Rev-02 S.No Comment Discipline Risk Rating System Sub system Status SPML response Rev -00 SABIC COMMENT- Rev 01 SPML response- Rev 02 SABIC COMMENT- Rev 02
DLP discussion; warranty certificates are not Draft warranty certificate is provided without
1 440 Warranty scope & certificate are not available for staircase pressurization fans. HVAC Non-Critical Ventilation system Staircase pressurization system Open Attached provided Warranty Certificate draft attached PO number and delivery date.
Attached (Refer BMS
Referred Transmittal is not submitted by BMS Enginerring Submittal Chapter -9 Sequence of operation Sequence of operation for Lift well
2 445 Sequence of operation of Lift well pressurization system is missing HVAC Critical Ventilation system Lift well pressurization system Open Enginerring Submittal-TR-
PMT/SPML attached pressurization system is still not provided.
SPML-SABIC-4423-20)
DLP discussion; warranty certificates are not Draft warranty certificate is provided without
3 448 Warranty scope & certificates are not available for Lift Well pressurization fans. HVAC Non-Critical Ventilation system Lift well pressurization system Open Attached provided Warranty Certificate draft attached PO number and delivery date.
EF-5006 & EF-5009 TAB IR list and final acceptance
4 455 EF-5006 IR Code is C its final approval required for same. HVAC Critical Ventilation system Kitchen ventilation system Closed shall be provided Third party TAB report attached
DLP discussion; warranty certificates are not Draft warranty certificate is provided without
5 457 Warranty scope & certificates are not available for Kitchen ventilation fans. HVAC Non-Critical Ventilation system Kitchen ventilation system Open Attached Warranty Certificate draft attached
provided PO number and delivery date.
DLP discussion; warranty certificates are not Draft warranty certificate is provided without
6 464 Warranty scope and certificates are not available for General ventilation fans. HVAC Non-Critical Ventilation system General Ventilation system Open Attached provided Warranty Certificate draft attached PO number and delivery date.
All comments has been closed with Code A for carpark ventilation
7 470 TAB IR list to be updated. All comments need to be closed with Code A for carpark ventilation fans. HVAC Non-Critical Ventilation system Car park Ventilation system Closed Updated TAB IR list Attached Page 3-3 few IR are still not A
fans refer attached update log
DLP discussion; warranty certificates are not Draft warranty certificate is provided without
8 472 warranty scope and certificates are not available for carpark ventilation fans. HVAC Non-Critical Ventilation system Car park Ventilation system Open Attached Warranty Certificate draft attached
provided PO number and delivery date.
Provide Duct, insulation Material details
9 476 Duct, Insulation,, Duct Accessories schedule is missing HVAC Non-Critical Ventilation system General Closed Not Applicable Attached
(Submittal) and Air outlets schedule
There is twin fans both fans
are work accordingly At site and as per TAB report both fans are running All tab reports are as per fan schedule. If any TAB report not correct
10 480 All smoke ventilation T&C report summary need to be replaced with correct data as duty+standby HVAC Critical Ventilation system General Closed
requirement (Refer IFC Fan at various locations please specify the fan Tag number which is need to be correction
Schedule 00-H-2002)
This as per IFC (23 09 93/11) and approved sequence of operation .
Section-2.2: System Operation mention all AHUs discharge coil air (dry bulb) temperature is 12 degree C
11 483 HVAC Non-Critical AHU-FAHU N/A Closed Open Refer the attached IFC (23 09 93/11) and approved sequence
Constant. While IFC Design has variable temperature of few degrees for different AHUs.
operation .
Section-11.1: AHUs/FAHUs FAT & SAT reports are not provided only Vendor-Carrier factory general certificate is
12 490 available. No third party inspection performed! HVAC Non-Critical AHU-FAHU N/A Closed Not Applicable Provide site inspection QA/QC Report QC SAT reports attached
Section-12: Provide Warranty certificate with start and completion date (2 years from startup & commission is DLP discussion; warranty certificates are not
13 491 mentioned from Carrier). HVAC Critical AHU-FAHU N/A Closed Attached provided Warranty Certificate draft attached
14 495 Section-2.1: CAV description is not provided; also verify total numbers given (2,422) of VAVs in building. HVAC Non-Critical VAV N/A Closed Attached CAV description is still not provided Attached
As per approved ITP there no separate T&C for VAV, only
15 502 Section-11: No Testing & Commission report of VAVs are provided. HVAC Critical VAV N/A Open In progress prformance to be done along with BMS system and it is covered in
BMS system
Updated Pump Schedule Primary Pump schedule is not matching with KSB Revised Equipment schedule of DCS Primary CHW Pumps has been
16 503 Section-2.3: Equipment schedule of DCS Primary CHW Pumps has to be revised due to replacement. HVAC Critical CHW Pump & Pipework N/A Closed
attached data sheet and performance curve attached
17 504 Section-2.3: Provide schedule of Valves and gauges including size, model, vendor and location. HVAC Critical CHW Pump & Pipework N/A Closed Attached Valves schedule is still pending Attached
New DCS CHW Primary Pumps model (ETN 250- As per vendor there is no separate IOM for each model, its covered
18 507 Section-3: Provide Installation & Operational Manual (IOM) of replaced DCS Primary CHW Pumps. HVAC Critical CHW Pump & Pipework N/A Closed Attached
150-400) is not mentioned in IOM. all model of ETN series, and ETN series IOM already provided
Section-10: Provide FAT & Testing/ Commission Reports for all CHW Pumps including replaced DCS Primary FAT/SAT & commissioning reports off all CHW
19 509 Pumps. HVAC Critical CHW Pump & Pipework N/A Closed Attached pumps are not provided. Attached
20 511 Section 2.1: Description of DX units serving the Auditorium screen is not mentioned. HVAC Non-Critical DX-Split & VRV N/A Closed Not Applicable Updated Description attached
There is no Zamil DX units installed in this project, only Carrier and
Section 3: Manufacturer Installation & Operational Manual (IOM) of Zamil units & auditorium screen units are
21 516 HVAC Non-Critical DX-Split & VRV N/A Closed Not Applicable Auditorium screen unit to be added Daikin DX units are installed and Carrier and Daikin IOM already
missing.
provided
Section 10: (As Built Drawings) Car Park Ventilation layout level CP-5 The new additional work DX unit that IFC do not show HVAC for level-05 Carpark security room ,
23 521 serves the security room has not been added, it must be added. HVAC Critical DX-Split & VRV N/A Open Attached Provide updated As-Built Drawing ( SPML-FM installed DX Units) Updated & show in final As-Built Drawing
28 528 Section-9: Recommended Spare parts list is not available. Complete part list is provided. HVAC Non-Critical Chiller N/A Closed Attached Recommended Spare parts list is still not provided. Attached
Section-11.1: Single plain page without any duty capacity, stamp/ signature & company name is provided for
34 543 HVAC Critical CRAH/CRAC N/A Open Not Applicable Provide FAT Report of CRAH/CRAC units Attached Single page and serial number provided
FAT. Provide official complete FAT report.
DLP discussion; warranty certificates are not
35 544 Section-12: Provide warranty certificate with start and end date. HVAC Critical CRAH/CRAC N/A Open Attached provided Warranty Certificate draft attached
50 574 Performance test and BMS functionality test for all fans required. HVAC Critical Ventilation System All Ventilation fans Closed BMS functionality & Performance test for all fans has been done. Testing is in progress