ARE 409 Construction Management and Economics Dr.

Hoshiar Nooraddin
Assignment 1 Grade 15% Assignment Date 5.10.2023

Group assignment. Each group composed of 3 students.


Each group select one of the following questions and present a short report about it.
Organize the report as following

1. First page: Name of the university, course name, professor name, assignment nr.,
assignment title, assignment date, students’ names and students’ nr.

2. Second page is the Chart

3. Third page construction cost

4. The client wants a high-class house

5. Hight of the house is one floor 3-meter-high and 1meter wall at the roof.

6. Construction material concrete, columns 30x30 (although in the drawing is


different dimension), External wall is brick 25 cm internal walls 15 cm width
finishes. Floor and ceiling concrete 20 cm thick

7. Don’t include finishing, pavements, false ceiling, electricity, water and drainage

8. Calculate approximate main structure cost in Saudi Arabia

9. Make a Schedule for main structure of the project using Gantt chart

Choose one of the following plans


Each group choose own plan different than others.
Develop a Schedule for its construction from start to hand over