Professional Documents
Culture Documents
27 IndexStudyofPerception
27 IndexStudyofPerception
27 IndexStudyofPerception
net/publication/318311931
CITATIONS READS
7 385
1 author:
SEE PROFILE
All content following this page was uploaded by Kennedy Chibuzor Onyelowe on 20 July 2017.
Onyelowe, K. C.
ABSTRACT
Most of the road pavements in developing countries of Africa are in deplorable condition and Nigeria being one of these
countries is not an exception. The present statistical research work has discovered 51 causes of road pavement failures which
have been assessed and analyzed statistically from the perceptions of contractors and consultants in the industry through a
means of responses, severity index and ranking which lead to the development of an agreement based on the analyzed factors
by both parties through a means of null hypothesis. By the assessment and agreement fully depicted in the table and the null
hypothesis analysis carried out, the contractors and consultants collectively highlighted several factors as the intricate causes
of road pavement failures in Nigeria. From Table 1, it has been shown that Contractors ranked “poor maintenance
policy/culture”1st while consultants had ranked it 5th. Further, “poor design and construction” and “inadequate strength in
surfacing and base” were equally ranked 2nd by Contractors whilst these were ranked 3rd and 4th respectively by Consultants.
Finally, “poor highway facilities” and “inadequate compaction before opening to traffic” were ranked 3 rd by Contractors whilst
Consultants on their part ranked these 2nd and 12th respectively. However, “defects caused during construction due to poor
construction quality” and “inferior asphalt mix design” that had been ranked 1 st by Contractors were ranked 8th and 5th
respectively by Consultants thereby recommending prompt attention by road workers, highway management and maintenance
agencies and government to look into these important critical factors causing road pavement failures in Nigeria, outline and
enforce ways of tackling them. Finally, the test of null hypothesis carried out went further to indicate the degree of agreement
between contractors and consultants in their assessment of the identified causes of road pavement failure in south eastern
Nigeria.
Key words: Index study, south-eastern, contractors, consultants, perception, pavement failure.
1. INTRODUCTION And this is the more reason why this research work is
undertaken to investigate from the perspective of the
The rate of road pavement failures in developing countries major players; contractors, consultants and construction
like Nigeria has reached a disastrous stage in recent times firms the root causes of the road pavement failures in
that it now claims lives and properties of road users. It has Nigerian roads. A road pavement section may be
made these developing countries loose properties worth generally defined as the structural material placed on the
billions of dollars through the failures and if nothing is natural soil(sub-grade), designed to withstand traffic
done, they will stand the risk of losing more. In Nigeria, loading and the action of the climate with minimal failures
“the annual loss due to bad roads is valued at N80 billion, and in the most economical way (Sultan and Mohmood,
while additional vehicle operating cost resulting from bad 2013). In asphaltic pavement, it is typically a multi-layered
roads is valued at N53.8 billion, bringing the total loss per system comprising the sub-grade (support), sub-base,
annum to N133.8 billion”. This figure does not take into base course and surfacing. The principal function of road
account the man-hour losses in traffic due to bad roads pavements is to receive load from the traffic and transmit
and other emotional and physical trauma people go it through its layers to the sub-grade (Sultan and
through plying the roads and the consequent loss in Mohmood, 2013).The aim of this project work is to reveal
productivity (NFMW, 1970). Over the years, considerable first hand information from the road contractors,
interest has been shown by the consultants & construction firms as the main actors in the
road constructions and maintenance process, on the root
Nigerian government in the construction and rehabilitation causes of road pavement failures in Nigerian roads
of roads, but the issue is “to what extent has their interest through the analysis of the diverse possible factors that
been driven to achieve desired results?” may lead to road pavement failures.
INDEX STUDY OF THE PERCEPTION OF CONTRACTORS AND CONSULTANTS ON THE CAUSES OF ROAD PAVEMENT
FAILURE IN SOUTH-EASTERN NIGERIA. Onyelowe, 2015
In the works carried out by previous researchers (Okigbo, from previous researchers and interviews from Nigerian
2012; 2013) on “causes of highway failures in Nigeria”, road contractors and consultants, a collection of 51 factors
they exposed the causes and effects of highway failures were identified from the different researchers and
in Nigeria. A researcher (Ette, 2010),brought to limelight contractors as possible factors causing road pavement
the condition of national road network as at 1999, he said failures on Nigerian roads. A questionnaire was designed
that of the National Road Network, 27% was good, 38% with these 51 factors causing road pavement failures. The
fair and 35% poor which really shows a very bad report of questionnaire was then sent out to about 52 respondents
the overall national road network. A road that is functional who were all experienced engineers and surveyors in
should possess the following characteristics; neighbourhood of contractors and consultants in the
1. The road should be able to give an all weather Nigerian road constructions, maintenance and
support to vehicles. That is, it should bear and rehabilitations industries. The Severity Index for all the
distribute wheel loads within the bearing capacity of identified causes of pavement failure was conducted as
the sub grade soil. shown in Eq.1 (Al-Hazmi and Asaf, 1987);
2. It should boast of adequate drainage facilities. This
∑𝑖=4
means that there should be free flow of water and 𝑆𝑒𝑣𝑒𝑟𝑖𝑡𝑦 𝐼𝑛𝑑𝑒𝑥 (𝐼𝑠) = 𝑖=0 𝑎𝑖 𝑥𝑖
(1)
∑𝑖=4
𝑖=0 𝑥𝑖
flood along its drainage system so that water will not
flow back on to the pavement to cause one problem Where ai = constant expressing the weight given to the ith
or the other. responses,
3. It should provide adequate skid resistance. This
ai = 0, 1, 2, 3 & 4 for i = 0, 1, 2, 3 & 4 respectively.
implied that it should provide enough frictional
a0 = 0 is equivalent to “does not cause”
adhesion to vehicle tyres especially during
a1 = 1 is equivalent to “disagree”
acceleration, deceleration and on curves.
a2 = 2 is equivalent to “slightly agree”
4. There should be adequate highway geometrical
a3 = 3 is equivalent to “moderately agree”
facilities like good geometric design of road widths,
a4 = 4 is equivalent to “strongly agree”
intersections, side-slopes, sight distance etc that
make for easy movement and passing with safety at
While Xi is the variable expressing percentage of degree
established level of service.
of importance of each factor,
In general, previous works have identified the following
X0 = Percentage of frequency of “does not cause”
causes of road pavement failure thus; Poor Design and
X1 = Percentage of frequency of “disagree”
Construction, Heavy Traffic, Poor Maintenance Culture,
X2 = Percentage of frequency of “slightly agree”
Poor Highway Facilities, Poor Laboratory and In-situ Tests
X3 = Percentage of frequency of “moderately agree”
on Soil, Use of Low Quality Materials, Poor Workmanship,
X4 = Percentage of frequency of “strongly agree”
Poor Supervision, Low Knowledge Based, No Local The spearman’s correlation coefficient was then carried
Standard of Practice, Inadequate Sanctions for Highway out to ascertain the degree of agreement and deviation
Failures, Not Co-Opting Local Professional Bodies in between the two parties under consideration for the
Highway Design, and Construction and Maintenance causes of pavement failure identified with the expression
(Okigbo, 2012; Oguara, 2010; Igomu, 2011) and their in Eq. 2 (Inyama, 1995);
consequent effects as; Accidents, Increase in Faulty
Vehicles, Waste of Journey Time, Traffic Congestion, Aid 6 ∑ 𝐷2
to Crime (Robbery), Soil Erosion, Adverse Economic 𝜆 =1−[ ] (2)
𝑛(𝑛2 −1)
Development etc (Igomu, 2011; Obi, 2010; Bashir, 2012;
Onyelowe, 2011;Nnanna et al., 2003; Ogundipe, 2001). Where D= the difference between the rankings of each
factor in both contractors and consultants,
2. RESEARCH METHOD n= the number of ranked factors.
This research work focuses mainly on the factors Further, a t-test null hypothesis analysis was conducted to
influencing road pavement failure in Aba, Owerri, establish the degree of agreement between
Umuahia and Enugu. Based on in-depth literature review
contractors and consultants on the causes of road Table 1 shows the responses and the results of the survey
pavement failure identified from study. carried out and their perspective rankings gotten through
the severity index (Is) of the respective factors from 27
∑D2 = 3651
100
S
e90
v80
e
r 70
i
t 60
y Contractors
50
I
n40 Consultants
d
e30
x
20
10
0
1 3 5 7 9 11 13 15 17 Pavement
19 21 23 25Causes
27 29 31 33 35 37 39 41 43 45 47 49 51
TEST OF NULL HYPOTHESIS (HO) USING T – TEST causes of road pavement failure in Nigeria based on the
The spearman’s rank correlation coefficient between the analyzed factors.
contractors and consultants is given by
6 ∑ 𝐷2
𝜆 =1−[ ]
𝑛(𝑛2 −1)
4. CONCLUSION
But ∑ 𝐷2 = 3651 (from Table 1)
Road pavement failure is apparently of incessant
𝑛 = 51
6𝑋3651
occurrence in the Nigerian road sector. And as such, it is
𝜆 =1−[ ] = 1- 0.165= 0.835 a critical situation for the Nigerian road sector because of
51(512 −1)
the high cost of construction of new roads and
The null hypothesis, HO states that CONTRACTORS and maintenance of existing roads and routes.
CONSULTANTS do not agree on the severity index CONTRACTORS and CONSULTANTS have a good
ranking of the factors causing road pavement failures. knowledge and capacity to highlight the areas of problems
The t – test was used for this hypothesis. in the sector. And going by the analysis so far, which has
Confidence limits = 95% been fully studied through the null hypothesis showing the
Degree of significance α = 0.05 agreement between the CONTRACTORS and
Decision rule: if -
𝑡∝ 𝑡
< t < ∝ (Accept HO) CONSULTANTS to the analyzed factors, the two parties
2 2
𝑡 agree on the identified factors but have the greatest
If t > ∝ (reject HO)
2 variance on factors 26, 35 and 40 as shown in Figure 1.
Using t = λ [√(n – 1)] where λ = 0.835 and n = 51
t = 0.835√ (51 – 1) = 5.90 And by this agreement from the analysis, it could be
From t – test table,
𝑡∝
= 1.8922 [14] observed that both parties in agreement are collectively
2
𝑡∝ recommending the attentions of road workers,
Thus t > (Reject HO) (Where Ho states that Contractors
2 maintenance agencies and government to look into these
& Consultants do not agree on the Severity index Ranking factors as the intricate causes of road pavement failures
of the factors). which includes
Negligence/non-existence of highway facilities
Therefore Rejecting “Ho” Implies that both including drainage systems and manholes, channels
CONTRACTORS and CONSULTANTS agree on the and other accessories like handrails and
curbs because of the poor design and the high cost “Poor maintenance policy for already built roads” that
of construction and maintenance as shown in Table was ranked 1st by contractors with index of 94.5% as
1 as consultants ranked it 2nd with index of 91%. shown in Table 1, lack of adequate sanction systems,
[3] Ette, I.E. (2010). Challenges of sustainable [14] Sultan, T. and Mohmood, S. (2013). Causes of
infrastructural development. Book of proceedings, 19th cracks and deterioration of pavement on highways in
Engineering Assembly, Council for the Regulation of Jordan from contractors perspective, Paper from Civil
Engineering in Nigeria. and Environmental Research Vol.3.No.10.