You are on page 1of 4

Learning Area TLE - Carpentry Grade Level 10

W3 Quarter THIRD Date Week 3

I. LESSON TITLE • Tools, Materials and Equipment Used in Assembling and Disassembling
Metal Scaffolding
• Personal Protective Equipment Used in Assembling and Disassembling
Metal Scaffolding
II. MOST ESSENTIAL LEARNING LO2. LAY-OUT/ASSEMBLE SCAFFOLDS AND
COMPETENCIES (MELCs) BRACES (TLE_IACP10IFIIa-IVj-2)

III. CONTENT/CORE CONTENT 2.1 Prepare work areas for safe laying out and
assembling of scaffolds and braces)

2.4 Select appropriate PPE

References: Carpentry Grade 10 Module


www.google.com
Suggested
IV. LEARNING PHASES Learning Activities
Timeframe
A. Introduction 4 HRS Presentation
Panimula In this module, you will learn the tools, as well as the Personal Protective
Equipment prescribed to be used in assembling and disassembling metal
scaffolding,

Complete the table: Write your answer on a separate sheet of paper

Tool/PPE Use or Purpose


Metal Scaffolding (1)

(2)Wrenches and pliers used for gripping, fastening, turning,


tightening and loosening things like
pipes, pipe fittings, nuts and bolts.
Claw hammer (3)

Nail box (4)

(5) Plumb bob tool with weight and string, used to


check the vertical alignment of
structures.
Spirit level (6)

(7) Gloves Use to protect hands from sharp


objects
Safety shoes (8)

(9)Hard hat Refers to head cover for safety

Safety belt (10)

Over all worn to protect the body

Read these new concepts

Materials, Tools, and Equipment:

1. Metal scaffolding is a temporary structure outside of a building, that are


made of metal poles with planks used by workers while constructing,
repairing, or cleaning the building.
Suggested
IV. LEARNING PHASES Learning Activities
Timeframe

2. Wrenches and pliers is a tool used for gripping, fastening, turning, tightening
and loosening things like pipes, pipe fittings, nuts and bolts.

3. Claw hammer is a driving tool used to drive and pull-out nails.

4. Nail box for lock pins tool to place nails and screws to use in assembling
and disassembling scaffolding.

5. Plumb bob is a testing tool used to check the vertical alignment of the
form in installation.

6. Spirit level is a testing tool used to check the horizontal alignment of the
form commonly used in the installation of beam forms.

Personal Protective Equipment


Suggested
IV. LEARNING PHASES Learning Activities
Timeframe

Gloves are hand coverings used for protection


from rough, dirty, and sharp objects.

Safety shoes refer to feet protection


used for personal safety; usually a
type of shoe with steel toe.

Safety hat and Helmet refers to a head


cover for safety protection, and is usually
made of hard plastic.

Safety belt refers to wide leather strap with


hook used to protect an individual from an
accidental fall.

Overall clothes refer to cotton clothing worn


during the actual work or in performing tasks.

B. Development
Pagpapaunlad Tools are extension of the hands. They make works easier and faster.
Accuracy in assembling the metal scaffolding is very important to assure
safety during usage. It is therefore very vital to use proper tools and
equipment during its assembly.

To ensure safety in work areas, workers must use Personal Protective


Equipment (PPE). PPEs when used properly help protect the workers against
injuries and prevent the occurrence of accidents.

C. Engagement Learning Task 1: Look for the tools, materials and equipment and PPE used in
Pakikipagpalihan assembling and disassembling scaffolding in the puzzle. Write your answer on
a sheet of paper.

W B P L U M B B O B
G L O V E S R L W U
H A R D H A T O R M
R C E M Z X T C E A
L E V E L I W K N R
E S U Z Y L X P C T
N A I L B O X I H Z
O V E R A L L N E Q
B E L T F O L D S T
C L A W H A M M E R

D. Assimilation Learning Task 2: Make a photo collage of the tools, materials and equipment
Paglalapat and Personal Protective Equipment in a short bond paper.

V. ASSESSMENT Learning Task 3: Identify the following. Write your answer


(Learning Activity Sheets for
Enrichment, Remediation or
1. Tool used to check the horizontal alignment of scaffold.
Suggested
IV. LEARNING PHASES Learning Activities
Timeframe
Assessment to be given on Weeks A. Long nose C. spirit level
3 and 6)
B. plier D. wrenches
2. A temporary structure outside of a building, that are made of metal poles
with planks used by workers while constructing, repairing, or cleaning the
building.
A. Long nose C. screwdriver
B. metal scaffolding D. wrenches
3. The following are tools in disassembling metal scaffold, except;
A. Claw hammer C. Ruler
B. Pliers D. Wrenches
4. Tool used to tighten and loosen nuts for lock pin and castors.
A. Claw hammer C. plumb bob
B. Nail box D. wrenches
5. Tool used in keeping lock pins after used.
A. Cross braces C. Lock pin
B. Frame D. Platform
6. This PPE is required to wear during actual work or performing a task to cover
and protect your whole body.
A. Belt C. Over All
B. Hard Hat D. Safety Shoes
7. Tool used to check for the vertical alignment of the frame.
A. plumb bob C. try square
B. pliers D. Wrenches
8. PPE used to protect hands from sharp objects while working
A. safety shoes C. over all
B. safety belt D. gloves
9. PPE used as head covering for protection
A. gloves C. safety hat
B. safety belt D. safety shoes
10. PPE worn before climbing in a scaffold to prevent accidental fall.
A. Gloves C. Safety Belt
B. Hard hat or helmet D. Over all
VI. REFLECTION
Write your personal insights about the lesson using the prompts below.
• I understand that ___________________.
• I realize that ________________________.
• I need to learn more about __________.

Prepared by: Checked by: JOEL D. SALAZAR
Maria Teresa V. Layugan EPS-CSDO Dasmariñas
CSDO Dasmariñas JHUN HANDAYAN
EPS-SDO Bacoor