Professional Documents
Culture Documents
GB1516 Sac 240 CV RP 0006 - A
GB1516 Sac 240 CV RP 0006 - A
Iraq
DOCUMENT DETAILS
EMPLOYER CONTRACT : 1516-23-BD-850-00
NO.
PROJECT TITLE : EPC for Installation of PWT, Republic of Iraq
REVISION DETAILS
REVISION RECORD
Hold
Para. Description of Hold
No.
EPC for Installation of PWT, Republic of Iraq
DESIGN REPORT OF OILY WATER SYSTEM
Doc. No.: GB1516-SAC-240-CV-RP-0006 Rev.: A Page 3 of 10
TABLE OF CONTENTS
1. INTRODUCTION ..................................................................................................................... 4
1.1 PROJECT Reference Documents ............................................................................................ 4
2. Definition of Oily water sewer system .................................................................................. 5
3. Oily Water Drainage System ................................................................................................. 5
3.1. Manholes ................................................................................................................................. 6
3.2. Vents ....................................................................................................................................... 7
4. Sizing Criteria for Underground Pipe Systems .................................................................... 7
4.1 Hydraulic Calculations .......................................................................................................... 7
EPC for Installation of PWT, Republic of Iraq
DESIGN REPORT OF OILY WATER SYSTEM
Doc. No.: GB1516-SAC-240-CV-RP-0006 Rev.: A Page 4 of 10
1. INTRODUCTION
The purpose of this report is to describe the calculations of velocity and discharge of closed
pipe sewer system and the minimum requirements for Underground services to works to
be performed as a part of the PROJECT.
Headers are sewer lines connecting manhole to manhole and carrying combined
effluents from collectors and/or sub-headers.
Sub-headers are sewer lines collecting the effluent from two or more sub-collectors
discharging to manholes on mains.
Sub-collectors are sewer branches collecting effluent from individual inlets such as
drains and catch basins.
Open channel floor or pavement drains are continuous troughs or trenches collecting
surface drainage discharging to the sewer system.
Catch basins are used to collect surface drainage and process wastes individual
drainage areas and to trap sediments at the point nearest of the source.
Manholes are used in sewers as junction points and sediment traps and to provide
access for maintenance and inspection
Seals (minimum 150mm hydraulic) are used to prevent vapor emission out of inlets and
to isolate the various parts of a sewer system preventing vapor travel and spread of fire
or explosion.
Kerbed (or curbed) areas are pipes with raised curbs which control spillage and
drainage of storm, process and fire water.
Vents are pipes open to the atmosphere to prevent blowing of seals by pressure buildup
The oil which will be contained in the bunded area of tanks would be controlled by the
valve before discharging into oily water sewer system.
The effluents collected in this system shall be led via underground pipes to the API
separator of the CPF for treatment. The velocity of flow in sanitary pipe based on the
design flow shall be maximum 1.5 m/s and min 0.9m/s
Oily water system shall be designed for the maximum of the following:
• Discharge from Rain + process flow to be eventually added
• Discharge from Fire water + process flow to be eventually added
Oily water drainage pipes are connected at tie-in points by each area. Tie-in points
are as per tie-in schedule.
Chemical drains shall not be done to OWS system and shall be trucked out. Chemical
pits shall be covered with acid resistant tiles and Acid proof mortar lining.
3.1. Manholes
For oily sewer system, all inlet pipes in a single compartment manhole shall be with a
submerged connection, which provides a hydraulic seal of minimum 150 mm in order
to avoid propagation of fire and/or gas. In Process/Utilities areas, all cover of closed
drain system manholes shall be sealed. All manholes with water seal shall be vented
by 4” pipes. In concrete paved areas, top of manholes shall be installed flush with the
paved surface. In other areas, top of manholes shall be approximate 150 mm above
grade. For storm water drainage system, Manholes shall be equipped with holed
cover for ventilation.
Systems handling flammable, toxic or lethal liquids or gases shall be provided with
solid vapor-tight sealed manhole covers.
EPC for Installation of PWT, Republic of Iraq
DESIGN REPORT OF OILY WATER SYSTEM
Doc. No.: GB1516-SAC-240-CV-RP-0006 Rev.: A Page 7 of 10
3.2. Vents
Vents shall be provided in any manhole where the inlet lines are liquid sealed. The
highest manhole in a system shall also be vented.
For size of pipe for oily water sewer Chezy’s equation is used as mentioned in FEED design
and level of manholes and dimension are represented in detailed drawing of manhole
Gravity, partially filled pipes & ditch shall be designed using the following Chezy
formula:
Q = 3600 x S x V
V = C (RI) 0.5
Where:
V - Velocity of effluent (m/s).
The drainage pipe shall be sized to flow at 100% of the internal height of pipe.
Calculation for 4-inch pipe at slope of 1:200 is attached in Annexure-I.
EPC for Installation of PWT, Republic of Iraq
DESIGN REPORT OF OILY WATER SYSTEM
Doc. No.: GB1516-SAC-240-CV-RP-0006 Rev.: A Page 9 of 10
ANNEXURE A
EPC for Installation of PWT, Republic of Iraq
DESIGN REPORT OF OILY WATER SYSTEM
Doc. No.: GB1516-SAC-240-CV-RP-0006 Rev.: A Page 10 of 10
Date: 22-Sep-2023
Roughness Coefficient of
= 0.05
Pipe ( γ )