
ect execution. The practical strategy for project planning requires you to make
a tentative initial version, use that version to spur your thinking and analysis
of these other issues, and then incorporate what you’ve learned into the plan.
For the time being, we’ll forget deadlines and budget. You need to know
whether you have a problem and how severe it is before you start figuring out
how to solve it.
In this chapter, we’ll create a project statement of work (SOW), a requirements
document, a work breakdown structure (WBS), and a network diagram. Though all
three of these items will almost certainly be modified, we still need to have
some general overview of the project to get started.
STATEMENT OF WORK
The project statement of work (SOW) is a narrative description of the
project. Usually fairly short (a couple of pages), it describes the output of the
project (a product, a service, or some other type of result) and what business
need it is expected to accomplish. It describes the project scope in terms of
its high-level characteristics or requirements. Exhibit 3–1 illustrates an SOW
for our case study PMO project.
Exercise 3–1
Research and the SOW
Instructions: You’ve been asked to set up your company’s PMO, and at least some of those who
take this course may not have any experience with PMOs. In the real world, that’s not necessarily
unusual. You are expected to learn on the job.
In this exercise, you are going to do some Internet research about PMOs to gain familiarity.
Then decide what changes (if any) you would make to the SOW in Exhibit 3–1.
xhibit 3–1
Statement of Work
REQUIREMENTS DOCUMENT
Not every project needs a formal requirements document; in many cases the
high-level requirements contained in the SOW are sufficient to allow the proj-
ect to move forward. Technology and construction projects, however, often
need a lot more detail in requirements, and if that is your situation, you should
consider preparing a separate requirements document. These documents can
be quite lengthy and detailed. In extreme cases, the work involved in devel-
oping requirements can be classified as a project in its own right.
A well-written requirement accurately describes an element of function-
ality or quality, and is both unambiguous and verifiable (you can tell if it has
xhibit 3–2
Guidelines for Writing Requirements
xhibit 3–3
Work Breakdown Structure in Org Chart and Outline Formats
This exhibit shows the same project, “Pharmaceutical Project,” in both the org chart WBS format and
the outline WBS format. Notice that the first level of the WBS is “Level 0,” not “Level 1.” Also notice the
format of WBS numbers in the outline version. These numbers are automatically created if you enter a
WBS into Microsoft Project®.
Pharmaceutical Level 0 (Project)
Project
Level 1 (Phase,
Research Testing Approval Release Functional Area, Majo
Deliverable)
Responses and
Initial Research Animal Testing Manufacturing
Presentations
Phase 1 Trials
Level 3
(Components)
Phase 2 Trials
Phase 3 Trials
Outline Version
1.0 Pharmaceutical Project
1.1 Research
1.1.1 Identification of Likely Drugs
1.1.2 Initial Research
1.1.3 Identification of Candidate Drugs
1.2 Testing
1.2.1 Computer Models and Cellular Testing
1.2.2 Animal Testing
1.2.3 Clinical Trials
1.2.3.1 Phase 1 Trials
1.2.3.2 Phase 2 Trials
1.2.3.3 Phase 3 Trials
1.3 Approval
1.3.1 FDA Application
1.3.2 Responses and Presentations
1.3.3 Final Approval
1.4 Release
1.4.1 Marketing Plan
1.4.2 Manufacturing
1.4.3 Outreach to Medical Community
xhibit 3–4
Department-Based vs. Phase-Based WBS
The two WBSs shown here reflect two different ways to organize the same project. In the first, the
work packages are grouped by the department responsible for them. In the second, the work pack-
ages are grouped by phase.
Develop a Course
Instructional Systems
Production Operations Marketing
Design
Ship Materials to
Develop Exercises Conduct Beta Test Approve New Course
Seminar Location
Finalize Course
Develop a Course
Ship Materials to
Write Workbook Finalize Course Market Course
Seminar Location
Produce Materials
outside the normal work of the company. There isn’t a “Picnic Department”
designed to handle it. Instead, you will typically set up a team of people who
have regular jobs that don’t involve picnics, organize them into committees
(food, games, site, etc.), and assign each committee appropriate activities. Before
you can set up the committees, however, it’s a good idea to figure out what ac-
tually must be done. In this case, you’re better off with a “bottom up” approach.
In the “top down” approach, WBS Level 1 already exists. Make sticky
notes for each participating department or work group, and stick them to the
whiteboard or flip chart underneath the name of the project. Then look at
each department or group to figure out what they are supposed to do. Make
a separate sticky note for each thing that group is supposed to do, and add
those to the chart underneath the department name.
In the “bottom up” approach, start by identifying all the work packages
that have to be done. Write each work package on a separate sticky note, and
when you’ve got enough notes done, figure out the most appropriate way to
group them so that they can be managed and executed effectively.
Think about a project you’ve been involved with. Would you have used a top down or a bottom up
approach in developing the WBS for that project? Why?
Exercise 3–2
Different WBS Approaches
Of the two approaches to the same project shown in Exhibit 3–4, what do you see as the advan-
tages and disadvantages of each?
Exercise 3–3
Build a Work Breakdown Structure
Instructions: In this exercise, you will prepare a work breakdown structure covering at least Levels
0–2 for our PMO case study project. You will need sticky notes and an appropriate surface (white-
board, flip chart) for this exercise. Use the information previously presented in Exhibits 1–1 and 3–
1, and Exercises 1–1, 1–2, 2–1, 2–3, and 2–4.
NETWORK DIAGRAMMING
The most common type of schedule in project management is the Gantt chart,
which is essentially a bar chart of activities on a calendar grid. Gantt charts
are easy to read and understand, but they aren’t actually the easiest type of
schedule to build. We recommend that you prepare a network diagram as the
first step in scheduling the process. A network diagram is essentially a flow-
chart of the project activities. Later in this chapter, we’ll show you how to con-
vert a network diagram into a Gantt chart.
And that’s just the summary. When you add all the supporting documen-
tation, clinical test reports, and other raw data, an application can be 100,000
pages long!
Clearly, preparing the FDA application can easily be considered a project
in its own right, as well as a phase inside the overall new drug approval process.
Though making it a work package in terms of the overall project makes sense,
it needs further levels of decomposition before you reach the point where it’s
manageable.
Much of the supporting documentation will have been created during
the research and clinical trials phases, so it mostly needs to be organized and
compiled so that reviewers can easily locate the relevant sections. As far as
the summary itself goes, it’s likely going to go through multiple drafts and
iterations, and may require numerous signoffs. It may also require multiple
authors who have specific subject-matter expertise, with an overall editor
whose job it is to manage the whole process. It may take months to prepare.
With that in mind, let’s look at some of the activities required to accom-
plish this work.
1. Assign editorial team
2. Obtain raw data from clinical trials and pharmacological studies
3. Organize data into categories
4. Prepare an index and table of contents for raw data
5. Develop summary sections for each category of data
6. Get summary sections reviewed for completeness and technical accuracy
7. Draft overall summary
8. Get reviews and input on summary draft
9. Rewrite summary to incorporate all comments
10. Conduct a secondary review
11. Write final summary version
12. Obtain final signoff
13. Print required number of copies of entire submission both for FDA and
for in-house files
14. Submit FDA application
Although the work package “FDA Application” in our WBS defines the
final deliverable, when it comes to scheduling the project, we are more inter-
ested in the list of activities. The amount of time each activity will take relates
to how long the overall project will take, and the cost of performing each ac-
tivity (person-hours, money) will determine the required budget to accom-
plish the work.
To calculate the total budget, figure out how much each activity will cost,
and add the numbers together. But when you try to calculate the total time
required, you run into a new complexity: parallel activities. Whereas some ac-
tivities can’t be started until one or more earlier activities are complete (you
can’t write the final summary version until you receive the comments on the
previous draft), others can take place in the same time period (print copies of
the raw research data while waiting for comments).
Exercise 3–4
Activity List
Instructions: Take your WBS from Exercise 3–3 and create an activity list for the project. To keep
the exercise manageable, try to limit the number of activities to between ten and fifteen.
1.
2.
3.
Exercise 3–4 continues on next page.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
xhibit 3–5
Network Diagram
1. 5. Write 6. Review
Assign Summary Summary
Team Sections Sections
7. Draft 8. 9. 10.
11. Write 12. Final
Start Overall Review Rewrite Review
Final Signoff
Summary 1st Draft Summary 2nd Draft
14.
FInish
Submit
2. Obtain 3. 4.
Raw Organize Prepare
Data Data Index 13. Print
Data
Exercise 3–5
Network Diagram
Instructions: Take the items from the activity list you prepared in Exercise 3–4. Write the activities
on sticky notes, with one activity per note. Add two additional notes for “Start” and “Finish.” Use
these notes to prepare a network diagram for the PMO project.
xhibit 3–6
Critical Path
Critical activities are shown in solid black; noncritical activities (those with slack or float) are shown
in gray.
Slack/Float = 6 weeks
1. 5. Write 6. Review
Assign Summary Summary
Team Sections Sections
you can even move resources from an activity with lots of slack to an activity
on the critical path as a way to make sure you stay on schedule.
Remember that cost isn’t affected by the critical path. If you spend extra
money on a noncritical activity, it has the same effect as if you spend extra
money on a critical one.
Although we haven’t yet estimated the duration of the various activities on the PMO project, what
is your current feeling about the time constraint based on your current network diagram? Is it com-
fortable, tight, or impossible? What makes you think so?
Forward Pass
If an activity has slack or float, there is flexibility in the start and finish dates.
The early start is the earliest the activity can start considering its predecessors,
and the early finish is simply the early start plus the duration. The late finish is
the latest date an activity can finish without affecting the critical path, and
the late start is the late finish minus the duration.
The forward pass calculates early start and early finish; the backward pass
calculates late start and late finish. An activity is critical if the early/late start
and early/late finish are the same. If there’s a difference, the amount of the
difference is how much slack or float exists for that activity.
Exhibit 3–7 shows a forward pass calculation. The top center number in
each box is the duration. The top left number is the early start; the top right
number is the early finish.
xhibit 3–7
Forward Pass
Source: Adapted from Managing Multiple Projects by Dobson and Dobson ©2011. Used by permission of the publisher, AMACOM Books, a division of
American Management Association, New York, New York. All rights reserved. www.amacombooks.org
Start with the first activity, “Activity A,” which always has an early start
of zero. Its duration is zero; it finishes at zero. (An activity with a duration of
zero is called a milestone.) Activities B and C are both dependent on A; they
can’t start until A is finished. Because A is a milestone, B and C both start at
zero as well. Because B has a duration of 15 days, its early finish is 15; C’s
early finish is 11.
Activity D is dependent on both B and C. Its early start is the latest of the
early finishes of its predecessors. It therefore starts at 15, and 15 + 21 = 36, its
early finish. E, on the other hand, only requires that C be finished, so its early
start is 11, add 9, and its early finish is 20.
Activity F only needs D. It starts at 36, adds 8, and ends at 44. G needs
both D and E, so it begins at 36 (the later of the two predecessors) and ends
at 48 (36 + 12). The last activity, H, needs both F and G. It takes the G finish
of 48, adds 2, and now we know the duration of the project: 50 days. Exhibit
3–8 summarizes all these numbers.
Backward Pass
For the backward pass, we start with the end of the project and work backward
to the start, figuring out the late finish and late start of each activity. Exhibit
3–9 shows how it works. The numbers are summarized in Exhibit 3–10.
xhibit 3–8
Forward Pass Summary
A N/A 0 0 0
B A 0 15 15
C A 0 11 11
D Larger of C or D 15 21 36
E C 11 9 20
F D 36 8 44
G Larger of D or E 36 12 48
H Larger of F or G 48 2 50
xhibit 3–9
Backward Pass
Source: Adapted from Managing Multiple Projects by Dobson and Dobson ©2011. Used by permission of the publisher, AMACOM Books, a division of
American Management Association, New York, New York. All rights reserved. www.amacombooks.org
xhibit 3–10
Backward Pass Summary
H Early Finish of H 50 2 48
G H 48 12 36
F H 48 8 40
E G 36 9 27
D Lesser of F or G 36 21 15
C Lesser of D or E 15 11 4
B D 15 15 0
A Lesser of B or C 0 0 0
For Activity H, the late finish is 50 days, and so the late start is 50 – 2, or
48. That number becomes the late finish for both F and G. For F, take the late
finish of 48, subtract 8, and the late start is 40. For G, 48 – 12 = 36.
Going backward, you pretend as if the arrows are reversed. If you have
more than one activity feeding a predecessor, this time you pass the lowest
number. Activity D’s late finish is governed by G’s 36, rather than F’s 40, and
36 – 21 = 15. E only cares about G, so its late finish is 36 and its early finish
is 27. However, it’s the late start of D that matters to both B and C. Both ac-
tivities have a late finish of 15; B’s late start is zero and C’s late start is 4. The
milestone, Activity A, ends up with a late finish and a late start of zero.
xhibit 3–11
Critical Path and Float
Source: Adapted from Managing Multiple Projects by Dobson and Dobson ©2011. Used by permission of the publisher, AMACOM Books, a division of
American Management Association, New York, New York. All rights reserved. www.amacombooks.org
xhibit 3–12
Critical Path and Float Summary
Note that you will get the same answers if you use “Late Finish” and “Early Finish” instead.
(minus)
Activity Late Start Float Critical?
Early Start
A 0 0 0 Critical
B 0 0 0 Critical
C 4 0 4 Noncritical
D 15 15 0 Critical
E 27 11 16 Noncritical
F 40 36 4 Noncritical
G 36 36 0 Critical
H 48 48 0 Critical
days of float, but if it uses all four days, Activity H still starts when scheduled.
Because none of Activity F’s float comes from H, it is considered free float.
Notice that in the case of Activity C, it can start as early as day 0 but can
start as late as day 4. It has four days of total float; extra time before lateness
jeopardizes the project deadline. However, if Activity C uses any of its float, the
float available for Activity E is reduced because E will no longer start on Day
11. The float is shared, not free. The float in E and F, however, is free float, be-
cause no other activity is affected if those activities use their available float. Ex-
ercise 3–6 gives you an opportunity to practice the forward and backward pass.
Exercise 3–6
Identify Critical Path and Float
Instructions: Perform a forward and backward pass on the following figure. Determine the critical
path and identify available float.
Source: Adapted from Managing Multiple Projects by Dobson and Dobson ©2011. Used by permission of the publisher, AMACOM Books, a division of
American Management Association, New York, New York. All rights reserved. www.amacombooks.org
GANTT CHART
A Gantt chart is a timeline of project activities drawn as a bar chart over a
calendar grid. Exhibit 3–13 shows a simple Gantt chart.
As we mentioned earlier, a Gantt chart is very easy to produce if you
have already done a network diagram. Create a table with a list of the activi-
ties, the duration of each, and the predecessor or predecessors of each. Exhibit
3–14 shows you such a table, as developed from the network diagram in Ex-
hibit 3–11.
To build a Gantt chart using project management software, you simply
enter this information in the appropriate columns and you’re done. To build
a Gantt chart by hand, create a calendar grid and draw each activity as a
straight line or bar from its start (determined by its predecessors) to its end
(determined by its duration). If the duration of an activity is zero, it’s a mile-
stone. The traditional symbol for a milestone in project management is a di-
amond ().
The sample Gantt chart in Exhibit 3–13 shows arrows connecting the
end of each line to the activity that’s dependent on it. This is optional. Exhibit
3–15 shows a Gantt chart built from the table in Exhibit 3–14.
xhibit 3–13
Gantt Chart
Credit: Gantt chart created using MindView Business Edition, authored by V. Heilman in 2011. Used under the Creative Commons Attribution-Share Alike
3.0 Unported license. Retrieved from http://commons.wikimedia.org/wiki/File:Gantt_chart_example.png, 5 August 2013.
xhibit 3–15
Completed Gantt Chart
GANTT CHART
Task Dur. Pred. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Task A 0d —
Task B 15d A
Task C 11d A
Task E 9d C
Task F 8d D
Task H 2d F,G
Source: Adapted from Managing Multiple Projects by Dobson and Dobson ©2011. Used by permission of the publisher, AMACOM Books, a division of
American Management Association, New York, New York. All rights reserved. www.amacombooks.org
Exercise 3–7
Draw a Gantt Chart
Instructions: Take the network diagram from Exercise 3–6 and turn it into a Gantt chart.
Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Review Questions
What are some elements of projects in your organization that have uncertain durations and costs?
To what extent can you predict or control that uncertainty?
ESTIMATING METHODOLOGIES
The basic estimating methodology is known as a WAG, or Wildly Aimed
Guess. (It’s also defined in a less family-friendly way.) That’s distinct from a
SWAG, or Scientific Wildly Aimed Guess, which is delivered with a calm and
confident air, as if you know what you’re talking about.
Sometimes, guesses are the best we can do, and as long as we label them
for what they are, they can have some value in the planning process. Estimates,
unlike guesses, have history: they are based on some real data and use some real
methodology. That doesn’t always make them superior to guesses; some people’s
WAGs are better than other people’s detailed and documented estimates.
Different estimates are used for different purposes, and are based on dif-
ferent levels of understanding about a project.
A rough order of magnitude (ROM) estimate is used by decision-makers to
decide if a project will be undertaken at all. The estimator starts with very
little knowledge about the project. “How much would a new office building
cost?” Obviously, that will vary by how large the building is, whether it has
any special characteristics, where it will be built, and many other factors. But
if none of that has been decided yet, you can only come up with a very general
number. ROM estimates are considered accurate if the project comes in within
-25% to +100% of the number provided.
A preliminary estimate is based on a written statement of work (SOW), so
you have more information to work with, but a detailed plan has not yet been
created. Preliminary estimates are often used as the basis of a budget request
or a proposal bid, and are considered accurate within a range of -10% to +25%.
A definitive estimate requires a complete plan, so it’s used as the project
baseline. Because reality never quite lines up with the plan, a definitive estimate
still has some variance. It’s considered accurate in the range of -5% to +10%.
If you’re asked to provide an estimate, you should always specify the type
of estimate you’re providing, and offer the estimate as a range, rather than as
a single number.
Analogous Estimating
An analogous estimate uses the real numbers from another similar project, and
adjusts them based on any known difference. How much does a new office
building cost? Well, that new five-story building over on Main Street was built
two years ago and cost $15 million. It holds 200 people. If you know you’re
going to need space for 500 people, you could multiply $15 million by 150%,
and offer an analogous estimate of $22.5 million. Notice that this type of es-
timate is a ROM, which suggests a range between $16.875 million (25% less)
and $45 million (100% more).
Parametric Estimating
A parametric estimate is one that uses a statistical model. If you ask a commercial
real estate person how much office space in your area costs, you’ll normally
get a cost-per-square-foot number. If office space goes for $35 a square foot,
and you need 1,200 square feet, the estimated annual rent is $42,000, or about
$3,500/month. Of course, the price of office space varies, but if a particular
landlord quotes a figure much higher or much lower than $3,500/month, it
should raise questions. Perhaps the difference is completely appropriate, but
you want to understand why.
That’s a simple parametric. A more complex parametric is one you’ve
encountered if you’ve purchased life insurance. An agent interviews you: your
age, your health history, whether you smoke, and many other factors. The
model queries a large statistical database and calculates what your premium
should be.
Depending on the sophistication of the model and the data available,
parametric estimates can be produced in all three categories of accuracy.
Bottom-Up Estimating
To prepare a bottom-up estimate, you need a comprehensive and complete proj-
ect plan, along with all the necessary supporting data. In a bottom-up estimate,
you begin by estimating each activity separately, rolling them up into WBS
work packages, then to control accounts, until you get to the final figure. Be-
Exercise 4–1
Types of Estimates
Instructions: For the following estimates, list the estimating methodology (WAG, analogous, expert,
Delphi, parametric, bottom-up) used and classify the expected accuracy (ROM, preliminary, budg-
etary, variable) of the number.
THREE-POINT ESTIMATING
In addition to these common estimating techniques, project management has
two unique estimating methodologies: PERT and Monte Carlo simulation.
Both are built on what are known as three-point estimates. This estimating tech-
nique is useful on projects that have a high degree of inherent uncertainty
and a need for accurate predictions.
Because it’s a fair amount of work, you should evaluate whether these
techniques are appropriate for your project. Even if you don’t need the infor-
mation right now, you may in the future. And if you plan to take the PMP® ex-
amination, you’ll need to have a grasp of the basic concepts of these methods.
xhibit 4–1
PERT Formulas
𝐸 = 𝑂 + (4∗𝑀) + 𝑃 6
𝞼 = 𝑃 − 𝑂/6
Where:
E = PERT Estimate
O = Optimistic Estimate
M = Most Likely Estimate
P = Pessimistic Estimate
𝞼 = Standard Deviation
xhibit 4–2
Standard Deviation Diagram
Credit: Standard deviation diagram, based on an original graph by Jeremy Kemp, 2005. Licensed under the Creative Commons Attribution 2.5 Generic
license; downloaded from Wikimedia Commons on 1 August 2013.
The standard deviation helps you determine the probability of your actual
result meeting a given target. Exhibit 4–2 shows how the standard deviation
relates to the PERT estimate. Exhibit 4–3 provides a helpful “Z table” showing
your probability of meeting a given deadline or budget when expressed in stan-
dard deviations from the PERT estimate.
PERT calculations can be made for both time and cost. If the optimistic
estimate for an activity is $500, the most likely $750, and the pessimistic
$1,500, the PERT estimate will be ($500 + (4 * $750) + $1,500)/6, or $833.33,
and the standard deviation will be ($1,500 – $500)/6, or $166.67.
With time, there’s one additional fact you should know. If you want to know
the standard deviation for a series of activities, you have to square each of the
standard deviations, add them together, and take the square root of the sum.
Example: Take the path sequence A→B→C. A has a standard deviation
of 2 days, B has a standard deviation of 3 days, and C has a standard deviation
of 1 day. 22 + 32 + 12 = 4 + 9 + 1 = 14. The standard deviation of A→B→C is
the square root of 14, or about 3.74, which we’ll round to 4.
Exercise 4–2
Calculating PERT Estimates
Instructions: Use the PERT formulas and Z table to answer the following questions. Round all num-
bers to the nearest integer.
1. For Activity A, the optimistic estimate is 10 days, the most likely estimate is 12 days, and the
pessimistic estimate is 25 days. What is the PERT estimate and standard deviation?
2. For Activity A, the optimistic cost estimate is $5,000, the most likely estimate is $15,000, and
the pessimistic estimate is $21,000. What is the PERT estimate and standard deviation?
3. You are given a deadline of 15 days and a budget of $13,000 for Activity A. What is the proba-
bility that you will achieve the time and cost objectives?
4. For the path A→B→C, if the standard deviations are A = 4, B = 5, and C = 7, what is the stan-
dard deviation of the path?
xhibit 4–3
Z Table
This table, called a “Z table” in statistics, gives you the statistical probability of achieving a given
cost or time goal expressed in terms of the PERT estimate and the standard deviation.
Example 1: Your PERT estimate for a given activity is 10 days, and the standard deviation is 3
days. Your probability of meeting the goal in 10 days (E + 0𝞼) is 50%. Meeting the goal in 13 days
(E + 1𝞼) is 84.13%. Your probability of meeting the goal in 7 days (E – 1𝞼), however, is only 15.87%.
Example 2: Your PERT estimate for the activity is $15,000, and the standard deviation is $3,000.
If you are given a $16,000 budget, that’s $1,000 more than E, which is a third (0.3) of the standard
deviation. E + 0.3𝞼 is 61.79%. If you are given $14,000, the chance is now E – 0.3𝞼, or 38.21%.
𝞼 Probability 𝞼 Probability
-3 0.13% 0 50.00%
-2.9 0.19% 0.1 53.98%
-2.8 0.26% 0.2 57.93%
-2.7 0.35% 0.3 61.79%
-2.6 0.47% 0.4 65.54%
-2.5 0.62% 0.5 69.15%
-2.4 0.82% 0.6 72.57%
-2.3 1.07% 0.7 75.80%
-2.2 1.39% 0.8 78.81%
-2.1 1.79% 0.9 81.59%
-2 2.28% 1 84.13%
-1.9 2.87% 1.1 86.43%
-1.8 3.59% 1.2 88.49%
-1.7 4.46% 1.3 90.32%
-1.6 5.48% 1.4 91.92%
-1.5 6.68% 1.5 93.32%
-1.4 8.08% 1.6 94.52%
-1.3 9.68% 1.7 95.54%
-1.2 11.51% 1.8 96.41%
-1.1 13.57% 1.9 97.13%
-1 15.87% 2 97.72%
-0.9 18.41% 2.1 98.21%
-0.8 21.19% 2.2 98.61%
-0.7 24.20% 2.3 98.93%
-0.6 27.43% 2.4 99.18%
-0.5 30.85% 2.5 99.38%
-0.4 34.46% 2.6 99.53%
-0.3 38.21% 2.7 99.65%
-0.2 42.07% 2.8 99.74%
-0.1 46.02% 2.9 99.81%
0 50.00% 3 99.87%
Not every project or every organization will receive enough benefit from PERT or Monte Carlo to
justify the time and effort involved, but in some cases it’s extremely valuable. Do these techniques
have a place in your organization’s projects? Under what circumstances would you want to use
these tools?
ISSUES IN ESTIMATING
Pretty much by definition, estimates aren’t the same thing as reality: your
mileage may vary. A healthy dose of skepticism about estimates is recom-
mended.
Overoptimism
Although some projects do come in ahead of their estimates, by far the more
common outcome is that projects tend to be late and over budget. There’s a
general bias toward optimism in the estimating process. People tend to over-
estimate how productive they are likely to be, underestimate the number of
interruptions and distractions, and fail to account for emergencies. According
to the annual Standish Group CHAOS Report on large corporate IT projects,
only 32% of projects actually meet their goals of time, cost, and performance
(Gruebl and Welch, 13).
Parkinson’s Law
Some project management authorities recommend adding a contingency al-
lowance to the time and cost estimates to account for poor estimating. Though
this has some virtues, it runs afoul of a well-known management principle
called Parkinson’s Law: work expands so as to fill the time available for its
completion (Parkinson, 1958).
If you have a comfortable amount of time in which to accomplish an ac-
tivity, there’s not a lot of urgency to get started, and there are almost always
various other issues that are calling for your attention. Adding contingency
to activities may in fact make them take longer, and the project will still be
late and over budget.
A project management technique known as critical chain project management
(CCPM) suggests that you should take the contingency allowance away from
individual activities and add them to the network diagram in the form of buffers
(Goldratt, 1997). This reduces the incentive for procrastination.
Exercise 4–3
Estimating Review
Instructions: For your PMO project, you will need to make some estimates. For each estimate re-
quired, explain what technique or methodology you would use from the ones described in this
chapter, and where you might get any information necessary to develop those estimates. These
questions assume you’re using the network diagram from the Answer Key for Exercise 3–5.
1. How would you estimate the time required for Activity 1 (“Research”)?
2. How would you estimate the time required for Activity 3 (“Obtain Feedback”)?
3. How would you estimate the likely price of Activity 8 (“Obtain Outside Trainer”)?
4. How would you estimate the time required for Activity 6 (“Recruit PMO Head”)?
5. How would you estimate how much it will cost for Activity 11 (“Prepare Stockholder Presentation”)?
Review Questions
2. One reason why projects are more frequently late and over budget 2. (a)
than early and under budget is:
(a) overoptimism in the estimating process.
(b) changes in scope requested by customers.
(c) using rough order of magnitude rather than preliminary estimates.
(d) incorrect calculations of the critical path.
4. If you decide the quickest an activity can be completed is six weeks, 4. (c)
the worst case is 24 weeks, and the most likely time is 12 weeks, what
is the PERT estimate and the standard deviation?
(a) E = 7, 𝞼 = 3
(b) E = 13, 𝞼 = 18
(c) E = 13, 𝞼 = 3
(d) E = 12, 𝞼 = 2
CALCULATION: The formula for the PERT estimate is (O + 4M + P)/6, or (6 + (4 * 12) +
24)/6 = 13. The formula for the standard deviation (𝞼) is (P – O)/6, or (24 – 6)/6 = 3.
To find out whether your team is sufficient for your project, you must
assign team members to work packages or activities to see if there are any
problems. In addition to making sure that each activity is covered, you also
need to check that you haven’t inadvertently double-booked people on par-
allel activities. For the first, you’ll begin with a responsibility assignment ma-
trix (RAM), and for the second, we’ll look at resource loading and leveling.
Exercise 5–1
Skill Requirements
Instructions: For the PMO case study project, analyze the network diagram you developed in Ex-
ercise 3–5 and list the skills your team needs to accomplish the work.
Exhibit 5–1 shows that we need one or more writers, at least one editor,
and one or more people in data management. Although project management
is involved throughout the project, the project manager has primary respon-
sibilities in such activities as assigning the team and in overseeing the review
process and completion of the final package.
Notice that we’ve listed “technical and management reviewing” as a skill
required to accomplish this project, but it’s pretty clear that those technical
and management reviewers aren’t part of our project team in any normal
sense. But they are part of the team in the sense that we can’t get the project
done without their input. The project manager doesn’t only have to manage
xhibit 5–1
Skill Requirements
Slack/Float = 6 weeks
1. 5. Write 6. Review
Assign Summary Summary
Team Sections Sections
Skills required:
Writing (Activities 5, 7, 9, 11)
Editing (Activities 5, 7, 9, 11)
Data Management (Activities 2, 3, 4, 13)
Project Management (Activities 1, 6, 8, 10, 12, 13)
Technical and Management Reviewing (Activities 6, 8, 10, 12)
the official team, but also has to “manage up” (Dobson and Dobson, 2000). In
this case, the project manager needs to identify the reviewers, make sure they
schedule the necessary time, make sure they get the information they need,
and follow up to make sure it all gets done.
The next step is to link those required skills to the skills possessed by
your team, which we’ve done in Exhibit 5–2. (We don’t need to assess the re-
viewers, so they don’t go on this list.) In Exercise 5–2, you will prepare your
own team skill assessment.
Exercise 5–2
Skill List
Instructions: As project manager, we assume that you have project management skills. You may
choose three of the following five candidates to complete your team.
Nguyen: Five years’ experience with the company in staff-level roles, BS degree in
Information Management. Skilled with PowerPoint.
Sean: Edits company newsletter while serving as human resources manager for one
of the divisions, BA, four years’ experience.
Nguyen
Susan
Gemma
Jurgen
Sean
Now, we need to put this together into the final RAM table, shown in
Exhibit 5–3. For simplicity, we’ll add two reviewers: Yuri, the project sponsor,
and Maria, the technical reviewer. The project manager is Aliverdi. Exercise
5–3 gives you the opportunity to develop your own RAM.
xhibit 5–2
Team Skills
Harry A N A N
Sally E E A N
François E A A A
Mariko A N E A
Aliverdi A A N E
xhibit 5–3
Responsibility Assignment Matrix
Exercise 5–3
Responsibility Assignment Matrix
Instructions: Prepare a RAM for the PMO case study project based on your network diagram and
the information you developed in Exercises 5–1 and 5–2.
Have you encountered situations in which a staff member was “double booked” for project activi-
ties? At what point did you realize it? Could you have found the problem earlier, and if so, what
might you have done differently?
OUTSOURCING
We also don’t necessarily have to confine ourselves to resources on hand.
Maybe we don’t have people with all the necessary skills, or perhaps we have
so much going on that everybody’s fully booked with other work. In that case,
we could consider outsourcing.
Almost any aspect of a project can, at least in theory, be handed off to some-
one else. If you have to make widgets, you can hire a manufacturer to make
them for you, or an engineering firm to design them. If you need writers, editors,
or indexers, you can hire them as consultants. If you’ve got to organize 100,000
pages of raw data, there are consulting firms that specialize in just that service.
Make or buy decisions are a powerful tool in the project manager’s arsenal.
Depending on your organizational circumstances, sometimes doing it yourself
is the best option, and sometimes it’s better to hire it out. Such factors as qual-
ity, speed, relative experience or capabilities, and what else internal resources
could do instead of that work can influence the decision. The best time for
make or buy decisions is early in the planning process, because they will have
a significant effect on the final project plan.
Procurement Planning
As you decide what you will be procuring as part of managing your project, you
need to start a procurement process. You need to define what you want to buy,
and identify one or more vendors who can supply your need. You will have to
get bids or proposals, evaluate them, choose your supplier, and negotiate nec-
essary contracts. Throughout the procurement process, you will need to make
sure that the vendor is performing on schedule and meeting requirements. You
will need to receive, inspect, and approve what you bought, and you will need
to pay invoices. All of these are activities that belong in your project plan.
The procurement process can turn into a major part of a project man-
ager’s responsibilities. A comprehensive study of procurement is, however, a
bit beyond the scope of this course. Many resources are available on this topic,
both in print and online.
but you’d be paying two people. Add more people, and you’ll continue to re-
duce the total time, up until some point of diminishing returns, where another
body doesn’t save you very much (or worse, the bricklayers start tripping over
one another).
It should be noted that extra resources don’t always produce a time ben-
efit. The classic project management example is that it take one woman nine
months to have a baby, but it doesn’t follow that nine women could get the
job done in one. In addition, there are some tasks that are highly uncertain,
and you cannot predict the value of adding people. If you want to develop a
new concept design, two people might get the job done faster than one, but
they could get mired in an argument and actually take longer.
Crashing a Project
Under normal conditions, we’d spend a certain amount of money to get a job
done is a normal amount of time. If we crash the project, we add resources.
The crash duration, in CPM, is the shortest possible time in which an activity
can be completed, and the crash cost is how much you have to spend to achieve
it. The value of early completion is how much it’s worth to get it done early.
Since the goal of spending this extra money is to speed up project com-
pletion, it only makes sense to crash activities on the critical path. Crashing
noncritical activities just creates more slack. Using the network diagram in
Exhibit 5–4, we’ll demonstrate a step-by-step crashing of a project. In Exercise
5–4, you’ll do your own.
Let’s assume that the value of early completion is $250,000 per week.
Clearly, it makes sense to crash Activity A ($200,000 per week), but not Ac-
tivity H ($260,000 per week, more than the value of early completion). We
spend an extra $1 million, but get $1.25 million in early completion value, for
a net savings of $250,000.
Crashing any of the noncritical activities doesn’t give us any benefit. On
the critical path, we start with the cheapest crash (Activity F, save 1 week and
xhibit 5–4
Crashing a Project Using CPM
11, 8 15, 8 6, 5
10, 5 5, 3
9, 6 11, 9 8, 5
Key:
“11, 8” = Normal time, Crash time (in weeks)
$150 = Cost per week of crashing (in thousands)
Critical path activities in black; noncritical activities in gray
Value of early completion = $250,000 per week
$150,000). Next, we crash Activity B, saving 3 weeks and $300,000. (Our proj-
ect expenditure, however, increased by $550,000.)
Before we start on Activity D, let’s go back and look at the critical path
again. In the original project, BDF = 32 weeks, and CEG = 28 weeks.
(We only count normal time for the initial calculation.) We’ve now crashed
BDF by a total of four weeks, meaning that both paths are now 28 weeks,
and critical! Even though there’s still the opportunity to crash Activity D,
doing so won’t speed up our completion any more.
But we’re not done yet. We can continue crashing, but now we have to
crash both paths at the same time to get any more schedule benefit. The only
crashable activity on the top route is Activity D, with a crash cost per week of
$165,000. Of the three noncritical activities, the cheapest to crash is Activity
E, at $50,000. There are two days in Activity E, so we only crash Activity D
by the same two days. It costs us $165,000 + $50,000 per week, or $215,000,
and we pick up another two days and save an additional $70,000.
Are we done yet? The next cheapest pair is Activity D (which is now 13,
8) and Activity G. The combined crash cost of these activities is $245,000.
This is very close to our limit. Depending on how confident we are of our
numbers, we might or might not take this. If we do, we can take another three
days out of Activity D and three out of Activity G for a net savings of $10,000.
Activity D still has two days of potential crash left, and Activity C has
three. But the cost of crashing both has now reached $265,000, above our
$250,000 value. Therefore, we won’t crash those last two activities. Exhibit
5–5 summarizes what we did.
If this sounds a little too good to be true, notice we spent an additional
$2,715,000 to achieve a time savings of 14 weeks. The gross benefit of being
14 weeks early is $3,500,000. Subtract those extra costs to get a net benefit of
$785,000.
Exercise 5–4
CPM Analysis
Instructions: Perform a CPM analysis of the following project. Critical path activities are shown in
black and noncritical activities are shown in gray. The value of early completion is $250 per day.
Critical Path = 0 + 15 + 21 + 8 + 2 = 46
15, 10 21, 18 8, 1
Activity A
Activity H
0, 0
2, 1
$0
$50
11, 9 9, 7 12, 5
Slack = 46 - (0 + 11 + 9 + 12 + 2) = 46 - 34 = 12
xhibit 5–5
Summary of Crashing Activities
Cumulative Cumulative
Crash Activities Time Saved Money Saved
Time Saved Money Saved
1 A 5 weeks $250,000 5 weeks $250,000
Exercise 5–5
Communications and Stakeholder Management Plan
Instructions: Complete the communications and stakeholder management plan for four stakehold-
ers of your choice.
xhibit 5–6
Communications and Stakeholder Management Plan Template
Project team Successful outcome, Hard work, results, Daily check-in, weekly Project
members knowing overall status, early warning of status meeting, regular manager
having clear direction issues, creative praise for achievements
and support problem-solving,
teamwork
Review Questions
RISK
The PMBOK® Guide defines risk as “an uncertain event or condition that, if it
occurs, has a positive or negative effect on one or more project objectives such
as scope, schedule, cost, and quality.” This should be interpreted in a broad
sense. Some risks have no immediate project impact, but can cause widespread
and long-term collateral damage outside the envelope of the project. Although
xhibit 6–1
The Project Environment
Quality
Risk
these may not always be project risks per se, they very definitely fall within the
project manager’s area of concern.
The term risk always describes the future, which is uncertain by defini-
tion. A risk may or may not actually happen. If it does happen, it’s no longer
a risk: it’s a problem. When we manage risk on a project, we are managing
some events that wouldn’t have happened anyway. The problem is that we
don’t always know which events those are.
The philosophy of risk management can be summarized in the Godzilla
Principle (Dobson, 1996). In the archetypical Japanese monster movie, the
monster often starts as a little baby, and as a result is ignored until massive ra-
diation exposure turns it into a rampaging giant with the desire to destroy
downtown Tokyo. All the people who ignored the baby monster are now out
in the streets, crying, “What are we going to do?” Unfortunately, most of the
good and easy options now lie in the past. Though not every baby monster
will grow into Godzilla, baby monsters in general are much easier to kill. In
other words, the opportunities to resolve an issue tend to decrease over time.
Though risk management is proactive and problem solving reactive, that
doesn’t mean problem solving isn’t important. No matter how well you plan,
sometimes Godzilla sneaks into Tokyo on the back roads.
Pricing Risk
Because risks, by definition, may or may not happen, the question arises: how
much should we be willing to spend in order to manage a particular risk? To
determine this, we have to figure out how likely it is that the risk will occur,
and how serious the impact of the risk will be if it occurs. That leads us to the
fundamental formula of risk:
R=P×I
In this formula, “P” stands for probability, “I” stands for impact, and “R”
is the risk score, or value of the risk itself. If there’s a 25% chance that a risk
could cost your project $10,000, the risk score is $2,500. If you can deal with
the risk effectively for less than $2,500, you’ve got a pretty strong business
case justification for action. However, the reverse isn’t automatically true.
When you buy car insurance, what you have to pay consists of the value of
the risk (how much the insurer expects to pay out for claims), plus the insurance
company’s cost of doing business and the profit the company hopes to make.
(Compensating for that somewhat is the income the insurance company makes
from investing the pool of money it takes in.) The bottom line is that you end
up paying more than the underlying value of the risk. This extra money is
known as a risk premium (which is why your bill says “premium” on it).
Is this a good idea? Well, for most of us, having to shell out several hun-
dred thousand dollars if we’re in a major accident is likely to be financially
devastating. Paying a premium to protect ourselves against a potentially cat-
astrophic risk is sensible. Because we’re paying more than the underlying
value of the risk, we do have to make a business case for why spending the
additional money is a good idea.
What about business risk? The P x I formula still applies, but we have to
consider both sides. Let’s say that we’re considering an investment in new
technology. There’s a 50-50 chance we’ll succeed. If we succeed, we expect
to make $100,000. If we fail, we’ll lose our investment of $50,000. The value
of the risk is (50% x +$100,000) + (50% x -$50,000), which works out to
+$25,000. In other words, this particular business investment has a positive
net risk score.
Should we make the investment? Not so fast. We should consider what
the impact on the company will be if we lose $50,000. For a mid-size or large
company, that’s unlikely to be fatal. If we’re financing a start-up with a second
mortgage on our house, the loss of $50,000 could be very serious indeed. We
should also consider what else we could do with that $50,000. If we are com-
paring two investments, one with a positive risk score of +$25,000 and the
other with a positive risk score of +$50,000, we will probably pass on the first
opportunity to take the one with a higher potential payoff.
Risk Tolerance
For most of us, a $300,000 car accident would be financially devastating, and
paying a premium for insurance is a very good idea. (In many places, it’s also
the law.) For Bill Gates or Warren Buffett, however, $300,000 is a minor ex-
penditure. There’s no value in paying a premium for a risk you can afford. For
those of us of more modest means, we normally have a deductible on our in-
surance policy, which represents an amount of money we can afford to pay
should we have an accident.
We’ve talked about risk in financial terms, because that’s the easiest to
measure. However, risks can fall into many different categories: safety and
health, reputation, legal or regulatory, or our personal career. You may have
a different attitude about risks in one category than in another. Some people
are reluctant to invest in the stock market but skydive on the weekend.
We use the term risk tolerance to describe the amount of threat risk we are
willing to accept in a specific category. Our personal risk tolerance may not
be the same as the risk tolerance of our company or our customer, and we
must often accept their risk tolerances as a constraint on our project. The term
risk appetite describes our willingness to accept opportunity or business risk.
In each category of risk, we (and our organization and our customers)
have a risk threshold. Some risks are simply too expensive and we are unwilling
to accept them; risks below the threshold are ones we are willing to consider.
In an organization, you as the project manager may be able to address risks
below the threshold on your own initiative, but risks above the threshold re-
quire review and approval by senior managers.
It’s often the case that neither we nor our organization have fully thought
through our risk tolerance, appetite, or thresholds. You may need to do some
inquiry to pin down these elements to determine your appropriate actions.
Exercise 6–1
Risk Tolerance
Instructions: Compare your tolerance for risk to that of your employer or organization. How much
risk would you take if the net benefit were positive? If you can quantify the risk threshold, do so; if
not, describe the tolerance as “high,” “medium,” or “low.”
Organizational Risk
Risk Category Personal Risk Tolerance
Tolerance
Financial Risk
Legal/Regulatory Risk
Risk to Reputation
Publicity Risks
Does your organization or department have a formal risk management policy? If so, what types of
projects or situations are covered? How does the system you use work in practice? If not, how are
risks managed today? What works and what doesn’t work?
Identifying Risks
Once you’ve decided on your overall approach, the next step is to identify the
risks themselves. This can be as simple as having a meeting to brainstorm pos-
sible risks, or depending on what’s at stake, can be an intensive process that
potentially yields hundreds of risks worthy of further study. Exhibit 6–2 pro-
vides a number of ways to find risks on your project. Select those that seem
most appropriate.
A risk should be written in the format “Condition Consequence.” The
statement “We might be late” isn’t a risk because there are thousands of po-
tential reasons why that might happen, each of which may require a different
answer. The statement “The report may contain errors” is not a risk because
we don’t know the effect those errors might have on project objectives. The
statement “If there are errors in the report that require revision, then the ac-
tivity will take two days longer than planned” is a risk, because we know know
both the cause and the effect that concerns us. The easy way to write risks in
the proper format is to write them as “if…then” statements. The “if ” is the
condition or cause, and the “then” is the effect or consequence. (“Because…
then” works, too.)
Risks can be positive or have mixed potential outcomes. Don’t overlook
opportunities or business risks in risk identification.
xhibit 6–2
Risk Identification
Document Analysis Review all the paperwork associated with the project looking
for risks. There’s a potential risk lurking in every declarative
statement. “We will deliver on July 1” carries the implicit risk
that we may not meet that delivery date.
Assumption Analysis Assumptions are unavoidable, especially in early stages of
the project. Not all assumptions are bad; some promote
safety, such as the assumption that an unknown gun is
loaded. The dangerous assumptions are the ones you don’t
notice. Develop a list of assumptions in the initiating phase
and continue to add to it through the life of the project. Turn
assumptions into facts or falsehoods when possible;
assumptions that can’t be validated are risks.
Work Breakdown Some risks can happen at any time, such as losing a
Structure member of your team to other work. Other risks are confined
to specific work packages. If you’re planning to test your new
widget design, there’s a risk the widget may fail. The widget
can’t fail the test until you begin testing, and after the test is
over, there’s no longer any risk: it passed or it failed. The first
is a non-event; the second is now a problem. Look at each
work package for the risks associated with it.
Network Diagram In addition to studying the WBS, review the network
diagram. If there’s a chance an activity might be two days
late, it’s more meaningful if it’s on the critical path. If it’s not
critical, and there are five days of slack, a two-day delay may
be irrelevant.
Stakeholder Stakeholders are not infrequently sources of project risk. If
Management Plan you have a stakeholder known for changing his or her mind,
and or one who tends to micromanage project details, or one
Communications who needs daily reassurance, those risks will affect the
Management Plan management of your project.
Estimates Estimates, like risks, are future tense. When you’re done,
you can figure out the actual cost and time. Until that point,
there is uncertainty. How reliable is a given estimate? What
is the range of potential variance? Are there root causes or
triggers that would invalidate certain estimates?
Procurement Outsourcing can be a highly valuable tool, but it’s not without
Documents risk. Review bids and proposals, check the history of the
company you’re working with, call references if appropriate,
and make sure you understand the contract, especially if it
was prepared by someone else.
Lessons Learned If your organization has done similar projects, review the
lessons learned from those projects. What risks were feared,
which occurred, and how well were they handled?
Checklists Airplane pilots review a checklist before taking off. Checklists
focus on areas where it’s easy to make a mistake or overlook
something and where the consequences of doing so can be
serious. Checklists are enormously valuable, but don’t ever
let a checklist replace the entire risk management process.
Experts In the same way experts are helpful in estimating, they often
have good insights on the risks you may face. You may also
use the Delphi technique if you are surveying multiple
experts and need to avoid groupthink.
Analysis Tools Several commonly used management tools can be helpful in
risk management. A SWOT analysis involves brainstorming
Strengths, Weaknesses, Opportunities, and Threats for a
well-rounded picture of the project. Quality tools such as the
Ishikawa (fishbone) diagram help break down problems into
components, allowing deeper insight into risks.
Organize your risks into a risk register. Add additional information about
each risk as you develop it. Exhibit 6–3 provides a sample format for a risk
register. Use the risk register to organize information about each risk, and to
track risks as the project moves forward. Some risks require far more infor-
mation than the space provided; you can develop those risks in separate doc-
uments, but keep a note on the risk register referencing where the appropriate
information can be found.
You may categorize risks to help in organizing and acting on them. You can
categorize risks according to risk tolerance (financial, legal, political, safety, rep-
utation), impact on objectives (time, cost, scope, quality), or however it makes
most sense to you. Your risk management plan will often define categories you
should use. “Where Found” on the risk register links the risk to some other proj-
ect document, such as WBS, network diagram, requirements lists, etc.
Exercise 6–2 is an opportunity for you to practice risk identification on
our PMO case study project; you will develop further information about each
risk as we move forward.
xhibit 6–3
Sample Risk Register
Exercise 6–2
Risk Identification
Instructions: For our PMO case study, identify five risks based on the work you’ve done so far, and
write each one in the “condition consequence” format. Try to find at least one opportunity risk or
business risk among them.
1. _________________________________________________________________________
2. _________________________________________________________________________
3. _________________________________________________________________________
4. _________________________________________________________________________
5. _________________________________________________________________________
Risk Triage
As a preliminary step before the “assessing and combining their probability
of occurrence and impact,” we must first sort our identified risks into some
action categories. For many—perhaps even most—risks, we will classify them
as minor risks, where no further action is warranted, at least initially. For other
risks, we may find that we are not the proper people to address them, and we
must make sure those risks are reassigned to the appropriate people. A few
risks may require top management attention, and may even call into question
whether the project should continue to move forward. Follow the flowchart
in Exhibit 6–4 to sort risks for qualitative risk analysis.
Exercise 6–3
Qualitative Risk Analysis
Instructions: For each risk you identified in Exercise 6–2, determine its probability and impact using
the scale provided in Exhibit 6–5, and determine its category on the risk triage flowchart shown in
Exhibit 6–4.
1. _________________________________________________________________________
2. _________________________________________________________________________
3. _________________________________________________________________________
4. _________________________________________________________________________
5. _________________________________________________________________________
xhibit 6–4
Risk Triage Flowchart
Source: Adapted from Project Risk and Cost Analysis by Dobson and Dobson ©2012. Used by permission of the publisher, AMACOM Books, a division
of American Management Association, New York, New York. All rights reserved. www.amacombooks.org
xhibit 6–5
Probability and Impact Matrix
Probability
Impact 1 2 3
1 LOW
2 MEDIUM
3 HIGH
risk than a costly project with a score of 500, if considered from a larger or-
ganizational perspective.
Low risk projects don’t need tremendously robust risk management plans.
In a high risk situation, however, planning is essential. The “raw” risk score can
often be lowered substantially, which is the ultimate goal of our risk management
process.
xhibit 6–6
Expected Monetary Value
Sensitivity Analysis
How accurate are those estimates of probability and impact? Is the success-
failure ratio really 30-70? How do we know? What about that $1 million pay-
day? It may be certain we lose our investment if it fails, but are we really
certain the payoff will be exactly $1 million?
When people see numbers, they’re often inclined to take them more se-
riously than they deserve. When you’re measuring risk, challenge your as-
sumptions. Sensitivity analysis is the study of how the variation (uncertainty)
in the output of a mathematical model can be apportioned, qualitatively or
quantitatively, to different sources of variation. It involves varying your as-
sumptions and redoing the EMV calculation, as practiced in Exercise 6–4.
Exercise 6–4
EMV Calculations and Sensitivity Analysis
Instructions: In this exercise, we will perform EMV calculations and a sensitivity analysis. The first
line describes the case we’ve been discussing in the text. Each subsequent line involves a different
set of assumptions. Perform an EMV calculation for each case. Notice that cases 5 and 6 involve
an additional case.
Exercise 6–4 continues on next page.
(0.3 x $1,000,000) +
1 30% $1 million 70% -$50,000
(0.7 x -$50,000) = $265,000
5% $1,000,000
5 70% -$50,000
25% $250,000
5% $500,000
6 85% -$50,000
10% $250,000
Many times, when you’re asked to provide numbers, those numbers con-
tain assumptions. What will be the interest rate in four years? How much will
the price of raw materials fluctuate in the next three months? Consider con-
ducting a sensitivity analysis on your assumed numbers. If you’re wrong, what
would the consequences be?
Decision Trees
A decision tree compares EMVs side to side, usually graphically. Exhibit 6–7
provides an example.
In this example, the first block on the left is called a decision node : Which
investment? Investment A costs $8,000, and Investment B costs $12,000. Each
investment has three potential outcomes.
• For Investment A, there’s a 25% chance of earning $5,000, a 25% chance
of earning $10,000, and a 50% chance of earning $20,000.
• For Investment B, there’s a 60% chance of getting nothing, a 30% chance
of $20,000, and a 10% chance of $100,000.
Which investment has the better EMV? For Investment A, the first box
shows it costs $8,000, leaving you down $8,000. If we only get $5,000 in re-
xhibit 6–7
Decision Tree
Source: Adapted from Project Risk and Cost Analysis by Dobson and Dobson ©2012. Used by permission of the publisher, AMACOM Books, a division
of American Management Association, New York, New York. All rights reserved. www.amacombooks.org
turns, we’re at -$3,000. Multiply -$3,000 by 25% and you end up with -$750.
Work the next two branches the same way, then add up the answers: -$750 +
$500 + 6,000 = $5,750. That’s the EMV for Investment A, and you write it
just above the decision node.
Now calculate the outcomes for Investment B. Even though there’s a
chance of earning $100,000, the EMV totals only $2,800. Write that below In-
vestment A’s EMV, then label them. The better value, Investment A, is “true,”
and the other path is “false.”
You don’t have to turn your EMV comparisons into a graphic unless
there’s a specific requirement for it. You can simply provide the EMVs side
by side and prepare your recommendation.
xhibit 6–8
Risk Response Strategies
Transfer Share
Avoid
When you avoid a risk, you change the project or the environment so that the
risk can no longer happen, or if it does happen, the project is completely pro-
tected from its effects. If a particular investment could lose a lot of money, we
might decide not to invest. We no longer have that risk of losing money. (We
might, however, be passing up the possibility of gain.) If we’re worried about
hurricanes, we could move away from coastal areas. The hurricanes will still
happen, but we won’t be subject to their effects.
Mitigate
You might not be able to avoid a risk altogether, but you might be able to mit-
igate it. When you mitigate a risk, you make it smaller, lowering probability or
impact. If you drive safely, your risk of being in an accident is lower. The risk
is mitigated, but it’s not avoided. Driving safely lowers the probability, but the
potential impact is unchanged. Modern cars are often designed around “crash
cages” that give greater protection to driver and passenger in case of an acci-
dent. These safety features lower the impact of an accident, but its chance of
happening remains unchanged.
There’s no reason you can’t drive a safe car and drive safely at the same
time, and reduce the probability as well as the impact of an accident. Don’t
feel limited to one solution to a problem. Sometimes a number of small steps
can reduce the risk to acceptable levels.
Transfer
Another response to the potential of an accident is insurance, or paying a com-
pany a premium so they’ll pay in case you get in an accident. This is an ex-
ample of transfer. Transfer doesn’t necessarily change the risk itself, but merely
shifts ownership. My probability of being in an accident isn’t affected by
whether I have insurance. The financial impact is also the same; the only dif-
ference is whose signature is on the check.
In procurement, some contracts are fixed price and others are cost plus.
In a fixed price contract, the seller agrees to accept a price for goods and serv-
ices. The risks belong to the seller. In cost plus, the buyer agrees to cover the
costs of the vendor plus some additional money for profit. The risks now be-
long to the buyer.
There’s more to the story, of course. Fixed price contracts might exclude
certain risks. If a flight is cancelled for mechanical reasons, the airline owes
stranded passengers a hotel room as part of the fixed price of the ticket. If the
reason for cancellation is weather, passengers are on their own. Many terms
and conditions in a contract are about the transfer of particular risks between
buyer and seller.
Harry Truman famously had a sign on his White House desk reading,
“The buck stops here.” “Passing the buck” is another way to transfer risks. Some
decisions rightfully belong to people higher up the food chain, or in different
parts of the organization. Some belong to the customer, and some belong to
regulators or outside parties. Though passing the buck can be a way to shirk
responsibility, some bucks need to be passed so they end up in the proper hands.
Exploit
When you encounter an opportunity, you can exploit it and capture its value. If
your stock goes up in value, you can sell it and pocket the profit (less taxes, of
course). If it turns out you can buy an off-the-shelf product instead of building
it from scratch, you can save the money and time it would have taken to build
it from scratch. If the price of aluminum drops, you can buy extra to cover up-
coming projects.
You can plan for exploitation. If there’s a chance of finding an off-the-
shelf replacement for an expensive and time-consuming development process,
you definitely want to have someone looking to see if it exists.
If you’re going to cash in at some point, decide when that might be.
Should you sell if your stock reaches $40? What price for aluminum would
make bulk purchases worthwhile?
Enhance
If our stock has gone up $5, should we sell? If we think we’re close to the top of
the market, it’s probably a good idea to exploit the gain. If we think the stock
will keep going up another $20, we might want to hold onto it longer. That de-
cision contains risk, of course. What if our estimate of the stock’s target is wrong?
If you look for a new job, you probably want to polish your résumé or
get in touch with your contact list. That improves the probability of getting
that new job. If that updated résumé gets you a better job at a higher salary,
you’ve enhanced the impact.
Share
We don’t have to hog all the benefit of opportunities; we can share them with
others. We learned in kindergarten that sharing is nice. In the world of work,
sharing can also be practical, and we often underestimate its benefits to our-
selves as well as others.
If we’re looking for a job, we might come across an opportunity that’s
completely wrong for us, but might be just the thing for a friend or colleague.
Sharing the information takes little effort, and you’ll usually earn some good-
will in the process. The other person may or may not come across the job of
your dreams in return, but the more people you help, the greater the chances.
Exercise 6–5
Risk Response Planning
Instructions: For each risk you analyzed in Exercise 6–3, develop a risk response. Explain which
category the risk response falls into as part of your answer. Is there significant residual or second-
ary risk after your proposed response?
1. _________________________________________________________________________
2. _________________________________________________________________________
3. _________________________________________________________________________
4. _________________________________________________________________________
5. _________________________________________________________________________
your schedule only exist because of risk. If you plan to test your product, it’s
because there’s a risk it might not meet all its objectives. If there’s no doubt
whatsoever about the outcome, the test is redundant. Prototypes, inspections,
and reviews also address risk. If you have to buy new equipment, you need a
purchasing activity in your schedule to make sure it’s done.
You should still complete the appropriate block in the risk register, even
if all you do is indicate where in the plan you put the risk response. You want
to have a record that the response was acted on, and when you conduct lessons
learned, you’ll want a consolidated risk list to review how effective your over-
all risk process has been, and how it can be strengthened in the future.
QUALITY
The PMBOK® Guide defines quality as “the extent to which the project’s pro-
duct, service, and result satisfies the needs for which it was undertaken.”
Quality, from a management perspective, isn’t an abstract concept of
“goodness,” but something measurable and concrete: the degree to which it
satisfies the needs of the customer and other stakeholders. (Although cus-
tomers are generally the most important stakeholders, they usually aren’t the
only ones who matter.)
Your stakeholders define what quality is, and ultimately judge the extent
to which you have achieved it. Stakeholders don’t always start with a full un-
derstanding of their own wants and needs, and sometimes what they ask you
to do won’t achieve their goals. It’s your responsibility to understand what
they want and need, and to translate those desires and needs into specific ac-
tions and decisions. Sometimes, it’s your responsibility to push back.
Is Quality Scope?
We tend to associate quality with scope, but that’s not always the case. Legitimate
stakeholder needs often include time and cost, not just scope or performance.
A lot of project managers resist the idea that they have to make it “cheap,”
which sounds like the antithesis of quality. But it isn’t. Customers have lots of
needs and wants, but limited amounts of money. If they spend more money
on your project, they have to spend less on something else that they might
need more. And they don’t always find value in extra bells and whistles.
In addition, sometimes when you get to “good enough,” there isn’t much
extra value in “better.” A world-class surgeon can’t really put on a bandage
any better than an EMT. Better to save the world-class surgeon’s time for
more challenging assignments.
Value can change over time. In the Apollo 13 rescue, NASA engineers
had to figure out a way to make a CO2 exchanger out of loose material on the
spacecraft, while the clock was ticking. Solving the problem too late would
have been the same thing as not solving it at all. That’s why quality is usually
portrayed at the center of the triple constraints. It affects all three.
Process Quality
On May 16, 1924, Bell Telephone Head of Inspection Engineering Dr. Walter
A. Shewhart presented a page-long memorandum to his supervisor that is
considered the beginning of process quality control. Most of our modern quality
management initiatives, from TQM to Six Sigma, can trace their origins back
to that memorandum.
Process quality control, as the name suggests, is about improving the way
in which you do things. In the world of operations and ongoing work, there’s
always room for improvement. That’s called continuous process improvement. In
project management, continuous improvement is about improving the way in
which we do projects. It can’t be about the project itself, which has to end.
Does your organization use a formal quality management process, such as Six Sigma or TQM?
Have you been trained in it? How effective do you think it is? What aspects of it are applicable to
the project management experience?
Product Quality
Quality gurus universally tell you that you must “design quality in,” rather
than “inspect it in.” Inspection doesn’t add quality; it catches defects before
they get to the customer.
How do you design quality into a project? First, understand what the cus-
tomer wants and needs. Second, prioritize those wants and needs so you can
make the fewest and least harmful tradeoffs. Third, write down the needs in
the most measurable, concrete way you can, prioritize those wants and needs,
and spell them out in a way that lets team members get them done. When
you’ve done all that, you’ve designed quality into the project. In other words,
you “design quality in” through setting requirements: the concrete expectations
of the customers, users, or other key stakeholders.
By the way, quality is not the same thing as grade. Grade describes tech-
nical characteristics such as materials used, number and type of features, or
fitness for particular uses. In our EMT versus world-class surgeon example
above, we would classify the medical skills of the EMT as being of lower grade
than those of the surgeon. The quality of each is a separate consideration: how
well does each person meet the needs of the particular patient? In that sense,
an extremely skilled and conscientious EMT can provide services of much
higher quality than a careless or incompetent surgeon.
Exercise 6–6
Functional and Nonfunctional Requirements
Risk Type (F or N)
ence from previous projects. In risk identification, err on the side of inclusion.
Write risks in the form “condition consequence,” group them by categories
if appropriate, and put them on a risk register.
In qualitative risk analysis, you should perform a risk triage to sort risks
by the type of action required, and use a probability and impact matrix to rank
actionable risks against each other. Consider the overall project risk as an ad-
ditional factor. In quantitative risk analysis, apply statistical tools to important
risks and to the project as a whole to gain a deeper understanding. Quantitative
risk tools include PERT and Monte Carlo simulations, expected monetary value
(EMV), and decision trees. When numbers are uncertain, sensitivity analysis can
help tell how useful those numbers are.
Beginning with your highest priority risks, develop appropriate risk re-
sponses. For threats, you can consider avoidance, mitigation, and transfer. For op-
portunities, you can consider exploitation, enhancement, or sharing. The strategies
of contingent response and acceptance work for both threats and opportunities.
Consider residual risk and secondary risk in evaluating your responses. Imple-
ment risk responses (except for contingent) in your overall project manage-
ment plan.
Quality is “the extent to which the project’s product, service, and result
satisfies the needs for which it was undertaken.” To manage quality, you must
first establish concrete measurements based on the needs and wishes of cus-
tomers and other stakeholders. Quality isn’t limited to scope; in some cases
time and cost are major quality factors.
There are two basic types of quality: process quality, or how well we do
things, and product quality, or the extent to which the project output meets the
customer’s wants or needs. Improving process quality mostly comes from project
lessons learned. Managing process quality during the project is part of project
leadership.
Planning product quality in your project mostly comes through setting re-
quirements, both functional and nonfunctional. Managing product quality during
the project is done through the processes of quality assurance and quality control.
Numerous tools exist to help manage project quality, including cost-benefit
analysis, benchmarking, experiments, and the consideration of cost of quality.
Review Questions
2. If a particular risk has a 25% chance of costing $20,000 and a 75% 2. (a)
chance of earning $10,000, what is the value of that risk?
(a) $2,500
(b) $12,500
(c) -$2,500
(d) -$5,000
SOLUTION: R = (0.25 * -$20,000) + (0.75 * $10,000) = (-$5,000 + $7,500) = $2,500
3. The extent to which the project’s product, service, and result satisfies 3. (c)
the needs for which it was undertaken is known as:
(a) process quality.
(b) cost of quality.
(c) product quality.
(d) the “-ilities.”
5. There is a risk that our vendor will be late, and we are responding 5. (c)
to that risk by adding a penalty clause to the contract with the vendor.
What risk response strategy are we using?
(a) Avoid
(b) Mitigate
(c) Transfer
(d) Accept
PLAN APPROVAL
Get your plan approved by key stakeholders to avoid potential miscommuni-
cation about objectives and deliverables, help stakeholders understand the
costs and risks associated with the project, and ensure that you and your stake-
holders are in alignment.
The two methods of getting plan approval are to provide a written plan
and to conduct a briefing or presentation—or both. Make sure you commu-
nicate the plan in ways your audience can understand. Not all stakeholders
are necessarily familiar with project management, and a bewildering array of
network diagrams and PERT calculations can confuse rather than illuminate.
Depending on the urgency and complexity of the project, give stakehold-
ers some time to review plans in as much depth as they choose. Don’t be sur-
prised if you have to go back and redraft sections of the plan as a result of
feedback. The more sensitive and expensive the project, the more challenges
you should expect to get. If your plan and approach is challenged or ques-
tioned, keep an open mind. It’s cheaper and easier to resolve issues in planning
than to find out after the fact that what you did (brilliantly, on time, and under
budget) turns out not to be what they really wanted. Always confirm plan ap-
proval in writing.
Schedule
A tracking Gantt chart can serve as a schedule baseline. In Microsoft Project®,
there’s a function to “Set Schedule,” after which the tracking Gantt option
appears. (Similar options are available in all but the most basic project man-
agement software.) If you can read an ordinary Gantt chart, a tracking Gantt
is easy. Instead of one bar representing an activity, you now have two. The
first bar represents the schedule. Underneath it, a second bar represents the
actual start, finish, and duration of completed activities. For activities not yet
started, the tracking Gantt shows when they will start and finish based on
what’s happened to early activities.
Exhibit 7–1 takes the Gantt chart from Exhibit 3–13 and turns it into a
tracking Gantt. The gray bars represent the original schedule, the black bars
represent actual performance, and the striped bars are a forecast based on re-
sults to date. The dotted line represents where we are in the project: the end
of Week 24.
You’ll notice that Task B finished two weeks ahead of schedule, and Task
C finished one week behind schedule. Task D, which was dependent on both,
still started two weeks early because only Task B was critical. Task E, depend-
ent on Task C, started and finished a week late.
Notice that Task D is in progress as of Week 24. We know when it started,
but we can only forecast when it will finish. That’s why the bar changes from
solid black to striped. Assuming Task D takes as much time as scheduled, it
will finish two weeks early. It’s on the critical path, which means all remaining
tasks are expected to start early, and we forecast that the project will end two
weeks ahead of schedule. But that’s not the final word. If we encounter prob-
lems in the second half of Task D or in subsequent tasks, we could consume
those two weeks and more. Still, it’s good news that as of right now we are
ahead of schedule.
Exercise 7–1
Analyzing a Tracking Gantt Chart
Instructions: You have just completed the seventh week of a twelve-week project. Complete the
tracking Gantt chart assuming that remaining tasks will take the planned amount of time. Do you
forecast that the project will end up on schedule, ahead of schedule, or behind schedule? By how
much?
Task A 0d —
Task B 15d A
Task C 11d A
Task E 9d C
Task F 8d D
Task H 2d F,G
KEY
Schedule
Actual
Forecast
Scope Verification
The tracking Gantt chart tells us about the schedule, but it doesn’t indicate
what has been done. The process of scope verification involves whatever steps
are necessary to ensure that the work is done and done in line with require-
ments. Each work package creates some sort of deliverable, whether it’s a final
deliverable to be handed to the customer, or an interim deliverable that will
support another activity or work package within the project.
You can use the WBS as a tool to manage scope verification. Depending
on the level of work maturity and the difficulty or sensitivity of the work, you
must decide how carefully you need to check that the work is being done. For
some work packages, the word of the person you assign may be fully satisfac-
tory. In other cases, you may need to perform in-depth analysis and inspection.
If the output requires full-blown testing, it’s usually smarter to make the test
a separate activity or work package.
Cost Baseline
Different projects and organizations require different ways of tracking project
costs. You may need to review reports from the financial office to classify all
project expenses against specific accounting categories, or prepare detailed
xhibit 7–1
Tracking Gantt Chart
Task A 0d —
Task B 15d A
Task C 11d A
Task E 9d C
Task F 8d D
Task H 2d F,G
KEY
Schedule
Actual
Forecast
budget vs. actual spreadsheets. However, the best way to track a cost baseline
is with an “s-curve” chart showing cumulative sunk costs to date, as shown in
Exhibit 7–2.
This baseline describes a project that has a budgeted cost of $25,000 and
will take place over twelve weeks. As with the tracking Gantt chart, you can
add a second line representing the actual money expended to date as the fig-
ures come in.
As we’ll learn in the discussion of the earned value method in Chapter 8,
you can use the cost baseline as a PMB for all three constraints. We spend the
money in the plan to accomplish specific elements of work, so the money
spent to date parallels the work accomplished to date. We spend the money
over time, so the money spent to date also tracks whether we’re accomplishing
the work according to the schedule.
The cost baseline can’t distinguish between critical and noncritical ac-
tivities, and it can’t indicate how well the work was completed, but it’s a good
proxy for showing overall performance.
xhibit 7–2
Cost Baseline
$30.000
$25,000
$20.000
$15,000
$10,000
$5,000
$0
1 2 3 4 5 6 7 8 9 10 11 12
plan approval. In some cases, you may need to negotiate with stakeholders or
resource owners to acquire what you need.
your team has people in high demand, don’t be surprised if other projects or
operations take them away. That’s a common risk, and should be addressed in
your risk management plan.
Team Development
Project managers often aren’t the permanent supervisors of their team mem-
bers. Many team members have regular positions and official supervisors. As
a result, you don’t have the same type and level of power. That’s not neces-
sarily harmful. One of the simplest and best definitions of a leader is “someone
who gets followed.” We follow people for all sorts of reasons, ranging from at-
titude to skill to persuasiveness to rewards. The importance of official super-
visory status may be less than you think.
The subject of team building has filled hundreds of books, and a full dis-
cussion is far beyond the scope of this volume. The AMACOM Self-Study
program includes a course called Making Teams Work, along with numerous
other courses in leadership and supervision, and there are hundreds of courses
and workshops in team building offered around the world. Your success as a
project manager usually rests on the backs of your team members, so develop-
ing a high performance team is a core project management need. That doesn’t
merely help you succeed on today’s project, but builds a reputation that will
help you manage larger and more important projects in the future.
How have you learned about teamwork? Have you had formal training or only experience—positive
or negative? Are there resources available to you in your position that would improve teamwork
on your projects? What will you do to advance your knowledge and skill?
Kickoff Meeting
Many project management authorities recommend a kickoff meeting as a way
to get a project started. The kickoff meeting should include team members,
project sponsors, customers, and other important stakeholders. Review the
plan, identify and share the roles that each participant will review, and start
the project with a burst of high energy.
Work Management
Because team members on a project must perform certain activities in a cer-
tain sequence, on more complex projects it becomes all too easy to overlook
work or forget important details. Always keep some sort of record of who has
been assigned to what activity as a fundamental part of keeping track of proj-
ect progress.
If the project is particularly large or complicated, details are critical, and
you have a large team, consider using a work management form, often called a WBS
Dictionary. An example of this kind of form is shown in Exhibit 7–3, but feel free
to modify it to suit your situation. Complete this form (or have the appropriate
team member complete it) and make two copies: one for the team member and
one for you to serve as an overall control log. Keep status information on your
copy of the form. When the activity is complete, the team member signs and
dates the form and gives it to you as a record of work complete.
CHANGE MANAGEMENT
Change is the only certainty on projects. The needs may change. People may
change. Technology may change. What we discover as we do the project may
surprise us.
Change by itself is normal and natural, and must be accommodated in
your project. However, when change is not managed effectively, the result is
scope creep, which we defined earlier as unplanned and unmanaged change.
This can kill a project—an old joke describes a project disaster as the moment
in which the speed of change starts to exceed the speed of progress.
The alternative to scope creep is to establish and maintain an effective
change management system.
xhibit 7–3
Work Management Form
The completed version of this form is based on the “Prepare Index” activity from the FDA project
shown in Exhibit 3–5. A blank copy is provided for your use.
Does your organization, work group, or current project have a formal change management plan?
If so, is it proportionate and effective? Do people follow the process?
SOLVING PROBLEMS
As we discussed in Chapter 6, risks are future tense, but problems are in the
present. No matter how well you plan, sometimes threats turn into problems.
Three types of problem solving activities belong in project execution: imple-
menting contingency plans, corrective actions, and workarounds.
Contingency Plans
For many of our risks, we modified the project plan to include our risk re-
sponse. For some risks, we chose to develop contingency plans: things we will
do if and only if the issue actually occurs or sends a warning signal that it is
about to occur. Some contingency plans exist because we’re really hoping to
avoid a large expenditure to address a rare event—but if that event happens,
we’re stuck with the bill.
Every contingency plan must have a trigger, which is an event that tells
us that we should put that plan into operation. As part of project execution,
you need to watch for those triggers, and when appropriate, launch contin-
gency plans.
By their nature, contingency plans are effectively project changes. They
consume resources and time, and may alter scope. Though you don’t neces-
sarily have to enter these into the change log, you may need to rebaseline
parts of the project once the emergency has passed.
Evaluate the performance of the contingency plan. Is it solving the issue
appropriately? Now that you see it in the real world, could it be improved?
Could we have addressed the underlying risk more effectively?
xhibit 7–4
Problem Solving Strategy
Exercise 7–2
Problem Solving
Instructions: You experience the following problems on the PMO project. For each:
1. The consultant you were planning to hire has problems and cannot do the job. You hired the
consultant five weeks before the engagement was due to begin, and two weeks later the con-
sultant had a medical problem and can no longer keep the engagement. It will take five more
weeks under normal conditions to get someone new, affecting all activities that use the con-
sultant.
2. A story appeared in the Wall Street Journal criticizing cost overruns and delays in one of your
larger projects. You are still a month away from being able to launch the PMO.
3. Your project sponsor is the deputy to the Chief Information Officer, a responsibility delegated
by the CEO. Your sponsor has been particularly supportive in dealing with skeptical managers,
keeping a lot of pressure off your project. Two months into the project, the deputy suddenly re-
signs to take a better job elsewhere.
Review Questions
1. Which baseline can serve as a PMB for the entire project? 1. (c)
(a) Tracking Gantt chart
(b) Scope verification system
(c) Cost baseline
(d) Responsibility assignment matrix (RAM)
4. To ensure that you keep track of who has been assigned to what 4. (a)
work activity, you may use a:
(a) work management form.
(b) tracking Gantt chart.
(c) configuration management system.
(d) performance measurement baseline.
Learning Objectives
By the end of this chapter, you should be able to:
• Identify the six questions to ask when plan-
ning for project monitoring and control.
• Explain three different methods for obtaining
project status information.
• Describe the options for reporting project
status.
• Establish a risk monitoring and control sys-
tem and explain when to update and modify
your risk management plan.
• Define quality assurance and quality control
and list ways to implement these on your
projects.
• Define earned value management (EVM) and
explain how to determine BAC, PV, AC, EV,
SV, CV, SPI, CPI, and EAC.
• Explain the importance of managing the
project plan and baseline.
As with most project decisions, you don’t want to make this kind of choice
on the fly. In this chapter, you’ll learn a number of tools and techniques for
project monitoring and control so that you can make effective choices when
planning your next project.
You may find some choices have been made for you. Your organization
may have standard forms or report formats. There may be predetermined
thresholds for reporting project issues. In many cases, however, these decisions
will be yours as project manager.
Because monitoring and control is so important, you should be prepared
to allocate resources—including a substantial amount of your own time—to
this work. Because resources are usually in short supply, you don’t want to
overdo it. Be careful to select techniques and tools that add value and improve
your ability to manage the project.
What are some ways you currently monitor and control work on your projects? Do those methods
work well for you? How could they be improved?
Status Reports
Members of your project team prepare status reports on their activities, and
you provide status reports on the overall project to appropriate stakeholders.
Which stakeholders and what information is decided when you prepare your
stakeholder management and communications management plans.
When the team is small and the project is not terribly complicated, it
may not be the best use of time to prepare a status report, but as team size
and complexity grows, it becomes harder for the project manager to keep all
the information in his or her mind.
Exhibit 8–1 shows a sample status report template for team members to
report status to you. “Stoplight Status” is green if everything is on track, yellow
if there is a minor variance, and red if there is a serious problem.
Status Meetings
There are several schools of thought on how to run a good status meeting.
One approach is to keep it to an absolute minimum: have each team member
xhibit 8–1
Team Member Status Report Form
Planned Total Cost Expenditures to Date Estimate to Complete Current Variance Total Variance
summarize his or her own status, and then adjourn. (Some people even rec-
ommend that you should not allow chairs as a way to keep the meeting short.)
Of course, often issues crop up in status meetings that require fuller attention,
but not everybody needs to be part of every discussion. Set separate meetings
following the status meeting involving just the people who need to be there,
and let everybody else get back to work.
Another approach takes into account that the team status meeting may
be the only structured opportunity to bring everyone into the same room. Use
the meeting not merely to get updated status info (a form may accomplish
just as much) but as an opportunity to build trust, air issues, and recognize
achievements. Such team meetings can build morale.
Many project teams today are not co-located: team members may be in
different states, time zones, or countries. The travel costs to bring everybody
together are so high that it’s not feasible to have regular all-hands get-togethers.
If possible, do bring everyone together for the kickoff meeting and for the les-
sons learned workshop, but that’s usually enough. Status meetings can be done
through teleconference or videoconference. That limits the role of team build-
ing, but you still have the opportunity to acknowledge and praise good work.
No matter which approach is right for you, always practice good meeting
rules: distribute an agenda, make sure that you and team members are pre-
pared with the right information, control interruptions and sidebars, and be
mindful that if a meeting runs too long (over 40 minutes or so), people start
to lose focus and effectiveness drops. If you need more total meeting time to
get through all the issues, consider having more frequent, shorter, and more
focused meetings instead of a single marathon session.
What grade (A, B, C, D, F) would you give to your organization’s meeting culture? What works and
what doesn’t? How could you improve the effectiveness of meetings on your project?
When you perform inspections and reviews, it’s important not to let it
become an inquisition. When people think the goal is to find an opportunity
to criticize, they become risk averse and may go so far as to hide bad news.
Establish clear criteria up front through the requirements process so that team
members can measure their own progress and be in control of results. Avoid
surprise inspections. When deficiencies are found, focus on ways to help the
team member make necessary corrections rather than spend excessive time
figuring out what went wrong.
If the final product must undergo testing, it’s important to test compo-
nents at earlier stages of the project. If each component is right, it’s less likely
the final product will fail, and it’s easier to pinpoint problems if they should
be found in the testing process. Document all test and inspection results as
part of the overall project record.
Frequency of Reviews
It doesn’t make sense to have a status meeting or require a status report if
nothing much has happened since the last one. The frequency of reports has
to be based on the speed of change within the project. If you measure activity
duration in weeks, have a weekly meeting. If you measure it in months, have
a monthly meeting. If you measure it in hours, you may need to meet daily.
The tempo of a project often accelerates as it moves through the project
life cycle. In preliminary stages, activities could last a month or more, espe-
cially if the project involves a long lead time. As the project picks up speed,
you may start to measure activities in weeks. When you reach crunch time,
you might measure in days. In a rocket launch, the last project activities are
measured in seconds: 10-9-8-7-6-5-4-3-2-1. For each of those final ten sec-
onds, there are specific defined activities taking place, and should those ac-
tivities not produce green lights on the board, the launch will be stopped.
The information needs of stakeholders often influence the status update
timetable. If the customer and project sponsor want a monthly report, you
might schedule brief updates weekly and have an all-hands staff meeting once
a month, a few days before the report is due.
Decide on your review cycle as part of planning, and make sure your
team members know what is expected of them in the process.
Don’t be constrained by a regular meeting schedule. If nothing much is
happening in a particular week, you might choose to skip the status meeting.
If, on the other hand, you’re dealing with major issues or changes, you may
want to put additional emergency meetings on the schedule.
xhibit 8–2
Project Status Report
Project Name
Project Summary:
Change Orders
Change Requests Requester Disposition Impact Summary
•
Additional Information
Risk Reassessment
In our risk triage process, we put aside a number of risks because their impact
or probability was too low, or the solution disproportionately expensive. For
risks we did address, we developed risk responses and contingency plans.
Characteristics of these risks may change during the project. Depending on
the overall level of risk, the amount at stake, and the changes you’ve experi-
enced, you may find it desirable to hold one or more special risk meetings in
which the entire risk register is reassessed based on the current situation.
Risk Audits
Both during the project and in lessons learned, evaluate the effectiveness of
your risk responses. If a risk was identified in a specific activity, the status re-
port should list whether the risk event occurred and how well the solution
worked.
Managing Reserves
One response to risks that we addressed earlier is to have a contingency re-
serve, which can consist of extra resources (financial and otherwise), extra
time (a schedule with a planned finish date in advance of the actual deadline),
or optional scope (desirable but nonmandatory project elements). During the
project, you’ll normally need to draw down some part of that reserve to ad-
dress those events.
Quality Assurance
Quality assurance is the name given to the activities involving the management
of process quality. In technical quality management, we often use the tools of
statistical process control (SPC) to track quality data and monitor variances
in our processes. Common quality assurance tools include:
• Process maps. A process map is a flowchart of the way in which we go about
certain work. A process map can help identify whether a process is need-
lessly complicated, or if the same work is handed back and forth multiple
times.
• Checksheets. Checksheets are forms for collecting data in an organized fash-
ion. For example, if we examine a product for defects, we can tally the cat-
egory of each defect in order to detect any patterns or common issues.
• Pareto diagrams. Pareto diagrams organize data in a vertical bar chart to make
it easy to distinguish the “vital few” sources that produce most threats or
opportunities.
• Control charts. Control charts keep track of whether a process is stable or
shows great variation.
These tools are common in such quality systems as total quality man-
agement (TQM) and Six Sigma. Appendix D: Additional Resources lists some
sources for additional information on quality management.
Quality Control
Quality control describes the various ways to ensure product quality. Tradition-
ally, quality control primarily meant inspection and testing, but the definition
has widened over time.
Simply saying that you plan to inspect or test a particular product isn’t
very helpful. Part of planning involves determining how you will inspect and
test. What are the most important requirements, or the requirements most vul-
nerable to error? Will testing be destructive (the test product is torn apart and
destroyed in the process) or nondestructive? In destructive testing, you can verify
every aspect of a product, but you can’t send it to the customer. That’s fine if
you’re making a thousand widgets, but less fine if you’re making one very ex-
pensive custom item. Nondestructive testing may not be able to look at the
product in the same depth, but it may still give you enough information.
Sometimes failure is inevitable. Mean time between failures (MTBF)
measures the average time a product can run until it breaks, and serves as a
measure of overall reliability and durability. MTBF helps determine proper
maintenance, repair, and upgrade cycles. If your project output is not a phys-
ical item, you might use checklists, user focus groups, or outside evaluations
to measure quality and compliance.
Establish your quality control methods and targets in the planning
process and implement them during project monitoring and control. During
lessons learned, review how effective and efficient your quality management
has been, and how you might improve it next time.
well. That’s the first key idea in how EVM works. Exhibit 8–3 takes that cost
baseline diagram and adds additional information.
Exhibit 8–3 shows that we have completed Week 8 of our 12-week proj-
ect. The original cost baseline from Exhibit 7–2 is shown as the planned value
(PV). As of the end of Week 8, the PV, or what we should have spent in order
to accomplish the work we were supposed to do is $16,250. (In older versions
of EVM, the term budgeted cost of work scheduled, or BCWS, is used instead
of PV.) Because it’s the plan, the PV goes all the way to the final planned proj-
ect cost of $25,000, which is known as the budget at completion (BAC).
The actual cost (AC), previously known as the actual cost of work per-
formed (ACWP) is how much money we’ve actually spent to date, regardless
of whether we’ve done more or less work than planned. At Week 8, the AC
stands at $20,000, meaning we’ve spent $3,750 more than planned.
Is that a problem? If that extra money is because we’re way ahead of
schedule and we’re doing stuff we wouldn’t otherwise have gotten done until
Week 9 or 10, that could arguably be good news. That’s why we have to com-
pare the AC to the value of the work we actually got done. The earned value
(EV), which used to be the budgeted cost of work performed (BCWP) is the
planned cost for the actual work—a hybrid measurement.
xhibit 8–3
Earned Value
$30,000
Now
BAC
$25,000
$20,000
EV
$15,000
AC
PV
$10,000
$5,000
$0
1 2 3 4 5 6 7 8 9 10 11 12
Confusing? Imagine that the plan says we should have done three activ-
ities by today, and each activity had a budget of $2,000. That means the PV is
$6,000. Unfortunately, we only got two activities done, so our EV is only
$4,000. We’re behind schedule by $2,000 worth of work.
Let’s imagine that we spent $5,000 on that work. The PV is still $6,000,
and the AC is $5,000. At first glance it looks like we’re under budget, but we
still have to do that third activity. Instead, we should compare the AC of $5,000
to the EV of $4,000. We got $4,000 worth of work accomplished, but we spent
$5,000 to get it done. That means we’re really $1,000 over budget from the
perspective of the overall project.
What if instead, we got four activities done instead of the three that were
scheduled? Our PV is still $6,000, because it only measures what’s in the
schedule. Our EV, however, is now $8,000! That means we’re ahead of sched-
ule by $2,000 worth of work.
Now let’s imagine that we spent $7,000 to get the work done. At first
glance, we appear to be over budget, with our AC of $7,000 comparing to the
PV of $6,000. But when we look at the EV of $8,000, it’s clear that we’re really
$1,000 under budget compared to the project as a whole.
Exercise 8–1
Earned Value Metrics
Instructions: For each problem, define the PV, AC, and EV. These questions use our network dia-
gram for the PMO project from the Answer Key to Exercise 3–5.
1. Today, the plan said that we should have accomplished Activity 1 “Research,” Activity 2 “Write
Policy,” Activity 3 “Obtain Feedback,” Activity 4 “Finalize Policy,” and Activity 5 “Org Chart and
Position Descriptions.” Each of these activities has a planned (budgeted) cost of $2,000. We
have accomplished all except Activity 5 and we have spent $9,500.
EV = _________
PV = _________
AC = _________
2. The financial report we just got tells us that we have spent $22,000 to date, and the schedule
says we should have just finished Activity 6 “Recruiting.” Since the last reporting period, we
have accomplished three tasks that were planned to cost $8,000, $4,000, and $9,000 each,
but have only completed half of Activity 6, which was supposed to cost $5,000.
EV = _________
PV = _________
AC = _________
3. The plan tells us that we were supposed to get $10,000 work of work done, but we actually got
$15,000 worth of work done as of the end of Activity 9 “Conduct Training.” So far, we have spent
$12,500.
EV = _________
PV = _________
AC = _________
Exercise 8–2
Cost and Schedule Variance
Instructions: For the three situations described in Exercise 8–1, calculate CV and SV for each.
1. _________________________________________________________________________
2. _________________________________________________________________________
3. _________________________________________________________________________
Exercise 8–3
Performance Indices
Instructions: For the three situations described in Exercise 8–1, calculate the CPI and SPI for each.
Round your answers to the nearest whole percentage point.
1. _________________________________________________________________________
2. _________________________________________________________________________
3. _________________________________________________________________________
Advanced EVM
If you end up in a position requiring EVM, you will want to study it in more
depth. There are many more EVM calculations and formulas than we have
shown here, and the exact application of EVM varies based on the kind of
project. On smaller projects, the cost of setting up and reporting EVM meas-
urements is often excessive, although Microsoft Project® and other scheduling
software provides some EVM features, such as automatic calculation of PV,
EV, and AC values if all the necessary information has been entered into the
software.
Are earned value techniques used in your organization or on projects you’re involved with? Would
they be useful and appropriate tools in your project environment? What potential benefits would
you get if you used EVM information?
The three basic ways to gather information on project status are meetings,
reports, and inspections. You usually use all three techniques. If you do not
already have standard forms for status reporting, develop them. If the mem-
bers of your team are not co-located (are geographically dispersed), you need
to develop tools to allow them to communicate effectively in spite of distance
barriers. Establish frequency of reporting based on the tempo of the project,
but feel free to modify the reporting schedule based on issues that may arise.
Risk monitoring and control involves tracking identified risks, monitoring
the effectiveness of risk responses, adding new risks and modifying existing
risks, and monitoring residual and secondary risk. Make risks a discussion
item at every status meeting and a category on every status report. Carefully
monitor the use of any contingency allowance or reserve.
The process of quality assurance and quality control are how we manage
process and product quality during the execution phase of the project. Quality
assurance and control use such tools as statistical process control (SPC),
process mapping, and other standard quality tools. Establish your quality con-
trol methods and targets in the planning process and implement them during
project monitoring and control. During lessons learned, review how effective
and efficient your quality management has been, and how you might improve
it next time.
Earned value management (EVM) is an advanced method used to mon-
itor and control large projects in such fields as construction, engineering, and
information technology. It is in widespread use in the US federal government,
where it has successfully identified troubled projects at early stages of their
life cycle. The three key metrics used in EVM are the planned value (PV),
the actual cost (AC), and the earned value (EV). Combined, they allow you
to measure cost and schedule variance in terms of the value of work. The per-
formance indices of CPI and SPI are particularly valuable in identifying issues
early.
One EVM lesson applicable to all projects is the importance of watching
for trends. A seemingly small variance can sometimes indicate a growing prob-
lem. Do not rebaseline the project for minor issues, but remember that major
changes, whether voluntary or in response to problems, may render the cur-
rent baseline useless as a monitoring tool, making rebaselining mandatory.
Review Questions
1. What are the three basic ways to gather information on project status? 1. (d)
(a) SV, CV, and CPI
(b) Stakeholder management plan, communications management
plan, and responsibility assignment matrix
(c) Test results, customer feedback, and sponsor reaction
(d) Meetings, reports, and inspections
4. The total project is planned to cost $100,000. The project currently 4. (b)
has a CPI of 85% and an SPI of 90%. What is the EVM forecast of
the likely total cost of the project, rounded to the nearest dollar?
(a) $111,111
(b) $117,647
(c) $85,000
(d) $90,000
CALCULATION: EAC (Estimate at Completion) = BAC (Budget at Completion) /
CPI (Cost Performance Index) = $100,000 / 0.85 = $117,647.06 = $117,647.
5. How frequently should you gather status information on your project? 5. (a)
(a) Based on the speed of change within the project
(b) At least weekly
(c) Whenever the customer or project sponsor wants an update
(d) No less often than monthly
Learning Objectives
By the end of this chapter, you should be able to:
• List the five elements of project closeout and
define each one.
• Prepare a closeout checklist from a template.
• Plan transfer of a project’s output to its final
destination.
• Plan and execute contract and procurement
closure.
• Plan and execute administrative closure.
• Celebrate project success and recognize pro-
ject performance.
• Establish a comprehensive lessons learned/
project salvage process.
PROJECT CLOSEOUT
The official PMBOK® definition of project closeout is “the process of finalizing
activities across all of the Project Management Process Groups to formally
complete the project or phase.” Let’s start with the last word: you’re not merely
supposed to close out a project, but also a phase, which we discussed in Chapter
2. You also need to close out a project (or phase) if it is cancelled or ended
short of completion, even though in one sense you haven’t “finalized activi-
ties…to formally complete the project.”
As we said earlier, no matter why the project ends, there’s still paperwork,
documentation, releasing resources, and preparing lessons learned. Therefore,
you must conduct project closeout for every project, regardless of the circum-
stances of its end.
When we talk about a project’s deadline, we normally mean the point at
which the the project’s “product, service, or result” has been completed and
transferred to the customer or other end user. Pretty much by definition, pro-
ject closeout happens after that. In spite of that, the vast majority of project
plans, including those developed by experienced project management pro-
fessionals, fail to include “Closeout” in their WBS list of work packages. That’s
a mistake. Closeout takes time and resources, and the failure to close a project
properly can have significant consequences.
Project closeout involves several steps:
1. Transfer. The product, service, or result has to be transferred to its ultimate
owner, whether it’s the customer or a group of end users. That may be as
simple as sticking a shipping label on it and calling for pickup, or it may
require a complex process of integration and training.
2. Contract closure. If your project requires procurement or contracting, all
contracts must be resolved, the contracts must be closed, and vendors must
be paid.
3. Administrative closure. You must notify stakeholders that the project is com-
plete and gain any necessary approvals. You must prepare and file any pa-
perwork your organization requires. You need to release team members
and other resources so they can be assigned to new work.
4. Celebration and reward. You owe your success in part to the people who
worked on your project. Acknowledging and rewarding performance is the
right thing to do, but it’s also the smart thing to do.
5. Lessons learned. No matter the outcome, every project has elements that are
useful in the future. In addition to analyzing performance and finding op-
portunities for improvement, don’t forget to salvage all the parts of the
project you might be able to reuse.
Depending on the complexity and size of the project, you may want to
create more WBS elements than simply “Closeout.” For example, the process
of turning the deliverables over to their final owners might require a WBS
package all its own.
Do you have a formal closeout process for your projects? What works and does not work about
your current closeout activities, whether formal or nonexistent? What areas seem ripe for improve-
ment?
CLOSEOUT CHECKLIST
For many project managers, closeout is the least fun part of the project. By
project’s end, you’re usually ready to move on to something new, and nobody
likes being stuck with administrivia. By organizing your closeout strategy in
advance, you can reduce the amount of pain and boredom commonly associ-
ated with the process.
The first tip for running a smooth closeout is to close as you go. Create
both a physical folder (or inbox tray) and a folder on your computer labeled
“Closeout,” and whenever you come across documents, emails, or other ma-
terial you’ll need at the project’s end, add it to the folders.
Second, create a closeout checklist. Exhibit 9–1 provides a closeout checklist
template you can modify to fit your needs. A general checklist will serve most
projects; you usually only need to tweak a line item or two. A good closeout
checklist organizes the material and makes sure you don’t forget any steps.
Some items can be checked off long before the actual project ends, making
the final steps easier.
Exercise 9–1
Closeout Checklist
Instructions: How would you customize the closeout checklist for the PMO project?
xhibit 9–1
Closeout Checklist
TRANSFER
The end of the project is usually determined at the beginning. Visualize exactly
how you will take the product’s output and deliver it to its intended customer.
What steps are necessary? Is there supporting documentation? Training? Ship-
ping? Packaging? As-builts? A period of transitional support? Will there be in-
stallation required? Will your product or service need to integrate with other
systems? How much time will all this take? How much will it cost? What re-
sources are required?
These are vital questions, and if they aren’t asked early and integrated
into the project plan, you may find yourself in trouble. An example: When
Chrysler designed the PT Cruiser, they neglected to consider how it would
be assembled. It wasn’t until the assembly line started up that they discovered
that car’s narrow hood was so constrained that there was only 0.6” of clearance
to fit the engine inside. Instead of being able to roll a new car off the assembly
line every two minutes, it took workers a day to fit each engine into each car.
Although ingenious workers found a workaround, eventually producing a car
every eighty seconds, this is an example of the kind of problem that occurs
when project managers think their work is done when the product is delivered
to the next stage of the process.
Exercise 9–2
Implementing the PMO
Instructions: How will your PMO be transferred from project status to full operation? Give specifics.
to use a backup. Those contracts have to be closed as well, and any related fi-
nancial issues resolved. As long as those actions are in the proper hands (your
purchasing or legal staff), you can also mark them “closed.”
When you are buying large, complex items or services, or ones with a par-
ticularly long lead time, you may need to conduct procurement audits or in-
spections. As part of closeout, you may have to engage in negotiations with
vendors to resolve issues sufficiently to allow you to mark those contracts closed.
Keep a procurement file with all contract and purchasing materials. It
should be archived along with other elements of administrative closure.
ADMINISTRATIVE CLOSURE
Most organizations have policies on document retention. You are normally
responsible for ensuring that a complete project file with all documentation
is archived in your records management system, in case of future claims or
problems that might arise. This file is separate from any “lessons learned,” al-
though your lessons learned report may be one of the items in your adminis-
trative closure file.
Different projects produce different amounts of information, and in some
cases administrative closure can take significant effort. If you think that might
be the case, that’s another reason why it’s so important to close as you go and
keep files up to date.
Administrative closure normally includes the release and return of assets.
Team members may return to their regular jobs or be transferred to a new
project team. If you’ve used consultants or outside resources, you’ll release
them to seek other work and handle the related contract issue as part of con-
tract closeout.
The accounting and finance departments will need final budget infor-
mation, and if you haven’t used all the allocated funds, you will need to turn
those over as well. If you use capital or durable assets, ranging from working
space to heavy machinery or anything else that isn’t used up in the perform-
ance of the project, those must also be relinquished or returned. Unused con-
sumables also need proper disposition.
What ways have the ending of your projects been recognized and celebrated? Are there any par-
ticular things that have worked well or poorly? How important is it to you that your work on projects
and the ends of projects be recognized and celebrated?
LESSONS LEARNED
Project management authorities are unanimous in recognizing the importance
of conducting project “lessons learned” reviews, and we agree. However, in the
real world, lessons learned are frequently skipped, people often resist the
process, and the lessons themselves are seldom integrated into other projects.
Establishing a useful and effective “lessons learned” process isn’t easy or auto-
matic. As with other elements of closeout, it’s essential to plan before you act.
What are some reasons people dislike “lessons learned”? First, the process
too often turns into blamestorming, in which figuring out who messed up seems
to be more important than figuring out how to do it better next time. The idea
of “lessons” makes the process seem designed to focus on criticisms. People
aren’t sure what they’re supposed to be looking for. There is no clear mechanism
for making the information and results available to other project leaders. The
lessons learned report itself talks about the old project and doesn’t emphasize
transferrable lessons. The lessons themselves can appear to be patronizing. And,
of course, there’s the famous “Not Invented Here” (NIH) syndrome that makes
people resist knowledge from outside. “Our project is different,” they say.
Exercise 9–3
Lessons Learned Questions
Instructions: What elements in the PMO project can be salvaged to add future value? List at least five.
1. _________________________________________________________________________
2. _________________________________________________________________________
3. _________________________________________________________________________
4. _________________________________________________________________________
5. _________________________________________________________________________
6. _________________________________________________________________________
7. _________________________________________________________________________
8. _________________________________________________________________________
9. _________________________________________________________________________
10. _________________________________________________________________________
xhibit 9–2
Lessons Learned/Project Salvage
1. What planning materials did we create that might have value for future projects?
1.1 Work Breakdown Structure
1.2 Project Schedule
1.3 Cost Breakdown
1.4 Responsibility Assignment Matrix
1.5 Communications and Stakeholder Management Plans
1.6 Risk Register
1.7 Others?
2. What did we learn about how long it takes and how much it costs to complete
certain activities?
2.1 Raw information to improve future estimates
2.2 Possible causes of variance between estimates and actuals
2.3 Ideas for shortening time, lowering costs, and improving performance
3. Which risks from our risk register occurred? What unforeseen issues occurred?
3.1 Should we alter estimates of probability based on this experience?
3.2 Were our risk responses effective?
3.3 Did we have to implement contingency plans?
3.4 Did the contingency plans work as expected?
3.5 What workarounds or corrective actions did we need to take? Should we alter our
planned risk responses on future projects based on this information?
3.6 If we had unforeseen issues, are they likely to recur? If so, how would we address
them in future risk plans?
3.7 Based on experience, would we want to adjust our planned risk responses to be
more effective?
3.8 Was our contingency allowance appropriately sized? Do we need more or less in the
future?
4. What change requests did we receive and what actions did we take?
4.1 If we had surveyed stakeholder needs better, could we have changed our initial
project to integrate these issues, or did the change result from factors that could not
have been known in the planning phase?
5. Did our project team have all the necessary skills and work maturity to accomplish what
needed to be done?
5.1 Do we need to provide training and coaching opportunities to develop skills we are
likely to need on future projects?
5.2 Are there any overall performance issues we need to address?
6. How did vendors perform?
6.1 Should we use particular vendors again, or should we seek alternatives in the future?
6.2 If we used outside consultants or other resources, are there any people we might use
again—or people we shouldn’t use again?
7. Were stakeholders happy with the process and the outcome? Why or why not? How could
we improve in the future?
8. Did our project create any products, processes, or other results that might have more
general use in our organization?
What are the most important ideas you will take away from this course? How will you implement
them in your future projects?
Celebrate a project’s success and make sure you take personal action to
recognize and reward performance. That’s not only the right thing to do, but
also the practical thing to do: you’ll end up with a more motivated team in fu-
ture projects.
Although project management authorities are unanimous in recommend-
ing “lessons learned,” in practice it’s not so easy. Lessons learned can devolve
into criticism, and all too often the lessons are archived and never seen again.
Consider reframing it as “project salvage,” with a goal of taking everything
reusable from the project, from WBS to risk plans to research data. Even failed
projects can produce things of surprising value.
Even if no one else uses lessons learned, you can. Project management
can be difficult and time consuming. When you build future projects on the
foundation of previous ones, you save time and increase quality. Every disci-
pline has a learning curve. Though it may be tough today, it can get easier to-
morrow.
Review Questions
2. What is a reason for keeping a log of all procurement and contracts? 2. (c)
(a) Lessons learned
(b) Administrative closure
(c) Contract closure
(d) OMB Circular A-11
4. What is a good first step to put lessons from this course to use? 4. (c)
(a) Put in a comprehensive project management system first thing
tomorrow
(b) Use every concept described in this book
(c) Perform earned value management on your next project
(d) Start slowly and build up
2. Project Time Management. What we know about the schedule and any
time constraints.
We know that the project must be complete in time for the stockholders’
meeting, nine months from now. We do not yet know how challenging this
schedule will be, or how much the schedule can be improved through extra
people or money.
3. Project Scope Management. What we know about the work that must be
done, and the work that is not included in this project.
Our current description of scope is rather limited: a “functioning PMO.”
Exactly what this looks like has to be fleshed out fairly quickly. There may
be long-term issues that are not part of this project, even though they will
have to be addressed eventually.
4. Project Cost Management. What we know about the budget, resource
availability, and anything else we might spend to accomplish the project.
We have received no guidance on budget or resources. This suggests that
our priority is more likely going to be time, and that we may have flexibil-
ity in the resources we request to accomplish the work.
5. Project Communications Management. What we know about the need
to report and communicate with others during the project.
The CEO’s personal interest means that the CEO will probably want to
keep track of progress, and in particular know about any issues that would
jeopardize the deadline. We will have standard project communications
issues, such as the need for status meetings and reports. Individual project
managers will be impacted by the new PMO and will also need to be con-
sulted about their issues, needs, and concerns, and about any changes they
will have to make to their own activities based on this new PMO struc-
ture.
6. Project Stakeholder Management. What we know about people affected
by the project, their interests, and their issues.
We are already aware that some managers have concerns about this new
PMO, and we need to discover exactly what those issues are and how we
can address them. We also need to understand the issues that make our
stockholders interested in the PMO so that our project scope addresses
the reasons they want a PMO in the first place.
7. Project Human Resources Management. What we know about the peo-
ple and skills we need to accomplish the work.
Aside from the assignment of a project manager, we have not yet received
any guidance on the team we will have to do the work. Given that the proj-
ect is to develop a new department, we will need to do the necessary
staffing, whether that involves transferring or reassigning existing employ-
ees or hiring new ones.
8. Project Quality Management. What we know about factors that deter-
mine whether this project will meet the needs for which it was established.
We seem to have two initial quality objectives: solve the problems that have
led to recent project failures, and show the stockholders that we are adopt-
ing industry best practices. Although these objectives are compatible, they
are not identical. It’s not enough to solve the problem; we must also demon-
strate the solution. And it’s equally not enough to show off a PMO; the
PMO actually has to work.
9. Project Procurement Management. What we know about any products
or services to be acquired outside the organization.
Any number of outside resources are available to us. We can hire project
management consultants with experience in setting up PMOs. We can hire
trainers to develop project management skills among our staff. If we must
recruit new employees to staff the PMO, we can hire outside recruiters.
This suggests that we will need to consider a variety of “make or buy”
choices, which will be affected by both the budget and the schedule.
10. Project Risk Management. What we know about project threats and op-
portunities.
We already know about potential internal resistance on the part of some
managers, and we do not yet know whether the time constraint is realistic.
Because we do not yet have much information on cost and resources, we
are uncertain what risks may exist in those areas. There are also substantial
opportunities available to us, not the least is that we are building a PMO
using project management, which means we will be building resources we
can take immediate advantage of.
Skeptical May be asked Will this project Positive: May May have political Interested in the In initial phases,
managers to furnish take away their improve project influence that can initial planning and identify concerns
resources or power, authority, or performance and be used for or strategy, which and potential
information in resources? Will it deliver better against you; may may or may not issues; address
support of the actually work, or results for their provide support or reassure them them as much as
project. merely add an departments or hindrance in the about some of their possible in hopes
additional layer of programs. process; may need concerns. Work of of reducing some
bureaucracy? What Negative:May take to provide the project may of the opposition.
powers will the new away some of their resources. impact their Show them
department have? power and resources. Output potential benefits of
authority; may take of the project may the project’s
away resources. affect their success. Escalate
May not work as authority and role. any major
advertised. problems to the
CEO.
Consultants Consulting and Depending on the Their particular Can fill in any Consultants will only Consider these
training extent and areas of expertise knowledge or skill be involved after the issues in “make or
services availability of and the functions gaps and decision is made to buy” decisions on
internal resources, we decide to supplement internal recruit and hire whether and where
and the overall acquire from resources. Will them. Will be to use outside
budget and timing, outside. Money consume project involved with services. Negotiate
we may want to they make from budget. May be operational decisions contracts carefully.
use outside providing the tempted to oversell and work in their Establish incentives
consultants and service. services and push area of expertise. to ensure their
trainers with Opportunity for for long-term May or may not have services are in line
experience in follow-up work. contracts. a long-term role in with your long-
setting up PMOs. the operation of the term goals.
PMO.
Project What the PMO We may survey The product, not While the needs, Project managers Survey project
managers can do for project managers the project, will be interests, and ideas will provide input, managers and
them to get their ideas the major impact of the project but not direction, to evaluate what is
about what the on them. Until the managers are the initial project working and not
PMO should do PMO is up and important and definition, and will working about the
and how it will running, project should be be the major end present system.
work. May use managers will considered, they are users of the PMO Develop an
some PMs as part continue to operate not the decision- once established. implementation
of the project team. as they have makers. Potential strategy to handle
previously. Some career opportunity the transition from
project managers for project current methods to
may be recruited to managers who want the new PMO.
work in the PMO. to be in the PMO.
Training and skill
building opportunity
for PMs.
Customers The quality of None Reducing project Some customers They may want to We may want to
projects failure rates will may be consulted know about the provide press
benefit customers. during the project, efforts we are releases or other
but in general, they undertaking to information to
will only deal with improve projects, customers
the result. but don’t care advertising our new
about the PMO as capabilities as part
such. of obtaining new
business, but this
work will probably
be handled by our
marketing and
sales team
separately from the
PMO project itself.
Stockholders None Our project results; Project success will Little or none They care about Communication
concerns about grow the company, during the project results, not about with stockholders
company which in turn will itself. the project or the will probably be
performance and increase stock PMO itself. kept with the CEO
stock price. price. and stockholder
relations people,
not with the project
team.
Cost: There are two separate cost considerations. First is the project
budget itself. You have been asked to cap it at $50,000. This would include
any costs for outside consultants, software, training, etc. The value of em-
ployee time will not be charged to the budget. The second consideration
is the cost of running the PMO itself: no more than $200,000 per year.
While this is not technically a “project cost,” but rather an operational cost,
it still serves as a constraint on the PMO that you develop.
Performance: We have not been told the details of how this PMO should
work, but we have been told what its goals are. The first goal is to reassure
the stock analysts and stockholders that yes, we have a PMO. The second
goal, based on the management skepticism, is that the PMO needs to im-
prove the management of projects without adding excessive bureaucracy
or threatening the authority of line managers.
Hierarchy of Constraints
Driver: The need to have something to show the stock analysts and stock-
holders is dominant, so we conclude that time is the driver. After all, we
can continue to upgrade the new PMO after the meeting is over.
Middle Constraint: While the exact shape and structure of the PMO has
been left to us, the goals of (a) happy stock analysts and (b) greater project
management effectiveness are the reason for undertaking the project in
the first place. If the PMO doesn’t deliver the promised benefits, it hardly
matters whether we meet the budget or not: the money will have been
wasted. We conclude that performance is the middle constraint.
Assumptions
• The proposed budget of $50,000 and operating budget of $200,000 per
year will turn out to be reasonable once we develop the project scope.
• Only a few managers are worried about their authority being chal-
lenged; the managers who talked only about the PMO’s effectiveness do
not have a hidden agenda.
• Our competitions’ PMOs are benefitting their projects.
• The stock analysts’ concern about our company will go away if we
demonstrate that we have a functioning PMO.
• We will not be able to use in-house people to staff the PMO because
those who would be qualified cannot be spared from their current jobs.
• Nine months is a reasonable timeframe to accomplish this work.
• Even though you, the project manager, have no experience in setting up
a PMO, it is well within your ability to do so.
• Of all the ways we could improve project performance in our organiza-
tion, the PMO is the best strategy right now.
Stockholder
Project Management
Presentation
Evaluation of Results
4.
1. 2. Write 3. 10. PMO Stockholder 12.
Start Finalize FInish
Research policy Feedback project Meeting Evaluate
policy
5. Org 11.
chart and 6. Recruit 7. Hire Stock-
PDs holder
Notes: Notice that we begin looking for an outside trainer and start setting
up the new PMO after we’ve received feedback but before the policy doc-
ument is finalized. This allows us some extra time for adjustment. The final
policy only needs to be in place when we hire.
To develop the stockholder presentation, we need to have the depart-
ment set up and running, with work being done to support one or more
projects. The stockholders’ meeting, like “Start” and “Finish,” is a project
milestone. Although in one sense the stockholders’ meeting is the deadline,
the evaluation and fine-tuning of the new PMO can and should take place
afterward—not all project work necessarily needs to be done before the
deadline to consider it a success. The project isn’t finished until final rec-
ommendations have been made.
This version shows the connecting lines, although they are optional, especially
in hand-drawn Gantt charts.
Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
4. How would you estimate the time required for Activity 6 (“Recruit
PMO Head”)?
Expert judgment from the HR department is the most obvious way.
Given that the time to hire is going to be a critical issue in making the
deadline, you might use the opportunity to negotiate with HR to see
how quickly they can do it. You probably would not want to use analo-
gous estimating, because that would use normal times, not expedited
processes.
5. How would you estimate how much it will cost for Activity 11 (“Prepare
Stockholder Presentation”)?
Analogous estimating or expert judgment would both work.
Policy Project
Team Procure Org. Present
Research Develop Writing Manage HR
Member -ment Devel. -ation
-ment -ment
Nguyen E A A N N N N E
Susan A E A N A E E A
Gemma E E A A A E A A
Jurgen A E E N A N N E
Sean A E E N A E E E
HR Department,
Hire staff Project Manager Project Sponsor CEO
Sean
Hire outside Gemma, Jurgen,
Project Manager Project Sponsor CEO
trainer Sean
Note 1. After the fourth crash, all activities are critical. Any further crashes
must be taken equally from both paths.
Note 2. After the fifth crash, there is still one available day to crash in Ac-
tivity F. However, the next cheapest combination (Activity F + Activity
G) will cost $275, which is more than our $250 value of early completion.
Total savings through CPM analysis: 15 weeks, $1,625.
The following is the final version of the network diagram.
Critical Path = 0 + 10 + 18 + 2 + 1 = 31
10, 10 18, 18 2, 1
Activity A
Activity H
0, 0
1, 1
$0
$50
9, 9 9, 7 12, 5
Critical Path = 0 + 9 + 9 + 12 + 1 = 31
Project that Support and help Active embracing Choose project Project manager,
PMO is without feeling of the new work early, involve project CEO
assigned overburdened with group, help in manager in PMO
administrivia. making it planning
successful, good discussions, offer
project outcome. rewards for
cooperation and
performance.
Other managers A project outcome Lack of active Survey managers to Project manager
(especially the that doesn’t cause resistance, positive discover their main
skeptical ones) them to lose support, concerns, address
authority and power cooperation in concerns in plan,
and that improves implementing the brief managers
their success. new system. monthly.
*These answers are common, but we don’t recommend them. It is important, however,
that you be honest with yourself on the risks you do and do not choose to accept.
Acceptance
1 – No
3 2 6 (high) (we don’t have it)/Act on the
experience
risk (get outside expertise)
Act on the risk
2 – Skeptical (listen to and address their
1 3 3 (medium)
managers concerns)/Transfer the risk
(get CEO involved)
Act on the risk (get it done
3 – Staffing
3 2 6 (high) early)/Transfer the risk
speed
(involve HR)
Transfer the risk
4 – Stock
1 3 3 (medium) (we aren’t in charge of
analysts
shareholder relations)
This investment appears very safe. Very large fluctuations in payoffs and prob-
ability still lead to an EMV that is positive. You might make only a little bit
of money, but it seems highly unlikely you will lose. Whether or not you make
the investment may rest on what options you have for your money.
2– Mitigate/ We will mitigate the risks by Residual risk is fairly low, but the
Skeptical Transfer interviewing these managers secondary risk is that the CEO will
managers and attempting to address not think well of us if we must
their concerns. We will transfer invoke that help.
the remaining risk to the CEO
in case we encounter strong
resistance.
5 – No Mitigate We will try to locate a suitable The residual risk is that the project
current project early. we select may not benefit
project immediately and measurably from
the PMO; the secondary risk is that
they (and other projects) may
resent outside interference.
6– Mitigate/ We will prepare the draft early Residual risk is low; secondary risk
Needs Transfer and only after consulting with is that we could create resentment.
Revision stakeholders about their
needs. If people are slow in
responding, we will ask the
CEO to make it a priority.
7– Exploit We will immediately search for Residual risk is low; secondary risk
Templates templates we might be able to is that we may pick a template that
use. isn’t suitable for our needs.
8– Mitigate/ We will research and interview The residual risk is that we could
Consultant Enhance consultants and check still get it wrong; the secondary risk
references carefully before is that these steps take extra time.
making a selection.
Risk Type (F or N)
The product will fit inside a 20” x 40” x 60” box. Functional
Risk Type (F or N)
Activity A 0w 0w —
Activity B 2w 3w A
Activity C 2w 2w B
Activity D 1w 2w B
Activity E 2w 2w D
Activity F 2w 3w B
Activity G 3w 2w E
Activity H 3w F, G
Activity J 3w H
Activity K 2w E, G
Activity L 2w K
Activity M 0w J, L
Scheduled Milestone As of today, Activity F has taken two weeks. We estimate there is still one week of effort needed to finish.
Actual Forecast
Milestone
Forecast
The schedule forecast says the project will be completed one week behind
schedule.
2. Major project in trouble. (1) Solution 1: This situation is a crisis for the
company, and they’re very lucky that your PMO project is already in
progress. Because of this major outside issue, you should talk to the
sponsor or CEO about whether a new approach that spends more money
is justified. Your initial budget was built on the assumption that the crisis
wasn’t immediate. It may now be desirable to increase the budget sub-
stantially and bring in more outside resources to assign to the project
emergency as well as to build the most effective PMO. Solution 2: You
could work with the corporate communications office to provide press
releases on the PMO work in progress as a counter to the press story
and continue the project as is. (2) If this wasn’t on your risk list, that’s
okay. It’s way outside the project scope. The exception would be if you
already knew that a troubled project was one of the motivators for the
PMO. In that case, escalating trouble on that project would be a high
risk. (3) This could be an opportunity as well as a threat—whether you
can fix all the problems with the troubled project or not, it’s a way of
getting the strongest possible support to make your PMO outstanding.
3. Project sponsor leaves. (1) Solution 1: Depending on the level of opposition
from skeptical managers, you might want to set up a meeting with the
CEO to arrange a new sponsor with appropriate power and influence.
Solution 2: You could ask the CEO to take direct action to support your
project over the objections of those skeptical managers. (2) Though the
departure of the sponsor might not be a risk you could have anticipated,
you already knew the risk from skeptical managers was high. Therefore,
you shouldn’t have been counting on the project sponsor to solve 100%
of the problem for you. Other steps in your risk plan, including outreach
to those managers and trying to address their concerns, should have re-
duced the problem. If their opposition is strong and ongoing, you would
have developed evidence to help persuade the CEO to take a stronger
personal stand. (3) This problem can be mitigated, but the skeptical
manager issue won’t go away and the transition of responsibility will
give you some problems no matter what.
Actual cost (AC). In earned value management (EVM), how much we spent
for the work we have accomplished at this moment in the project.
Change control board (CCB). A formal board that reviews and approves
technical changes to a project. See configuration management.
Co-location. The degree to which the members of your project team are
physically close to one another. Compare to virtual team.
Cost variance (CV). In earned value management (EVM), the earned value
(EV) minus actual cost (AC).
Critical path. The sequence of project activities that determines the du-
ration of the project; the longest path through a project network diagram.
Deadline. The date on which the project’s product, service, or result must
be completed. It is not necessarily the date of the last activity in a project.
Driver. The element of the triple constraint that is essential to success and
has the least flexibility
Early start. The earliest the activity can start considering its predeces-
sors.
Earned value (EV). In earned value management (EVM), how much we have
actually accomplished and how much we should have spent for that work at
a given point in the project.
Finish to finish (FF). A situation in which one activity can’t finish until
its predecessor has finished.
Finish to start (FS). A situation in which one activity can’t start until its
predecessor has finished.
Forward and backward pass. A technique for calculating the critical path.
Free float. Extra time before the next task begins, whether the subsequent
task is on the critical path or not. See float.
Gantt chart. A bar graph drawn over a calendar grid, showing when spe-
cific tasks will be accomplished in the schedule.
Godzilla principle. The earlier you catch a risk, the greater the options
available to deal with it.
Kickoff meeting. The initial meeting that begins the actual project work.
Knowledge areas. In the PMBOK® Guide, knowledge areas are the iden-
tified areas of project management and the processes needed to perform them.
There are ten knowledge areas.
Late finish. The latest the activity can finish without affecting the critical
path.
Leveling. The process of balancing the workload and the resources avail-
able to do it.
Network diagram. A flow chart picture of the work of the project that
shows interdependencies and connections.
Parallel activity. An activity taking place at the same time as another ac-
tivity.
Parkinson’s law. “Work expands so as to fill the time available for its com-
pletion.”
Process group. One of the stages in the project life cycle. The process
groups are project initiation, project planning, project execution, project man-
agement and control, and project closeout.
Project charter. The document that that formally authorizes the exis-
tence of a project and gives the project manager working authority to proceed,
whether it’s a memo, an email, or a contract. It doesn’t matter if the project
charter is labeled “project charter” or not.
Project life cycle. The stages of a given project. May be general or spe-
cific to the needs of the project.
Project scope. All the work necessary to complete the project, and no
more.
Pure risk. A risk situation that only has a negative outcome (also known
as insurable risk).
Quality. The extent to which the project’s product, service, and result
satisfies the needs for which it was undertaken.
Residual risk. Risk left over after you have taken action on the primary
risk.
Risk management plan. A document that is part of the project plan and
that identifies and describes the risks, rates their relative seriousness by con-
sidering their probability and impact, lists any planned responses or actions
intended to reduce downside risks or improve upside risks, and explains how
the project team will monitor risks and responses for effectiveness.
Risk mitigation cost. What you would need to spend to reduce the risk to an
acceptable level.
Risk reassessment. The process of reviewing risks from the project plan
in light of actual project information.
Risk response planning. The process of deciding what action (if any) to
take in response to a specific risk or category of risk.
Risk threshold. The level above which we are not willing to accept risk
in a particular category.
Rolling wave estimate. An estimate iterated during the project life cycle
as more information becomes available.
Secondary risk. A risk that comes into existence as a result of your at-
tempt to solve the original risk.
Start to start (SS). A situation in which one activity can’t start until its
predecessor has started.
Value of early completion. The payoff for finishing a project early. See
critical path method (CPM).
Weak constraint. The element of the triple constraint with the greatest
flexibility.
Budd, Charles I. and Charlene S. Budd. A Practical Guide to Earned Value Project
Management. Vienna, Virginia: Management Concepts, 2005.
Crosby, Philip B. Quality Is Free: The Art of Making Quality. New York: Mentor,
1980.
Darmody, Peter B., PSP. “Henry L. Gantt and Frederick Taylor: The Pioneers
of Scientific Management.” AACE International Transactions, 2007, pp. 15.1–
15.3.
Dobson, Michael. Project: Impossible: How the Great Leaders of History Identified,
Solved, and Accomplished the Seemingly Impossible—and How You Can Too! Oshawa,
Ontario: Multi-Media Publications, 2013.
Dobson, Michael and Deborah Singer Dobson. Project Risk and Cost Analysis
(AMACOM). New York: AMACOM, 2012.
Dobson, Michael S. and Heidi Feickert. The Six Dimensions of Project Manage-
ment: Turning Constraints Into Resources. Vienna, Virginia: Management Con-
cepts, 2007.
Gruebl, Tony and Jeff Welch. Bare-Knuckled Project Management. Arlington, Vir-
ginia: Gameplan Press, 2013.
Kuehn, Ursula, PMP. Integrated Cost and Schedule Control in Project Management.
Vienna, Virginia: Management Concepts; 2006.
Kwak, Young Hoon and Lisa Ingall, “Exploring Monte Carlo Simulation Ap-
plications for Project Management,” Risk Management (2007) 9, 44–57.
doi:10.1057/palgrave.rm.8250017
Miller, Michael J. InfoWorld, April 18, 1988. Vol. 10, No. 16, p. 64.
Mooz, Hal, PMP, Kevin Forsberg, and Howard Cotterman. Communicating Proj-
ect Management: The Integrated Vocabulary of Project Management and Systems En-
gineering. New York: John Wiley & Sons, 2003.
US Food and Drug Administration, Center for Drugs and Biologics. “Guide-
line for the Format and Content of the Summary for New Drug and Antibiotic
Applications.” Rockville, Maryland: Office of Training and Communications;
1987. Retrieved from http://www.fda.gov/downloads/Drugs/GuidanceCom
plianceRegulatoryInformation/Guidances/UCM072058.pdf, 31 July 2013.
In addition to the many fine books (some listed in the bibliography) and sem-
inars available from a variety of sources, the Web is a rich source of informa-
tion on project management. The following list is not intended to be
comprehensive, and new resources appear on the Web all the time.
American Management Association
http://www.amanet.org
Earned Value Management:
Tutorial: http://www.tutorialspoint.com/earn_value_management/
Wikipedia:
http://en.wikipedia.org/wiki/Earned_value_management
Sidewise Insights (Michael Dobson, PMP)
http://sidewiseinsights.com
http://sidewiseinsights.blogspot.com
http://www.twitter.com/SideWiseThinker
Requirements Template Examples
www.hud.gov/offices/cio/sdm/devlife/tempchecks/frtemplate.doc
http://web.mit.edu/ssit/cis/CISRequirements.html
Quality Resources
The Basics of Project Quality Management:
http://blogs.attask.com/the-basics-of-project-quality-
management/
Project Quality Management Plan Template:
http://www.itplanning.org.vt.edu/pm/qualitymgmtplan.html
Measuring and Managing Project Quality:
http://sinche.uom.gr/sites/default/files/managingquality.pdf
FOR QUESTIONS AND COMMENTS: You can also contact Self Study at 1-800-225-3215
or visit the website at www.amaselfstudy.org.
10. Look at the WBS that follows this question. How is it organized?
(a) By department or work group
(b) By phase
(c) By cost account
(d) By difficulty or risk
Develop a Course
Instructional Systems
Production Operations Marketing
Design
Ship Materials to
Develop Exercises Conduct Beta Test Approve New Course
Seminar Location
Finalize Course
13. The extent to which the project’s product, service, and result satisfy the
needs for which it was undertaken is known as:
(a) quality.
(b) scope.
(c) risk.
(d) WBS.
14. Look at the following network diagram. What is the critical path?
(a) A→B→D→H
(b) A→E→C→D→H
(c) A→E→F→G→H
(d) A→C→H
Activity B Activity D
4 days 3 days
15. Today, we were supposed to have completed four activities that were
planned to cost $2,500 each. We have actually accomplished only three
of those activities and we have spent $7,000 to date. In earned value
method terms, what is our cost performance index, rounded to the
nearest whole percent?
(a) 93%
(b) 107%
(c) 75%
(d) 133%
18. What performance measurement baseline can serve as a metric for all
three triple constraints?
(a) Cost baseline
(b) Responsibility assignment matrix
(c) Tracking Gantt chart
(d) Weekly status reports
20. How frequently should you hold status meetings or require status
reports?
(a) Preferably weekly, but no less often than monthly
(b) Whenever a problem or issue arises
(c) When the project sponsor or customer need an update
(d) Varies based on the speed of change within the project
25. You have identified a risk that the price of raw materials you need for
the project could potentially double in price by the time you would
normally purchase them. You decide you will buy the materials far in
advance of need to lock in the price. What risk response strategy have
you used?
(a) Avoid
(b) Mitigate
(c) Transfer
(d) Contingency plan
AC (actual cost), 147–149, 195 in defining the project, 33–34 buy-in, obtaining, 37
acceptance, of risk, 114–115, 195 definition of, 195
activity(-ies) in project initiation, 8 Canceled projects, 10
assigning team members to, 81 recognizing, 33 CCB (change control board),
definition of, 195 authority, 195 133, 196
double-booked, 85–86 avoidance, of risk, 112, 195 CCPM (critical chain project
estimating, see estimating management), 74, 197
activities BAC (budget at completion), celebration, at project closeout,
finalizing, 158 196 158, 162–163
parallel, 51, 201 backward pass, 55–58, 199 change control board (CCB),
planning, see planning baseline(s) 133, 196
activity(-ies) cost, 126–128, 197 change log, 130
in project time management, definition of, 195 change management, 10, 124,
11 definitive estimates as, 69 130, 133, 196
in responsibility assignment and IPMA Competence change management system, 130
matrix, 84 Baseline certification, 2 change requests, 130
activity list, constructing, 50–52 performance management, checksheets, 146
“activity on arrow,” 50 124–126, 201 Chrysler, 161
“activity on node,” 50 schedule, 125–126 closeout, 196, see also project
actual cost (AC), 147–149, 195 updating, 153 closeout
actual cost of work performed BCWP (budgeted cost of work closeout checklist, 159–160, 196
(ACWP), 148 performed), 148 co-location, 196
Adamiecki, Karol, 2 Bell Telephone, 117 communications and stakeholder
administrative closeout, 158, 162 benchmarking, 119 management plan, 90–92,
Alesia, Battle of, 2 biases, of experts, 68 145
American National Standards blamestorming, 163, 196 communications management,
Institute (ANSI), 3 Booz Allen Hamilton, 2 see project communications
analogous estimates, 67, 195 bottom up approach (WBS), 48 management
APM (Association for Project bottom-up estimates, 68–69, 196 competitors, as stakeholders, 26
Management), 2 budget, closing, 162 condition consequence, 196
Apollo 13 rescue, 116 budget at completion (BAC), 196 configuration management, 133,
approval, obtaining, 37 budgeted cost of work 196
Association for Project performed (BCWP), 148 constraints
Management (APM), 2 buffers, 74 in defining the project, 29–32
assumptions business risks, 16, 97, 98, 196 definition of, 196
hierarchy of, 30–33, 66, 199 critical path method (CPM), 2, 152, 198
interplay of, 96 88, 197 early finish, 45, 55, 87, 198
in project initiation, 8 critical path method (CPM) early start, 55, 198
ranking, 31 analysis, 87–90 earned value (EV), 147–149
triple, 29–30, 96, 207 Crosby, Philip, 119 advanced, 152
contingency allowance, 13, 74, C/SCSC (Cost/Schedule applying, 151
109, 196 Control Systems Criteria), cost baseline in, 127
contingency plans, 114, 134, 196 147 definition of, 198
contingency reserve, 13, 196 customers earned value management
contingent response, to risk, 114 communication needs of, 13 (EVM), 147–153
continuous improvement, 15, as stakeholders, 25 cost and schedule
117, 196 CV (cost variance), 150, 197 performance indices in, 151
continuous process cost variance and schedule
improvement, 117 Deadline, 10–11, 158, 197 variance in, 150
contract closure, 158, 161–162 decision node, 110 definition of, 198
contracts log, 161 decision trees, 110–111, 197 planned value, earned value,
control, see project monitoring defining projects, 21–38 and actual cost in, 147–149
and control assumptions in, 33–34 effort, 198
control charts, 146 constraints in, 29–32 Eiffel, Gustave, 2
COQ (cost of quality), 119, 197 and obtaining approval and EMV (expected monetary
corrective actions, 134, 197 buy-in, 37 value), 108–110, 198
cost progressive elaboration and end users, 26
actual, 147–149, 195 project objective in, 37 enhancement, 113, 198
balancing time, resources, and, and project charter, 34–36 estimate at completion (EAC),
87–90 project initiation in, 23 152, 198
budgeted, 148 and projects vs. phases of estimates
PERT calculations for, 71 projects, 23–24 adjusting, 69
risk mitigation, 205 and reasons for projects, 22 definition of, 198
cost baseline, 126–128, 197 stakeholder considerations in, evolution of, 80
cost-benefit analysis, 119 24–28 three-point, 207
cost constraint, 29 definitive estimates, 67, 69, 197 estimating activities, 65–76
cost estimating, 197 deliverables, 50, 197 issues in, 74
cost management, 13, 202 Delphi technique, 68, 198 methodologies for, 67
cost of quality (COQ), 119, 197 department-based WBS, 45, with Monte Carlo simulation,
cost performance index (CPI), 47–48 73
151, 197 dependency relationships, with PERT, 70–72
Cost/Schedule Control Systems 52–53, 198 standard techniques for, 67–69
Criteria (C/SCSC), 147 design of experiments (DOE), three-point, 69–73
cost variance (CV), 150, 197 119 uncertainty in, 66
CPI (cost performance index), destructive testing, 147 EV, see earned value
151, 197 distribution, 198 EVM, see earned value
CPM, see critical path method documentation management
CPM (critical path method) of contracts, 161 execution, see project execution
analysis, 87–90 of lessons learned, 163 expected monetary value
crash, 197 of procurements, 161, 162 (EMV), 108–110, 198
crash cost, 88 of requirements, 15, 43–44 experiments, 119
crash duration, 88 retention policies for, 162 expert judgment, 68
crashing projects, 88–91 DoD (US Department of exploitation, of risk, 113, 198
critical chain project Defense), 147
management (CCPM), 74, DOE (design of experiments), Failed projects, 164
197 119 filtering, 199
critical path drivers, 30–32, 198 finish to finish (FF), 54, 199
definition of, 197 DuPont Corporation, 2, 88 finish to start (FS), 54, 199
determination of, 53–54 duration, 198 firefighting, 199
in network diagramming, float, 53, 88
58–60 EAC (estimate at completion), definition of, 199
free, 58, 59, 199 Kennedy, John F., on forward and backward pass in,
in network diagramming, commitment to goal, 30 55–58
58–60 kickoff meeting, 129, 199 project layout in, 52–53
forward and backward pass, knowledge areas, 11–18, 200 scheduling relationships in, 54
55–58, 199 NIH (Not Invented Here)
free float, 58, 59, 199 Lag, 54, 200 syndrome, 163
FS (finish to start), 54, 199 late finish, 55, 200 Nixon, Richard, 37
functional organizations, 6, 199 late start, 55, 200 nondestructive testing, 147
functional requirements, 118, lead, 54, 200 nonfunctional requirements, 118,
199 lessons learned, 10, 117 200
definition of, 200 Northridge earthquake, 87
Gaius Julius Caesar, 2 documenting, 162 Not Invented Here (NIH)
Gantt, Henry, 2 in project closeout, 158, syndrome, 163
Gantt chart, 60–62 163–165
definition of, 199 leveling (term), 200, 204 OMB (US Office of
from network diagrams, 49 leveling the schedule, 85–86 Management and Budget),
origin of, 2 Liddy, G. Gordon, 37 147
tracking, 207 loading (term), 200, 204 one hundred percent rule, 49
goals loading the schedule, 85–86 ongoing work efforts, 3, 200
quality, 66 operations, 3, 200
for stakeholder and Make or buy decisions, 86, 87 opportunities
communication management, as scientific definition of, 16, 200
management, 90 discipline, 2 as positive risk, 16, 97
Godzilla principle, 199 managers, as stakeholders, 25, 26 risk responses for, 110–112
Godzilla Principle (Dobson), 97 matrix organizations, 7, 200 optimistic estimates, 70, 71
grade, 118, 199 McNeil, 164 organizational structure, 6–7
grading policy, xvi mean time between failures org chart format (WBS), 45, 46
groupthink, 68 (MTBF), 147 outline format (WBS), 45, 46
guesses, 67 Microsoft Project®, 73, 125, 152 outsourcing, 86–87
A Guide to the Project Management middle constraints, 31–32 overoptimism, in estimating, 74
Body of Knowledge (PMBOK® milestones, 56, 143, 145, 200
Guide), 3, 23, 100 Miller, Michael J., on project Parallel activities, 51, 201
management, xiii parametric estimates, 68, 201
Hierarchy of constraints, 30–33, mitigation, risk, 112, 200 Pareto diagrams, 146
66, 199 monitoring and control, see Parkinson’s Law, 74, 201
project monitoring and PDM (precedence diagramming
ICB ® (IPMA Competence control method), 50
Baseline) certification, 2 Monte Carlo simulation, 73, 108, performance constraint, 29
IEEE (Institute of Electrical and 200 performance evaluations, 163
Electronics Engineers), 3 most likely estimates, 70 performance management
-ilities (term), 118, 199 motivation, 163 baseline (PMB), 201
imposed dates, 54 MTBF (mean time between performance measurement
inspections, 142–143 failures), 147 baseline (PMB), 124–127,
Institute of Electrical and 153
Electronics Engineers Negative stakeholders, 14, 24 performance rewards, 162–163
(IEEE), 3 network diagram PERT, see Program Evaluation
insurable risks, 16, 97, 199 definition of, 200 and Review Technique
internal managers, evolution of, 80 PERT charts, 50, see also network
communication needs of, mapping assignments to, 85 diagramming
13 network diagramming, 49–60 PERT/COST, 147
International Project activity list construction in, pessimistic estimates, 70, 71
Management Association 50–52 phase (term), 201
(IPMA), 2 critical path and float in, phase-based WBS, 45, 47–48
IPMA Competence Baseline 58–60 phases of projects, projects vs.,
(ICB®) certification, 2 critical path determination in, 23–24
iterative activity, 3, 42, 199 53–54
planned value (PV), 147–149, Program Evaluation and Review project human resources
201 Technique (PERT), 70–72 management, 14–15, 203
planning activity(-ies), 41–63 CPM vs., 88 project initiation, 23
Gantt chart creation in, 60–62 creation of, 2 definition of, 22, 23, 203
iterative nature of, 42 definition of, 202 elements in, 23
for monitoring and control, as quantitative risk system, process of, 7–9
140 108 project integration management,
network diagramming in, program management, 202 16, 203
49–60 program(s) projectized organizations, 6–7
requirements document in, definition of, 6, 202 project layout, 52–53
43–44 projects grouped into, 6 project leadership, 117
risk management as, 100–101 progressive elaboration project life cycle, 143, 203
statement of work in, 42–43 concept of, 3 project management, 1–19
work breakdown structure in, definition of, 202 borders of, 3
44–49 in planning, 42 definition of, 3, 203
PMB (performance management and project objective, 37 growth of, 2
baseline), 201 and project plan, 80 knowledge areas in, 11–18
PMB (performance project charter, 34–36 organizational environment
measurement baseline), definition of, 202 for, 6–7
124–127, 153 elements of, 35 and organization structure,
PMBOK® Guide, see A Guide to the importance of, 9 6–7
Project Management Body of outline of, 35–36 origins of, 2–3
Knowledge project closeout, 157–167 process groups in, 7–11
PMI (Project Management administrative, 162 Project Management Institute
Institute), 3 celebration and reward in, (PMI), 3
PMO, see Project Management 162–163 Project Management Office
Office checklist for, 159–160 (PMO), 4, 66, 203
PMP® (Project Management for contracts and Project Management
Professional ), 3, 69 procurements, 161–162 Professional (PMP®), 3, 69
Polaris submarine project, 70 definition of, 158, 202 project management software, 73
portfolio, 6, 201 lessons learned reviews in, project management work, in
portfolio management, 201 163–165 WBS, 49
positive stakeholders, 14, 24 process of, 10–11 project managers
Post-it® notes, 114, 164 steps in, 158 knowledge areas for, 11–18
post-test, xv, 217–222 transfer of product in, 161 as project stakeholders, 25
precedence diagramming project communications as stakeholders in other
method (PDM), 50 management, 13, 90, 202 projects, 26
preliminary estimates, 67, 201 project control, 10, see also project monitoring and control,
preliminary project plan, 80 project monitoring and 139–154
pre-test, xv, xvii–xxii control definition of, 10, 203
pricing risk, 97–98 project cost management, 13, 202 earned value management for,
probability, 71, 201 project environment, 96, 145 147–153
probability and impact matrix, project execution, 123–136 planning for, 140
105, 201 change management in, 130, process of, 10
problem solving, 133–135 133 and project plan/baseline
process group, 201 definition of, 202 updating, 153
process maps, 146 and kickoff meeting, 129 project status monitoring in,
process quality, 117, 201 performance measurement 140–143
process quality control, 117 baseline in, 125–127 of quality, 146–147
procrastination, 74 plan approval in, 124–125 and reporting of project
procurement closure, 161–162 problem solving in, 133–135 status, 143–145
procurement management, 15, process of, 10 of risk, 100, 145–146
203 team and resource selection of schedule, 12
procurement planning, 86 in, 127–129 project objective, 37
procurements log, 161 team development in, 129 project plan, 79–93
product quality, 117–119, 202 work management in, 129–132 approval of, 124–125
risk response planning, 111–115, sharing, of risk, 113–114, 206 3M, 114, 164
205 Shewhart, Walter A., 117 three-point estimate, 207
risk responses skill set three-point estimating, 69–73
implementing, 115–116 for project team members, 81, with Monte Carlo simulation,
planning, 111–115 128–129 73
risk(s), 96–100 in responsibility assignment with PERT, 70–72
adjusting for, 69 matrix, 81–83 time
definition of, 16, 96, 204 slack, 53, 88, see also float balancing cost, resources, and,
fundamental formula of, SOW, see statement of work 87–90
97–98 SPC (statistical process control), PERT calculations for, 71
identifying, 101–104 146 time constraint, 29, 66
monitoring and control of, spend plan, 206 time management, 11, 12, 207
145–146 SPI (schedule performance top down approach (WBS), 48
pricing of, 97–98 index), 151, 206 total float, 58
in project environment, 96 sponsor, see project sponsor tracking Gantt chart, 125–127,
reassessment of, 145 SS (start to start), 54, 207 207
types of, 97, see also individual staffing requirements, 80–81 transfer
types stakeholder management, 14, 204 definition of, 207
risk score, 97–98, 107–108 in communications and of product, service, or result,
risk threshold, 99, 205 stakeholder management 158, 161
risk tolerance, 99–100, 206 plan, 90–92, 145 of risk, 112
risk triage, 105, 106, 206 goals of, 90 triggers
rolling wave estimates, 74, 206 issues in, 26–28 for contingency plans, 114,
rough order of magnitude stakeholder register, 26, 27 134
(ROM), 67, 206 stakeholders definition of, 207
RPP (Registered Project common, 24–26 triple constraint, 29–30, 96, 207
Professional), 2 communication needs of, 13 Truman, Harry, 113
and defining projects, 24–28 Tylenol® murders case, 164
Salvage, project, 164, 165 definition of, 14, 206
schedule getting plan approval from, Uncertainty, 66
baseline for, 125–126 124 about uncertainty, 98
loading and leveling the, identifying needs and of the future, 97
85–86 expectations of, 145 US Department of Defense
project plan vs., 9 impact levels of, 24 (DoD), 147
in project time management, standard deviation, 70–71, 207 US Navy, 2
11–12 start to start (SS), 54, 207 US Office of Management and
schedule compression, 206 statement of work (SOW), Budget (OMB), 147
schedule performance index 42–43, 80, 207
(SPI), 151, 206 statistical process control (SPC), Value of early completion, 88,
schedule variance (SV), 150, 206 146 207
scheduling, resource, 204 status meetings, 141, 142 vendors
scheduling relationships, in status monitoring, 140–143 closeout of contracts with,
network diagramming, 54 status reporting, 141, 207 161–162
Scientific Wildly Aimed Guess supervisors, as stakeholders, 25, as stakeholders, 26
(SWAG), 67, 207 26
scope SV (schedule variance), 150, 206 WAG, see Wildly Aimed Guess
project, 12, 203 SWAG (Scientific Wildly Aimed Watergate, 37
quality vs., 116 Guess), 67, 207 WBS, see work breakdown
scope constraint, 29 structure
scope creep, 37, 130, 206 Tangential stakeholders, 14, 24 WBS Dictionary, 130–132, 207
scope management, 12, 206 Taylor, Frederick W., 2 weak constraints, 31, 32, 208
scope statement, 12, 206 team, see project team weighted average, 70
scope verification, 126, 206 threats Wildly Aimed Guess (WAG), 67,
s-curve chart, 127, 128 definition of, 16, 207 69, 207
secondary risk, 115, 206 as negative risk, 16, 97 work, 208
sensitivity analysis, 109–110, 206 risk responses for, 110–112 workarounds, 134, 208