ZEWAY-BUTAJIRA-GUBRE

ROAD UPGRADING PROJECT


CONTRACT-2 : BUTAJIRA-GUBRE

Owner : Ethiopian Roads Authority


Consultant : Highway Engineers
& Consultants / HEC / joint with Panaf & Hamda.
Contractor : Sun Shine construction p.l.c.
SIVE ANALYSIS FOR SUB-BASE MATERIAL
WET-SIVE METOHD.

Sampled station : 0+000 LHS offset 6.0k.m on the way to worabe road. MATERIAL DESCRIPTION:- RED CINDER
Sampled Date : 8/3/2009 Tested Date : 13/3/2009 Material Source : STOCKPILE Lab. # :S.B-02
100
% Passing

90

80

70

60

50

40

30

20

10

0
1 10 100
Sieve Size

Sieve Sizes 63 50 25 4.75 0.075 pan Total Remark: TRIAL ONE BY WET SIVE, ONLY RED CINDER.
Weight Retained 0 409 4149 3876 830 20 9284.0
% Retained 0.00 4.41 44.69 41.75 8.94 0.22 100.00
% Passing 100 96 50.90 9.16 0.22 0
Speci. Upper Limits 100 100 80 70 15
Speci. Lower Limits 100 90 51 35 5
BEFOR WASH 9391
AFTER WASH 9284
LOSS 107

CONTRACTOR'S CONSULTANT'S
ZEWAY-BUTAJIRA-GUBRE
ROAD UPGRADING PROJECT
CONTRACT-2 : BUTAJIRA-GUBRE

Owner : Ethiopian Roads Authority


Consultant : Highway Engineers
& Consultants / HEC / joint with Panaf & Hamda.
Contractor : Sun Shine construction p.l.c.
SIVE ANALYSIS FOR SUB-BASE MATERIAL
WET-SIVE METOHD.

Sampled station : 0+000 LHS offset 6.0k.m on the way to worabe road. MATERIAL DESCRIPTION:- RED CINDER
Sampled Date : 8/3/2009 Tested Date : 13/3/2009 Material Source : STOCKPILE Lab. # :S.B-02
100
% Passing

90

80

70

60

50

40

30

20

10

0
1 10 100
Sieve Size

Sieve Sizes 63 50 25 4.75 0.075 pan Total Remark: TRIAL ONE BY WET SIVE, ONLY RED CINDER.
Weight Retained 0 388 2976 4332 867 39 8602.0
% Retained 0.00 4.51 34.60 50.36 10.08 0.45 100.00
% Passing 100 95 60.89 10.53 0.45 0
Speci. Upper Limits 100 100 80 70 15
Speci. Lower Limits 100 90 51 35 5
BEFOR WASH 8651
AFTER WASH 8603
LOSS 48

CONTRACTOR'S CONSULTANT'S
ZEWAY-BUTAJIRA-GUBRE
ROAD UPGRADING PROJECT
CONTRACT-2 : BUTAJIRA-GUBRE

Owner : Ethiopian Roads Authority


Consultant : Highway Engineers
& Consultants / HEC / joint with Panaf & Hamda.
Contractor : Sun Shine construction p.l.c.
SIVE ANALYSIS FOR SUB-BASE MATERIAL
DRY-SIVE METOHD.

Sampled station : 0+000 LHS offset 6.0k.m on the way to worabe road. MATERIAL DESCRIPTION:- RED CINDER
Sampled Date : 8/3/2009 Tested Date : 12/3/2009 Material Source : STOCKPILE Lab. # :S.B-02
100
% Passing

90

80

70

60

50

40

30

20

10

0
1 10 100
Sieve Size

Sieve Sizes 63 50 25 4.75 0.075 pan Total Remark: TRIAL TWO, ONLY RED CINDER.
Weight Retained 0 277.4 3030.7 4463.9 843.4 39.6 8655.0
% Retained 0.00 3.21 35.02 51.58 9.74 0.46 100.00
% Passing 100 97 61.78 10.20 0.46 0
Speci. Upper Limits 100 100 80 70 15
Speci. Lower Limits 100 90 51 35 5
CONTRACTOR'S CONSULTANT'S
ZEWAY-BUTAJIRA-GUBRE
ROAD UPGRADING PROJECT
CONTRACT-2 : BUTAJIRA-GUBRE

Owner : Ethiopian Roads Authority


Consultant : Highway Engineers
& Consultants / HEC / joint with Panaf & Hamda.
Contractor : Sun Shine construction p.l.c.
SIVE ANALYSIS FOR SUB-BASE MATERIAL
WET-SIVE METOHD.

Sampled station : 0+000 LHS offset 6.0k.m on the way to worabe road. MATERIAL DESCRIPTION:- RED CINDER
Sampled Date : 8/3/2009 Tested Date : 13/3/2009 Material Source : STOCKPILE Lab. # :S.B-02
100
% Passing

90

80

70

60

50

40

30

20

10

0
1 10 100
Sieve Size

Sieve Sizes 63 50 25 4.75 0.075 pan Total Remark: TRIAL ONE BY WET SIVE, ONLY RED CINDER.
Weight Retained 0 409 4149 3876 830 20 9284.0
% Retained 0.00 4.41 44.69 41.75 8.94 0.22 100.00
% Passing 100 96 50.90 9.16 0.22 0
Speci. Upper Limits 100 100 80 70 15
Speci. Lower Limits 100 90 51 35 5
BEFOR WASH 9391
AFTER WASH 9284
LOSS 107

CONTRACTOR'S CONSULTANT'S
Hadero - Durgi Road Upgrading Project
Client: ERA Contractor: Aster Mengistu General Contractor & WW Consultant: Beza Consulting Engineers

PARTICLE SIZE DISTRIBUTION (AASHTO T 11 & T 27)

Date Tasted: 27/01/2013 Sample Ref: BC- 01 Date sampled: 25/01/2013

Description: Crushed Rock Location: 52+800 offset 50m RHS Tested by: Jointly

Material Type: Base Course Test Method:- Wet Sieve ✘ Dry Sieve

TEST DATA
Spec.
grading limit Sample Before Wash (gm) 12417
Wt. Retained Retained Passing
Sieve Size (mm)
(gm) (%) (%) Speci. Lower Speci. Upper
Limits Limits Sample After Wash (gm) 11928
50 0 0 100 100 100
37.5 385 3.1 96.9 95 100
20 3241 26.1 70.8 60 80
10 2248 18.1 52.7 40 60
5 2129 17.1 35.5 25 40
2.36 1186 9.6 26.0 15 30
0.425 1626 13.1 12.9 7 19
0.075 1113 9.0 3.9 5 12
Pan 489 3.9
Total 12417

Specimen Grading Graph

100
SPECIMEN GRADING 1
90
Speci. Upper Limits

Speci. Lower Limits


3
80
% Passing

70

4
60
3
50

5
40
4
6
30

20
7 5
8
10 6
8 7
0
0.01 0.1 1 10 100
Sieve Size

Remark:- The crusher was inactive from January 05/2013 - January 23/2013

Lab.Tec. Lab.Tec.
Aster Mengistu GC & WW Beza Consulting Engineers
Material Eng: Material Eng:
Aster Mengistu GC & WW Beza Consulting Engineers
Hadero - Durgi Road Upgrading Project
Client: ERA Contractor: Aster Mengistu General Contractor & WW Consultant: Beza Consulting Engineers

PARTICLE SIZE DISTRIBUTION (AASHTO T 11 & T 27)

Date Tasted: 27/01/2013 Sample Ref: BC- 01 Date sampled: 25/01/2013

Description: Crushed Rock Location: 52+800 offset 50m RHS Tested by: Jointly

Material Type: Base Course Test Method:- Wet Sieve ✘ Dry Sieve

TEST DATA
Spec.
grading limit Sample Before Wash (gm)
Wt. Retained Retained Passing
Sieve Size (mm)
(gm) (%) (%) Speci. Lower Speci. Upper
Limits Limits Sample After Wash (gm)
50 0 0 100 100 100

37.5 385 3.1 96.9 95 100

20 3241 26.1 70.8 60 80

10 2248 18.1 52.7 40 60 10 pass, 5 ret 300g add

5 2429 19.6 33.1 25 40 2129 2.36 pass, 0.425 ret 300g deduct

2.36 1186 9.6 23.6 15 30

0.425 1326 10.7 12.9 7 19 1626

0.075 1113 9.0 3.9 5 12

Pan 489 3.9

Total 12417

Specimen Grading Graph


100

SPECIMEN GRADING
1
90
Speci. Upper Limits
3
80 Speci. Lower Limits
% Passing

70

4
60
3
50

5
40
4
6
30

20
7 5
8
10 6
8 7
0
0.01 0.1 1 10 100
Sieve Size

Remark:- The crusher was inactive from January 05/2013 - January 23/2013

Lab.Tec. Lab.Tec.
Aster Mengistu GC & WW Beza Consulting Engineers
Material Eng: Material Eng:
Aster Mengistu GC & WW Beza Consulting Engineers
ZEWAY-BUTAJIRA-GUBRE
ROAD UPGRADING PROJECT
CONTRACT-2 : BUTAJIRA-GUBRE

Owner : Ethiopian Roads Authority


Consultant : Highway Engineers
& Consultants / HEC / joint with Panaf & Hamda.
Contractor : Sun Shine construction p.l.c.
SIVE ANALYSIS FOR SUB-BASE MATERIAL BY BLENDING 1:1 RATIO.
DRY-SIVE METOHD.

Sampled station :17+000 RHS & 31+720 LHS 1k.m offset. MATERIAL DESCRIPTION:- STONE GAVEL -1
WHITE TUFF -1
Sampled Date : 8/3/2009 Tested Date : 12/3/2009 Material Source : STOCKPILE Lab. # :S.B-01
100
% Passing

90

80

70

60

50

40

30

20

10

0
1 10 100
Sieve Size

Sieve Sizes 63 50 25 4.75 0.075 pan Total Remark: TRIAL ONE, BLENDED SUB-BASE BY 1:1 RATIO.
Weight Retained 0 410 4133.3 4004.9 815.6 38.4 9402.2
% Retained 0.00 4.36 43.96 42.60 8.67 0.41 100.00
% Passing 100 96 51.68 9.08 0.41 0
Speci. Upper Limits 100 100 80 70 15
Speci. Lower Limits 100 90 51 35 5
CONTRACTOR'S CONSULTANT'S