ACCOMPLISHMENT REPORT
For the Month of: November 2021

Name: DARYL JAMES M. BACERA Date: November 29, 2021


Position: Admin Aide IV Division: Supply Unit
Status of Employment (please check):
Regular _____ COS __✓__ Co-terminus _____

Status of the
Date/s
Activities Undertaken During The Period Activity
Undertaken
Undertaken
 Assisted in clerical activities of the unit. Done
Nov. 2-5, 2021  Released requested items to end users. Done
 Assisted in clerical activities of the unit. Done
Nov. 8-12,  Released requested items to end users. Done
2021  Conducted sticker tagging Partially Done
 Assisted in clerical activities of the unit. Done
Nov. 15-19,  Prepared necessary needs for the new Done
2021 stockroom.
 Transferred whole office supplies to new Done
stockroom.
 Received deliveries of supplies. Done
 Inspected delivered office supplies Done
Nov. 22-26,  Released requested items to end users. Done
2021  Received deliveries of supplies. Done
 Conducted partial physical inventory Done
count in preparation for the audit.
 Assisted in clerical activities of the unit. Done
Nov. 29, 2021  Preparation of documents needed for the Done
audit.
Note: Use additional sheet if necessary

Prepared by:

DARYL JAMES M. BACERA


Printed Name over Signature

Checked and Reviewed by: Approved by:

BAI NAZIBA K. DIBARATUN RONNA FARIDA M. BUISAN, MPA


Immediate Supervisor HRMO III