MATERIAL REQUISITION

Project: Sodic
Date:18_3_2023
MATERIALS FOR MECHANICAL WORKS
Take Off Quantity Required Quantities

Vendor
Serial

Qty..
Material Description Unit Manufacturer Vendor Model Phase Phase Phase Remarks
LEVEL TOTAL 01 02 03
Ground
A Fittings floor

1 ‫عدد‬
1 90 ‫"كوع زاوية‬ 30
2 ‫عدد‬
1.5 45 ‫"كوع زاوية‬ 2

10 ‫عدد‬
‫ مشترك‬T ''1 12

11 ‫عدد‬
‫ مشترك‬T ''1*1.5 5

16 ‫عدد‬
‫ مشترك‬T ''1.25*''1 1

17 ‫عدد‬
0.5 ‫''نبل‬ 10

18 ‫عدد‬
0.5 ‫''محبس‬ 10

19 ‫عدد‬
0.5 ‫''طبة‬ 111

20 ‫عدد‬
1*''0.5 ‫''مسلوب‬ 111

21 ‫عدد‬
4*''2.5 ‫''مسلوب‬ 1

22 ‫عدد‬
1.25*''1.5 ‫''مسلوب‬ 1

Page 1 of 4
MATERIAL REQUISITION
Project: Sodic
Date:18_3_2023
MATERIALS FOR MECHANICAL WORKS
Take Off Quantity Required Quantities

Vendor
Serial

Qty..
Material Description Unit Manufacturer Vendor Model Phase Phase Phase Remarks
LEVEL TOTAL 01 02 03
Delivery Date Authorized Signatures
Phase 01 Deliverd QA/QC Engineer Site Engineer Construction Manager
Phase 02 Deliverd
Phase 03 Immediately

Attachments Technical Department Operation Manager





Remarks :
all Materials to be Comply with all consultant 's comments

Page 2 of 4