Professional Documents
Culture Documents
Condition Assessment
Condition Assessment
Condition Assessment of Concrete Bar-Wrapped Cylinder Pipe, the Next Phase of San
Diego County Water Authority’s Asset Management Program
Martin R. Coghill, C.Eng1; Nathan D. Faber, P.E.2; Andi Corrao, P.E.3; and Chris Garrett4
1
San Diego County Water Authority, 610 West 5th Ave., Escondido, CA 92025. E-mail:
mcoghill@sdcwa.org
2
San Diego County Water Authority, 610 West 5th Ave., Escondido, CA 92025. E-mail:
nfaber@sdcwa.org
3
infrastructureMD, Inc. E-mail: ACorrao@infrastructureMD.com
Downloaded from ascelibrary.org by Tufts University on 07/16/18. Copyright ASCE. For personal use only; all rights reserved.
4
Pipeline Inspection and Condition Analysis Corporation (PICA). E-mail:
cgarrett@picacorp.com
ABSTRACT
The San Diego County Water Authority’s asset management activities commenced over 25
years ago and initially focused on the highest risk pipelines consisting of prestressed concrete
cylinder pipe (PCCP). With active acoustic monitoring and rehabilitation of the PCCP ongoing,
and scanning of the oldest portions of welded steel pipe complete, the next focus was concrete
bar-wrapped cylinder pipe. This paper will discuss a 5-mile comprehensive condition assessment
of concrete bar-wrapped cylinder pipe constructed in 1948, including the basis for the selection
of the technology used, the results of the assessment, and the actions taken by the San Diego
County Water Authority to verify the findings.
INTRODUCTION
The San Diego County Water Authority (Water Authority) provides a safe and reliable water
supply to the San Diego region through its aqueduct delivery system, which consists of
approximately 310 miles of large-diameter pipelines, more than 1,400 aqueduct-related
structures, and over 100 flow control facilities. These facilities occupy approximately 1,400
acres within the Water Authority's right-of-way and deliver water for over 3.3 million residents
via the Water Authority’s 24-member agencies.
With a significant proportion of its infrastructure approaching the end of its useful life, the
Water Authority embarked on an effort to strategically manage its assets over the long-term
through asset management activities that began over 25 years ago, now consolidated into an
Asset Management Program (Coghill et al 2014). Through this program, the following pipe types
were prioritized:
Prestressed Concrete Cylinder Pipe (PCCP)
o 82 miles total
o Wire breaks electromagnetically assessed
o Active acoustic fiber optic monitoring since 2006
o Over 50% rehabilitated with steel liners (Stine and Stift 1998)
Welded Steel Pipe (WSP)
o 140 miles total
o 40 miles assessed using magnetic flux leakage 2011–2016 (Faber et al 2013; Coghill
et al, 2015)
o 4 localized repairs performed
o Future localized repairs planned
© ASCE
Pipelines 2018
Pipelines 2018 164
Downloaded from ascelibrary.org by Tufts University on 07/16/18. Copyright ASCE. For personal use only; all rights reserved.
Figure 1. San Diego County Water Authority Aqueducts with LMSE highlighted
The next pipe type the Water Authority had planned to examine per a 5-year rolling
Condition Assessment Plan was concrete bar-wrapped cylinder pipe (BWP). Of the total 28
miles of BWP pipe, five miles were identified as a priority – the La Mesa Sweetwater Extension
(LMSE) pipeline.
© ASCE
Pipelines 2018
Pipelines 2018 165
Downloaded from ascelibrary.org by Tufts University on 07/16/18. Copyright ASCE. For personal use only; all rights reserved.
MODES OF FAILURE
Previous internal visual inspections of the pipeline found minor mortar lining damage, but
there had been no indications of corrosion or defects in the steel cylinder or reinforcing bars.
Since the Water Authority had not experienced any failures of this pipe and it was thought to be
in good condition from the visual inspections, the expected mode of failure was not proven. This
presented a challenge when selecting the appropriate technology to perform the condition
assessment.
A Request for Proposals (RFP) was advertised in March of 2016 seeking a comprehensive
non-destructive condition assessment of the entire length and circumference of the pipeline. No
specific technology or method was prescribed in the RFP. Two proposals were received
containing differing strategies to assessing the condition of the pipe. The first proposal utilized a
robotic unit with an electromagnetic array capable of detecting the following:
Broken (discontinuous) bars – minimum of 5
Cylinder corrosion greater than 50% metal loss, minimum dimensions 5-inches by 10-
inches (for 39-inch pipe)
The second proposal, submitted by PICA Corporation, utilized an inflatable electromagnetic
tool capable of detecting the following:
Cylinder corrosion greater than 30% metal loss, minimum dimensions 1.5-inches by 1.5
inches (for 39-inch pipe)
© ASCE
Pipelines 2018
Pipelines 2018 166
per the proposals received in 2016 and that developments to the technologies may have changed
the resolutions since.
TOOL DEVELOPMENT
Six months before the field inspection, PICA began modifications and developments for an
inspection tool for the project. There were two important elements to the development:
1) The technology, and the science to collect accurate data on the type of pipe being
inspected
2) The tool or platform that is used to carry and transmit the technology through the pipe.
PICA utilized remote field technology, with some variations. This technology has been
successfully applied to the inspection of a wide variety of ferrous materials, including industrial
and municipal pipelines. However, prior to this project, it had not been specifically applied to the
inspection of BWP. PICA considered the five most critical factors affecting the tool development
for the LMSE pipeline to be:
© ASCE
Pipelines 2018
Pipelines 2018 167
In-line Obstructions: While the pipeline would be dewatered, the Water Authority’s
previous experience suggested that up to 10 inches of standing water may still be present,
as well as up to 2 inches of mud, muck, and debris. The inspection tool would need to be
able to traverse these conditions.
Pipe Deflections: Over the five miles of pipe, many both horizontal and vertical bends
were present. The inspection tool would need to be able to traverse bends up to 60-
degrees.
Pipeline Access: With access to the Water Authority’s pipeline limited to 20-inch
manways, tool components would need to be collapsible, and individual components
Downloaded from ascelibrary.org by Tufts University on 07/16/18. Copyright ASCE. For personal use only; all rights reserved.
With these design requirements in mind, the PICA Research and Development team opted
for an inspection tool comprised of both rigid and inflatable components, all mounted on a
wheeled system to ensure smooth travel through the pipeline. Additionally, the tool would
incorporate shared components that could be modified in the field to accommodate changes in
pipe diameters from 39-inch to 48-inch. Table 1 summarizes the challenges considered and the
solutions developed by PICA during tool development.
The culmination of the design and fabrication work resulted in a tool named the Restricted
Access Flexible Tool, or ‘RAFT’ as shown in Figure 3.
CALIBRATION
Proper calibration of the RAFT was required. The calibration served two purposes: building
confidence for the Water Authority that the technology would perform; and saving field work
time by determining the acceptable inspection frequencies beforehand. In the months preceding
the fieldwork, PICA procured calibration pipe and had it delivered to their storage yard. Defects
of predetermined sizes were milled into the calibration pipe (See Figure 4). The defects would
© ASCE
Pipelines 2018
Pipelines 2018 168
test two aspects; accuracy in sizing defect depth, and accuracy in sizing defect size. The
calibration pipe was also used for testing the tool and electronic component assembly.
Downloaded from ascelibrary.org by Tufts University on 07/16/18. Copyright ASCE. For personal use only; all rights reserved.
Figure 3. RAFT tool being checked in the field prior to its first inspection
INSPECTION
On January 6, 2017, the WA initiated the shutdown of the LMSE pipeline and PICA field
crews mobilized. Dewatering and lock-out/tag-out of the pipeline took 48 hours. During that
time, PICA unpacked equipment and coordinated inspection activities with Water Authority
support staff.
© ASCE
Pipelines 2018
Pipelines 2018 169
Downloaded from ascelibrary.org by Tufts University on 07/16/18. Copyright ASCE. For personal use only; all rights reserved.
© ASCE
Pipelines 2018
Pipelines 2018 170
anomalies and, if necessary, rehabilitate the pipeline during the scheduled shutdown. The process
for validating defects consisted of the following steps:
1. Properly locate the pipe segment and mark up a 3-foot by 3-foot grid
2. Chip away the cement mortar lining
3. Visually assess the internal cylinder
4. Perform ultrasonic thickness testing of the area
Ultrasonic testing was performed by Water Authority staff using a UT flaw detector, which
was a recent purchase that has proven valuable in verifying defects.
The review of preliminary data of one pipe section (Mk #623) indicated clear signs of the
Downloaded from ascelibrary.org by Tufts University on 07/16/18. Copyright ASCE. For personal use only; all rights reserved.
existence of defects. Internal visual inspection revealed no signs of distress, however the
verification procedure confirmed the findings presented by PICA. In one location, the removal of
the cement mortar lining revealed a leaking ‘pinhole’ defect. The Water Authority decided to
excavate the pipe and externally examine Mk #623 and verify the level of corrosion. Figure 6
shows images of two of the three defects found on Mk #623. The first shows the ‘pinhole’
corrosion in the steel cylinder (hole enlarged due to chipping out the corrosion bi-product). The
second image shows a similar active corrosion cell that has disintegrated the reinforcement bars
and has attacked the steel cylinder. Three reinforcing bars were affected by the corrosion cell,
with only 1 bar being discontinuous. The Water Authority believes this evidence supports the
decision to examine the condition of the steel cylinder with the higher-resolution technology.
CONCLUSION
The Water Authority completed a successful non-destructive, high-resolution scan of the
LMSE which is a concrete bar-wrapped cylinder pipeline. The Water Authority used an
electromagnetic inspection technology designed and implemented by PICA Corp. Preliminary
inspection results were reported on-site within 48 hours, providing actionable data. These data
allowed the Water Authority to verify defects and perform a pipe section replacement within a
compressed pipeline shutdown timeline. The Water Authority believes the successful location of
© ASCE
Pipelines 2018
Pipelines 2018 171
three verified corrosion defects (one pinhole leak) justified the decision to use a higher-
resolution technology focused on the cylinder. More importantly, the location of the defects
justified the entire project and prevented a potential pipeline failure. Overall, this proactive repair
helped the Water Authority meet its mission to deliver a safe and reliable supply of water to its
member agencies serving the San Diego region.
REFERENCES
Coghill, Martin R., Eaton, Gary A., Faber, Nathan D., (2014) “A Long Term Commitment to
Pipeline Infrastructure: Implementing, Funding and Delivering the San Diego County Water
Downloaded from ascelibrary.org by Tufts University on 07/16/18. Copyright ASCE. For personal use only; all rights reserved.
© ASCE
Pipelines 2018