Quiz 4 - S-Curve Project - Attempt Review

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

16/10/23, 10.

25 Quiz 4: S-Curve Project: Attempt review

WRAP APPRENTICESHIP PROJECT MANAGEMENT - MK 2: MANAJEMEN PROYEK


TOOLS AND TECHNIQUE TI-44-22
Dashboard / My courses / FAKULTAS REKAYASA INDUSTRI (FRI) / PRODI S1 TEKNIK INDUSTRI (FRI) / 2324/1 / UPI4B3-TI-44-22

/ Membuat S-Curve Project / Quiz 4: S-Curve Project

Started on Monday, 16 October 2023, 10:23 AM

State Finished

Completed on Monday, 16 October 2023, 10:24 AM

Time taken 1 min 41 secs

Marks 4.00/5.00

Grade 8.00 out of 10.00 (80%)

Question 1

Correct

Mark 1.00 out of 1.00

A horizontal bar chart that shows project tasks against a calendar is called

Select one:

a. milestone

b. Gantt chart 

c. PERT chart

d. goal

The correct answer is: Gantt chart

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=7514715&cmid=3196733 1/3
16/10/23, 10.25 Quiz 4: S-Curve Project: Attempt review

Question 2

Correct

Mark 1.00 out of 1.00

At a minimum, the SoW document should clearly detail, EXCEPT:

Select one:

a. Resource Allocation 

b. Purpose & Scope

c. Milestones & Deliverables

d. Schedule & Requirement

The correct answer is: Resource Allocation

Question 3

Incorrect

Mark 0.00 out of 1.00

It provides high-level overarching project information and defines detailed deliverables, standards, criteria, and
requirements for each phase. It is a simple definition of..

Select one:

a. Project Initiating

b. Statement of Work

c. Project Plan 

d. Work Breakdown Structure

The correct answer is: Statement of Work

https://lms.telkomuniversity.ac.id/mod/quiz/review.php?attempt=7514715&cmid=3196733 2/3
16/10/23, 10.25 Quiz 4: S-Curve Project: Attempt review

Question 4

Correct

Mark 1.00 out of 1.00

What Should A Statement Of Work Contain?

Select one:

a. Milestones & Deliverables

b. All of above 

c. Schedule & Requirement

d. Purpose & Scope

The correct answer is: All of above

Question 5

Correct

Mark 1.00 out of 1.00

When creating a WBS, we need to follow the best practice. One of them is to Ensure there is no overlap between
components within the WBS. What is it called?

Select one:

a. None of above

b. Be Consisten

c. Make everything mutually exclusive 

d. Focus on deliverables

The correct answer is: Make everything mutually exclusive