Business Plan for 150 MW

ECOPROJECTS
Production line of turnkey photovoltaic modules

INDEX

Mr. No. Subjects Pg. No.

1 Basic assumptions 1

2 Material cost per module 2

3 Total cost of production per year 3

4 Total summary of the project 4

5 Company summary 5
Machine Translated by Google

Basic assumptions

Buy/sell rate € / watt Conversion rate

Conversion rate from


Cell 0.12 1.12
Euros to USD

Selling price of the module 0.27

Capacity calculation Forms


Capacity 4200 Cells / Time Modules /hour 57

Cell / Watt 5.5 Watt Modules/day 1272

No. of Cells/Module 72 Pcs Modules/year 381696

Working Hours / Day 22.5 Hours

Module power 396 Watt

working days/year 300 Days

Shifts / Day 3 Shifts

Uptime 100 %

Yield 95 %

Line Capacity 151 MW extension

Cost of machinery Euros (€) Interest rate


Cost of machinery 1,850,000 Interest rate (%) 4

Cost of labor Ancillary cost

Wage /
Operational staff No. Operators Details (€)
Year (€)
Warehouse workers 4,800 2 Compressor 10,000

Operator 4,800 10 Air conditioning 10,000

Engineer 12,000 2 Electricity 20,000

Manager 24,000 1 Certification costs 50,000

Commercial Manager 24,000 1

Administrative employees 4,800 2

Safety 3,600 1

SMOKING data Site costs


Requirements Dimension Unit Details Cost / KWH (€)

Production (area) 1100 m² Electricity costs 0.80

Production (height) 4.5 m²

Load capacity 800 kg/m²

Factory 2000 m²

Power (peak) 450 kW

Average power 225 kW

Air 1500 Lt/min


Machine Translated by Google

Material cost per module

0%
1%
0% 0% 1% 1% Cells

Tempered glass (1,650m x 1m)


3%
4%
Backsheets
9%
EVA Fast Cure

5% Aluminum frame kit

Junction Box with cables


4%
Flux

60%
Silicone sealant

12% Welding cable for interconnection

Ribbon 1.7mm

Ribbon 5mm

Adhesive

Packing box / form

2 Glass m²
Production cost/Module 396 WATTS

Amount Cost per


Unit of Qty per
Mr. No. Raw material Unitary module %
measure module
(€) (€)

1 Cells 72
Pcs 0.66 47.52 59.66

2 Tempered glass (1,650m x 1m) m² 4.70 2.00 9.40 11.80

3 Backsheets m² 1.80 2.00 3.60 4.52

4 EVA Fast Cure m² 1.10 4.00 4.40 5.52

5 Aluminum frame kit Kit 1


7.00 7.00 8.79

8 Junction Box with cables Kit 1


3.50 3.50 4.39

9 Flux Lt 5.40 0.025 0.14 0.17

10 Silicone sealant Lt 9.00 0.056 0.50 0.63

11 Welding cable for interconnection Kg 15.00 0.0025 0.04 0.05

12 Ribbon 1.7mm 11.00 0.2 2.20 2.76


Kg

13 Ribbon 5mm
Kg 11.00 0.05 0.55 0.69

14 Adhesive Roll 5.90 0.0075 0.04 0.06

15 Packing box / form Kit 0.76 1 0.76 0.95

Total cost / module 79.7 100.0

Total cost / module € / watt 0.201 €/ watt


Machine Translated by Google

Total cost of production per year

4%
0%
1%

Material Cost/Watt/Year (€)

Total labor cost for 3 shifts / year / watt (€)

Total energy cost / Watt (€)

Total Interest / Watt (€)


95%

Material cost / Year


line capacity
line capacity Stringer required for line Material cost / Year (€
(Watt) capacity million)
(MW)
151 151,151,785.71 1 30.40

Labor cost/year
Operational Staff Total cost for
line capacity
3 shifts /
(MW) Manager Operator Engineer Warehouse workers
year (millions €)
10 2 2

151 1 0.313
Commercial Manager Administrative Employees 2 Safety
1 1

Energy costs/year
line capacity Energy consumption Energy consumption / Cost / KWH Total costs
(MW) / kW year (€) (millions €)
151 225 1518750 0.8 1.22

Interest / Year
Interest on
Investment
Cost of machinery Auxiliary cost Line capital line capital
Line capacity total
(millions €) (millions €) (millions €)
(MW) (millions €)
TO b C=(A+B) (million €)
C+D
d
151 1.85 0.090 1.94 0.08 2.02

Conversion cost (without cell)


Material cost/ Total Interest
line capacity Total labor cost for 3 shifts / Total energy cost / Watt (€) Total cost (€)
Watts / Year / Watts
(MW) year / watt (€)
(€) (€)

151 0.081 0.002 0.008 0.001 0.092


% 88.42 2.26 8.76 0.56 100.00

Total cost of production (with cell)


Material cost/ Total Interest
line capacity Total labor cost for 3 shifts / Total energy cost / Watt (€) Total cost (€)
Watts / Year / Watts
(MW) year / watt (€)
(€) (€)

151 0.201 0.002 0.008 0.001 0.212


% 94.98 0.98 3.80 0.24 100.00
Machine Translated by Google

Total summary of the project

22%

0%
3%
Material cost
1% (millions €)

Labor cost (millions


€)

Cost of energy
74% (millions €)

Interests
(millions €)

Profit
(millions €)

Total production cost / year


Total cost of Total cost Total cost Total cost
material labor (millions of energy prod.
Line capacity (MW)
(millions €) €) (millions €) (millions €)
TO b c (A+B+C)
151 30.40 0.31 1.22 31.931

Turnover
Sale Module /
Line capacity (MW) year

(millions €)
151 40.81

Profi neo

Profit with interest


Pay Back
before tax Profit
Line capacity (MW) with interest
(without %
(years)
depreciation)

151 8.80 9.57pm 0.80

Summary
Cost Total
Material cost Cost of energy Interests Profit
Line capacity (MW) Labor Turnover
(millions €) (millions €) (millions €) (millions €)
(millions €) (millions €)

151 30.40 0.31 1.22 0.08 8.80 40.81

% 74.5 0.8 3.0 0.2 21.6


Machine Translated by Google

Summary

Million €

total investment 2.02

Capital (2 months) 5.07

Total Turnover / Year 40.81

Total Net Profit / Year 8.80

Pay Back with interest and


0.80
capital (years)