Casale Strategies For Complete Ammonia Plant Revamping, The Example of Al Bayroni

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

C

CM

MY

CY

CMY

K
AmmoniaCasale

Casale Strategies for Complete


Ammonia Plant Revamping
The example of AL BAYRONI

1. Introduction The plant was originally started up in interventions and a reharping of the
Al-Jubail in March 1983. It is a natural almost new primary reformer tubes
The strategy followed by AMMONIA gas based plant, i.e. using natural gas in the short-term would have been
CASALE in ammonia plant revamping for feed and for fuel. uneconomical, CASALE’s minimum
has always been to develop and Before revamping, the plant, was investment revamping option was
apply new advanced technologies to operating at a capacity of about 1170 prepared according to the following
improve the plants’ performances MTD after an initial revamping o f the guidelines:
at a minimum cost and at maximum converter internals in 1989 with a • Avoid revamping or replacement of
benefit. traditional two-bed one-interchanger the main rotating equipment;
design, (not a CASALE design), •No modifications to the primary
The performance improvement and addition of a membranes-type reformer section;
is normally a reduction in energy Hydrogen Recovery Unit. • Modifications to the equipment had
consumption, an increase in capacity to be suitable for the further capacity
or a combination of the two. The production increase to 1300 MTD expansion;
was the main goal of the project. Further • Possible variations in natural gas
It is also important to find out what targets were the energy saving, the quality had to be considered;
are the most critical items, the cooling water consumption reduction • Plant shall be able to operate when
improvement of which gives the best and the reliability improvement. new sections are isolated;
return. A second step of capacity increase • Possible trip of new sections shall
up to 1800 MTD had also been not involve the trip of the existing
Following this strategy AMMONIA considered. All the new equipment plant.
CASALE has developed and applied a had therefore to be designed for the
number of proprietary items. highest capacity. The 1300 MTD ammonia production
was selected since this value was
The paper summarizes the content An important requirement was the positioned at the very limits of the
and results obtained in the AL BAYRONI very tight project schedule. The project existing syngas compressor suction
(ex-SAMAD) project. started in October 2000. All the capacity and of the refrigeration
Engineering and Procurement services compressor capacity.
for the De-bottlenecking project
2. Complete Plant Revamping were completed within September The modifications implemented are
Description 2001. Turnaround took place in the following:
In 2002 AMMONIA CASALE had January 2002. All modifications were
completed the revamping of a 1000 implemented during the period of a Feed gas desulphurisation
MTD ammonia Plant based on M.W. standard shut-down. Start-up followed The desulphurization section and the
Kellogg’s technology at the AL-JUBAIL immediately after. feed gas compression were suitable
FERTILIZER COMPANY (SAMAD), for the new operating conditions and
located in Al-Jubail, Kingdom of Saudi Since every modification to needed no modifications.
Arabia. machinery results in very expensive

1
AmmoniaCasale

Prereforming and Primary reforming • increased process air preheating; In 1989 after the first plant revamping
The Primary Reformer of the SAMAD • mixed feed coil replacement could the plant production has been ranging
Ammonia Plant is a typical Kellogg be avoided (only a mechanically simple between 1170 and 1220 MTD of
top-fired unit with 416 catalytic tubes tube rows removal will be necessary); ammonia. The air compression section
arranged in 8 rows. The reformer tubes • BFW preheating level could be that was constantly operated at its
were replaced in 1997 using HK40 maintained; maximum suction capacity limited the
material (the same as per original • flexibility for every possible change production.
design) and the tubes thickness is in natural gas composition. For the capacity increase the section
also identical to the original design. needed to be debottlenecked.
The intervention consisted in the
The heat flux to the primary reformer Process Air addition of a booster on the suction of
without replacing the reformer tubes The section was designed to provide in the air compressor. The booster was
could only be marginally increased. normal conditions sufficient process sized so as to be suitable also for the
Therefore, to increase the capacity of air for a production of 1000 MTD of major expansion planned in the future.
the reformer up to the level needed for ammonia.
the capacity expansion, the steam to
carbon ratio had to be decreased from SIMPLIFIED PROCESS SCHEME
3.7 to 3.2.

Having a high concentration of higher


hydrocarbons in natural a pre-reformer
unit was installed to enable safe S/C
reduction. Prereformer feed has to be
preheated to about 440°C, therefore
a fired heater was installed for this
scope, as illustrated above.

The advantages of the use of the pre-


reformer and of the fired heater can
be summarized as follows:
• safe reduction of the S/C ratio;
• increased superheating of steam
without interventions on steam
superheating coil;

2
AmmoniaCasale

The following modifications have been • lower CO slip and thus lower inerts without appreciably increasing the
implemented in the air compression concentration in the make-up gas for system pressure drop.
section: the whole catalyst life; The only modification to the syngas
• installation of a new intake air filter; • longer catalyst life; compressor was the replacement of
• addition of 1101-J air booster driven • catalyst protection against water the recycle wheel by a new one that
by 1101-JT back-pressure steam droplets. allowed the synloop to be operated
turbine; at the maximum discharge pressure
• addition of 1129-JC aftercooler achieved by the M.U.G. stages at the
downstream the new air booster; 2.1 Synthesis Gas increased suction flow rate.
• installation of a flow deviator to Purification System The new recycle wheel was designed
connect air booster to existing air for the lower recycle flow rate and lower
compressor. Carbon Dioxide removal head necessary with the revamped
The performance of 101-J existing The CO2 from the ammonia synthesis synthesis converter internals.
compressor have been also improved gas was scrubbed using Union Carbide
by the replacement of 129-JC first licensed MEA Amine Guard (AG II) With the new wheel the loop operated
interstage cooler; the remaining system. The CO2 content of purified at a higher pressure and at low recycle
intercoolers will be replaced in near gas was satisfactorily low (around 120 flow rate. This reduced the power
future. ppm) but corrosion problems were requirement in the 103-J machine as
observed. well as in the 105-J machine.
The BASF aMDEA process was best
Secondary reformer suited for revamping the MEA unit
No modifications were necessary to by a simple solvent swap, keeping Synthesis
the secondary reformer and to its the existing section configuration. The main modifications regarding
burner. There was no need of any equipment the ammonia synthesis loop were
The downstream waste heat boiler modification. the converter internals retrofit and
101-C was replaced for maintenance. the recycle wheel replacement with a
The specific energy consumption was smaller one. These two interventions
decreased from 36’900 to 30’700 allowed the 105-D synthesis converter
Shift converters kcal/kmol CO2. Thanks to this energy to reach higher performances, thus
The shift converters had a relevant saving it was possible to reduce the resulting in a higher ammonia outlet
pressure drop, 0.5 bar for H.T. Shift S/C ratio. This reduction resulted concentration and temperature.
and 1 bar for L.T. Shift. These high also in a significant saving in the The increased outlet temperature
values were due to the axial design sea cooling water fed to the stripper made necessary the replacement
of these converters and to the large overhead condenser. of the converter outlet pipe and the
catalyst volumes installed. Their replacement of the BFW preheater
retrofit with CASALE axial-radial 123-C.
internals was necessary to reduce the Methanator
pressure drop. No modifications were required to the The benefits achieved by these
heat exchangers and to raw syngas modifications were:
The pressure drop after revamping separator. Also the 106-D methanator • reduction of the power consumption
is about 0.3 bar each, that will was suitable for the new operating in the 103-J machine, that allowed
correspondingly increase the suction conditions. avoiding the revamping of this
pressure of the syngas compressor. compressor and of its driving turbine;
This pressure increase is very • reduction of the loop chillers duty,
important to allow this machine 2.2 Ammonia Production necessary to avoid the revamping
achieving the higher capacity without System of the existing 105-J compressor
any modification to the make-up (refrigerant ammonia compressor).
stages. Compression of purified synthesis gas
The advantages that resulted from The reduction of the steam to carbon
this revamping can be summarized as ratio and the revamping of the shift
follows: converters internals allowed an
• lower pressure drop; increase in the plant throughput

3
AmmoniaCasale

Ammonia Converter pressure the temperature at converter


3. Conclusions
The ammonia converter was revamped outlet is higher and above the design
The project has been concluded
to a two bed-intercooler design in values for the existing converter outlet
successfully; performances of the
1989. pipe and 123-C exchanger. For the
Revamped Plant have entirely met
The performance of the converter above reason it was necessary to
and exceeded expectations both in
was further enhanced by installing replace the outlet pipe with one with
capacity increase target and in energy
the CASALE technology, transforming improved metallurgy.
saving, as given in Table 1.
the internals to a three bed-quench-
intercooling design. The following table 1 gives a summary
Refrigeration of the main plant performances
The cartridge configuration was The higher performance of the
compared to the Base Case (i.e. before
changed to a modern axial-radial synthesis loop after converter
revamping).
design with intermediate cooling. The revamping allowed a significant
new cartridge configuration was 3-bed reduction of the chillers specific duties,
with one quench between the first and thanks to this improvement, the plant
the second bed and one interchanger capacity increase has been born by the
between the second and the third bed. 105-J ammonia compressor and by its
Due to the better converter steam driver without any modification.
performance and higher operating

TABLE 1

Description Base Case Revamped


Production: MTD 1170 1312

ENERGY CONSUMPTION
Total specific cons. Gcal/MTNH3 9.77 9.23

SEA COOLING WATER


3
Specific consumption m /MTNH3 416.0 388

4
C

CM

MY

CY

CMY

You might also like