Professional Documents
Culture Documents
Transmission Board Expansion
Transmission Board Expansion
RNC
OPERATING INSTRUCTIONS
Copyright
Disclaimer
No part of this document may be reproduced in any form without the written
permission of the copyright owner.
The contents of this document are subject to revision without notice due to
continued progress in methodology, design and manufacturing. Ericsson shall
have no liability for any error or damage of any kind resulting from the use
of this document.
Contents
1 Overview 1
1.1 Prerequisites 1
2 Procedure 5
2.1 Preparing the Subrack for Expansion by Replacement of
Dummy Boards 5
2.2 Removing a Dummy Board 6
2.3 Installing an ET Board 7
2.4 Installing Signal Cables 9
2.5 Concluding the Expansion in a Subrack 42
2.6 Verifying the Installation 43
2.7 Creating a Configuration Version 44
2.8 Performing Concluding Routines 44
2.9 Reference Section: Accessing the area behind the ICF 44
2.10 Reference Section: Examples of ICF Connection Plate
Reconfiguration 45
1 Overview
Iub over IP will only run over subracks in which all the GPBs (General
purpose Processor Boards) are hardware release 4/5.
1.1 Prerequisites
This section provides information on the documents, tools and conditions that
apply to the procedure.
1.1.1 Documents
Before starting this procedure, ensure that the following documents have been
read:
• Product Handling
• Element Manager
1.1.2 Tools
Before starting this procedure, ensure that the following tools are available:
• A torque driver that can be set to the torque values 0.3, 0.5, 1.5 and 8 Nm.
• A screwdriver Torx T8 x 50 mm
• A flashlight
1.1.3 Conditions
Before starting this procedure, ensure that the following conditions are met:
0 ET-MC1 Board
0 ET-MFG Board
0 ET-M3 Board
0 ET-M4/22 Board
0 ET-MF4 Board
0 ET-MC41 Board
0 ET-MFX12 Board
0 ET-MFX13 Board
• The new ET-board configuration must not exceed the maximum allowed
subrack power consumption. See Technical Product Description for details
on power consumption.
• The appropriate cable kits and applicable ICF connection plates are
available.
• A Thin Client configured to run the EM with the relevant Java plug-in
version is installed.
2 Procedure
• Installing ET-Boards.
To start the Element Manager use the start method selected during the
installation, see Installing an Element Management Application.
Note: If something goes wrong during HW power on, and if the CV has been
used to rollback the node, then the Reset button can reset the GUI to
the node original setting.
2. For each board to expand with select the correct ET role for the slot in
the Role (SwAllocation) column.
4. Click Apply.
5. Wait until the Configuration Result Window appears and make sure that
the subrack that shall be expanded has the result Subrack Partly
Configured. Click OK.
Caution!
Do Always use an approved ESD wrist strap when working with sensitive
equipment. Damage to components mounted on printed board assemblies
can occur if an ESD wrist strap is not used.
2. Using a Torx T8 screwdriver, release the captive screws and remove the
board according to Figure 2 on page 7.
Note: Always handle boards by the front, edge, or back frame, and do not
touch the circuit pattern or any pins.
1 2 3
C 00 00530
1. Check that the pins in the backplane connector are straight before
proceeding with installation.
3. Press the latches toward each other and push the board into the subrack
until it mates with the guide pins in the backplane.
4. Simultaneously rotate both locking clamps inward towards the board to lock
the board into the subrack (see #2 in Figure 3 on page 8).
5. Thread the Torx screws in manually using a Torx T8 screwdriver until the
threads of the screws have engaged the subrack correctly.
Caution!
To avoid stripping the threads in the subrack, do not use power tools to
tighten the screws.
1 2 3
C 00 00531
6. Wait until the LEDs on the inserted boards emit steady green and yellow
light.
Note: When installing cables it is recommended to route the new cables from
a board - through the cable shelf - down the side of the RNC and fed
to the ICF from the rear. See example in Figure 32 on page 45. It
is also recommended to attach labels to the new cables to simplify
future identification.
In RNCs with a 22 slot ICF, the cabling between the ETB and the ICF is
recommended to be in accordance with Table 2 on page 9 and Table 3 on
page 9.
Table 2 Allocation of ICF slots in Main Cabinet for RNCs with 22 slot ICF
ES-2 Connections from ES-2
ES-1 Connections from ES-1
MS Connections from MS 10/11
ICF- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
slot
Table 3 Allocation of ICF slots in Extension Cabinet for RNCs with 22 slot ICF
ES-5 S
p
Connections from ES-5 a
r
e
ES-4 Connections from ES-4
Table 3 Allocation of ICF slots in Extension Cabinet for RNCs with 22 slot ICF
ES-3 Connections from
ES-3
ICF- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
slot
C
B
A
C 00 0552D
B
A
C 0001345A
3. Feed the cable down the rear of the ICF, and out through the ICF gap.
– Press the locking catch towards the socket, push the socket directly into
place from the back face of the connection plate, until the locking catch
clicks into place.
C 00 00951A
7. Using the torque driver with a Torx T20 bit, tighten the two screws to a
torque of 1.5 Nm.
8. If the ICF was removed, install it as described in Section 2.9.2 on page 45.
10. If applicable, align and replace the front plate of the cable shelf. Ensure
that no cables are pinched.
2. If necessary assemble the ICF connection plate with the cables according
to Figure 7 on page 13 using a torque wrench set to 2 Nm.
D
C
C 00 01070A
D
2
C
B
A 1
B
A
C 00 01069D
4. Feed the cable down the rear of the ICF, and out through the ICF gap.
5. Position the ET-M3 Board connection plate on the ICF according to Figure
9 on page 15.
C 00 01090A
7. Using the torque driver with Torx T20 bit, tighten the two screws to a torque
of 1.5 Nm.
9. If the ICF was removed, install it as described in Section 2.9.2 on page 45.
10. If applicable, align and replace the front plate of the cable shelf. Ensure
that no cables are pinched.
• Clean the connectors before fitting them together. Only use approved
cleaning systems, cleaning agents, and lint free wipe for all optical
connectors.
• Fit the cable hood (A in Figure 10 on page 16) over the connectors.
• Fit the two cable hood screws and tighten them to a torque of 0.3 Nm
using the torque driver and Torx T8 bit.
B C
A
D
E
D
E
C 00 01195A
3. Feed the cable down the rear of the ICF, and out through the ICF gap.
C 00 01093A
6. Using the torque driver and Torx T20 bit, tighten the two screws to a torque
of 1.5 Nm.
8. If the ICF was removed, install it as described in Section 2.9.2 on page 45.
9. If applicable, align and replace the front plate of the cable shelf. Ensure
that no cables are pinched.
If expanding from an ET-M4/22, the old cable might be reused, requiring only
one extra cable. The ICF connection plate still needs to be replaced.
– Clean the connectors before fitting them into the appropriate socket. Only
use approved cleaning systems, cleaning agents, and lint free wipes for
all optical connectors.
– Fit the cable hood (for example, A in Figure 12 on page 19) over the
connectors.
– Fit the two cable hood screws and tighten them to a torque of 0.3 Nm
using the torque driver and Torx T8 bit.
- Do not clean the transceiver ports. Keep the transceiver ports clean by
making sure that contamination never gets into the transceiver ports.
B C G H
A F
L M
K
D E I J
N O
Q R
P
S T
M L
N O
R Q
S T
C B
D E
H G
I J
C0001299A
3. Feed the cable down the rear of the ICF, and out through the ICF gap.
C0001301A
6. Using the torque driver and Torx T20 bit, tighten the two screws to a torque
of 1.5 Nm.
8. If the ICF was removed, install it as described in Section 2.9.2 on page 45.
9. If applicable, align and replace the front plate of the cable shelf. Ensure
that no cables are pinched.
To install the ET-MC41 Board-to-ICF Signal Cables, perform the following steps:
– Clean the connectors before fitting them into the appropriate socket. Only
use approved cleaning systems, cleaning agents, and lint free wipes for
all optical connectors.
– Push each connector (B and C in Figure 14 on page 22) of the pair into
the socket according to Figure 14 on page 22.
Note: For the ET-MC41/1 board, SC connectors are used. The orientation
of B and C in Figure 14 on page 22 will be switched.
– Fit the cable hood (A in Figure 14 on page 22) over the connectors.
– Fit the two cable hood screws and tighten them to a torque of 0.3 Nm
using the torque driver and Torx T8 bit.
- Do not clean the transceiver ports. Keep the transceiver ports clean by
making sure that contamination never gets into the transceiver ports.
A C
C 00 01197B
3. Feed the cable down the rear of the ICF, and out through the ICF gap.
C 00 01093A
6. Using the torque driver and Torx T20 bit, tighten the two screws to a torque
of 1.5 Nm.
8. If the ICF was removed, install it as described in Section 2.9.2 on page 45.
9. If applicable, align and replace the front plate of the cable shelf. Ensure
that no cables are pinched.
C 00 01065A
5. Align and replace the front plate of the cable shelf, if applicable. Ensure
that no cables are pinched.
Note: Configuration rules for ET-MFX state that any cabinet with ET-MFX's
has at least one subrack with two or more ET-MFX12.
2.4.7.1 Overview
• Instructions for the first subrack where ET-MFX are to be installed, see
Section 2.4.7.3 on page 26.
• For ICF connector plates for ET-MFX, seeSection 2.4.7.7 on page 39.
3. Feed the cable down the rear of the ICF, and out through the ICF gap.
2.4.7.2 Definitions
If the RNC does not have any ET-MFX installed before the expansion procedure
is started - it is required that the first subrack that is expanded - is expanded
with a minimum of two ET-MFX12 boards. These two boards will be referred
to as the Main Interconnection Boards. They will offer redundant transmission
paths out of the RNC. When transmission is further expanded, each board that
is added needs a path to the Main Interconnection Boards, either directly to the
Main Interconnection Boards or switched through other ET-MFX boards.
A typical configuration where the first two ET-MFX12 boards are installed in a
Main Subrack is presented in Figure 17 on page 27.
F
O
I
A
C
E
F
F
E O
I
A
D C
E
F
G
C
F
A
D E
E C D
C0001388A
Figure 17 Expansion with the first two ET-MFX12 boards in a Main Subrack
Expansion with ET-MFX type boards can be done in many ways and will vary
depending on the configuration before the expansion. The expansions shown
below should be treated as examples illustrating the principles for expansion.
When the Main Interconnection Boards are installed the principles for expansion
are quite straightforward. Each board that is added should have a connection
to the Main Interconnection Boards. For full link redundancy, two paths to the
Main Interconnection Boards should exist from the ET-MFX board. The figures
below show the sequence of installing the first, second and third expansion
board within a cabinet. Figure 18 on page 29 to Figure 20 on page 31, show the
expansion of ET-MFX12 boards. Figure 21 on page 33 to Figure 25 on page
37, shows the installation of ET-MFX13 boards in a subrack that already has
one or two ET-MFX12 boards installed.
Note: For full link redundancy it is necessary to have one link to each
of the left-hand or right-hand board in the subrack containing the
Main External Interconnections.
F
O
I
A
C
E
F
F
O
I
A
C
B
E
F
D
F
O
I
C
A
C
E
F
B G
A F
F
O
I
A
C
E
F
F
E O
I
A
D C
E
F
G
C
F
A
C0001391A
When the second board is added in a subrack, two cables need to be installed
or moved:
• If only one Inter Subrack Cable (A in Figure 19 on page 30) was previously
installed, one additional Inter Subrack Cable should be installed connecting
the added board to the Main Interconnection Boards. The cable should be
connected to the first free connector on the outermost board in the subrack
containing the Main External Interconnections. To connect the Inter
Subrack Cable it may be necessary to move one board-to-ICF connection
from the Main Interconnection Boards to the board that is added.
• One subrack internal cable should be installed between the two boards
within the subrack. This cable is illustrated as B in Figure 19 on page 30.
F
O
I
A
C
E
F
F
B
O
I
B A A
C
E
F
A A
F
O
I
A
C
E
F
C0001392A
When the third ET-MFX12 board is installed in a subrack, the only addition that
is necessary is a new subrack internal cable. Move one of the already existing
subrack internal cables and install one new cable. Use the first available
connectors on adjacent ET-MFX12 boards. A subrack with three ET-MFX12
boards installed is shown in Figure 20 on page 31. Additional interconnections
may be installed (see B in Figure 18 on page 29). Further expansions with
ET-MFX12 are made according to the same principles; move one old link and
add one new link between the existing boards and the newly installed board.
F
O F
I O
I
A
C
E A
F C
E
G F
F
F
E
E
D F
D O
I
C
A
C C
E
F
B
G
B
A
A
F
O
I
A
C
E
F
C0001393A
When the first ET-MFX13 board is installed in a subrack where one ET-MFX12
is already installed the following cables need to be moved or installed:
• If only one Inter Subrack Cable (B in Figure 19 on page 30) was previously
installed, one additional should be installed connecting the added board
to the Main Interconnection Boards. The cable should be connected to
the first free connector on the outermost board in the subrack containing
the Main External Interconnections. To connect the Inter Subrack Cable
it may be necessary to move one board-to-ICF connection from the Main
Interconnection Boards .
• A subrack internal cable should be installed between the two boards within
the subrack. In the example shown in Figure 21 on page 33, the subrack
internal cable needs to be an optical fibre. The fibre needs to be connected
to SFP modules installed in the boards. For installation of SFP modules
see Section 2.4.7.5 on page 37.
F
O
I
A
C
E
F
F
B
O
I
A A
C
E
F
F
O
I
A
C
E
F
C0001395A
• The subrack internal fibre should be moved so that it connects the two
ET-MFX13 boards according to A in Figure 22 on page 34.
• A new electrical subrack internal cable should be installed between the new
ET-MFX13 board and the ET-MFX12 board, see B in Figure 22 on page 34.
F
O F
I O
I
A
C
E A
F C
E
G F
D
D F
O
C I
B
C
A
C
E
F
B
B
G
A
A
A D
F
O
I
A
C
E
F
C0001396A
• One end of the electrical subrack internal cable should be moved so that it
connects the ET-MFX12 board with the added ET-MFX13 board according
to A in Figure 23 on page 35.
• A new optical subrack internal fibre should be installed between the new
ET-MFX13 board and the ET-MFX13 board that previously was connected
with the electrical cable, see B in Figure 23 on page 35.
F
O F
I O
I
A
C
E A
F C
E
G F
D F
D O F
I O
C I
A
A
C C
E
A
F C
E
B
G F
B
G
A
A
F
F
E
E
B D
C
D
B
B
A
A
F
O
I
A
C
E
F
C0001397A
The first ET-MFX13 board being installed in a subrack where two ET-MFX12
boards are previously installed is shown in Figure 24 on page 36. The following
cables need to be moved or installed:
• A subrack internal fibre should be installed between the added board and
one of the already existing boards. See A in the example shown in Figure
24 on page 36. The fibre needs to be connected to SFP modules installed in
the boards. For installation of SFP modules see Section 2.4.7.5 on page 37.
• The existing subrack internal cable between the ET-MFX12 boards needs
to be moved to the added board. See B in Figure 24 on page 36.
F
O F
I O
I
A
C
E A
F C
E
G F
D
D F
O
C I
B
C
A
C
E
F
B
B
G
A
A
A E
F
O
I
A
C
E
F
C0001398A
The second ET-MFX13 board being installed in a subrack where two ET-MFX12
boards are previously installed is shown in Figure 25 on page 37. The following
cables need to be moved or installed:
• One end of the previously installed subrack internal fibre should be moved
from the ET-MFX12 board to the added board. See A in the example
shown in Figure 25 on page 37.
F
O F
I O
I
A
C
E A
F C
E
G F
D F
D O F
I O
C I
B
A
C C
E
A
F C
E
B
G F
B
G
A
A
F
A D
C
E
C
B
B
A
F
O
I
A
C
E
F
C0001399A
F
O
I
A
C
E
F
C0001389A
Note: Multi-mode optical fibre cables can only be connected directly to the
SFP module. Multi-mode cables for connection to the ICF are not
provided by the RNC.
If a fibre is connected directly to an SFP, the fibre should still be routed along
the cable shelf to the side of the cabinet to prevent the fibre from obstructing
access to other boards. See the installation of optical cables in an SFP module
in Figure 27 on page 39.
F
O
I
A
C
E
F
C0001390A
– Remove the protective dust caps and clean the connectors before fitting
them together. Only use approved cleaning systems, cleaning agents, and
lint free wipes for all optical connectors.
– Note which of the fibres are connected to TX and RX on the SFP module.
The fibres can be separated by the white ring on one of the fibres.
3. Using the torque driver and Torx T20 bit, tighten the two screws to a torque
of 1.5 Nm.
5. If the ICF was removed, install it as described in Section 2.9.2 on page 45.
6. If applicable, align and replace the front plate of the cable shelf. Ensure
that no cables are pinched.
C 00 00951A
C0001386A
C0001387A
LEDs on the added ET-board should have a steady green and steady yellow
light. If the LEDs do not light steady green and yellow check that the correct
slot has been used and that the right board type has been chosen.
Note: If something goes wrong during HW power on, and if the CV has been
used to rollback the node, then the Reset button can reset the GUI to
the node original setting.
The Expand RNC Tool dialog box opens, see Figure 31 on page 43.
2. Make sure that the same selection as in is Section 2.1.2 on page 5 still used.
4. Click Apply.
5. Wait until the Configuration Result Window appears and make sure that
the subrack that shall be expanded has the result Subrack Completely
Configured. Click OK.
To verify that the installed hardware is operational, perform the following steps:
Note: Software loading time for boards can vary. Wait for downloading to
complete before confirming LED status.
1. In the RNC EM, ensure that the administrative state of the boards is
Unlocked.
4. In the EM Equipment view, check that the operational state of the boards
is Enabled.
2. Disconnect the ESD wrist strap from the RNC grounding point.
7. Follow the procedures for the return and disposal of replacement parts, see
Product Handling for more information.
1. Using the Torx T30 screwdriver, remove the four retaining screws. Place
the screws in a secure location for later use.
2. Carefully lift the ICF from the cabinet according to Figure 32 on page 45.
C0000983B
2. Using the Torx T30 screwdriver, fasten and tighten the two retaining screws
at each side of the ICF to a torque of 8 Nm.
1 2 3 4
C0001336B
For new nodes the rules presented on Page46 are used. If possible it is
recommended to use the same rules at transmission expansion. The ICF is
divided into sections according to Table 1 on page 9, Table 2 on page 9 and
Table 3 on page 9. When referring to the right or left side in the rules, reference
is to the left or right side of the section associated with the subrack that is
being expanded.
Based on the available connection plates and the rules presented above - two
examples are shown. The first example show a major reconfiguration where
the following changes are made:
• In MS - four ET-M4 boards are expanded to two ET-MF4 boards using the
Transmission Board Change instruction.
• In MS - two ET-M4 boards are changed to two ET-MFG boards using the
Transmission Board Changeinstruction.
• In ES-1 - four ET-M4 boards are expanded to two ET-MF4 boards using
the Transmission Board Change instruction.
• In ES-2 - four ET-M4 boards are expanded to two ET-MF4 boards using
the Transmission Board Change instruction.
Original configuration 1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
New configuration 1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
C0001337B
• ES-1 is expanded with two ET-MF4 boards using this instruction starting
at Section 2.1 on page 5. Original configuration of two ET-MC41 boards
are kept
• ES-2 is expanded with two ET-MF4 boards using this instruction starting at
Section 2.1 on page 5. Original configuration of two ET-MC1 boards and
two ET-M4 boards is kept.
Original configuration 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
New configuration 2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
C0001338B