SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Submitted by: Concurred by:

Project QA/QC Manager Project Manager/Assistant Project Manager

Monthly Quality Management Report (MQMR)


Nov 16, 2016 to Dec 15, 2016
Report N0: SAC-MGSE2C-QC-MRP-0003

1
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Monthly Quality Management Report (MQMR)


FROM November 16, 2016 to December 15, 2016
Report No. SAC-MGSE2C-QC-MRP-0003

SECTION - 1

2 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

SECTIO ITEM DESCRIPTION PAGE No.


N
1 General Items: (As per Schedule “Q”).

1a Listing of Quality Audits completed (Internal and Sub-Contractor), in progress and planned for next QA OOK
month.
1b Status of corrective actions for non-conformance reports, audits and management reviews. QA OOK
1c Quality personnel Listing by Discipline as specified in Atta 6 of Schedule “Q”
1d Listing and status of all Engineering Waivers requested. QA OOK
1e Summary of Technical Query.
1f Procurement and construction progress summary report.
2 Procurement Phase Item (As per Schedule “Q” Attachment 3) PQCS &
QA OOK
2a Listing of supplier survey performed and summary of finding QA OOK
2b Listing of pre-inspection meeting conduct and planned for next month. PQCS &
QA OOK
2c Listing of supplier inspections performed and those planned for next month. PQCS &
QA OOK
2d Purchase order status
2e Procurement quality dashboard for the period of Nov 16, 2016 to Dec 15, 2016
3 Construction Phase Items (As per Schedule “Q” Attachment 4).
3a Listing and disposition of all defective or rejected material or equipment received at job site by
contractor
3b Welding rejection rate, reported on per joint basis for piping and alloy welds.
3c Welding rejection rate historical performance chart
4 Narrative Sections of process Improvements activities
4a Attachments

3
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

1) QA/QC organization chart


2) QA/QC Manpower mobilization/demobilization plan
3) Status of internal quality audits and schedule
4) Radiography request/tracking sheet
5) Non-Conformance reports issued by Saudi Aramco or contractor during PQCS &
QA OOK
procurement, number issued, closed out and pending for this month.
6) Non-Conformance reports issued by Saudi Aramco or contractor during
construction, number issued, closed out and pending for this month
7) Summary of Non-Conformance Reports Issued by Saudi Aramco or Contractor during QA OOK
Procurement and Construction; Number issued, closed out and pending for this month
8) Summary table of RFIs issued from Nov 16, 2016 to Dec 15, 2016.
9) Summary of QMIS Surveillances from Nov 16, 2016 to Dec 15, 2016.
10) Testing measuring and inspection equipment calibration status
11)Summary of testing conducted from Nov 16, 2016 to Dec 15, 2016.

4 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

SECTION 1.0: GENERAL ITEMS (AS PER SCHEDULE “Q” PAR.)


Section. ITEMS DESCRIPTION
1a Listing of Quality Audits completed (Internal and Sub-Contractor), in progress and planned for next month.
1b Status of corrective actions for non-conformance reports, audits and management reviews.
1c Quality personnel Listing by Discipline as specified in Paragraph 5.11 of Schedule “Q”
1d Listing and status of all Engineering Waivers requested.
1e Summary of Technical Query.
1f Procurement and construction progress summary report.

5
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

SECTION 1a: Listing of Quality Audits Completed (Internal and Subcontractor), in -progress, and planned for next
month
DATE PLANNED
SN DESCRIPTIONS SCHEDULE COMPLETED REMARKS
1 DOC control center Dec 15, 2015 Jan 28, 2016 SEP-MGSE2C-QA-AUD-0001

2 15% Design completion Mar 28, 2016 Mar 27, 2016 SEP-MGSE2C-QA-AUD-0002

3 Project control audit(PCD) Apr 18, 2016 Apr 18, 2016 SEP-MGSE2C-QA-AUD-0003

4 QA & QC Dept audit May 08, 2016 May 09, 2016 SEP-MGSE2C-QA-AUD-0004

5 60 % Design Completion July 24, 2016 July 25, 2016 SEP-MGSE2C-QA-AUD-0005

6 15 % Procurement completion July 26, 2016 July 27, 2016 SEP-MGSE2C-QA-AUD-0006

7 One time vendor quality assessment Aug 31, 2016 Sep 02, 2016 SEP-MGSE2C-QA-VAR-0001
audit
8 One time vendor quality assessment Nov 13, 2016 Nov 14, 2016 SEP-MGSE2C-QA-VAR-002
audit

Last Month and Planned Audit Schedule and findings and finding status will be provide by QA Manager

Section 1b: Status of corrective actions for Non-conformance reports, audit and
management review
6 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

SN Description of corrective actions Issued CAR Ref,# CAR Remarks


By and date Open Closed
On On

Management review meeting results and recommendation will be provided by QA Manager

Section 1b: Status of corrective actions for Non-conformance reports, audit and

7
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

management review

Corrective action summary


Number Issued
This month ( from Oct 16, 2016 to Nov 15, 2016 Cumulative (As Jan, 2016)
Total This Month Closed Pending Issued Closed Pending

Data will be provided by QA Manager Team

Quality personnel Listing as specified in Atta 6 of Schedule “Q” and Mobilization / demobilization

8 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

plan for next month

SN Quality personnel Name Schedule Approved Mobilization date Demobilizat Vacation plan R
“Q” ion date e
Reference m
a
r
k
s
Section 1c.1 Common Quality Personnel
1.0 Corp. QA/QC Manager Shi Jing N.A N.A

Section 1c.2 Procurement / Material & Equipment (Provide by OOK QA and Procurement team)
1.0

Section 1c.3 Construction Phase


1.0 QA Project Manager Madhusudan Sen Atta 6 Yes Nov 21, 2015 Sep 2018 Dec 15, -
2016
1.2 Construction QC Anjum Ghaffar Atta 6 Yes Aug 23, 2016 Sep 2018 Aug 10, -
Manager 2017
1.3 Civil QC Supervisor Saqib Ali Atta 6 Yes Apr 30, 2016 Sep 2018 July 20, 017 -
1.4 Civil QC Inspector Naeem Sarwar Atta 6 Yes Apr 30, 2016 Sep 2018 Jan 15, 2017 -

1.5 Batch Plant Inspector Mohammad Imran Atta 6 Yes Aug 23, 2016 May2018 Jun 10, 2016 -

1.6 Material Receiving Majid Ali Atta 6 Yes Sep 12, 2016 Feb 2018 May10, 2017
Inspector

9
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

1.7 Documents Controller Abdul Rahman Atta 6 N.A July 29, 2016 Feb 2018 Nov 23, -
2017
1.8 Civil QC Inspector Maqsood Ahmad Atta 6 Yes Nov 08, 2016 Dec 2017 Aug 18.
Khan 2017
1.9 Building QCI Mohammad Rashid Atta 6 Yes Nov 24, 2016 March, Dec 15,
2018 2017
1.10 E&I QCI Numan Raza Atta 6 Yes Nov 28, 2016 May, June 25,
2017 2017
1.11 E&I Material QCI Atta 6 Yes Dec 06, 2016 Aug, Mar 10,
Vergl Javonillo 2017 2017
1.12 Paint Coating QCI Ayub Mustafa Atta 6 Yes Dec 18, 2016 Sep, July 30,
2018 2017
1.13 Equipment QCI Shabeer Ahmed Atta 6 Yes Dec 17, 2016 Sep, Sep 08,
2018 2017
1.14 Documents controller Sibtain Abass Atta 6 Yes Nov 20, 2016 Sep, Nov 25,
2018 2017
1.15 E&I QC Supervisor TB Atta 6 Yes Jan 20, 2017
1.16 Mechanical QC TB Atta 6 Yes Jan 10, 2017
Supervisor
1.17 Welding QC TB Atta 6 Yes Jan 25, 2017
Supervisor

Section 1c.4 Procurement QA/QC Personnel (for 3rd party)

10 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Section 1c.5 QA/QC Personnel for QMS Audits QA MANAGER

Section: 1d- Listing and status of all Engineering waivers requested


11
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

S.L. No Description of Engineering Waiver Issued By Approved by Remarks

OOK and QA Manager will provide above part

Section: 1e- Summary of Technical Query


12 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Sr. TQ Number Discipline Subject Date Engineering Date Status Remark


No Submitte Response Receive ed
d d
1 MGSE2C-IK- Civil/ Requirement for concrete mix Aug 2, Exposure 2 Aug 7, Closed
TQ-0001 Building design BGCS#1 2016 cement type V 2016
2 MGSE2C-IK- Civil/ Below Lean concrete Elevation Aug 15, Same Aug 15, Closed
TQ-0002 Building 2016 Elevation 2016
3 MGSE2C-IK- Civil/ Site preparation Zone Drawing Aug 17, Accepted Aug 21, Closed
TQ-0003 Building 2016 2016
4 MGSE2C-IK- Civil/ Below foundation Select Fill Material Aug 17, Accepted Aug 21, Closed
TQ-0004 Building Requirements 2016 2016
5 MGSE2C-IK- Civil/ Building and other BOC ELE Sep 28, Elevation was Oct 03, Closed
TQ-0005 Building 2016 provided 2016
6 MGSE2C-IK- Civil/ Rebar and Hook detail Oct 01, Not Required Oct 03, Closed
TQ-0006 Building 2015 Hook 2016
7 MGSE2C-IK- Civil/ The Earthwork of Flare Area and Oct 11, Slope Provided Oct 17, Closed
TQ-0007 Building Slope Area(Zone 5 &6) 2016 2016
8 MGSE2C-IK- Civil/ The reinforcement Details for Oct 16, 600 Space Oct 18, Closed
TQ-0008 Building Compressor FDN Train 1 to Train 6 2016 2016
BGCS#1
9 MGSE2C-IK- Civil/ Query About Cut slope Angle Nov 10, Top level Nov, 13, Closed
TQ-0009 Building 2016 should be 2016
correct
10 MGSE2C-IK- Civil/ Query for cancelling monitoring Nov 12, Proposal Nov 13, Closed
TQ-0010 Building Concrete hydration and Temp 2016 rejected 2016
monitoring
11 MGSE2C-IK- Civil/ Anchor Support and Anchor Guide Nov 13, Accepted Nov 13, Closed
TQ-0011 Building Support Fastened 2016 2016
Section: 1f- Procurement and Construction Progress Summary Report

13
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Phase This month Cumulative


(from Oct 16, 2016 to Nov 15, 2016)
Planned Actual Variance Planned Actual Variance
Procurement 1.54 % 0.96 % 0.58 % 41.04 % 35.81 % -05.23 %

Construction 0.63 % 0.74 % +0.11 % 11.45 % 11.45 % 0.00 %

14 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Monthly Quality Management Report (MQMR)


FROM November 16, 2016 to December 15, 2016
Report No. SAC-MGSE2C-QC-MRP-0003

SECTION – 2
Section 2 will be up-date By Procurement and QA Manager

15
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Monthly Quality Management Report (MQMR)


FROM November 16, 2016 to December 15, 2016
Report No. SAC-MGSE2C-QC-MRP-0003

SECTION – 3

16 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Section 3.0: Construction Phase Items (As per Schedule “Q”

Sectio Item Description


n
3a Listing and disposition of all defective or rejected material or equipment received at job site by contractor

3b Welding rejection rate reported as per joint basis for piping, structural and ally welds.

3c Welding rejection rate historical performance chart

17
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Section 3a – Listing & disposition of all defective or rejected material or equipment received at job by
Contractor

S.L Item Description of defective / rejected P.O No. Date Quantity Date Delivered Disposition Remarks
No material equipment received at site

Not any Defective or rejected material received at site

Section 3b – Welding Rejection rate, reported on per joint for Piping, Structural and Ally Welding
18 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Month:
From Nov 16, 2016 to Dec 15, 2016 Cumulative
S.L Welder’s Name Welder’s % %
No ID No of No of No of Joint Rejected No of No of No of Joint Rejected Remarks
Joints Joints for Rejected Joints Joints for Rejected
Welded RT Welded RT

So for no any Welding Activity at Site

Section 3c – Welding Rejection Rate Historical Performance chart

19
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Series 1
1

0.9

0.8

0.7

0.6

0.5 Series 1

0.4

0.3

0.2

0.1

0
6 6 6 6 6 6 6 6 6 6 6 6
n-1 b-1 r -1 r -1 y-1 n-1 l-1 g-1 p-1 ct-1 v-1 c-1
Ja Fe a p a u e
M A M Ju J Au Se O No D

20 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Monthly Quality Management Report (MQMR)


FROM November 16, 2016 to December 15, 2016
Report No. SAC-MGSE2C-QC-MRP-0003

SECTION – 4

21
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Section 4.0: Narrative Section of Process Improvements Activities(As per Schedule “Q” Para 7
Sectio Item Description Remarks
n
4a Attachments
1) QA/QC Organization Chart
2) QA/QC Manpower Mobilization/Demobilization Plan
3) Status of Internal Quality Audits and Schedule OOK QA
Manager
4) Radiography Request Tracking Sheet
5) Non-Conformance Reports Issued by Saudi Aramco or Contractor during Procurement;
Number issued, closed out and pending for this month.
6) Non-Conformance Reports Issued by Saudi Aramco or Contractor during Construction;
Number issued, closed out and pending for this month.
7) Summary of Non-Conformance Reports Issued by Saudi Aramco or Contractor during OOK QA
Procurement and Construction; Number issued, closed out and pending for this month Manager
8) Summary Table of RFIs Issued from Nov 16, 2016 to Dec 15, 2016
9) Summary of QMIS Surveillance from Oct Nov 16, 2016 to Dec 15, 2016
10)Testing Measuring and Inspection Equipment Calibration Status
11)Summary of Test Conducted from Nov 16, 2016 to Dec 15, 2016

Section 4.0: Narrative Section of Process Improvements Activities(As per Schedule “Q” Para 7

22 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

SEPCO ARABIA Continually improves the effectiveness of its Quality Management System through the use of the Quality
Policy, Quality Objectives, Audit results, Analysis of data, corrective and preventive actions. All relevant data shall be
reviewed during the Management review to assess Company performance as specified in the Quality Plan and
Objectives, to identify area for improvement including the beneficial effects.

Construction Phase
Prior to start of any activities, Quality requirements are addressed effectively at all times to the concerned and directly
involved authorities and taking greater consideration to define the Pro-active measures. Sufficient quality control coverage
by QA/QC department during the execution of the activity will provide the pro-active actions for any potential
discrepancies.

Procurement Phase
SEPCO approved procurement plan are properly implemented and all SEPCO contract supplied materials adhere to typical
Contract Schedule “Q”. SEPCO shall ensure that all materials will be procured as per approved material requisition.
Packages and all material to be delivered at site will be properly handled with care during loading, unloading, storage and
preservation in accordance with approved material preservation plan.

SEPCO and Saudi Aramco representative will conduct visual inspection prior to transportation as per the SATIP and
SAIC.

23
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Section 4a : Attachment

SN Attachment Description
1 QA/QC Organization Chart
2 QA/QC Manpower Mobilization/Demobilization Plan
3 Status of Internal Quality Audits and Schedule QA Manager
4 Radiography Request Tracking Sheet
5 Non-Conformance Reports Issued by Saudi Aramco or Contractor during Procurement; Number issued,
closed out and pending for this month. PQCS & QA
6 Non-Conformance Reports Issued by Saudi Aramco or Contractor during Construction; Number issued,
closed out and pending for this month.
7 Summary of Non-Conformance Reports Issued by Saudi Aramco or Contractor during Procurement and
Construction; Number issued, closed out and pending for this month. Procurement summery provide
by PQCS
8 Summary Table of RFIs Issued from Nov 16, 2016 to Dec 15, 2016
9 Summary of QMIS Surveillance from Nov 16, 2016 to Dec 15, 2016
10 Testing Measuring and Inspection Equipment Calibration Status
11 Summary of Test Conducted from Nov 16, 2016 to Dec 15, 2016

24 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 1.0

` QA/QC Organization Chart

25
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 2.0

QA/QC Manpower Mobilization/Demobilization Plan

Quality personnel Listing as specified in Atta 6 of Schedule “Q” and Mobilization / demobilization
plan for next month

26 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

SN Quality personnel Name Schedule Approved Mobilization date Demobiliz Vacation plan Rem
“Q” ation date arks
Reference
Section 1c.1 Common Quality Personnel
1.0 Corp. QA/QC Manager Shi Jing N.A N.A

Section 1c.2 Procurement / Material & Equipment (Provide by OOK QA and Procurement team)
1.0

Section 1c.3 Construction Phase


1.0 QA Project Manager Madhusudan Sen Atta 6 Yes Nov 21, 2015 Sep Dec 15, -
2018 2016
1.2 Construction QC Anjum Ghaffar Atta 6 Yes Aug 23, 2016 Sep Aug 10, -
Manager 2018 2017
1.3 Civil QC Supervisor Saqib Ali Atta 6 Yes Apr 30, 2016 Sep -July 20, -
2018 2017
1.4 Civil QC Inspector Naeem Sarwar Atta 6 Yes Apr 30, 2016 Sep Jan 15, -
2018 2017
1.5 Batch Plant Inspector Mohammad Imran Atta 6 Yes Aug 23, 2016 May June 10, -
2018 2016
1.6 Material Receiving Majid Ali Atta 6 Yes Sep 12, 2016 Feb May 10, -
Inspector 2018 2017
1.7 Civil QC Inspector Maqsood Ahmad Atta 6 Yes Nov 08, 2016 Dec Aug 18, -
Khan 2017 2017
1.8 Building QCI Mohammad Rashid Atta 6 Yes Nov 24, 2016 March, Dec 15, -
2018 2017
1.9 E&I QCI Numan Raza Atta 6 Yes Nov 28, 2016 May, June 25, -
2017 2017

27
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

1.10 E&I Material QCI Atta 6 Yes Dec 06, 2016 Aug, Mar 10, -
Vergl Javonillo 2017 2017
1.11 Paint Coating QCI Ayub Mustafa Atta 6 Yes Dec 18, 2016 Sep, July 30, -
2018 2017
1.12 Equipment QCI Shabeer Ahmed Atta 6 Yes Dec 17, 2016 Sep, Sep 08, -
2018 2017
1.13 Documents controller Abdul Rahman Atta 6 Yes Nov 20, 2016 Sep, Nov 25, -
2018 2017
1.14 Documents controller Sibtain Abass Atta 6 Yes Nov 24, 2016 Sep, Dec 17, -
2018 2017
1.15 E&I QC Supervisor TB Atta 6 Yes Jan 20, 2017 -
1.16 Mechanical QC TB Atta 6 Yes Jan 10, 2017 -
Supervisor
1.17 Welding QC TB Atta 6 Yes Jan 25, 2017 - -
Supervisor

28 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 3

Status of Internal Quality Audits and Schedule

By QA Manager

29
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 4

Radiography Request/Tracking Sheet

No Activity

30 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 5
Non-Conformance reports issued by Saudi Aramco or contractor during procurement, number issued,
closed out and pending for this month

OOK Procurement TEAM and QA Manager

31
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 6
Non-Conformance reports issued by Saudi Aramco or contractor during construction, number issued,
closed out and pending for this month

Non-Conformance reports issued by Saudi Aramco or contractor during construction,


number issued, closed out and pending for this month
32 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

NCR Summary (Construction)


NCR Issued By This Month(From Oct 16, 2016 To Nov 15, 2016) Cumulative

Total This Month Closed Pending Issued Closed Pending


Saudi Aramco 0 0 0 0 0 0
SEPCO 1 1 0 3 3 0

33
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 7
Summary of Non-Conformance reports issued by Saudi Aramco or contractor during Procurements and
construction, number issued, closed out and pending for this month

Procurement phase NCR/INCR data will be provided by


Procurement PQCS OOK and QA Manager

34 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 8
Summary Table of RFIs issued from Nov 16, 2016 to Dec 16, 2016

Summary Table of RFIs issued from Nov 16, 2016 to Dec 15, 2016

35
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

Closed Accepted Closed


Discipline Issued New On Hold % Rejection
Inspected Not Standard Job Not %
Accepted Inspected violation Ready/Rejected
540 0 0 532 0 98.52 % 1 8 1.48 %
Civil/Structural/
Building
Material Receiving 4 0 0 4 0 100 % 0 0 0%

Electrical 7 0 0 7 0 100 % 0 0 0%

Electrical Material 13 0 0 13 0 100 % 0 0 0%

Welding

Piping

Mechanical

Total 564 0 0 556 0 98.58 % 1 8 1.42 %

36 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 9
Summary of QMIS Surveillance from Nov 16, 2016 to Dec 15, 2016

37
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003
SEPCO Electric Power Construction Corporation

Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 10 Schedule Q Atta 4 Para 7


Testing, Measuring and Inspection Equipment Calibration Status

38 | Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003


SEPCO Electric Power Construction Corporation
Master Gas System Expansion Phase 2 BGCS-1 Contract No.: 6600036038 BI/JO: 10-01810-0006

ATTACHMENT 11
Summary of Testing Conducted from Nov 16, 2016 to Dec 15, 2016

39
Monthly Quality Management Report No: SAC-MGSE2C-QC-MRP- 0003