Professional Documents
Culture Documents
Saic H 2010
Saic H 2010
00 31-May-18
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Contractor Qualifications - Coating Personnel
SAIC-H-2010 15-Jul-18 COATING-
Certification (In-Kingdom Field Application Only)
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements (This checklist applies to all Coatings Applicator Personnel as listed below)
Every protective coatings applicator personnel has been qualified & SAEP-316,
A1
certified prior to work and has a SA Coating Certification Card. Para. 5.2
The Coating Certification Card should indicate the personnel name, SAEP-316,
A2
picture and all the information specified in Appendix G. Para. 5.3
The Coating Certification Card can be tracked in the SAP system. SAEP-316,
A3
Para. 5.4
SAEP-316,
A4 The Coating Certification Card is properly signed within the validity period.
Para. 5.4
Personnel involved in protective coating activities has been qualified and SAEP-316,
A6
certified to perfom their task. Para. 5.1
REMARKS:
REFERENCE DOCUMENTS:
1. SAEP-316, Performance Qualification of Coating Personnel, (31 July 2016)