This document summarizes the receipt of concrete material for the FC 10 project site from April 10th to May 8th. A total of 291 cubic meters of concrete were received from 44 deliveries during this period. The report records details of each delivery such as date, truck number, time of dump, quality of concrete, aggregate quantity and cumulative total.
This document summarizes the receipt of concrete material for the FC 10 project site from April 10th to May 8th. A total of 291 cubic meters of concrete were received from 44 deliveries during this period. The report records details of each delivery such as date, truck number, time of dump, quality of concrete, aggregate quantity and cumulative total.
This document summarizes the receipt of concrete material for the FC 10 project site from April 10th to May 8th. A total of 291 cubic meters of concrete were received from 44 deliveries during this period. The report records details of each delivery such as date, truck number, time of dump, quality of concrete, aggregate quantity and cumulative total.
LAPORAN PENERIMAAN MATERIAL CONCRETE/BETON FC 10 - SITE PALARAN
PROYEK JALAN AKSES STADION UTAMA PALARAN
KAMULATIF(M3) NO TANGGAL NO PENGIRIMAN UNIT MIXER VENDOR WAKTU DUMP LOAD MUTU BETON AGGREGAT JUMLAH (M3) / TANGGAL 1 10-Apr-23 01 KT8771NS PAB 11:04 FC10 30 5
KAMULATIF(M3) NO TANGGAL NO PENGIRIMAN UNIT MIXER VENDOR WAKTU DUMP LOAD MUTU BETON AGGREGAT JUMLAH (M3) / TANGGAL 1 8-May-23 01 KT8771NS PAB 12:00 FC10 30 6