Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

MANILA WATER COMPANY INC.

DESIGN AND BUILD OF THE KAYSAKAT

RAW WATER TRANSMISSION LINE - TUNNEL


WORKS

TRAINING PLAN

Page 1 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

Table Contents

1. INTRODUCTION..............................................................................................................4
2. TRAINING NEEDS ASSESSMENT.................................................................................4
3. TRAINING DEVELOPMENT............................................................................................5
3.1 MAIN EQUIPMENT TRAINING..................................................................................................... 5
3.2 PROCESS SYSTEM TRAINING.................................................................................................... 7
3.2.1 System Training........................................................................................................... 7
3.2.2 Electrical, Instrumentation, Control, and Automation System................................8
4. TRAINING FOR OPERATION AND MAINTENANCE...................................................10
4.1 THEORETICAL TRAINING COURSES.........................................................................................10
4.1.1 Introduction and Basics............................................................................................10
4.2 ON‐THE‐JOB TRAINING.......................................................................................................... 10
5. TRAINING EVALUATION..............................................................................................11
6. TRAINING IMPLEMENTATION.....................................................................................11
7. END‐OF‐COURSE ASSESSMENT................................................................................11
7.1 ANNEXES:............................................................................................................................. 12

Page 2 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

Page 3 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

1. INTRODUCTION
The main targeted groups for training programs of the Kaysakat Raw Water Transmission Line –
Tunnel Works will include the Employer’s management team and technical staff.

This Engineer Training Program will include construction, installation, testing, and commissioning
engineers as well as maintenance engineers and/or operators and electricians in all major works under
the scope of the Contractor.

Controllers and operators will take this opportunity to grab professional skills such as controlling and
operating the water conveyance system, to make it more reliable and efficient.

The Operation & Maintenance Manager will collaborate with the Contractor’s Representative, in
accordance with the employer’s requirement of trainees, to develop training content and design the
structure of training programs, method of training, and evaluation or assessment.

The Operation & Maintenance Manager will prepare the program by adopting following steps:

 Demand Assessment
 Training Design
 Training Development
 Trainees Classification
 Training Implementation
 End of Course Evaluation

2. TRAINING NEEDS ASSESSMENT


The purpose of assessment is to identify the level of knowledge, skills, and abilities required by the
Employer to meet the performance requirements of maintenance and operation in the future.

For every individual, in the Training Needs Assessment, the gap of knowledge and the lack of
operational capabilities will be identified, considering different levels of responsibility and capability,
the training sessions will be scientifically organized for the professionals or technicians are the
example of the following field:

 Electric Butterfly Valve


 Air Valve
 Manual Gate Valve
 Manual Ball Valve
 Ultrasonic Flow meter device

Page 4 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

 Other usages such as computer, automatic control system, etc.

3. TRAINING DEVELOPMENT
The Contractor’s Operation & Maintenance Manager will be responsible for assigning the content,
designing appropriate activities, and research evaluation process, Contractor will discuss and receive
constructive suggestions from the Engineer who gather data, analyze information, and report to the
Employer for final approval.

The trainer from the contractor shall prepare the necessary curriculum, including principal theory,
safety, operation, manual of the equipment, and operation system, and submit it for approval by the
engineer.

3.1 Main Equipment Training

When the equipment arrives at the site, the contractor and the technical personnel of the equipment
manufacturer will conduct technical and on-site training on the system for the trainees.

During the installation and commissioning process, the contractor and the equipment manufacturer
will conduct training on installation, commissioning, testing, and the principle of system structure
composition.

 Ultrasonic Flowmeter

Ultrasonic Flowmeter is a type of flowmeter that determines the flow velocity of fluid using
ultrasonic soundwaves.

 Submersible liquid level meter/sensor/transmitter

Submersible level transmitter monitors the continuous liquid level in e.g., wells, reservoirs,
tanks, boreholes (wells), rivers, and others. The submersible transmitter senses the hydrostatic
pressure at the bottom of the liquid.

 PLC Control Panel

Programmable Logic Controllers (PLCs) are widely used in various industries to control and
automate processes, machines, and systems. PLCs rely on sensors and actuators to monitor
and manipulate physical variables, such as temperature, pressure, flow, speed, position, and
force.

Page 5 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

 UPS (Uninterruptible Power Supply)

This configuration will safeguard the PLC from shutting down when there is a power failure.

 Air Valve

Air release valve is typically used in water or irrigation schemes to ensure that any entrained
air in the water system is automatically released in order to maximize the system’s
performance. Entrained air pockets in pipes can cause excessive head loss and flow
reductions if the air is not effectively released.

 Electric Butterfly Valve

A butterfly valve is a valve that isolates or regulates the flows of a fluid. The closing mechanism
is a disk that rotates. Butterfly valves are high pressure recovery valves (also called high
capacity and high area ratio valves) with relatively small overall pressure drop in the fully
open position.

Figure 3.1.1 Electric Butterfly Valve

3.2 Process System Training

3.2.1 System Training

The main contents of the control system training include system operation and inspection etc., Aiming
to enable them to carry out daily maintenance of the equipment and to repair general faults. The

Page 6 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

contractor shall provide the trainers with special tools, commands, drawings, and maintenance
manuals required for maintenance.

Trainee Training Content Method Location

Process and Principal Training PPT

Detailed introduction of the process


equipment Jobsite training and
The role in the system and the PPT
operation and maintenance methods

Electrical control system training:


introduction of the system control
Operator, equ Jobsite training and Office
principle, the equipment targeted by
ipment mana PPT
each operation process, and its and/or
gement team significance in the system control
job site
Daily maintenance training Jobsite training

Troubleshooting training: common


faults that may occur in daily operation Jobsite training
and effective measures to solve them

Questions & Answers

Evaluation Process and Report

3.2.2 Electrical, Instrumentation, Control, and Automation System

No. Training Content

1 Principle and composition of the system

2 Operation and maintenance

3 Failure analysis and troubleshooting

Page 7 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

4 Jobsite operation

4. TRAINING FOR OPERATION AND MAINTENANCE


The training process consists of two main parts, Theoretical Training Courses, and On ‐the ‐
Job Training. The commissioning team will immediately start this training process regarding
the Operation & Maintenance manual after the commissioning.

4.1 Theoretical Training Courses

The Operation & Maintenance Manager shall be the organizer of training courses held by qualified
trainers. Operational & Maintenance will demonstrate the whole process, the techniques, and the
result to be achieved. Local regulations, Codes, and Standards shall be educated and emphasized with
the importance of compliance.

4.1.1 Introduction and Basics

 Testing and commissioning plan


 Facilities management and control system
 Flow meter reading
 Water level in inlet/outlet
 Maintenance of valves
 Operation during flooding time
 Electric Butterfly Valve operation
 Water quality management
 Cleaning of trash rack screen
 Others

4.2 On‐The‐Job Training

The trainees assigned by the Employer will receive on ‐the ‐job training in their working expertise,
which will contain all topics related to the operation and maintenance of the equipment.

The Operation & Maintenance Manager will organize the training for the Employer’s staff as well as
the Contractor’s construction teams.

Page 8 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

The On‐The‐Job training will include practical and realistic components, firstly, through hands-on
exercises where trainees will be able to relate tasks to actual work. Secondly, a computer program will
be utilized where trainees are assisted and guided efficiently with the assistance of professional staff.

The scope of training in operation and maintenance will cover the main topics of operation and
maintenance work in accordance with requirements in the contract, the theoretical phase, and the on-
the-job phase, including the following courses.

 Concepts and procedures of operation and maintenance and safety measures during maintenance

 Levels of operation and maintenance

 O&M management documentation and software

 O&M quality control and monitoring systems

O&M training will contain an overview of the project E&M systems, subsystems, system
components, etc., and the O&M manuals, which include as-built drawings, maintenance requirements,
service procedures, etc. Maintenance management will include the basic principles, scheduling,
records and documentation.

5. TRAINING EVALUATION
Ongoing evaluation by the Operation & Maintenance Manager and Engineer will assess whether the
needs of the trainees are being satisfied and which methods are working, and which are not so
effective. With the database gathered during the evaluation, the training program and curriculum will
be continuously updated to meet the actual work demand and individual preferences of the trainees

6. TRAINING IMPLEMENTATION
The Employer's staff will be well-trained by selected Contractor experts who excel in construction
and management. The Operation & Maintenance Manager will develop instructors to prepare the
courses in advance, based on the staff training plans stipulated by the Employer, and ensure that the
training activities will achieve the desired results for Employer’s staff.

7. END‐OF‐COURSE ASSESSMENT
The purpose of the End-of-Course Assessment (ECA) is to measure the learning achievement and
effectiveness of the employer's personnel in terms of this training. The assessment will refer to pre-
defined criteria, which shall be discussed and approved by the employer. The ECA may include

Page 9 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

practical hands-on testing and theoretical examination. The results of the assessment will be
summarized in a final training assessment report for each trainee.

At the end of the assessment, the Operation & Maintenance Manager and Engineer will analyze the
situation, evaluate the results, and submit a final report to the Employer.

7.1 Annexes:
Training Program

Item Operation Maintenance Schedule

Overview Operation Usage, frequency of


Electric Butterfly Valve Instruction Operation Menu maintenance, and Day 1
Control the valve functions cautions

Usage, frequency of
Overview Operation
Air Valve maintenance, and Day 1
Instruction cautions

Usage, frequency of
Lighting Switching maintenance, and Day 2
cautions
Usage, frequency of
Overview Operation
Generator set maintenance, and Day 3
Instruction cautions
Components Installation Usage, frequency of
Flow Measurement and System configuration in maintenance, and Day
Control System STANDARD mode System cautions
configuration in Expert Mode

Page 10 of 11
Design and Build of the Kaysakat Raw Water Transmission Line - Tunnel Works

Training Plan

End of Course Assessment (ECA)

Full Need for


System
understanding Clarification
Electric Butterfly Valve □ □

Air Valve □ □

Lighting □ □

Generator set □ □

Flow Measurement and Control System □ □

Page 11 of 11