Professional Documents
Culture Documents
CT 09 Balance Work Program
CT 09 Balance Work Program
CT 09 Balance Work Program
Task Name Duration Start Date End Date Delay Reason for delays Duration Start Date Finish Date
Major Construction Activities 266 days 9/1/2021 5/24/2022
Conveyor Trestle 9 161 days 9/1/2021 2/8/2022 102 days 10/30/2021 2/8/2022
Civil Works 25 days 9/1/2021 9/25/2021 28 days 10/30/2021 11/26/2021
Concrete Frame 01 Construction - Grid X1 15 days 9/1/2021 9/15/2021 41 day Embeded parts delivery delay 14 days 10/30/2021 11/12/2021
Concrete Frame 02 Construction - Grid X2 20 days 9/5/2021 9/24/2021 32 days Embeded parts delivery delay 14 days 11/6/2021 11/19/2021
Concrete Frame 03 Construction - Grid X3 16 days 9/10/2021 9/25/2021 31 days Embeded parts delivery delay 14 days 11/13/2021 11/26/2021
Steel Works 58 days 12/13/2021 2/8/2022 58 days 12/13/2021 2/8/2022
Metal Works & Steel Truss Erection 58 days 12/13/2021 2/8/2022 58 days 12/13/2021 2/8/2022
Completion of Conveyor Trestle 9 1 day 2/8/2022 2/8/2022 1 day 2/8/2022 2/8/2022