MONITORING GEOTEKNIK PROYEK JALAN TOLL PADANG - SICINCIN

TANGGAL 7 NOVEMBER 2023


REALISASI PEKERJAAN
No STA KEGIATAN PIC HKI KENDALA
Ya Tidak
1 PEKERJAAN PRELOADING, UNLOADING & EXTRALOAD
sta 4+300 timbunan timbunan extraload pak anang
sta 11.350 lanjut timb preload pak tarmuji
Sta 17+025 - Sta 17+275 timbunan preload ismail
2 SOILNAILING & SHOTCRETE
Sta 21+600 L shotcrete & soilnailing PT Reka Alam pak ismail
Sta 26+800-27+050R shotcrete & soilnailing oleh PT. trans data pak wibowo
Sta 27+075-27+100R shotcrete & soilnailing oleh PT. chemimdo pak wibowo
Sta 26+900-27+075L shotcrete & soilnailing oleh PT. Reka Alam pak wibowo
Sta 27+250-27+355R shotcrete & soilnailing oleh PT. trans data pak wibowo
Sta 27+750L shotcrete & soilnailing oleh PT. trans data pak wibowo
Sta 27+850R shotcrete & soilnailing oleh PT. Reka Alam pak wibowo
Sta 27+950R shotcrete & soilnailing oleh PT. RekaBumi pak wibowo
Sta 28+100R shotcrete & soilnailing oleh PT. RekaBumi pak wibowo
Sta 28+200L shotcrete & soilnailing oleh PT. trans data pak wibowo
CLEARING LAHAN, REPLACE , TIMBUNAN DAN
3 BRONJONG
sta 10.100-10.169ki galian replacement ,rencana pasang geotek pak tarmuji
Sta 19+900 - Sta 19+950 L Timbunan pak ismail
Sta 17+850 - Sta 17+950 R Timbunan pak ismail
Sta 21+500 - Sta 21+600 Timbunan pak ismail
Sta 27+100 - 27+400 Gali buang oleh PT. Petronesia & perapian sloop pak wibowo
Sta 27+400 - 28+400 Gali timbun oleh PT. Wira Agung pak wibowo
Sta 28+700 - 28+800 Gali timbun oleh PT. BSDA pak wibowo
Sta 29+000 - 29+100 Gali timbun oleh PT. BSDA pak wibowo
Sta 33+000 - 34+000 Clearing oleh PT. Petronesia pak wibowo
Sta 35+000 - 36+000 Gali timbun oleh PT. BSDA pak wibowo