HACKING WORK FOR SLAB OPENING NEW 33kV

PROJECT
(FOR NEW 33kV PROJECT)

JB1
MOP (Method of procedure)

Table of Contents
a) TABLE OF CONTENTS ---------------------------------------------------------------------------------------1
b) PURPOSE -----------------------------------------------------------------------------------------------------2
c) EMERGENCY CONTACT LIST & WORKER NAME LIST----------------------------------- --------------3
d) TOOLS AND EQUIPMENT ---------------------------------------------------------------------------------4
e) INVOLVED AREA LAYOUT ---------------------------------------------------------------------------------4
f) WORK PLANNING AND SCHEDULE ----------------------------------------------------------------------5
g) LAYOUT DRAWING AND SITE PHOTO REVIEW -------------------------------------------------------6
h) RISK ASSESSMENT --------------------------------------------------------------------------------------------10
i) FALLBACK PLAN -----------------------------------------------------------------------------------------------10

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 1
1. PURPOSE

1. To hack the floor slab opening dimension 1000mm x 250mm for new 33kV system inside Electrical Riser
Room from level 6 until level 16.

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 2
2. Emergency Contact List & Worker Name List

Name IC / PASSPORT Contact Number Department

Mr. Cheah CY 820117-14-5857 0127633221 Contractor

Mr. Tan JC 890814-02-5061 0125353103 Contractor

Mr. Danny 790502-01-6133 0197436411 Contractor

Md Parvez Bepari EK0306493 0199303991 Contractor

Sariful Islam EG0817455 - Contractor

Mohammed Yonos A05003113 01169548550 Contractor

Mohammad Tokon Hossain EB0405896 01877895636 Contractor

Mohammad Rokon Hossain EL0577582 0164278027 Contractor

Md Shakil Alom EK0330136 - Contractor

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 3
3. Tools And Equipment

Tools & Equipment


Hacker Machine
Hammer Drill Machine
Grinder Machine
Safety PPE

4. Involved Area Layout –


a) Level 6 until Level 16 – Electrical Riser Room

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 4
5. Work Planning and Schedule

REMARKS:

1. Hacking work will be start on night time from 6pm until 6am.
2. We will clear and disposal all the construction waste concurrently while hacking works in progress.
3. We do barricade the opening with safety barricade tape.
4. 5s housekeeping will be carry out at affected area.

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 5
6. Layout Drawing and Site Photo Review

Electrical Riser Room

LOCATION: Bilik Salur ( Electrical Service Riser Room ) Level 6 until Level 16

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 6
Slab Opening Size Dimension 1000mm x 250mm

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 7
Slab Opening Size Dimension 1000mm x 250mm

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 8
Slab Opening Size Dimension 1000mm x 250mm

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 9
7. Risk Assessment

Potential risk is very unlikely and negligible injuries.

8. Fallback Plan
- Stop the activity immediately if there is any surge/fire happened.
- Contact emergency number – 999
- Remove the new added cable tapping and resume the power
- If power tapping unsuccessful, escalate to PCS and ask for solution ASAP.

Method of Procedure HENG TAC ENGINEERING


SDN.BHD
Page 10