Project Name : Footpath


Location :
Appropriation : 100000
Contract Reference Num.: 1006

UNIT PRICE SUMMARY SHEET

I. MATERIALS UNIT UNIT PRICE


Portland Cement bag 250
Crushed Sand Cu. m. 1350
¾” Gravel Cu. m. 1463

II. LABOR UNIT RATE


Construction and Maintenance General daily 716.22
Foreman
Mason daily 483.36
Electrician General Foreman daily 716.22

III EQUIPMENT UNIT RATE


.
Plate Compactor daily 123
Crawler Crane daily 1522

PREPARED BY: RECOMMENDING