BEHU Project_MWP_ Oct 23

Status as on 23-Oct-23
Controller Mr.Nagindra singh
Sr.no Work description Responsible person Target date Status

1 EC- Paper publication


i Dist- Belgaum paper publication 05-oct 25 oct
ii Dist- Raichur paper publication 07-Oct-23 Paper Publication-Done
iii Dist- Bhagalkote paper publication 10-Oct-23 Paper Publication-Done
iv Dist- Belgaum public hearing Mr.Bhimrao 29-Nov-23
v Dist- Raichur public hearing 17-Nov-23
vi Dist- Bhagalkote public hearing 16-Nov-23
1.1 Environmental clearance 25-Dec-23
2 LA 30 Oct /30 Nov 23
i 3G approval for RO office-Balance 3 nos village 15-Oct-23 Pending
ii Disbursement to be completed Mr. Basavaj 30-Oct-23 Disburse land-0.105 Ha. (Amdihal village 2 survey no.)
iii ROW possession (Govt & Private) 30 Oct /30 Nov 23
3 Quarry & Crusher 15-Nov-23
i Drilling & Blasting Permission 15-Oct-23 Approval pending
ii Quarry Permission 25-Oct-23 Govt quarry permission under progress
iii Boulder crushing permission at camp location -Qty-20k MT Mr.Bhimrao 24-Oct-23
iv Crushing Start date 15-Nov-23
v CTE & CTO permission 30-Oct-23
4 Borrow Area
i 3000 cum soil approval for Govt + Private (Royalty submission) 12 Oct 20 Oct Pvt Borrow area-Tehsildar permission awaited
Pond ash procurement letter-NTPC-Raichur & Kudgi (Qty-5 Lacks Mr.Bhimrao &
ii Mr Manoj uniyal 19-Oct-23 Pending
Cum from each source)
iii Borrow area permission- 2 Lacs Cum 12-Oct-23 Pending
5 Tree cutting 30-Dec-23
Dist.Bhagalkote-Valuation Completed & Dist. Rauchur-
i Tree cutting valuation to be done (RFO-ACFO-DCFO) 05-Oct-23
Valuation wip
ii NHAI to deposit money with in a 1 week Mr. Bhimrao 12-Oct-23
iii Tree cutting permission 27-Oct-23
iv Tree cutting 30-Dec-23
6 Electric utility shifting
i Joint Inspection to be done 07-Oct-23 Done
6.1 Estimates from the respective sub division
i Ilkal Sub division Mr.Nagindra Sharma 19-Oct-23
Estimation forwarded from SDO to DO for Verification
ii Lingsugur Sub division 19-Oct-23
& Approval
iii Mhaski sub division 19-Oct-23
7 Water utility shifting
i Joint Inspection to be done 8 oct 19 oct Joint verification completed & estimate work in
Mr.Nagindra Sharma &
progress
ii Estimate to be done Mr. Manoj uniyal 15-Oct-23
iii Sub -con finalisation from CO 30-Oct-23
8 CAMP Electric connection
10 KVA temporary
i 07-Oct-23 Done
Cost benefit analysis to be done wrt DG
Mr.Nagindra Sharma &
ii 10 Kva temporary connection 25-Oct-23 Pole fixing & cable laying wip
Mr. Manoj uniyal
iii 650 KW connection with 100 KW connection
iv Connection at site 21 Oct 20 Nov Security deposite done
9 ROW possession (Govt & Private) Mr. Manoj uniyal 30-Oct-23
10 Soil investigation Mr.Sunil 05-Oct-23 4 nos additional bore hole WIP
11 Tempory NA Mr. Ajay manawat 20-Oct-23 Approval pending
12 CTE permission 30-Oct-23
Mr. Ajay manawat WIP
13 CTO permission 30-Oct-23
14 Village panchyat NOC (BP,HMP,WMM etc.) 10-Oct-23 Done
15 Village panchyat/Govt NOC (Borrow earth extraction) Mr. Ravi raju 10-Oct-23 Pending
16 Labour licence 10-Oct-23 Form-3 pending
17 RTO Mr. Bhimrao 15-Oct-23
18 Camp construction
Mr.Nagindra Sharma &
i Temporary Office shifting 15-Oct-23 Done
Mr. Manoj uniyal
ii Staff shifting 15-Oct-23 Done
Project work
1 Identification of priority stretches Mr.Nagindra Sharma 09-Oct-23 Done
3 Design priority Mr. Rajeev Naryal 10-Oct-23 Done
4 CBR testing report Mr.Sunil 13-Oct-23 Done
MS-1 Achievement plan as per Schedule-G along with Qty &
5 Mr.Nagindra Sharma 9 oct 23 oct
material requirement.