MOP Hacking Work For New 33kV Project
MOP Hacking Work For New 33kV Project
MOP Hacking Work For New 33kV Project
PROJECT
(FOR NEW 33kV PROJECT)
JB1
MOP (Method of procedure)
Table of Contents
a) TABLE OF CONTENTS ---------------------------------------------------------------------------------------1
b) PURPOSE -----------------------------------------------------------------------------------------------------2
c) EMERGENCY CONTACT LIST & WORKER NAME LIST----------------------------------- --------------3
d) TOOLS AND EQUIPMENT ---------------------------------------------------------------------------------4
e) INVOLVED AREA LAYOUT ---------------------------------------------------------------------------------4
f) WORK PLANNING AND SCHEDULE ----------------------------------------------------------------------5
g) LAYOUT DRAWING AND SITE PHOTO REVIEW -------------------------------------------------------6
h) RISK ASSESSMENT --------------------------------------------------------------------------------------------10
i) FALLBACK PLAN -----------------------------------------------------------------------------------------------10
1. To hack the floor slab opening dimension 1000mm x 250mm for new 33kV system inside Electrical Riser
Room from level 6 until level 16.
REMARKS:
1. Hacking work will be start on night time from 6pm until 6am.
2. We will clear and disposal all the construction waste concurrently while hacking works in progress.
3. We do barricade the opening with safety barricade tape.
4. 5s housekeeping will be carry out at affected area.
LOCATION: Bilik Salur ( Electrical Service Riser Room ) Level 6 until Level 16
8. Fallback Plan
- Stop the activity immediately if there is any surge/fire happened.
- Contact emergency number – 999
- Remove the new added cable tapping and resume the power
- If power tapping unsuccessful, escalate to PCS and ask for solution ASAP.