PT Mintec Abadi

Project : EPCC of 1500 TPD Physical Refinery & 1200 TPD Dry Fractionation Plant
Client : PT TRIPATRA
Location : Kariangau, Balikpapan
Job No. : -
Rev : Rev A

APPENDIX C
SCHEDULE OF PRICE
WORK ITEM: SOIL INVESTIGATION, TOPOGRAPHICAL SURVEY

NO. ITEM Qty


Bor dan SPT
1 Deep Boring (Incl. setup & moving of Drilling rig) 2 Hole
2 SPT every 1.5 m depth 53 ea
3 Undisturbed Soil Sampling 8 ea
4 Soil Resistivity 2 ea
Laboratory
5 Specific Gravity 8 ea
6 Permeability Test 2 ea
7 Consolidation Test 8 ea
8 UU Triaxial Compression Test 6 ea
9 CU Triaxial Compression Test 3 ea
10 unconfine Compression Test (soil) 8 ea
GRAND TOTAL