Professional Documents
Culture Documents
19 Appendix-7.2.1 LD-P2M2
19 Appendix-7.2.1 LD-P2M2
LD-P M
Land Disturbing Pollution Prevention and Mitigation Measures (LD-P2M2)
Proposed Paper Mill on Part of PT 47766 Mukim Tanjong Duabelas, Daerah Kuala Langat, Selangor Darul Ehsan
1.1 INTRODUCTION
LD-P2M2 document is a pledge made by the Project Proponent to take efforts, measures,
actions, or due diligence in accomplishing the overarching goal of protecting the environment
and in mitigating the environmental impact in the process of implementation of the proposed
development. The focus of the LD-P2M2 is on the prevention, mitigation and control of the
discharge from the development area containing the major pollutant (suspended solids) resulting
from land disturbing activities.
The LD-P2M2 will serve and be read with the LD-P2M2 Plan (ESCP) and other engineering
plans (i.e. development plan, earthwork plan, drainage plan, etc.) or written instructions that may
be issued in relation to development at the subject site.
a) Urban Stormwater Management Manual for Malaysia, MSMA 2nd Edition, Year 2011 by
Department of Irrigation and Drainage Malaysia.
b) Guideline for LD-P2M2 in Malaysia, October 2010 by Ministry of Natural Resources and
Environment, Malaysia and Department of Irrigation and Drainage Malaysia.
The design peak flows for the surface runoff generated from the project site during the
existing condition stage (pre-development), site clearing stage (earthwork and construction
stage) and operation stage (post-development) are assessed by using the following
assumptions:
Q = C. I .A / 360
Where,
C = runoff coefficient;
2) Peak flow occurs when the entire catchment is contributing to the flow.
3) Rainfall intensity is uniform over the entire catchment area and is uniform over a time
duration that equal to the time of concentration, tc.
4) Fitting constants for IDF empirical equation is adopted from the nearest to the site is the
JPS Sg. Manggis (Station ID = 2815001), nearest JPS station from project site.
Summary of the runoff estimation from the project site can be referred in Table 1 and further
detailed calculation is presented in Appendix 1.
Qpeak (m3/s)
Impacted
Project Phases ARI
Areas
5 10 20 50 100
Pre-development 2.223 2.471 2.745 3.944 4.382
Impacted
During development 2.779 3.088 3.431 4.733 5.259
Area 1
Post development 5.003 5.559 6.176 7.494 8.326
Pre-development 0.061 0.068 0.076 0.109 0.121
Impacted
During development 0.077 0.085 0.095 0.131 0.145
Area 2
Post development 0.138 0.153 0.170 0.207 0.230
A = R x K x (L x S) x C x P
• A represents the potential long-term average annual soil loss in tons per hectare per year. This is
the amount, which is compared to the "tolerable soil loss" limits.
• R is the rainfall and runoff factor by geographic location. The greater the intensity and duration of
the rain storm, the higher the erosion potential.
• K is the soil erodibility factor (refer to Soil Investigation Report). It is the average soil loss in
tons/ha per unit area for a particular soil in cultivated, continuous fallow with an arbitrarily selected
slope length and slope steepness. K is a measure of the susceptibility of soil particles to
detachment and transport by rainfall and runoff. Texture is the principal factor affecting K, but
structure, organic matter and permeability also contribute.
• LS is the slope length-gradient factor. The LS factor represents a ratio of soil loss under given
conditions to that at a site with the "standard" slope steepness of 9% and slope length of 22.1
metres. The steeper and longer the slope, the higher is the risk for erosion.
• C is the crop/vegetation and management factor. It is used to determine the relative effectiveness
of soil and crop management systems in terms of preventing soil loss. The C factor is a ratio
comparing the soil loss from land under a specific crop and management system to the
corresponding loss from continuously fallow and tilled land. The C Factor can be determined by
selecting the crop type and tillage that corresponds to the field and then multiplying these factors
together. The C factor resulting from this calculation is a generalized C factor value for a specific
crop that does not account for crop rotations or climate and annual rainfall distribution for the
different agricultural regions of the country. This generalized C factor, however, provides relative
numbers for the different cropping and tillage systems; thereby helping you weigh the merits of
each system. For this Project, C = 0.35 (existing condition); and 1.0 (bare earth).
• P is the support practice factor. It reflects the effects of practices that will reduce the amount and
rate of the water runoff and thus reduce the amount of erosion. The P factor represents the ratio
of soil loss by a support practice to that of straight-row farming up and down the slope. The most
commonly used supporting cropland practices are cross slope cultivation, contour farming and
strip-cropping. For this Project, P = 0.6 (existing condition); 1.0 (bare earth); 0.18 to 0.59 (with
proper BMPs).
All values of parameters in this equation will be obtained using data that has been obtained
for Malaysia condition. All the relevant data can be referred in the “Guideline for LD-P2M2 in
Malaysia” published by Ministry of Natural Resources and Environment and Department of
Irrigation and Drainage Malaysia (October, 2010).
Based on the Department of Agricultural Land Erosion Risk Map, the erosion risk categories
are as follows:
For the course of this proposed project site, the soil loss projection based on four (4)
scenarios were developed to identify the prone of soil erosion from each earthwork impacted
site for each development stage. Table 2 shows the summary of soil loss projection.
1. Existing condition (assuming the project site is covered mainly of minor bushes);
3. After development with mitigation measures (earthwork controlled with proper BMPs,
e.g. sediment basin, check dams, sediment trap).
Impacted Area 1
Existing 18000 0.055 0.0807 0.030 0.600 1.438 Low
Earthwork Above
18000 0.050 0.0667 1.000 1.000 60.058
(Uncontrolled) average
Earthwork
18000 0.050 0.0667 1.000 0.500 30.029 Average
(Controlled)
Post
18000 0.050 0.0667 0.050 0.500 1.501 Low
Construction
Impacted Area 2
Existing 18000 0.050 0.0630 1.000 1.000 1.358 Low
Earthwork Above
18000 0.050 0.0630 1.000 0.500 56.700
(Uncontrolled) average
Earthwork
18000 0.050 0.0630 0.050 0.500 28.350 Average
(Controlled)
Post
18000 0.050 0.0630 1.000 1.000 1.418 Low
Construction
*Note: Refer also to Appendix 1 for the detail soil loss assessment.
After the completion of the construction phase/during post construction stage, soil erosion
and its affect will be reduced significantly, as the site will be paved to a uniform platform
level.
The Modified Universal Soil Loss Equation (MUSLE) is perhaps the most frequently used
equation for sediment yield estimation. It is developed to calculate the sediments yields of a
catchment as a result of a specific storm event. The equation is presented in the form: -
Sediment
Project Site
V (m3) Q10 (m3/s) K LS C P Yield, Y
Condition
(tonne)
Impacted Area 1
Existing 5393.51 2.471 0.0550 0.0807 0.03 0.60 1.4612
Earthwork 7881.38 3.088 0.0500 0.0667 1.00 1.00 85.4935
(Uncontrolled)
Earthwork 9869.54 5.559 0.0500 0.0667 1.00 0.50 67.3852
(Controlled)
Post Construction 9869.54 5.559 0.0500 0.0667 0.05 0.50 3.3693
Impacted Area 2
Existing 113.45 0.068 0.0550 0.0762 0.03 0.50 0.0177
Earthwork 164.28 0.085 0.0500 0.0630 1.00 1.00 1.2373
(Uncontrolled)
Earthwork 180.90 0.153 0.0500 0.0630 1.00 0.50 0.9075
(Controlled)
Post Construction 180.90 0.153 0.0500 0.0630 0.05 0.50 0.0454
*Note: Refer also to Appendix 1 for the detail sediment yield estimation
The amount of sediment yield during earthwork-controlled stage is considered very minimal.
The outline of the LD-P2M2 for the establishment of the project site is described in Section
1.5.1 and 1.5.2.
• Two separate access points will be provided to allow for an effective management of
transport throughout the earthwork and construction process.
• Wash trough/wheel washing facilities with sediment trap shall be located near to the 2
proposed access points of the project site.
• Temporary earth drain shall be constructed to direct all surface runoff from the stabilised
area around the proposed mill site area to the proposed sediment basin, i.e. SB-1 prior
to discharging to nearby river (i.e. Sg. Langat).
• Rock Filter Check dams shall be installed at every 20m along the temporary earth
drains at each turning to reduce flow velocity and promote sedimentation within the
proposed project site.
• Domestic waste from the project site shall be temporarily stored at the Solid Waste
Management (SWM) area before being disposed to the nearby local approved disposal
site by local authority.
• The overall LD-P2M2 Site Plan of the proposed Project site can be referred in Figure 1.
• Wash trough/wheel washing facilities with sediment trap shall be located near to the
proposed access point of the project site.
• Temporary diversion channel/ earth drain shall be constructed to direct all surface runoff
from the stabilised area around the proposed new gas station to the proposed sediment
trap, i.e. ST-1 prior to discharging to nearby river (i.e. Sg. Langat).
• Rock Filter Check dams shall be installed at every 20 m along the temporary earth
drains at each turning to reduce flow velocity and promote sedimentation within the
proposed project site.
• Domestic waste from the project site shall be temporarily stored at the Solid Waste
Management (SWM) area before being disposed to the nearby local approved disposal
site by local authority.
• The overall LD-P2M2 Site Plan of the proposed Project site can be referred in Figure 1.
• The LD-P2M2 Plan shall be read in conjunction with the engineering plans, earthwork
plans, topographical survey plan, drainage plan or any other written instructions that
may be issued in relation with the Project.
• No works shall commence on site until the earthwork plans and Erosion and Sediment
Control Plan (ESCP) have been approved by the authorities and DID, respectively.
• All contractors shall be informed of their responsibilities in minimizing the potential for
soil erosion and pollution from the earthwork and construction works.
• After the site is stabilised, all temporary BMPs shall be removed and permanent
vegetations or structures shall be installed on the disturbed areas.
Temporary diversion channel or earth drain may be used to divert off-site runoff around the
construction site, divert runoff from stabilised areas around disturbed areas, and direct
runoff into sediment basins. Diversion channels should be installed when the site is initially
graded and remain in place until permanent BMPs are installed.
The temporary drainage system features are designed for hydraulic efficiency and also for
ease of maintenance. The sizing of the channel is based on Manning’s Formula (MSMA,
2011) while the runoff estimation is based on the Rational Formula (MSMA, 2011).
a) Design Storm - First 40mm rainfall for site < 2 year construction
period
- First 50mm rainfall for site ≥ 2 year construction
period
b) Maximum Contributing - 0.4 hectares
Area
c) Hydraulic For any point along the fence,
- Concentrated flow shall not exceed 50 l/s
- Maximum water depth shall not exceed 600 mm.
d) Sitting of facility - Shall not be installed in areas receiving concentrated
flow, i.e. stream or ditches.
- Maximum length of each fence segment shall not
exceed 30m.
- The at least 1 m from ends of each segment shall be
turned uphill to prevent runoff from flowing around the
fence.
e) Slope - Slope draining to fence shall be 1:1 or flatter.
- Length of draining to fence shall not exceed 60m
f) Storage Area - Storage area to be provided behind the fence.
- Approximately 280 m2 per hectar of contributing area
is required
Rock filter check dams for this Project shall be proposed along the temporary drain prior to
any discharges into any main culverts.
Sediment basin/trap is designed to collect and store sediment from the site clearing and/or
for extended periods of time before re-establishment of permanent vegetation and/or
construction of permanent drainage structures. The basin is a temporary measure (with a
design life of 12 to 18 months) and is maintained until the site is permanently protected
against erosion. It will be located at the lower area of the project site.
Based on the MSMA guidelines, there are two (2) types of sediment basin/trap, namely Dry
Sediment Basin and Wet Sediment Basin. The type of basin to be adopted is dependent on
the nature of the soil material. In this development, Dry Sediment Basin is used since Type
A1 soil (sandy loam) is encountered.
The design of sediment basin/trap is based on Table 12.17 of MSMA 2nd Edition, Year 2012
which requires the following criteria to be met: -
b) The basin/trap length to settling depth ratio should be less than 200:1.
c) The basin/trap length to width ratio should be greater than 2:1 to prevent short-
circuiting.
d) Side slopes should not be stepper than 2 (H): 1 (V) to prevent sloughing.
e) The settling zone should be at least 0.6 m deep to contain runoff and allow suspended
sediment to settle.
f) The sediment storage zone should be at least 0.3 m deep to store settled sediment until
the basin/trap is cleaned out.
The proposed sizing of the sediment basin/trap for this Project is summarized in Table 5.
1 According to the Hydrological Soil Group as per Table 12.16, MSMA (2012)
The typical BMPs construction details for the proposed Project are as depicted in Figure 2 to
Figure 5.
Figure 2: Construction Entrance Stabilisation (CES) with Wash Bay/Wheel Wash Facilities
The Project Manager should assign on-site staff (i.e. Environmental Officer) to maintain
constant vigilance over the sedimentation status of sediment basin/trap, check dams, etc.
installed within the Project Site. If these installations are not functioning properly, the Site
Environmental Officer should be notified immediately. The Environmental Officer shall
ensure that the sediment containments are inspected, maintained routinely and work
effectively.
Proposed site for monitoring of water quality is to be located at the discharge point of the
sediment basin/trap. Parameter to be monitored is mainly Total Suspended Solids (TSS)
and Turbidity. The Project Manager should be notified on a regular basis the performance of
the water quality at this point and instruct the Environmental Officer to carry out
maintenance works when necessary.
A qualified person will be required to oversee the installation and maintenance of all LD-
P2M2 measures on site. The responsible person will ensure that:
Proposed maintenance programs and the maintenance requirement for the proposed BMPs
are shown in Table 6 and Table 7.
1.8 LD-P2M2
1.8.1 Soil Erosion
The soil erosion rate under existing condition is projected to be low at the earthwork impacted
sites. Under development condition, the soil loss rate is projected to be average if no erosion
control measures are taken as most of the earthwork activities have been completed earlier. Soil
erosion can be effectively reduced by the adoption of mitigation measures such as sediment
basin/trap and diversion channel for runoff to divert runoff from the work areas. Such measures
are essential on major construction sites to facilitate the construction activities as well as to
control erosion.
For soil erosion, appropriate mitigating measures are deemed necessary to reduce the potential
risk posed during project development and post development. The potential soil loss will be
minimised by adoption of the following measures:
• Design and construction planning will consider hydrological and climatic conditions
experienced in the area particularly the rainfall and surface runoff patterns. Land clearing
during the monsoon season will be minimised.
• Planting of grass and suitable cover crops will be used to protect newly cleared area against
soil erosion. Legumes are preferred as they are able to colonise bare areas quickly and also
improve the nitrogen status of the soil, which aids other vegetation growth.
• The provision of diversion channel and toe drain to divert the runoff from the impacted areas
to the proposed sediment basin/trap prior to discharging into the river nearby (i.e. Sg.
Langat) is deemed necessary to reduce the total bed and suspended sediment load to the
stream.
• A detail LD-P2M2 plan (ESCP) for soil management and control with specific measures for
incorporating temporary and permanent measures during earthworks, construction and
during completion stage of the Project will be prepared and submitted to Department of
Irrigation and Drainage (DID). This plan will form part of the requirements of the contract
agreement for contractors undertaking works in the Project area.
• A temporary earth drain is proposed around the proposed mill site and hostel areas
(impacted area 1 and impacted area 2) together with rock filter check dams to divert runoff
from the project site to the proposed sediment basin (SB-1) and sediment trap (ST-1) as
illustrated in Figure 1. The detail design of the BMPs for this Project shall be assessed
separately and submitted to DID Selangor for final review and approval.
Hydrologic events are described by stating the Annual Exceedance Probability (AEP) or the Average
Recurrence Interval (ARI). The AEP is the probability that an event of specified magnitude, or volume and
duration, will be exceeded in a time period, is the average length of time between events that have the same
magnitude, or volume and duration. A flood with a discharge of say 50m3/s may have an AEP of 0.01, meaning
that on the average there is a 1% chance that a flow of 50m3/s will be equally or exceeded in any year.
1) Impacted Areas
Impacted Areas
No Project Site
Hectares (Ha) Acres (Ac)
i) Impacted Area 1 31.52 77.887
ii) Impacted Area 2 0.870 2.150
TOTAL 32.390 80.037
Impacted Areas Project Phases Type of drain/ pipe C L (m) V (m/s) V (m/min) td (min)
Peak Runoff
Peak Runoff
CHEMSAIN KONSULTANT SDN. BHD. Dwg. No. : Date : 21/11/2019
Estimation
Consulting Engineers Designed by : Terence K.C Lee
Project : ESCP for Jinxing Holdings (M) SB Checked by : Terence K.C Lee Remark :
Reference Calculation Output
Sediment Yield
21/11/2019 Estimation with
CHEMSAIN KONSULTANT SDN. BHD. Dwg. No. : Date :
MUSLE
Consulting Engineers Designed by : Terence K.C Lee
Project : ESCP for Jinxing Holdings (M) SB Checked by : Terence K.C Lee Remark :
Reference Calculation Output
The Modified Universal Soil Loss Equation (MUSLE) is used to estimate the sediment yield of this Project as a result
specific storm event. The empirical relationship is expressed by the following eqution:
a) Design Storm
Design Storm
Catchment Area,
Impacted Area Project Phases Storm (mm) (2) Tc (min) (3) duration, I10 (mm/hr) (5) Q10 (m3/s) (6)
(1) ha
D (min) (4)
1) Introduction
All procedures and calculations were in accordance with references from the Guideline for Erosion and
Sediment Control in Malaysia (Guideline, 2010) and the Urban Stormwater Management Manual for
Malaysia (Manual Saliran Mesra Alam Malaysia-MSMA, 2011). Universal Soil Loss Equation (USLE) as
shown below will be used to assess the erosion risk of the site under 4 conditions:
a) Existing (undisturbed)
b) Disturbed and Uncontrolled (no ESCP)
c) Disturbed but Controlled (with ESCP)
d) During Operation/ Post Construction
Figure 12.5
(MSMA 2)
K (tonnes.hr/
Series Layer Texture HSG
MJ/ mm)
Impacted Area 1
Impacted Area 2
For existing (undisturbed) condition, erosion took place on the ground surface hence the concerned soil
layer is measuring between 1.50 to 1.95 m depth. Meanwhile, for disturbed condition (uncontrolled and
controlled), the soil layer is represented at 3 m depth assuming earthwork activities have removed the
top layer of the soil hence exposinig the lower soil layer. The K factor determination is further
summarized as below:
Table 12.5 Existing Grass buffer strips (0 to 10% basin slope) 0.60
(MSMA 2) Earthwork (Uncontrolled) Bare soil 1.00
Impacted Area 1
Earthwork (Controlled) Sediment basin 0.50
Substituting the the values of R, K, LS, C and P into Equation 12.1 gives ,
A
Impacted Area Project Site Condition R K LS C P (tonnes/ha/y
r)
Existing 18000 0.055 0.0807 0.030 0.600 1.438
Earthwork
18000 0.050 0.0667 1.000 1.000 60.058
Impacted Area 1 (Uncontrolled)
Earthwork (Controlled) 18000 0.050 0.0667 1.000 0.500 30.029
Post Construction 18000 0.050 0.0667 0.050 0.500 1.501
Existing 18000 0.055 0.0762 0.030 0.600 1.358
Earthwork
18000 0.050 0.0630 1.000 1.000 56.700
Impacted Area 2
(Uncontrolled) ESC reduce the
amount of soil
Earthwork (Controlled) 18000 0.050 0.0630 1.000 0.500 28.350
loss thus
Post Construction 18000 0.050 0.0630 0.050 0.500 1.418 acceptable.