CT 09 Balance Work Program

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

As at 26-10-2021 Delay catchup

Task Name Duration Start Date End Date Delay Reason for delays Duration Start Date Finish Date
Major Construction Activities 266 days 9/1/2021 5/24/2022
Conveyor Trestle 9 161 days 9/1/2021 2/8/2022 102 days 10/30/2021 2/8/2022
Civil Works 25 days 9/1/2021 9/25/2021 28 days 10/30/2021 11/26/2021
Concrete Frame 01 Construction - Grid X1 15 days 9/1/2021 9/15/2021 41 day Embeded parts delivery delay 14 days 10/30/2021 11/12/2021
Concrete Frame 02 Construction - Grid X2 20 days 9/5/2021 9/24/2021 32 days Embeded parts delivery delay 14 days 11/6/2021 11/19/2021
Concrete Frame 03 Construction - Grid X3 16 days 9/10/2021 9/25/2021 31 days Embeded parts delivery delay 14 days 11/13/2021 11/26/2021
Steel Works 58 days 12/13/2021 2/8/2022 58 days 12/13/2021 2/8/2022
Metal Works & Steel Truss Erection 58 days 12/13/2021 2/8/2022 58 days 12/13/2021 2/8/2022
Completion of Conveyor Trestle 9 1 day 2/8/2022 2/8/2022 1 day 2/8/2022 2/8/2022