Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
1
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
SECTION - 1
1a Listing of Quality Audits completed (Internal and Sub-Contractor), in progress and planned for next QA OOK
month.
1b Status of corrective actions for non-conformance reports, audits and management reviews. QA OOK
1c Quality personnel Listing by Discipline as specified in Atta 6 of Schedule “Q”
1d Listing and status of all Engineering Waivers requested. QA OOK
1e Summary of Technical Query.
1f Procurement and construction progress summary report.
2 Procurement Phase Item (As per Schedule “Q” Attachment 3) PQCS &
QA OOK
2a Listing of supplier survey performed and summary of finding QA OOK
2b Listing of pre-inspection meeting conduct and planned for next month. PQCS &
QA OOK
2c Listing of supplier inspections performed and those planned for next month. PQCS &
QA OOK
2d Purchase order status
2e Procurement quality dashboard for the period of Nov 16, 2016 to Dec 15, 2016
3 Construction Phase Items (As per Schedule “Q” Attachment 4).
3a Listing and disposition of all defective or rejected material or equipment received at job site by
contractor
3b Welding rejection rate, reported on per joint basis for piping and alloy welds.
3c Welding rejection rate historical performance chart
4 Narrative Sections of process Improvements activities
4a Attachments
3
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
5
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
SECTION 1a: Listing of Quality Audits Completed (Internal and Subcontractor), in -progress, and planned for next
month
DATE PLANNED
SN DESCRIPTIONS SCHEDULE COMPLETED REMARKS
1 DOC control center Dec 15, 2015 Jan 28, 2016 SEP-MGSE2C-QA-AUD-0001
2 15% Design completion Mar 28, 2016 Mar 27, 2016 SEP-MGSE2C-QA-AUD-0002
3 Project control audit(PCD) Apr 18, 2016 Apr 18, 2016 SEP-MGSE2C-QA-AUD-0003
4 QA & QC Dept audit May 08, 2016 May 09, 2016 SEP-MGSE2C-QA-AUD-0004
7 One time vendor quality assessment Aug 31, 2016 Sep 02, 2016 SEP-MGSE2C-QA-VAR-0001
audit
8 One time vendor quality assessment Nov 13, 2016 Nov 14, 2016 SEP-MGSE2C-QA-VAR-002
audit
Last Month and Planned Audit Schedule and findings and finding status will be provide by QA Manager
Section 1b: Status of corrective actions for Non-conformance reports, audit and
management review
6 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
Section 1b: Status of corrective actions for Non-conformance reports, audit and
7
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
management review
Quality personnel Listing as specified in Atta 6 of Schedule “Q” and Mobilization / demobilization
SN Quality personnel Name Schedule Approved Mobilization date Demobilizat Vacation plan R
“Q” ion date e
Reference m
a
r
k
s
Section 1c.1 Common Quality Personnel
1.0 Corp. QA/QC Manager Shi Jing N.A N.A
Section 1c.2 Procurement / Material & Equipment (Provide by OOK QA and Procurement team)
1.0
1.5 Batch Plant Inspector Mohammad Imran Atta 6 Yes Aug 23, 2016 May2018 Jun 10, 2016 -
1.6 Material Receiving Majid Ali Atta 6 Yes Sep 12, 2016 Feb 2018 May10, 2017
Inspector
9
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
1.7 Documents Controller Abdul Rahman Atta 6 N.A July 29, 2016 Feb 2018 Nov 23, -
2017
1.8 Civil QC Inspector Maqsood Ahmad Atta 6 Yes Nov 08, 2016 Dec 2017 Aug 18.
Khan 2017
1.9 Building QCI Mohammad Rashid Atta 6 Yes Nov 24, 2016 March, Dec 15,
2018 2017
1.10 E&I QCI Numan Raza Atta 6 Yes Nov 28, 2016 May, June 25,
2017 2017
1.11 E&I Material QCI Atta 6 Yes Dec 06, 2016 Aug, Mar 10,
Vergl Javonillo 2017 2017
1.12 Paint Coating QCI Ayub Mustafa Atta 6 Yes Dec 18, 2016 Sep, July 30,
2018 2017
1.13 Equipment QCI Shabeer Ahmed Atta 6 Yes Dec 17, 2016 Sep, Sep 08,
2018 2017
1.14 Documents controller Sibtain Abass Atta 6 Yes Nov 20, 2016 Sep, Nov 25,
2018 2017
1.15 E&I QC Supervisor TB Atta 6 Yes Jan 20, 2017
1.16 Mechanical QC TB Atta 6 Yes Jan 10, 2017
Supervisor
1.17 Welding QC TB Atta 6 Yes Jan 25, 2017
Supervisor
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
13
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
SECTION – 2
Section 2 will be up-date By Procurement and QA Manager
15
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
SECTION – 3
3b Welding rejection rate reported as per joint basis for piping, structural and ally welds.
17
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
Section 3a – Listing & disposition of all defective or rejected material or equipment received at job by
Contractor
S.L Item Description of defective / rejected P.O No. Date Quantity Date Delivered Disposition Remarks
No material equipment received at site
Section 3b – Welding Rejection rate, reported on per joint for Piping, Structural and Ally Welding
18 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
Month:
From Nov 16, 2016 to Dec 15, 2016 Cumulative
S.L Welder’s Name Welder’s % %
No ID No of No of No of Joint Rejected No of No of No of Joint Rejected Remarks
Joints Joints for Rejected Joints Joints for Rejected
Welded RT Welded RT
19
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
Series 1
1
0.9
0.8
0.7
0.6
0.5 Series 1
0.4
0.3
0.2
0.1
0
6 6 6 6 6 6 6 6 6 6 6 6
n-1 b-1 r -1 r -1 y-1 n-1 l-1 g-1 p-1 ct-1 v-1 c-1
Ja Fe a p a u e
M A M Ju J Au Se O No D
SECTION – 4
21
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
Section 4.0: Narrative Section of Process Improvements Activities(As per Schedule “Q” Para 7
Sectio Item Description Remarks
n
4a Attachments
1) QA/QC Organization Chart
2) QA/QC Manpower Mobilization/Demobilization Plan
3) Status of Internal Quality Audits and Schedule OOK QA
Manager
4) Radiography Request Tracking Sheet
5) Non-Conformance Reports Issued by Saudi Aramco or Contractor during Procurement;
Number issued, closed out and pending for this month.
6) Non-Conformance Reports Issued by Saudi Aramco or Contractor during Construction;
Number issued, closed out and pending for this month.
7) Summary of Non-Conformance Reports Issued by Saudi Aramco or Contractor during OOK QA
Procurement and Construction; Number issued, closed out and pending for this month Manager
8) Summary Table of RFIs Issued from Nov 16, 2016 to Dec 15, 2016
9) Summary of QMIS Surveillance from Oct Nov 16, 2016 to Dec 15, 2016
10)Testing Measuring and Inspection Equipment Calibration Status
11)Summary of Test Conducted from Nov 16, 2016 to Dec 15, 2016
Section 4.0: Narrative Section of Process Improvements Activities(As per Schedule “Q” Para 7
SEPCO ARABIA Continually improves the effectiveness of its Quality Management System through the use of the Quality
Policy, Quality Objectives, Audit results, Analysis of data, corrective and preventive actions. All relevant data shall be
reviewed during the Management review to assess Company performance as specified in the Quality Plan and
Objectives, to identify area for improvement including the beneficial effects.
Construction Phase
Prior to start of any activities, Quality requirements are addressed effectively at all times to the concerned and directly
involved authorities and taking greater consideration to define the Pro-active measures. Sufficient quality control coverage
by QA/QC department during the execution of the activity will provide the pro-active actions for any potential
discrepancies.
Procurement Phase
SEPCO approved procurement plan are properly implemented and all SEPCO contract supplied materials adhere to typical
Contract Schedule “Q”. SEPCO shall ensure that all materials will be procured as per approved material requisition.
Packages and all material to be delivered at site will be properly handled with care during loading, unloading, storage and
preservation in accordance with approved material preservation plan.
SEPCO and Saudi Aramco representative will conduct visual inspection prior to transportation as per the SATIP and
SAIC.
23
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
Section 4a : Attachment
SN Attachment Description
1 QA/QC Organization Chart
2 QA/QC Manpower Mobilization/Demobilization Plan
3 Status of Internal Quality Audits and Schedule QA Manager
4 Radiography Request Tracking Sheet
5 Non-Conformance Reports Issued by Saudi Aramco or Contractor during Procurement; Number issued,
closed out and pending for this month. PQCS & QA
6 Non-Conformance Reports Issued by Saudi Aramco or Contractor during Construction; Number issued,
closed out and pending for this month.
7 Summary of Non-Conformance Reports Issued by Saudi Aramco or Contractor during Procurement and
Construction; Number issued, closed out and pending for this month. Procurement summery provide
by PQCS
8 Summary Table of RFIs Issued from Nov 16, 2016 to Dec 15, 2016
9 Summary of QMIS Surveillance from Nov 16, 2016 to Dec 15, 2016
10 Testing Measuring and Inspection Equipment Calibration Status
11 Summary of Test Conducted from Nov 16, 2016 to Dec 15, 2016
ATTACHMENT 1.0
25
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
ATTACHMENT 2.0
Quality personnel Listing as specified in Atta 6 of Schedule “Q” and Mobilization / demobilization
plan for next month
SN Quality personnel Name Schedule Approved Mobilization date Demobiliz Vacation plan Rem
“Q” ation date arks
Reference
Section 1c.1 Common Quality Personnel
1.0 Corp. QA/QC Manager Shi Jing N.A N.A
Section 1c.2 Procurement / Material & Equipment (Provide by OOK QA and Procurement team)
1.0
27
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
1.10 E&I Material QCI Atta 6 Yes Dec 06, 2016 Aug, Mar 10, -
Vergl Javonillo 2017 2017
1.11 Paint Coating QCI Ayub Mustafa Atta 6 Yes Dec 18, 2016 Sep, July 30, -
2018 2017
1.12 Equipment QCI Shabeer Ahmed Atta 6 Yes Dec 17, 2016 Sep, Sep 08, -
2018 2017
1.13 Documents controller Abdul Rahman Atta 6 Yes Nov 20, 2016 Sep, Nov 25, -
2018 2017
1.14 Documents controller Sibtain Abass Atta 6 Yes Nov 24, 2016 Sep, Dec 17, -
2018 2017
1.15 E&I QC Supervisor TB Atta 6 Yes Jan 20, 2017 -
1.16 Mechanical QC TB Atta 6 Yes Jan 10, 2017 -
Supervisor
1.17 Welding QC TB Atta 6 Yes Jan 25, 2017 - -
Supervisor
ATTACHMENT 3
By QA Manager
29
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
ATTACHMENT 4
No Activity
ATTACHMENT 5
Non-Conformance reports issued by Saudi Aramco or contractor during procurement, number issued,
closed out and pending for this month
31
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
ATTACHMENT 6
Non-Conformance reports issued by Saudi Aramco or contractor during construction, number issued,
closed out and pending for this month
33
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
ATTACHMENT 7
Summary of Non-Conformance reports issued by Saudi Aramco or contractor during Procurements and
construction, number issued, closed out and pending for this month
ATTACHMENT 8
Summary Table of RFIs issued from Nov 16, 2016 to Dec 16, 2016
Summary Table of RFIs issued from Nov 16, 2016 to Dec 15, 2016
35
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
Electrical 7 0 0 7 0 100 % 0 0 0%
Welding
Piping
Mechanical
ATTACHMENT 9
Summary of QMIS Surveillance from Nov 16, 2016 to Dec 15, 2016
37
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006
ATTACHMENT 11
Summary of Testing Conducted from Nov 16, 2016 to Dec 15, 2016
39
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003