Professional Documents
Culture Documents
Epc Projects 1669892800
Epc Projects 1669892800
OF EPC PROJECTS
1
2
Agenda
3
Introduction
4
EPC Project Management
- Introduction
5
EPC Project Management
EPC stands for Engineering, Procurement, Construction and is a prominent form of contracting
agreement in the construction industry.
The engineering and construction contractor will carry out the detailed engineering design of the project,
procure all the equipment and materials necessary, and then construct to deliver a functioning facility or
asset to their clients. Companies that deliver EPC Projects are commonly referred to as EPC
Contractors.
The EPC phase of the project is also known as the Execution phase which normally follows what is
know as a FEED or Front End Engineering Design phase. The FEED is a basic engineering design used
as the basis for the EPC phase.
The FEED can be divided into separate packages covering different portions of the project. The FEED
packages are used as the basis for bidding on when the client offers the EPC work to the market.
Under an EPC contract, the contractor designs the installation, procures the necessary materials and
builds the project, either directly or by of the work.
6
EPC Project Management
In some cases, the contractor carries the project risk for schedule as well as budget in return for a fixed
price, called lump sum LSTK depending on the agreed scope of work.
◼ EPCM stands for Engineering, Procurement, Construction Management. This type of contract is
different to an EPC Contract in that the Contractor is not directly involved in the construction but is
responsible for administering the Construction Contracts.
◼ EPCI stands for Engineering Procurement Construction and Installation which is a common form of
contracting arrangement in the Offshore Construction Industry. As opposed to an EPC contract, the
offshore facility or vessel that is constructed has to be transported and installed at the project
location.
◼ EPIC stands for Engineering Procurement Installation Commissioning is typically a Lump Sum Turn
Key (LSTK) type Contract integrating the responsibility going from the conception to the final
acceptance of one or more elements of a production system. It can be awarded for all, or part, of a
field development.
7
EPC Project Lifecycle
8
EPC Project Organization
9
EPC Project Organization
10
Engineering Discipline
11
EPC Project Management
- Work Flow
12
Engineering Work Flow
Engineering work flow concept is required to be fully understand for someone who involved in the EPC
Planning and Activity Sequencing.
The process of engineering work to produce the required deliverables depends on not only within the
functional discipline itself but also among the process, mechanical and piping engineering functions.
Engineering in EPC project is the task of translating a set of functional requirement into a full set of
drawings and specifications depicting every detail of a facility,
◼ Process
◼ Civil and Structure
◼ Mechanical
◼ Piping
◼ Electrical
◼ Instrumentation
◼ General Engineering
◼ Safety
13
Engineering Work Flow
There are many interdependencies between engineering documents.
For instance piping routing drawings are issued after the process diagram Is defined.
Most of the documents will usually issued several times, at different stages to for review as well as to
incorporate the comments.
Typically a document is first issued for Internal Review (IFR) of the other disciplines, then to client for
comment (IFC), it will be returned to be incorporated with the client comments and issue for Approval
(IFA), then for construction (IFC) and last once everything is confirmed and will Approve for Construction
(AFC)
14
Engineering Work Flow
15
Engineering Work Flow
Engineering phase is very much concerned with documentation.
16
Engineering Work Flow
Project Execution
17
Engineering Document –
Issuance Purpose
18
Engineering Document – Issuance Purpose
Project Execution – Issuing Purpose
Lead Engineer
Client Approved
Submission to Client
review
Revision
New work Comments
work
allocation
allocation
Production
Input to other
disciplines
Fail
QC
Pass
Archive by
DC
Comments
IDC
Accept Reject
QA
19
EPC Project Management
- Engineering Work Flow
20
Engineering Work Flow
Typical Instrumentation Engineering Work Flow
21
Engineering Document Review Cycle
22
Engineering Work Flow – Process Design
23
Piping Engineering Flow
24
3D
Modeling
(Skid
Project)
25
Skid 3D Modelling – Piping GA as Example
26
Engineering Work Flow
Process, Piping & Mechanical Engineering
27
Engineering Work Flow
Piping and Pipe line
• 3D Modeling
• Design calculations
• Preparation of PMS/VMS
• Isometrics, GA’s
• Bill of material/Quantity
28
Engineering Work Flow
Mechanical
• Mechanical Datasheets
29
Engineering Work Flow
Civil & Structural
• Structural GA Drawings
• Shop/Fabrication Drawings
30
Engineering Work Flow
Process & HSE
• Development of PFD/P&ID’S
• NPSH Calculation
• Process Datasheets
31
Engineering Work Flow
Electrical & Instrumentation
• Cable schedules
• P&ID’s
• JB termination
32
Engineering Work Flow – E&I
33
Engineering Work Flow – Instrumentation
34
Engineering Work Flow – Instrumentation
I/O List contains of instrumentation which serve as an input or output of control system.
Hence the tag number that physically has a cable which connects to the control system
appears on I/O list.
35
Engineering Work Flow – Instrumentation
Typical P&ID & Process Data
36
Engineering Work Flow – Instrumentation
Typical Inst. Index
37
Engineering Work Flow – Instrumentation
Typical I/O List
38
Engineering Work Flow – Instrumentation
Typical Instrument Loop Diagrams
39
Engineering Work Flow – Instrumentation
Typical Instrument Hookup Diagrams
40
Engineering Work Flow – Instrumentation
Typical Instrument Layout Diagrams
41
Engineering Work Flow – Instrumentation
Typical Instrument Layout Diagrams
42
Engineering Work Flow – Instrumentation
Typical Instrument Layout Diagrams
43
Engineering Work Flow – Instrumentation
Typical Instrument Cable Schedule, JB Schedule
44
Engineering Work Flow – Instrumentation
Typical Cause & Effect Dia. & Instrument Logic Diagram
45
Engineering Work Flow – Instrumentation
Instrument Data Sheet specifies general information of instrument such as tag number
identification, service description, location (line number/equipment number), P&ID
number or drawing number reference, process data (if applicable), calibrated range (if
applicable), material, performance details (such as accuracy, linearity – if applicable),
hazardous certification (for electrical device), accessories required, etc. The details of
information in data sheet may differ among each types of instrument such as
transmitter, switch, gauge, control valves.
Reference document: Piping and Instrumentation Diagram (P&ID), Heat and Material
Balance (HMB), line list, instrument specification, piping specification, calculation,
vendor catalog.
46
Engineering Work Flow – Instrumentation
Typical Inst. Data Sheet
47
EPC Project Management
- Procurement Work Flow
48
Procurement Work Flow
49
Typical On-Shore Schedule
and Dependencies
50
Typical
Project
Schedule
51
Work Front Concept
52
Work Front
Milestones associated with Construction: These are the IFC Plot Plan, a pre-requisite to start any site work, and
the IFC P&IDs, a pre-requisite to the issue of Piping isometrics. The 5O% IFC Piping isometric milestone comes
next, which typically falls half way through the Project, as ensuing works, such as pre-fab and erection have a rather
incompressible duration, due to site constraints (capacity of pre-fab shop, space constraints for erection limiting the
progress).
Even if engineering deliveries are in sequence, the above engineering progress measure might still be deceiving, as
it will only reflect the amount of engineering work completed and not the Workfront made available to construction.
let's consider for instance that two foundations are to be cast. The first one is a very large foundation and the second
one a small one. Issuing the drawing of either the large or small foundation will earn engineering the same progress,
although it will open quite a different Workfront to Construction.
53
Work Front
In the case of foundations, for instance, this will be done by monitoring the cumulative quantity of concrete (m3) of all
issued IFC foundation drawings.
Producing an S curve, such as the one shown in next slide, showing both planned and actually issued quantities will
give a true picture of how well engineering is supporting civil works.
One will similarly monitor, for an On-Shore project, the cumulative quantity of steel (tons) of issued IFC Structural
drawings.
The cumulative tons (or dia inch) of IFC issued Piping isometrics will show the available piping Workfront.
Such progress curves, showing the actual versus planned available work fronts are instrumental to monitor
engineering progress, identify shortage and take corrective actions (increase mobilisation).
It is not perfect however and can still be deceiving, in case of out-of-sequence issues: engineering may have issued
drawings representing significant quantities, but that does not generate construction workfront as such works can not
be performed at this time (due to lack of access or pre-requisite for another work to be completed before, for
instance).
54
Work Face Planning
55
HARD
DRIVE
WORKCONTROL
BUT……
56